Summary: TAFB Technical Specifications 2019 – Section 07 24 00: Exterior Insulation and Finish Systems

This is a technical specification document for the installation of Exterior Insulation and Finish Systems (EIFS) at Tinker Air Force Base in Oklahoma, dated April 2019. The specification requires a job-fabricated, drainable Class PB EIFS consisting of sheathing board, insulation board, reinforcing fabric, base coat, finish coat, adhesive, and mechanical fasteners as a single integrated system from a manufacturer regularly engaged in furnishing such systems. All materials must be installed by manufacturer-approved applicators, and the system must meet comprehensive performance and durability requirements including water penetration resistance, wind load capacity, fire safety, impact resistance, abrasion resistance, and weathering durability as verified through multiple standardized ASTM and NFPA tests.

The specification mandates detailed quality assurance requirements, including manufacturer qualification (minimum 3 years in EIFS business with five similar projects), EIFS installer training and experience (five comparable projects), third-party inspector certification from the Exterior Design Institute, and a pre-installation conference with all relevant trades. Submittals required include shop drawings, product data, sample boards with mock-up installation (8 feet high by 6 feet wide), design calculations, comprehensive test reports, and manufacturer's instructions. The contractor must maintain a qualified inspector on-site at all times, establish a detailed inspection checklist covering substrate preparation, material handling, installation procedures, joint sealing, and cleanup, and furnish a manufacturer's warranty running directly to the Government for a minimum of five years. All work must comply with manufacturer recommendations, environmental temperature requirements (minimum 40°F), and installation procedures documented in the specification with particular attention to substrate flatness tolerances (1/4 inch in 10 feet), insulation board adhesion drying time (minimum 24 hours), reinforcing mesh embedding, and joint sealant application protocols.

View the file

Other files

File Type Posted
03 39 00.00 10.pdf PDF
03 62 16.pdf PDF
04 20 00.pdf PDF
05 21 00.pdf PDF
06 20 00.pdf PDF
06 61 16.pdf PDF
07 60 00.pdf PDF
07 61 14.00 20.pdf PDF
07 84 00.pdf PDF
07 92 00.pdf PDF
08 11 16.pdf PDF
08 36 13.pdf PDF
08 71 00.pdf PDF
09 68 00.pdf PDF
10 28 13.pdf PDF
13 48 00.pdf PDF
21 13 17.pdf PDF
22 00 00.pdf PDF
23 00 00.pdf PDF
23 08 00.pdf PDF
23 11 25.pdf PDF
23 35 00.pdf PDF
23 64 26.pdf PDF
23 82 16.00 40.pdf PDF
23 82 43.00 40.pdf PDF
26 56 00.pdf PDF
31 23 06.pdf PDF
32 01 14.pdf PDF
32 13 74.pdf PDF
03 11 13.00 10.pdf PDF
03 20 00.00 10.pdf PDF
03 30 00.pdf PDF
07 14 00.pdf PDF
190023 Renovate Restrooms B117 RFIs_FINAL_COR_Signed.pdf PDF
TAFB_Tech_Reqs (Div 02-48).zip ZIP file
Model.zip ZIP file
00 71 00.pdf PDF
01 78 23.pdf PDF
000_TABLE OF CONTENTS.pdf PDF
01 32 16.00 20.pdf PDF
01 33 16.00 10.pdf PDF
01 42 00.pdf PDF
01 78 00.pdf PDF
Tinker General Requirements Specifications_Nov 2022_Change Log.pdf PDF
Initial Site Visit WWYK190023.pdf PDF
Solicitation - FA813726R0030.pdf PDF
Att10_190023_SOW.pdf PDF
EAL List - BLANK to Contractors WWYK190023.xlsx XLSX spreadsheet
Att12_190023_Drawings_Final.pdf PDF
Section L - Instructions to Offerors.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Ti nker AFB, OK TAFB Techni cal Spr ci f i cat i ons 2019

SECTI ON 07 24 00

EXTERI OR I NSULATI ON AND FI NI SH SYSTEMS

PART 1 GENERAL

1. 1 REFERENCES

The publ i cat i ons l i s t ed bel ow f or m a par t of t hi s speci f i cat i on t o t he ext ent r ef er enced. The publ i cat i ons ar e r ef er r ed t o wi t hi n t he t ext by t he basi c desi gnat i on onl y.

ASTM I NTERNATI ONAL ( ASTM)

ASTM B117 ( 2011) St andar d Pr act i ce f or Oper at i ng Sal t Spr ay ( Fog) Appar at us

ASTM C1177/ C1177M ( 2013) St andar d Speci f i cat i on f or Gl ass Mat Gypsum Subst r at e f or Use as Sheat hi ng

ASTM C1278/ C1278M ( 2007a; R 2015) St andar d Speci f i cat i on f or Fi ber - Rei nf or ced Gypsum Panel

ASTM C150/ C150M ( 2015) St andar d Speci f i cat i on f or Por t l and Cement

ASTM C473 ( 2015) Physi cal Test i ng of Gypsum Panel Products

ASTM C578 ( 2015b) St andar d Speci f i cat i on f or Ri gi d, Cel l ul ar Pol yst yr ene Ther mal I nsul at i on

ASTM C67 ( 2014) St andar d Test Met hods f or Sampl i ng and Test i ng Br i ck and St r uct ur al Cl ay Ti l e

ASTM C847 ( 2014a) St andar d Speci f i cat i on f or Met al Lath

ASTM C920 ( 2014a) St andar d Speci f i cat i on f or El ast omer i c Joi nt Seal ant s

ASTM D2247 ( 2015) Test i ng Wat er Resi st ance of Coat i ngs i n 100% Rel at i ve Humi di t y

ASTM D3273 ( 2012; E 2015) Resi st ance t o Gr owt h of Mol d on t he Sur f ace of I nt er i or Coat i ngs i n an Envi r onment al Chamber

ASTM D968 ( 2015) Abr asi on Resi st ance of Or gani c Coat i ngs by Fal l i ng Abr asi ve

ASTM E2098/ E2098M ( 2013) Det er mi ni ng Tensi l e Br eaki ng St r engt h of Gl ass Fi ber Rei nf or ci ng Mesh f or Use i n Cl ass PB Ext er i or I nsul at i on and Fi ni sh Syst ems ( EI FS) af t er Exposur e t o a Sodi um Hydr oxi de Sol ut i on

