Industry Day 2 Briefing on 8 March 2012

View the file

Other files

File Type Posted
NOCA 04 Sept 12.pdf PDF
RFP Letter 4 v1.pdf PDF
Atch 13 - Cost Formats 20120602.xlsx XLSX spreadsheet
RFP Letter 3 v2.pdf PDF
RFP Letter 2 v1.pdf PDF
GTRD 14 May Update Errata.docx DOCX document
1 RFP 20120424 Section J.pdf PDF
Atch 10 - Variable Quantity Pricing Table 20120424.xlsx XLSX spreadsheet
Atch 13 - Cost Formats 20120416v35.xlsx XLSX spreadsheet
RFP Letter v4.pdf PDF
1 RFP 20120424 No Attachments.pdf PDF
DRAFT RFP No Attachments.pdf PDF
DRAFT RFP Section J.pdf PDF
1 RFP No Attachments and Exhibits.pdf PDF
1 RFP Section J.pdf PDF
20120323_FABT_AltSource_Revised_and_New_Docs_Available_v2.pdf PDF
Revised_GTRD_20120224_FABT_AltSouce_Special_Handling.pdf PDF
Draft RFP 3_9_12 v30 Sections A-M.pdf PDF
Draft RFP 3_9_12 v30 Exhibits and Attachments.pdf PDF
NOTICE OF CONTRACT ACTION.pdf PDF
ESC_OCI_PolicyBrief_IDB2008.ppt PPT presentation
Atch 13 - Cost Formats 20120228 v23.pdf PDF
SECTION L 20120301 cdl.pdf PDF
FAB-T RFI for 8 March 2012 Industry Day Jan 2012 V1.pdf PDF
Atch 10 - Variable Quantity Pricing Table 20120216 v3.pdf PDF
Exhibit E - Data Requirements List for TM86-01 20120223 v36.pdf PDF
Exhibit A - Instructions for Data Requirements List 20120223 v36.pdf PDF
Atch 14 - Cost and Software Data Reporting Plan.pdf PDF
Exhibit C - Data Requirements List for LRIP 20120223 v36.pdf PDF
Exhibit D - Data Requirements List for Production 20120223 v36.pdf PDF
CLIN structure V26 - 2.pdf PDF
Exhibit F - Data Requirements List for PDAL - full 20120223 v36.pdf PDF
Exhibit B - Data Requirements List for EMD 20120223 v36.pdf PDF
Atch 3 - Entrance and Exit Criteria for SRR PDR CDR 20120223.pdf PDF
Atch 1 - Statement of Work 20120223 v36.pdf PDF
Exhibit G - Data Requirements List for PDAL - sust 20120223 v36.pdf PDF
Atch 4 - Preliminary WBS.pdf PDF
Atch 13 - Cost Formats 20120223 v23.pdf PDF
Atch 9 - Terminal Delivery Schedule 20120223 v4.pdf PDF
Gov_Proposed_WBS.pdf PDF
FAB_T_Corporate_NDA.pdf PDF
SECTION_M.pdf PDF
DD Form 254.pdf PDF
SECTION_L.pdf PDF
GTRD_and_Other_Documents_Requiring_Special_Handling.pdf PDF
FA8307_12_R_0003.pdf PDF
FAB_T_Individual_NDA.pdf PDF
FAB_T_RFI_for_Industry_Day.pdf PDF
FAB_T_Industry_Day_Brief_Jan_12.pdf PDF
Show all 49

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Family of Advanced

Beyond Line-of-Sight

Terminals (FAB-T)

Alternate Source

Acquisition

Industry Day

8 MAR 2012

ESC/HNT

Electronic Systems Center

Industry Day Schedule

Day 1

0900 – 0915 Kickoff

0915 – 0930 Organizational Conflict of Interest (OCI)

0930 – 0945 Opening Remarks from Col DeLaPena

0945 – 1030 Industry Briefing

1030 – 1100 Question and Answer Session

1300 – 1730 One-on-one sessions

Day 2

0900 – 1230 One-on-one sessions

Administrative Information

• Shut off all electronic devices

• Restrooms are located outside of the auditorium to the left

• Escorts are required for any movement outside of this room

• Emergency exit is located in the C Lobby

• Forms are available to submit questions for the Q&A session

Disclaimer

• All acquisition strategy information is draft and subject to change pending receipt of the required approvals, including approval on the method of acquisition (full and open, small business set-aside, 8(a) program, etc)

• This briefing does not constitute an invitation for bid or request for proposal and is not to be construed as a commitment by the Government

Special Presentation

ESC/JA Presentation on Organizational Conflict of Interest

Alternate Source Acquisition Objective

• The program is focused on delivering Warfighters’ highest priority terminals: E-4, E-6, and Ground

Command Post Terminals with Presidential &

National Voice Conferencing (PNVC)

• Initial terminal deliveries no later than FY15 to meet

Warfighter needs

• The contract effort does not include Force Element requirements for the B-2, B-52, and RC-135 airborne and ground terminals

Business Opportunity

• Competitive award of a single fixed price contract for development/production in FY12 based on Offerors’ proposals and demonstrations of existing HW/SW

• Contract value will be capped at $70M for a Firm

Fixed Price (FFP) initial ten month development period

• Priced options for continuation of development and for production

Contracting

• The Alternate Source contract for development and production will be awarded through a full and open competition (after the exclusion of Boeing).

