Amendment_0007.pdf

PDF 345 KB Posted

Attached to
Restack of the William J. Green Federal Building
Solicitation number
GS-03-P-16-AZ-C-7004
Issued by

About this file

Amendment 0007

View the file

Other files

File Type Posted
Ta4.26_-_02_Enlarged_Plans_-_Conference_Room_05.pdf PDF
Amendment_0006.pdf PDF
Flow_Test.pdf PDF
23_0900_INSTRUMENTATION_AND_CONTROL_FOR_HVAC._-_Add__2.pdf PDF
S4-02_-_ENLARGED_PARTIAL_PLANS.pdf PDF
Amendment_0005.pdf PDF
Specification_-_Table_of_Contents.pdf PDF
10_2240_Folding_Glass-Panel_Partitions.pdf PDF
MS-502.pdf PDF
09_5113_acoustical_panel_ceilings.pdf PDF
23_2113_HYDRONIC_PIPING_-_Add__2.pdf PDF
MP-405.pdf PDF
01_1030_TELECOMMUNICATIONS_SYSTEMS_OVERVIEW.pdf PDF
08_8713_Window_Film_Type_01.pdf PDF
01_ARCHITECTURAL_-_Addendum_02.pdf PDF
Addendum_No_02_-_Cover_Sheet.pdf PDF
09_3033_stone_tiling.pdf PDF
10_1423_Panel_Signage.pdf PDF
MD-124.pdf PDF
MP-103_2.pdf PDF
M-001.pdf PDF
09_6813_tile_carpeting.pdf PDF
S3-01_-_TYPICAL_DETAILS.pdf PDF
MP-104.pdf PDF
MS-501.pdf PDF
10_2226_Operable_Partitions.pdf PDF
MD-123.pdf PDF
08_8713_Window_Film_Type_02.pdf PDF
09_3000_ceramic_tile.pdf PDF
10_2241_Vertically_Folding_Panel_Doors.pdf PDF
MD103.pdf PDF
MD501.pdf PDF
Pre-Alteration_Asbestos_Assessment.pdf PDF
Specification_-_23_0529_HANGERS_AND_SUPPORTS_FOR_HVAC_PIPING_AND_EQUIPMENT-Addendum__1.pdf PDF
Ty6-00.pdf PDF
Specification_-_09_6513_RESILIENT_BASE_AND_ACCESSORIES.pdf PDF
Specification_-_01_1000_SUMMARY.pdf PDF
MH104.pdf PDF
Amendment_0004.pdf PDF
Construction_Sequencing_Diagrams.pdf PDF
Addendum_No_01_-_Cover_Sheet.pdf PDF
01_ARCHITECTURAL_-_Addendum_01.pdf PDF
MH103.pdf PDF
Specification_-_01_2400_OPTIONS.pdf PDF
Specification_-_Table_of_Contents.pdf PDF
Specification_-_09_5113_ACOUSTICAL_PANEL_CEILINGS.pdf PDF
MD104.pdf PDF
Amendment_0003.pdf PDF
Amendment_0002.pdf PDF
02_STRUCTURAL.pdf PDF
Show 40 more

Latest 50 of 68 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION

NO.

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO.

IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

NSN 7540-01-152-8070

Previous edition unusable

The Restack of the William J. Green Federal Building.

Please see additional pages for details.

General Services Administration 100 S. Independene Mall West Philadelphia, PA 19106

General Services Administration 100 S. Independence Mall West Philadelphia, PA 19106

GS-03-P-16-AZ-C-7004

1 2

06/21/2016

05/10/2016

The Restack of the William J. Green Federal Building Sol: GS-03P-16-AZ-C-7004

The following items are hereby incorporated into the solicitation:

1. Drawing TA 4.26 Conference Room - is incorporated into the solicitation.

2. RFI 176 and GSA’s response to RFI 176 are incorporated into the solicitation.

Request of Information:

The proposal closing date remains as stated: 12:00 PM EST on June 27, 2016.

This amendment includes all of the RFIs that were submitted prior to the RFI closing date.

All other terms and conditions remain unchanged.

RFI No. RFI Response

Floor 2 (A1.22) and Floor 4 (A1.24b) indicate work not in contract however Fire protection drawing indicate work over the entire floors.

RFI response #18 indicated all piping to be replace on the floors. Is this work to be performed during regular hours?

We are only replacing fire protection in the areas that are being renovated. We are not replacing the fire protection systems in the areas that are not being renovated.

SF30
Page 2