Apr i l 2019 Page 1 SECTI ON 07 24 00

ASTM E2486 ( 2006) St andar d Test Met hod f or I mpact Resi st ance of Cl ass PB and PI Ext er i or I nsul at i on and Fi ni sh Syst ems ( EI FS)

ASTM E2570/ E2570M ( 2007; R 2014; E 2014) St andar d Test Met hods f or Eval uat i ng Wat er - Resi st i ve Bar r i er ( WRB) Coat i ngs Used under Ext er i or I nsul at i on and Fi ni sh Syst ems ( EI FS) or EI FS wi t h Dr ai nage

ASTM E330/ E330M ( 2014) St r uct ur al Per f or mance of Ext er i or Wi ndows, Door s, Skyl i ght s and Cur t ai n Wal l s by Uni f or m St at i c Ai r Pr essur e Difference

ASTM E331 ( 2000; R 2009) Wat er Penet r at i on of Ext er i or Wi ndows, Skyl i ght s, Door s, and Cur t ai n Wal l s by Uni f or m St at i c Ai r Pr essur e Di f f er ence

ASTM E695 ( 2003; R 2015; E 2015) Measur i ng Rel at i ve Resi st ance of Wal l , Fl oor , and Roof Const r uct i on t o I mpact Loadi ng

ASTM E84 ( 2015b) St andar d Test Met hod f or Sur f ace Bur ni ng Char act er i st i cs of Bui l di ng Materials

ASTM G153 ( 2013) Oper at i ng Encl osed Car bon Ar c Li ght Appar at us f or Exposur e of Nonmet al l i c Materials

I NTERNATI ONAL CODE COUNCI L ( I CC)

I CC I BC ( 2012) I nt er nat i onal Bui l di ng Code

NATI ONAL FI RE PROTECTI ON ASSOCI ATI ON ( NFPA)

NFPA 268 ( 2012) St andar d Test Met hod f or Det er mi ni ng I gni t i bi l i t y of Ext er i or Wal l Assembl i es Usi ng a Radi ant Heat Ener gy Source

NFPA 285 ( 2012) St andar d Fi r e Test Met hod f or Eval uat i on of Fi r e Pr opagat i on Char act er i st i cs of Ext er i or Non- Load- Bear i ng Wal l Assembl i es Cont ai ni ng Combust i bl e Component s

1. 2 SYSTEM DESCRI PTI ON AND REQUI REMENTS

The ext er i or i nsul at i on and f i ni sh syst em ( EI FS) must be a j ob- f abr i cat ed, dr ai nabl e, ext er i or wal l cover i ng consi st i ng of sheat hi ng, i nsul at i on boar d, r ei nf or ci ng f abr i c, base coat , f i ni sh coat , adhesi ve and mechani cal f ast ener s as appl i cabl e. The syst em component s must be compat i bl e wi t h each ot her and wi t h t he subst r at e as r ecommended or appr oved by, and t he pr oduct s of , a s i ngl e manuf act ur er r egul ar l y engaged i n f ur ni shi ng Ext er i or I nsul at i on and Fi ni sh Syst ems. Al l mat er i al s must be i nst al l ed by an appl i cat or appr oved by t he syst em manuf act ur er . EI FS must be Cl ass PB

Apr i l 2019 Page 2 SECTI ON 07 24 00 and must be col or and f i ni sh i ndi cat ed. .

1. 2. 1 Syst em Requi r ement s and Test s

The syst em must meet t he per f or mance r equi r ement s as ver i f i ed by t he t est s l i s t ed bel ow. Wher e a wal l syst em of s i mi l ar t ype, s i ze, and desi gn as speci f i ed f or t hi s pr oj ect has been pr evi ousl y t est ed under t he condi t i on speci f i ed her ei n, t he r esul t i ng t est r epor t s may be submi t t ed i n l i eu of j ob speci f i c t est s.

1. 2. 1. 1 Wat er Penet r at i on

Test t he syst em f or wat er penet r at i on by uni f or m st at i c ai r pr essur e i n accor dance wi t h ASTM E331. Ther e must be no penet r at i on of wat er beyond t he pl ane of t he base coat / EPS boar d i nt er f ace af t er 15 mi nut es at 6. 4 psf , or 20 per cent of posi t i ve desi gn wi nd pr essur e, whi chever i s gr eat er .

1. 2. 1. 2 Wi nd Load

Test t he syst em f or wi nd l oad by uni f or m st at i c ai r pr essur e i n accor dance with ASTM E330/ E330M ( pr ocedur e A) t o a mi ni mum pr essur e of __20___ psf .

Ther e must be no per manent def or mat i on, del ami nat i on, or ot her deterioration.

1. 2. 1. 3 Ful l scal e or i nt er medi at e scal e f i r e t est

Conduct wal l f i r e t est usi ng appar at us, speci men, per f or mance cr i t er i a, and pr ocedur e i n accor dance wi t h NFPA 285 when r equi r ed by I CC I BC 2603. 5. 5. The f ol l owi ng r equi r ement s must be met :

a. No ver t i cal spr ead of f l ame wi t hi n cor e of panel f r om one st or y t o t he next.

b. No f l ame spr ead over t he ext er i or sur f ace.

c. No ver t i cal f l ame spr ead over t he i nt er i or sur f ace f r om one st or y t o t he next .

d. No si gni f i cant l at er al spr ead of f l ame f r om compar t ment of f i r e or i gi n t o adj acent spaces.

1. 2. 1. 4 Mock- Up I nst al l at i on of EI FS

Compl et e wal l mock- up i nst al l at i on 8 f t hi gh by 6 f t wi de, i ncl udi ng t ypi cal cont r ol j oi nt s and at l east one wi ndow openi ng. Cont r ol j oi nt s t o be f i l l ed wi t h seal ant of t ype, manuf act ur er , and col or sel ect ed.

