Draft Work Breakdown Structure as of 1/6/12

View the file

Other files

File Type Posted
NOCA 04 Sept 12.pdf PDF
RFP Letter 4 v1.pdf PDF
Atch 13 - Cost Formats 20120602.xlsx XLSX spreadsheet
RFP Letter 3 v2.pdf PDF
RFP Letter 2 v1.pdf PDF
GTRD 14 May Update Errata.docx DOCX document
1 RFP 20120424 Section J.pdf PDF
Atch 10 - Variable Quantity Pricing Table 20120424.xlsx XLSX spreadsheet
Atch 13 - Cost Formats 20120416v35.xlsx XLSX spreadsheet
RFP Letter v4.pdf PDF
1 RFP 20120424 No Attachments.pdf PDF
DRAFT RFP No Attachments.pdf PDF
DRAFT RFP Section J.pdf PDF
1 RFP No Attachments and Exhibits.pdf PDF
1 RFP Section J.pdf PDF
20120323_FABT_AltSource_Revised_and_New_Docs_Available_v2.pdf PDF
Revised_GTRD_20120224_FABT_AltSouce_Special_Handling.pdf PDF
Draft RFP 3_9_12 v30 Sections A-M.pdf PDF
Draft RFP 3_9_12 v30 Exhibits and Attachments.pdf PDF
FAB_T_Industry_Day_Brief_8MAR2012_FEDBizOpps.pdf PDF
NOTICE OF CONTRACT ACTION.pdf PDF
ESC_OCI_PolicyBrief_IDB2008.ppt PPT presentation
Atch 13 - Cost Formats 20120228 v23.pdf PDF
SECTION L 20120301 cdl.pdf PDF
FAB-T RFI for 8 March 2012 Industry Day Jan 2012 V1.pdf PDF
Atch 10 - Variable Quantity Pricing Table 20120216 v3.pdf PDF
Exhibit E - Data Requirements List for TM86-01 20120223 v36.pdf PDF
Exhibit A - Instructions for Data Requirements List 20120223 v36.pdf PDF
Atch 14 - Cost and Software Data Reporting Plan.pdf PDF
Exhibit C - Data Requirements List for LRIP 20120223 v36.pdf PDF
Exhibit D - Data Requirements List for Production 20120223 v36.pdf PDF
CLIN structure V26 - 2.pdf PDF
Exhibit F - Data Requirements List for PDAL - full 20120223 v36.pdf PDF
Exhibit B - Data Requirements List for EMD 20120223 v36.pdf PDF
Atch 3 - Entrance and Exit Criteria for SRR PDR CDR 20120223.pdf PDF
Atch 1 - Statement of Work 20120223 v36.pdf PDF
Exhibit G - Data Requirements List for PDAL - sust 20120223 v36.pdf PDF
Atch 4 - Preliminary WBS.pdf PDF
Atch 13 - Cost Formats 20120223 v23.pdf PDF
Atch 9 - Terminal Delivery Schedule 20120223 v4.pdf PDF
FAB_T_Corporate_NDA.pdf PDF
SECTION_M.pdf PDF
DD Form 254.pdf PDF
SECTION_L.pdf PDF
GTRD_and_Other_Documents_Requiring_Special_Handling.pdf PDF
FA8307_12_R_0003.pdf PDF
FAB_T_Individual_NDA.pdf PDF
FAB_T_RFI_for_Industry_Day.pdf PDF
FAB_T_Industry_Day_Brief_Jan_12.pdf PDF
Show all 49

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W B

S L

E V

E L

W B

S N o

WBS Title

1 1 FAB-T COMPETITIVE AWARD

2 1.1 FAB-T Prime Mission Product (PMP)

3 1.1.1 Modem Processor Group (MPG)

4 1.1.1.1 MPG Hardware

4 1.1.1.2 MPG Software

4 1.1.1.3 MPG Integration, Assembly, Test, and Checkout

3 1.1.2 Operator Interface Group (OIG)

4 1.1.2.1 OIG Hardware

4 1.1.2.2 OIG Software

4 1.1.2.3 OIG Integration, Assembly, Test, and Checkout

3 1.1.3 Antenna Equipment Group (AEG)

4 1.1.3.1 AEG Hardware

4 1.1.3.2 AEG Software

4 1.1.3.3 AEG Integration, Assembly, Test, and Checkout

3 1.1.4 Prime Mission Product Software

4 1.1.4.1 Software Product Engineering

4 1.1.4.2 Computer Software Configuration Item (CPCI) 1….n

4 1.1.4.3 Subsystem Integration, Assembly, Test, and Checkout

3 1.1.5 FAB-T PMP Integration, Assembly, Test, and Checkout

2 1.2 Platform Integration, Assembly, Test, and Checkout

2 1.3 System Engineering

2 1.4 Program Management

2 1.5 System Test and Evaluation

3 1.5.1 Development Test and Evaluation

3 1.5.2 Operational Test and Evaluation

3 1.5.3 Mock-ups / System Integration Labs (SILs)

3 1.5.4 Test and Evaluation Support

3 1.5.5 Test Facilities

2 1.6 Training

3 1.6.1 Training Equipment

3 1.6.2 Training Services

3 1.6.3 Training Facilities

2 1.7 Data

3 1.7.1 Technical Publications

3 1.7.2 Engineering Data

3 1.7.3 Management Data

3 1.7.4 Support Data

3 1.7.5 Data Depository

2 1.8 Peculiar Support Equipment (PSE)

3 1.8.1 PSE Test and Measurement Equipment

3 1.8.2 PSE Support and Handling Equipment

2 1.9 Common Support Equipment (CSE)

3 1.9.1 CSE Test and Measurement Equipment

3 1.9.2 CSE Support and Handling Equipment

2 1.10 Operational / Site Activation

3 1.10.1 System Assembly, Installation and Checkout on Site

3 1.10.2 Contractor Technical Support

3 1.10.3 Site Construction

3 1.10.4 Site/Ship/Vehicle Conversion

3 1.10.5 Sustainment/Interim Contractor Support

2 1.11 Industrial Facilities

3 1.11.1 Construction/Conversion/Expansion

3 1.11.2 Equipment Acquisition or Modernization

3 1.11.3 Maintenance (industrial Facilities)

2 1.12 Initial Spares and Repair Parts