– The exclusion is in accordance with 10 U.S.C.

2304(b)(1) as implemented by DFARS 206.202.

RFP Key Features (1 of 2)

• Government Technical Requirement Document splits requirements into two blocks:

− Block 1 is focused on the high priority CPT w/PNVC mission

− Block 2 provides the remainder of CPT capabilities

• Proposals will describe a detailed schedule (e.g., SRR, PDR, CDR, SVRR) and event information for the entire CPT (Blocks 1

& 2) development and production

• Proposals will include contractor defined development events from the Integrated Master Plan (IMP) at nine months after award, and at the conclusion of CLINs 0003 & 0004, if options are exercised

RFP Key Features (2 of 2)

• Special Clauses will be used to implement contract incentives to assess Liquidated Damages

• Full Data Rights will be sought to enable the

Government to sustain the FAB-T system and reuse to support the future Force Element portion of the program

Contract Structure

• Development Period of Performance (FY12-14)

– FFP CLIN 0001 development of CPT w/PNVC for 10 months

– FFP Option CLIN 0003 for continuing development of CPT w/PNVC for 2 months

– FFP Option CLIN 0004 for continuing development of CPT w/PNVC for an additional 2 months

– FFP Option CLIN 0005 for complete development of CPT w/PNVC

– FFP Option CLIN 0020 for TT&C development

• Production six (6) annual buys

– FFP Option CLIN LRIP FY14

– FFP Option CLIN LRIP FY15

– FFP Option CLINs FRP FY16-19

Production Quantities

• Command Post Terminals

– Airborne Terminals

• E-4

• E-6

– Ground Terminals

• Fixed

• Transportable

Note: Force Element terminal requirements (Qty 132) to be addressed in a future acquisition

Terminals Quantity

E-4 4

E-6 17

Ground Fixed 41

Ground

Transportable

Total: 84

Source Selection

Draft Evaluation Factors for Contract Award

– Evaluation Factors

– Demonstration

– Past Performance

Draft Source Selection Criteria

• Evaluation Factors and Subfactors:

– Factor 1: Technical Capability

• Subfactor 1: Architecture, System Design and Performance

• Subfactor 2: Program Execution

– Factor 2: Past Performance

– Factor 3: Cost/Price

• Demonstration – To assess the technical risk associated with the Offeror’s proposed solution

• Solicitation Requirements – Offeror must meet all requirements OR clearly identify any exceptions and provide complete supporting rationale

Draft Relative Importance of Factors

• Factors

– Technical Capability and Cost/Price are approximately of equal importance and together are the most important. Past

Performance is less important than Technical Capability and

Cost/Price. All evaluation factors other than Cost/Price, when combined, are significantly more important than

Cost/Price

• Technical Subfactors

– Architecture, System Design, and Performance and Program

Execution Subfactors are of equal weight.

Draft Demonstration (Initial Award)

• A one day demonstration to be conducted at the

Offeror’s facility with the Offeror’s equipment

• The demonstration will be used as a means to assess the risk associated with the contents of the written proposal

– The demonstration will address the maturity and the performance of the Offeror’s proposed technical solution as well as the Offeror’s overall ability to deliver a sufficiently mature and integrated solution within the proposed contract schedule

• No GFE is planned to be used for the demonstration

Draft Past Performance Criteria (1 of 2)

• Recency will be based on performance in the last five years prior to RFP release

• Relevency will be based on experience in:

– Developing communication systems with layered communication architectures

– Developing EHF satellite communications systems or segments

– Developing, producing, and sustaining multi-band satellite terminals where the degree of complexity is similar to that of the FAB-T

– Development and platform integration of terrestrial and/or airborne satellite terminals

– Developing airborne terminals operating with narrow beam-width satellite tracking antennas

Draft Past Performance Criteria (2 of 2)

– Demonstrating understanding of strategic Nuclear

Command and Control Extremely Sensitive Information, formally known as Single Integrated Operations Plan (SIOP), radio communications requirements

– Demonstrating an understanding of security certification of satellite communication systems including cryptographic devices

– Large scale military software development

– Development and production of HEMP and nuclear hardened components

Contract Award Schedule

Final RFP release Mar 12

Proposal Receipt / Demonstration May 12

Source Selection May-Sep 12

Award Sep 12

Companies In Attendance

Boeing

General Dynamics C4S

Harris Corp.

Millitech, Inc

Cobham Electronic Systems

BTP Systems

Applied Companies

L-3 CSW

ViaSat

Lockheed Martin

Rockwell Collins

Raytheon

Excelitas Technologies

DRS ICAS, LLC

L-3 CSE

Northrop Grumman Corporation

File details come from the government source that posted it. Updated .