Const r uct mock- up i nst al l at i on at j ob s i t e. Bui l d mock- up t o compl y wi t h t he f ol l owi ng r equi r ement s, usi ng mat er i al s i ndi cat ed f or t he compl et ed work:

a. Locat e mock- up i nst al l at i on( s) i n t he l ocat i on and si ze i ndi cat ed .

b. Demonst r at e t he pr oposed r ange of col or , t ext ur e, t hi ckness, i nsul at i on, and wor kmanshi p.

c. Obt ai n Cont r act i ng Of f i cer ' s wr i t t en appr oval of mock- up bef or e st ar t i ng f abr i cat i on of wor k.

d. Mai nt ai n mock- up i nst al l at i on( s) dur i ng const r uct i on as a st andar d f or

Apr i l 2019 Page 3 SECTI ON 07 24 00 j udgi ng t he compl et ed wor k by pr ot ect i ng t hem f r om weat her and const r uct i on act i v i t i es.

e. When di r ect ed, demol i sh and r emove mock- up f r om t he si t e.

1. 2. 2 Component Requi r ement s and Test s

The component s of t he syst em must meet t he per f or mance r equi r ement s as ver i f i ed by t he t est s l i s t ed bel ow.

1. 2. 2. 1 Sur f ace Bur ni ng Char act er i st i cs

Conduct ASTM E84 t est on sampl es consi st i ng of base coat , r ei nf or ci ng f abr i c, and f i ni sh coat . Cur e f or 28 days. The f l ame spr ead i ndex must be 25 or l ess and t he smoke devel oped i ndex must be 450 or l ess.

1. 2. 2. 2 Radi ant Heat

The syst em must be t est ed i n accor dance wi t h NFPA 268 on bot h t he mi ni mum and maxi mum t hi ckness of i nsul at i on i nt ended f or use wi t h no i gni t i on dur i ng t he 20- mi nut e per i od.

1. 2. 2. 3 I mpact Resi st ance

a. Cl ass PB Syst ems: Hemi spher i cal Head Test ; 28 day cur ed speci men of PB EI FS i n accor dance wi t h ASTM E2486. The t est speci men must exhi bi t no br oken r ei nf or ci ng f abr i c per ASTM E2486 at an i mpact of __75___ in/lb.

b. I mpact Mass: Test 28 day cur ed speci men of PM EI FS i n accor dance wi t h ASTM E695. The t est speci men must exhi bi t no cr acki ng or dent i ng af t er t wel ve i mpact s by 30 l bs l ead shot mass f r om 6 i n t o 6 f t dr op hei ght s i n 6 i n i nt er val s.

1. 2. 3 Sub- Component Requi r ement s and Test s

Unl ess ot her wi se st at ed, t he t est speci men must consi st of r ei nf or ci ng mesh, base coat , and f i ni sh coat appl i ed i n accor dance wi t h manuf act ur er ' s pr i nt ed r ecommendat i ons t o t he i nsul at i on boar d t o be used on t he bui l di ng. For mi l dew r esi st ance, onl y t he f i ni sh coat i s appl i ed ont o gl ass s l i des f or t est i ng. These speci men must be sui t abl y s i zed f or t he appar at us used and be al l owed t o cur e f or a mi ni mum of 28 days pr i or t o testing.

1. 2. 3. 1 Abr asi on Resi st ance

Test i n accor dance wi t h ASTM D968, Met hod A. Test a mi ni mum of t wo speci mens. Af t er t est i ng, t he speci mens must show onl y ver y s l i ght smoot hi ng, wi t h no l oss of f i l m i nt egr i t y af t er 132 gal l ons of sand.

1. 2. 3. 2 Accel er at ed Weat her i ng

Test i n accor dance wi t h ASTM G153, Cycl e 1. Af t er 2000 hour s speci mens must exhi bi t no v i s i bl e cr acki ng, f l aki ng, peel i ng, bl i s t er i ng, yel l owi ng, f adi ng, or ot her such det er i or at i on.

Apr i l 2019 Page 4 SECTI ON 07 24 00

1. 2. 3. 3 Mi l dew Resi st ance

Test i n accor dance wi t h ASTM D3273. The speci men shal l consi st of t he f i ni sh coat mat er i al , appl i ed t o c l ean 3 i nch by 4 i nch gl ass s l i des and must be al l owed t o cur e f or 28 days. Af t er 28 days of exposur e, t he speci men must not show any gr owt h.

1. 2. 3. 4 Sal t Spr ay Resi st ance

Test i n accor dance wi t h ASTM B117. The speci men must be a mi ni mum of 4 i nch by 6 i nch and must be t est ed f or a mi ni mum of 300 hour s. Af t er exposur e, t he speci men must exhi bi t no obser vabl e det er i or at i on, such as chal k i ng, f adi ng , or r ust st ai ni ng.

1. 2. 3. 5 Wat er Resi st ance

Test i n accor dance wi t h ASTM D2247. The speci men must be a mi ni mum of 4 i nch by 6 i nch. Af t er 14 days, t he speci men must exhi bi t no cr acki ng, checki ng, cr azi ng, er osi on, bl i st er i ng, peel i ng, or del ami nat i on.

1. 2. 3. 6 Absorption-Freeze/Thaw

Cl ass PB syst ems must be t est ed i n accor dance wi t h ASTM E2570/ E2570M f or 60 cycl es of f r eezi ng and t hawi ng. Af t er t est i ng, t he speci men must exhi bi t no cr acki ng, checki ng, or spl i t t i ng, and negl i gi bl e wei ght gai n.

Cl ass PM syst ems must be t est ed i n accor dance wi t h ASTM C67 f or 50 cycl es of f r eezi ng and t hawi ng. Af t er t est i ng, t he speci mens must exhi bi t no cr acki ng or checki ng and have negl i gi bl e wei ght gai n.

1. 2. 3. 7 Sampl e Boar ds

Unl ess ot her wi se st at ed, pr ovi de sampl e EI FS Component 12 by 24 i nches, on sheat hi ng boar d, i ncl udi ng f i ni sh col or and t ext ur e, t ypi cal j oi nt s and seal ant . I f mor e t han one col or , f i ni sh, or pat t er n i s used, pr ovi de one sampl e f or each. The t est speci men must consi st of r ei nf or ci ng mesh, base coat , and f i ni sh coat appl i ed i n accor dance wi t h manuf act ur er ' s pr i nt ed r ecommendat i ons t o t he i nsul at i on boar d t o be used on t he bui l di ng.

1. 2. 4 Moi st ur e Anal ysi s

Per f or m a j ob speci f i c vapor t r ansmi ssi on anal ysi s based on pr oj ect speci f i c c l i mat e and speci f i ed wal l component s and mat er i al s. I ndi cat e t he t emper at ur es and r el at i ve humi di t i es f or t he i nsi de and out si de of t he bui l di ng; a compl et e l i s t i ng of t he bui l di ng component s, t hei r t hi ckness, t her mal r esi st ance and per meance, as wel l as bui l di ng l ocat i on and use.

I f a mat hemat i cal model was used f or t he anal ysi s, i ncl ude t he name of t he model and t he suppl i er / devel oper .

1. 3 SUBMITTALS

Gover nment appr oval i s r equi r ed f or submi t t al s wi t h a " G" desi gnat i on;

submi t t al s not havi ng a " G" desi gnat i on ar e f or Cont r act or Qual i t y Cont r ol appr oval . Submi t t he f ol l owi ng i n accor dance wi t h Sect i on 01 33 00

SUBMI TTAL PROCEDURES:

SD- 02 Shop Dr awi ngs

Shop Dr awi ngs; G

Apr i l 2019 Page 5 SECTI ON 07 24 00

Show wal l l ayout , const r uct i on and expansi on j oi nt s, decor at i ve gr ooves, l ayout of sheat hi ng boar d, t her mal i nsul at i on boar d, and r ei nf or ci ng mesh and st r i p r ei nf or ci ng f abr i c; j oi nt and f l ashi ng det ai l s; det ai l s at wal l penet r at i ons; t ypes and l ocat i on of f ast ener s; det ai l s at wi ndows and door s; and det ai l s at addi t i onal l ocat i ons as r equi r ed by t he cont r act document s.

SD- 03 Pr oduct Dat a

Sheat hi ng Boar d

Ther mal I nsul at i on

Adhesive

Mechani cal Fast ener s

Accessories

Base Coat

Por t l and Cement

Rei nf or ci ng Fabr i c

Fi ni sh Coat

Joi nt Seal ant

Seal ant Pr i mer

Bond Br eaker

Backer Rod

I nsul at i on Boar d

Warranty

I ncl ude j oi nt and ot her det ai l s, such as end condi t i ons, cor ner s, wi ndows, and par apet . I ncl ude shel f l i f e and r ecommended cl eani ng sol vent s i n dat a f or seal ant s. I ncl ude mat er i al saf et y dat a sheet s ( MSDS) f or al l component s of t he EI FS. The MSDS shal l be avai l abl e at t he j ob s i t e.

SD- 04 Sampl es

Sampl e Boar ds; G

Col or and Text ur e

Mock- up I nst al l at i on of EI FS; G

SD- 05 Desi gn Dat a

Wi nd Load Cal cul at i ons

Moi st ur e Anal ysi s Cal cul at i ons

Apr i l 2019 Page 6 SECTI ON 07 24 00

SD- 06 Test Repor t s

Abr asi on Resi st ance

Accel er at ed Weat her i ng

I mpact Resi st ance

Mi l dew Resi st ance

Sal t Spr ay Resi st ance

Wat er Vapor Tr ansmi ssi on

Absorption-Freeze-Thaw

Wal l Fi r e Test

Wat er Penet r at i on

Wat er Resi st ance

Ful l Scal e or I nt er medi at e Scal e Fi r e Test

Sur f ace Bur ni ng Char act er i st i cs

Radi ant Heat

Substrate

Wi nd Load

SD- 07 Cer t i f i cat es

Qual i f i cat i ons of EI FS Manuf act ur er

Qual i f i cat i on of EI FS I nst al l er

Qual i f i cat i on of Seal ant Appl i cat or

Cer t i f y t hat EI FS i nst al l er meet s r equi r ement s speci f i ed under par agr aph " Qual i f i cat i on of I nst al l er , " and t hat seal ant appl i cat or i s appr oved by t he EI FS Manuf act ur er .

Qual i f i cat i ons of Thi r d Par t y I nspect or

I nspect i on Check Li st ; G

Submi t f i l l ed- out i nspect i on check l i s t as r equi r ed i n par agr aph " Qual i t y Cont r ol , " cer t i f y i ng t hat t he i nst al l at i on of cr i t i cal i t ems meet s t he r equi r ement s of t hi s speci f i cat i on.

SD- 08 Manuf act ur er ' s I nst r uct i ons

Installation

Manuf act ur er ' s st andar d pr i nt ed i nst r uct i ons f or t he i nst al l at i on of t he EI FS. I ncl ude r equi r ement s f or condi t i on and pr epar at i on of subst r at e, i nst al l at i on of EI FS, and r equi r ement s f or seal ant s

Apr i l 2019 Page 7 SECTI ON 07 24 00 and seal i ng.

SD- 10 Oper at i on and Mai nt enance Dat a

EIFS

I ncl ude det ai l ed f i ni sh r epai r pr ocedur es and i nf or mat i on r egar di ng compat i bi l i t y of seal ant s wi t h base and f i ni sh coat i ngs.

1. 4 QUALI TY ASSURANCE

1. 4. 1 Qual i f i cat i ons of EI FS Manuf act ur er

The EI FS must be t he pr oduct of a manuf act ur er who has been i n t he pr act i ce of manuf act ur i ng and desi gni ng EI FS f or a per i od of not l ess t han 3 year s, and has been i nvol ved i n at l east f i ve pr oj ect s s i mi l ar t o t hi s pr oj ect i n s i ze, scope, and compl exi t y, i n t he same or a s i mi l ar c l i mat e as t hi s pr oj ect .

1. 4. 2 Qual i f i cat i on of EI FS I nst al l er

The EI FS I nst al l er must be t r ai ned by t he EI FS manuf act ur er t o per f or m t he i nst al l at i on of t he Syst em and must have successf ul l y i nst al l ed at l east f i ve pr oj ect s at or near t he s i ze and compl exi t y of t hi s pr oj ect . The cont r act or must empl oy qual i f i ed wor ker s t r ai ned and exper i enced i n i nst al l i ng t he manuf act ur er ' s EI FS.

1. 4. 3 Qual i f i cat i on of Seal ant Appl i cat or

The seal ant appl i cat or must be exper i enced and compet ent i n t he i nst al l at i on of hi gh per f or mance i ndust r i al and commer ci al seal ant s and must have successf ul l y i nst al l ed at l east f i ve pr oj ect s at or near t he s i ze and compl exi t y of t hi s pr oj ect .

1. 4. 4 Qual i f i cat i ons of Thi r d Par t y I nspect or

Submi t evi dence t hat t hi r d par t y i nspect or has cur r ent cer t i f i cat i on f r om t he Ext er i or Desi gn I nst i t ut e or equal i nspect or cer t i f i cat i on as i nspect or f or t he i nst al l at i on of EI FS.

1. 4. 5 I nsul at i on Boar d-

I nsul at i on Boar d must be appr oved and l abel ed under t hi r d par t y qual i t y pr ogr am as r equi r ed by appl i cabl e bui l di ng code.

1. 4. 6 Pr e- I nst al l at i on Conf er ence

Af t er appr oval of submi t t al s and bef or e commenci ng any wor k on t he EI FS, i ncl udi ng i nst al l at i on of any i nsul at i on, and associ at ed wor k, t he Cont r act i ng Of f i cer wi l l hol d a pr e- i nst al l at i on conf er ence t o r evi ew:

a. Dr awi ngs, speci f i cat i ons, and sampl es;

b. Pr ocedur e f or on si t e i nspect i on and accept ance of EI FS subst r at e and per t i nent det ai l s ( f or exampl e, mock- up i nst al l at i on) ;

c. Cont r act or ' s pl an f or coor di nat i on of wor k of t he var i ous t r ades

Apr i l 2019 Page 8 SECTI ON 07 24 00 i nvol ved i n pr ovi di ng EI F syst em and ot her component s;

d. I nspect i on pr ocedur es; and

e. Saf et y r equi r ement s.

Pr e- i nst al l at i on conf er ence must be at t ended by t he Cont r act or , EI FS Q. C.

Speci al i st ( EI FS I nspect or ) , and al l per sonnel di r ect l y r esponsi bl e f or i nst al l at i on of t he EI F syst em, i ncl udi ng seal ant appl i cat or , and per sonnel r esponsi bl e f or r el at ed wor k, such as f l ashi ng and sheet met al , wi ndows and door s, and a r epr esent at i ve of t he EI FS manuf act ur er . Bef or e begi nni ng EI FS wor k, t he cont r act or must conf i r m i n wr i t i ng t he r esol ut i on of conf l i c t s among t hose at t endi ng t he pr e- i nst al l at i on conf er ence.

1. 5 DELI VERY AND STORAGE

Del i ver mat er i al s t o j ob s i t e i n or i gi nal unopened packages, mar ked wi t h manuf act ur er ' s name, br and name, and descr i pt i on of cont ent s. St or e mat er i al s of f t he gr ound and i n accor dance wi t h t he manuf act ur er ' s r ecommendat i ons i n a c l ean, dr y, wel l - vent i l at ed ar ea. Pr ot ect st or ed mat er i al s f r om r ai n, sunl i ght , and excessi ve heat . Keep coat i ng mat er i al s whi ch woul d be damaged by f r eezi ng at a t emper at ur e not l ess t han 40 degr ees F. Do not expose i nsul at i on boar d t o f l ame or ot her i gni t i on sources.

1. 6 ENVI RONMENTAL CONDI TI ONS

a. Do not pr epar e mat er i al s or appl y EI FS dur i ng i ncl ement weat her unl ess appr opr i at e pr ot ect i on i s pr ovi ded. Pr ot ect i nst al l ed mat er i al s f r om i ncl ement weat her unt i l t hey ar e dr y.

b. Appl y seal ant s and wet mat er i al s onl y at ambi ent t emper at ur es of 40 degr ees F or above and r i s i ng, unl ess suppl ement al heat i s pr ovi ded.

The syst em must be pr ot ect ed f r om i ncl ement weat her and mai nt ai n t hi s t emper at ur e f or a mi ni mum of 24 hour s af t er i nst al l at i on.

c. Do not l eave i nsul at i on boar d exposed t o sunl i ght af t er i nst al l at i on.

1. 7 WARRANTY

Fur ni sh manuf act ur er ' s st andar d war r ant y f or t he EI FS. War r ant y must r un di r ect l y t o Gover nment and cover a per i od of not l ess t han 5 year s f r om dat e Gover nment accept ed t he wor k.

PART 2 PRODUCTS

2. 1 COMPATIBILITY

Pr ovi de al l mat er i al s compat i bl e wi t h each ot her and wi t h t he subst r at e, and as r ecommended by EI FS manuf act ur er .

2. 2 SHEATHI NG BOARD

2. 2. 1 Gl ass Mat Gypsum Sheat hi ng Boar d

a. Conf or m t o ASTM C1177/ C1177M; or .

b. ASTM C1278/ C1278M, Wat er Resi st ant Ext er i or Type onl y

Apr i l 2019 Page 9 SECTI ON 07 24 00

c. Fl exur al St r engt h __>80 l bf ___

d. Nai l Pul l Resi st ance: No l ess t han 120 l b when t est ed i n accor dance with ASTM C473.

2. 3 ADHESIVE

Manuf act ur er ' s st andar d pr oduct , i ncl udi ng pr i mer as r equi r ed, must be compat i bl e wi t h subst r at e and i nsul at i on boar d t o whi ch t he syst em i s applied.

2. 4 LATHI NG AND FURRI NG

Conf or m t o ASTM C847, 2. 5 l b/ sqyd, sel f - f ur r i ng, gal vani zed.

2. 5 MECHANI CAL FASTENERS

Cor r osi on r esi st ant and as appr oved by EI FS manuf act ur er . Sel ect f ast ener t ype and pat t er n based on appl i cabl e wi nd l oads and subst r at e i nt o whi ch f ast ener wi l l be at t ached, t o pr ovi de t he necessar y pul l - out , t ensi l e, and shear st r engt hs.

2. 6 THERMAL I NSULATI ON

2. 6. 1 Manuf act ur er ' s Recommendat i ons

Pr ovi de onl y t her mal i nsul at i on r ecommended by t he EI FS manuf act ur er f or t he t ype of appl i cat i on i nt ended.

2. 6. 2 I nsul at i on Boar d

I nsul at i on boar d must be st andar d pr oduct of manuf act ur er and must be compat i bl e wi t h ot her syst ems component s. Boar ds must be f act or y mar ked i ndi v i dual l y wi t h t he manuf act ur er ' s name or t r ade mar k, t he mat er i al speci f i cat i on number , t he R- val ue at 75 degr ee F, and t hi ckness. No l ayer of i nsul at i on shal l be l ess t han 3/ 4 i nch t hi ck. The maxi mum t hi ckness of al l l ayer s must not exceed 4 i nches. I nsul at i on Boar d must be cer t i f i ed as aged, i n bl ock f or m, pr i or t o cut t i ng and shi ppi ng, a mi ni mum of 6 weeks by ai r dr y i ng, or equi val ent .

a. Ther mal r esi st ance: As i ndi cat ed on dr awi ngs.

b. I nsul at i ng mat er i al : ASTM C578 Type I as r ecommended by t he EI FS manuf act ur er and t r eat ed t o be compat i bl e wi t h ot her EI FS component s.

Age i nsul at i on by ai r dr y i ng a mi ni mum of 6 weeks pr i or t o cut t i ng and shipping.

c. Dr ai nage: Pr ef or m channel s i nt o t he i nt er i or f ace of i nsul at i on boar d or pr ovi de pol ypr opyl ene dr ai nage l at h spacer t o pr ovi de wat er dr ai nage syst em.

2. 7 BASE COAT

Manuf act ur er ' s st andar d pr oduct and compat i bl e wi t h ot her syst ems components.

Apr i l 2019 Page 10 SECTI ON 07 24 00

2. 8 PORTLAND CEMENT

Conf or m t o ASTM C150/ C150M, Type I or I I as r equi r ed, f r esh and f r ee of l umps, and appr oved by t he syst ems manuf act ur er .

2. 9 REI NFORCI NG FABRI C

Rei nf or ci ng f abr i c mesh must be al kal i - r esi st ant , bal anced, open weave , gl ass f i ber f abr i c made f r om t wi st ed mul t i - end st r ands speci f i cal l y t r eat ed f or compat i bi l i t y wi t h t he ot her syst em mat er i al s, and compl y wi t h ASTM E2098/ E2098M and as r ecommended by EI FS manuf act ur er .

2. 10 FI NI SH COAT

Manuf act ur er ' s st andar d pr oduct conf or mi ng t o t he r equi r ement s i n t he par agr aph on Sub- Component Requi r ement s and Test s. For col or consi st ency, use mat er i al s f r om t he same bat ch or l ot number .

2. 11 SEALANT PRI MER

Non- st ai ni ng, qui ck- dr yi ng t ype r ecommended by seal ant manuf act ur er and EI FS manuf act ur er .

2. 12 ACCESSORIES

Conf or m t o r ecommendat i ons of EI FS manuf act ur er , i ncl udi ng t r i m, edgi ng, anchor s, and expansi on j oi nt s. Al l met al i t ems and f ast ener s t o be cor r osi on r esi st ant .

2. 13 JOI NT SEALANT

Non- st ai ni ng, qui ck- dr yi ng t ype meet i ng ASTM C920, as Type S or M, mi ni mum Gr ade NS, mi ni mum Cl ass 25 and compat i bl e wi t h t he f i ni sh syst em t ype and gr ade, and r ecommended by bot h t he seal ant manuf act ur er and EI FS manufacturer.

2. 14 BOND BREAKER

As r equi r ed by EI FS manuf act ur er and r ecommended by seal ant manuf act ur er and EI FS manuf act ur er .

2. 15 BACKER ROD

Cl osed cel l pol yet hyl ene f r ee f r om oi l or ot her st ai ni ng el ement s and as r ecommended by seal ant manuf act ur er and EI FS manuf act ur er . Do not use absor pt i ve mat er i al s as backer r od. The backer r od shoul d be si zed 25 per cent l ar ger t han t he wi dt h of t he j oi nt .

PART 3 EXECUTI ON

3. 1 EXAMINATION

Exami ne subst r at e and exi st i ng condi t i ons t o det er mi ne t hat t he EI FS can be i nst al l ed as r equi r ed by t he EI FS manuf act ur er and t hat al l wor k r el at ed t o t he EI FS i s pr oper l y coor di nat ed. Sur f ace must be sound and f r ee of oi l , l oose mat er i al s or pr ot r usi ons whi ch wi l l i nt er f er e wi t h t he syst em i nst al l at i on. I f def i c i enci es ar e f ound, not i f y t he Cont r act i ng Of f i cer and do not pr oceed wi t h i nst al l at i on unt i l t he def i c i enci es ar e

Apr i l 2019 Page 11 SECTI ON 07 24 00 cor r ect ed. The subst r at e must be pl ane, wi t h no devi at i on gr eat er t han 1/ 4 i nch when t est ed wi t h a 10 f oot st r ai ght edge. Det er mi ne f l at ness, pl umbness, and any ot her condi t i ons f or conf or mance t o manuf act ur er ' s instructions.

3. 2 SURFACE PREPARATI ON

Pr epar e exi st i ng sur f aces f or appl i cat i on of t he EI FS t o meet f l at ness t ol er ances and sur f ace pr epar at i on accor di ng t o manuf act ur er ' s i nst al l at i on i nst r uct i ons but pr ovi de a f l at ness of not mor e t hat 1/ 4 i nch i n 10 f eet . Pr ovi de cl ean sur f aces f r ee of oi l and l oose mat er i al wi t hout pr ot r usi ons adver sel y af f ect i ng t he i nst al l at i on of t he i nsul at i on boar d.

For adhesi vel y at t ached EI FS, exi st i ng det er i or at ed pai nt must be r emoved. Due t o subst r at e condi t i ons or as r ecommended by t he syst em manuf act ur er , a pr i mer may be r equi r ed. Appl y t he pr i mer t o exi st i ng sur f aces as r ecommended by t he manuf act ur er . Use maski ng t ape t o pr ot ect ar eas adj acent t o t he EI FS t o pr event base or f i ni sh coat t o be appl i ed t o ar eas not i nt ended t o be cover ed wi t h t he EI FS. The cont r act or must not pr oceed wi t h t he i nst al l at i on unt i l al l not ed def i c i enci es of t he subst r at e ar e cor r ect ed.

3. 3 INSTALLATION

I nst al l EI FS as i ndi cat ed, compl y wi t h manuf act ur er ' s i nst r uct i ons except as ot her wi se speci f i ed, and i n accor dance wi t h t he shop dr awi ngs. EI FS must be i nst al l ed onl y by an appl i cat or t r ai ned by t he EI FS manuf act ur er .

Speci f i cal l y, i ncl ude al l manuf act ur er r ecommended pr ovi s i ons r egar di ng f l ashi ng and t r eat ment of wal l penet r at i ons. Any mat er i al s t hat show vi sual evi dence of bi ol ogi cal gr owt h due t o t he pr esence of moi st ur e must not be i nst al l ed on t he bui l di ng pr oj ect .

3. 3. 1 Sheat hi ng Boar d

Edges and ends of boar ds must be but t ed snugl y wi t h ver t i cal j oi nt s st agger ed t o pr ovi de f ul l and even suppor t f or t he i nsul at i on. Do not al i gn sheat hi ng boar d j oi nt s wi t h wal l openi ngs. Pr ovi de suppor t at bot h ver t i cal and hor i zont al j oi nt s. At t ach sheat hi ng boar d t o met al st uds wi t h sel f - t appi ng dr ywal l scr ews . Pl ace f ast ener s suf f i c i ent l y c l ose t o suppor t i mposed l oads, but not mor e t han:

a. Maxi mum of 8 i nches apar t on each suppor t i ng st ud

Space f ast ener s mor e cl osel y when r equi r ed f or negat i ve wi nd l oad resistance.

3. 3. 2 I nsul at i on Boar d

Unl ess ot her wi se speci f i ed by t he syst em manuf act ur er , pl ace t he l ong edge hor i zont al l y f r om l evel base l i ne. St agger ver t i cal j oi nt s and i nt er l ock at cor ner s. But t j oi nt s t i ght l y. Pr ovi de f l ush sur f aces at j oi nt s.

Of f set i nsul at i on boar d j oi nt s f r om j oi nt s i n sheat hi ng by at l east 8 i nches. Al i gn dr ai nage channel s of i nt egr al dr ai nage syst em or pr ovi de pol ypr opyl ene dr ai nage l at h space t o pr ovi de a pat h f or any wat er weeped f r om behi nd t he i nsul at i on t o escape wal l const r uct i on. Use L- shaped i nsul at i on boar d pi eces at cor ner s of openi ngs. Joi nt s of i nsul at i on must be but t ed t i ght l y. Sur f aces of adj acent i nsul at i on boar ds must be f l ush at j oi nt s. Gaps gr eat er t han 1/ 16 i nch bet ween t he i nsul at i on boar ds must

Apr i l 2019 Page 12 SECTI ON 07 24 00 be f i l l ed wi t h s l i ver s of i nsul at i on. Uneven boar d sur f aces wi t h i r r egul ar i t i es pr oj ect i ng mor e t han 1/ 16 i nch must be r asped i n accor dance wi t h t he manuf act ur er ' s i nst r uct i ons t o pr oduce an even sur f ace. At t ach i nsul at i on boar d as r ecommended by manuf act ur er . The adher ed i nsul at i on boar d must be al l owed t o r emai n undi st ur bed f or 24 hour s pr i or t o pr oceedi ng wi t h t he i nst al l at i on of t he base coat / r ei nf or ci ng mesh, or l onger i f necessar y f or t he adhesi ve t o dr y. However , do not l eave i nsul at i on boar d exposed l onger t han r ecommended by i nsul at i on manufacturer.

3. 3. 2. 1 Adhesi vel y Fast ened I nsul at i on Boar ds

Appl y i nsul at i on boar d usi ng adhesi ve spr ead wi t h a not ched t r owel t o t he back of t he i nsul at i on boar ds i n accor dance wi t h t he manuf act ur er ’ s instructions.

3. 3. 3 Base Coat and Rei nf or ci ng Fabr i c Mesh,

3. 3. 3. 1 Cl ass PB Syst ems

Al l ow t he adher ed i nsul at i on boar d t o dr y f or 24 hour s, or l onger i f necessar y, pr i or t o pr oceedi ng wi t h t he i nst al l at i on of t he base coat / r ei nf or ci ng f abr i c mesh. I nst al l r ei nf or ci ng f abr i c i n accor dance wi t h manuf act ur er ' s i nst r uct i ons. Mi x base coat i n accor dance wi t h t he manuf act ur er ' s i nst r uct i ons and appl y t o i nsul at ed wal l sur f aces t o t he t hi ckness speci f i ed by t he syst em manuf act ur er and pr ovi de any ot her r ei nf or cement r ecommended by EI FS manuf act ur er . Tr owel t he r ei nf or ci ng f abr i c mesh i nt o t he wet base coat mat er i al . Ful l y embed t he mesh i n t he base coat . When pr oper l y wor ked- i n, t he pat t er n of t he r ei nf or ci ng f abr i c mesh must not be vi s i bl e. Pr ovi de di agonal r ei nf or cement at openi ng cor ner s. Back- wr ap or edge wr ap al l t er mi nat i ons of t he EI FS. Over l ap t he r ei nf or ci ng f abr i c mesh a mi ni mum of 2. 5 i nches on pr evi ousl y i nst al l ed mesh, or but t ed, i n accor dance wi t h t he manuf act ur er ’ s i nst r uct i ons.

3. 3. 3. 2

3. 3. 4 Fi ni sh Coat

The base coat / r ei nf or ci ng mesh must be al l owed t o dr y a mi ni mum of 24 hour s pr i or t o appl i cat i on of t he f i ni sh coat . Sur f ace i r r egul ar i t i es i n t he base coat , such as t r owel mar ks, boar d l i nes, r ei nf or ci ng mesh l aps, et c. , must be cor r ect ed pr i or t o t he appl i cat i on of t he f i ni sh coat .

Appl y and l evel f i ni sh coat i n one oper at i on. Obt ai n f i nal t ext ur e by t r owel s, f l oat s, or by spr ay appl i cat i on as necessar y t o achi eve t he r equi r ed f i ni sh mat chi ng appr oved mock- up i nst al l at i on. Appl y t he f i ni sh coat t o t he dr y base coat mai nt ai ni ng a wet edge at al l t i mes t o obt ai n a uni f or m appear ance. The t hi ckness of t he f i ni sh coat must be i n accor dance wi t h t he syst em manuf act ur er ’ s cur r ent publ i shed i nst r uct i ons.

Appl y f i ni sh coat so t hat i t does not cover sur f aces t o whi ch j oi nt seal ant s ar e t o be appl i ed.

3. 4 JOI NT SEALI NG

Seal EI FS at openi ngs as r ecommended by t he syst em manuf act ur er . Appl y seal ant onl y t o t he base coat or base coat wi t h EI FS Manuf act ur er ' s col or coat i ng. Do not appl y seal ant t o t he f i ni sh coat .

Apr i l 2019 Page 13 SECTI ON 07 24 00

3. 4. 1 Sur f ace Pr epar at i on, Backer Rod, and Pr i mer

I mmedi at el y pr i or t o appl i cat i on, r emove l oose mat t er f r om j oi nt . Ensur e t hat j oi nt i s dr y and f r ee of f i ni sh coat , or ot her f or ei gn mat t er .

I nst al l backer r od. Appl y pr i mer as r equi r ed by seal ant and EI FS manuf act ur er . Check t hat j oi nt wi dt h i s as shown on dr awi ngs but i n no case shal l i t be l ess t han 0. 5 i nch f or per i met er seal s and 0. 75 i nch f or expansi on j oi nt s. The wi dt h must not be l ess t han 4 t i mes t he ant i c i pat ed movement . Check seal ant manuf act ur er ' s r ecommendat i ons r egar di ng pr oper wi dt h t o dept h r at i o.

3. 4. 2 Sealant

Do not appl y seal ant unt i l al l EI FS coat i ngs ar e f ul l y dr y. Appl y seal ant i n accor dance wi t h seal ant manuf act ur er ' s i nst r uct i ons wi t h gun havi ng nozzl e t hat f i t s j oi nt wi dt h. Do not use seal ant t hat has exceeded shel f l i f e or cannot be di schar ged i n a cont i nuous f l ow. Compl et el y f i l l t he j oi nt sol i dl y wi t h seal ant wi t hout ai r pocket s so t hat f ul l cont act i s made wi t h bot h s i des of t he j oi nt . Tool seal ant wi t h a r ound i nst r ument t hat pr ovi des a concave pr of i l e and a uni f or ml y smoot h and wr i nkl e f r ee seal ant sur f ace. Do not wet t ool t he j oi nt wi t h soap, wat er , or any ot her l i qui d t ool i ng ai d. Dur i ng i ncl ement weat her , pr ot ect t he j oi nt s unt i l seal ant appl i cat i on. Use par t i cul ar caut i on i n seal i ng j oi nt s bet ween wi ndow and door f r ames and t he EI FS wal l and at al l ot her wal l penet r at i ons. Cl ean al l sur f aces t o r emove excess seal ant .

3. 5 FI ELD QUALI TY CONTROL

Thr oughout t he i nst al l at i on, t he cont r act or must est abl i sh and mai nt ai n an i nspect i on pr ocedur e t o assur e compl i ance of t he i nst al l ed EI FS wi t h cont r act r equi r ement s. Wor k not i n compl i ance must be r emoved and r epl aced or cor r ect ed i n an appr oved manner . The i nspect i on pr ocedur es, f r om accept ance of del i ver i es t hr ough i nst al l at i on of seal ant s and f i nal accept ance must be per f or med by qual i f i ed i nspect or t r ai ned by t he manuf act ur er . No wor k on t he EI FS i s al l owed unl ess t he i nspect or i s pr esent at t he j ob s i t e.

3. 5. 1 I nspect i on Check Li st

Dur i ng t he i nst al l at i on and at t he compl et i on of i nst al l at i on, per f or m i nspect i ons cover i ng at t he mi ni mum al l appl i cabl e i t ems enumer at ed on t he at t ached check l i s t . The i nspect or must i ni t i al and dat e al l appl i cabl e i t ems, s i gn t he check l i s t , and submi t i t t o t he Cont r act i ng Of f i cer at t he compl et i on of t he EI FS er ect i on.

CHECK LI ST

Item Description Appr'd/Date_

a. Mat er i al s ar e handl ed and st or ed cor r ect l y. _ ____

b. Envi r onment al condi t i ons ar e wi t hi n speci f i ed l i mi t s, _ _____ i ncl udi ng t emper at ur e not bel ow 4 degr ees C ( 40 degr ees F) , and t he wor k i s pr ot ect ed f r om t he el ement s as r equi r ed.

c. Pr epar at i on and i nst al l at i on i s per f or med by qual i f i ed _ _____ per sonnel usi ng t he cor r ect t ool s.

Apr i l 2019 Page 14 SECTI ON 07 24 00

CHECK LI ST

Item Description Appr'd/Date_

d. Adj acent ar eas t o whi ch EI FS i s not t o be appl i ed _ ____ ( such as on wi ndow and door f r ames) ar e pr ot ect ed wi t h maski ng t ape, pl ast i c f i l ms, dr op cl ot hs, et c.

t o pr event acci dent al appl i cat i on of EI FS mat er i al s.

e. Cont r ol , expansi on and aest het i c j oi nt s ar e i nst al l ed as _ ____ i ndi cat ed or r ecommended. Accessor i es ar e pr oper l y i nst al l ed.

f . Subst r at e i s i n- pl ane, pr oper l y at t ached, c l ean, dr y, and _ ____ f r ee of cont ami nant s. Concr et e subst r at e i s f r ee of ef f l or escence.

g. Mat er i al s ar e mi xed t hor oughl y and i n pr oper pr opor t i ons. _ ____

h. Adhesi ve i s appl i ed i n suf f i c i ent quant i t y wi t h pr oper - _ ____ s i ze not ched t r owel .

i . Mechani cal at t achment s have pr oper spaci ng, l ayout and _ ____ f ast ener dept h.

j . I nsul at i on boar ds ar e t i ght l y abut t ed, i n r unni ng bond _ ____ pat t er n, wi t h j oi nt s st agger ed wi t h t he sheat hi ng, boar d cor ner s i nt er l ocked, L- shaped boar ds ar ound openi ngs, edges f r ee of adhesi ve, and pr ovi s i on f or j oi nt s. Gaps ar e f i l l ed and sur f aces r asped.

k. I nsul at i on adhesi ve must be al l owed t o dr y ( a mi ni mum of _ ____ 24- hour s) pr i or t o t he appl i cat i on of t he base coat .

l . Rei nf or ci ng f abr i c mesh i s pr oper l y back- wr apped at _ ____ t er mi nat i ons.

m. Rei nf or ci ng f abr i c mesh i s f ul l y embedded and pr oper l y _ ____ pl aced. Cor ner s ar e r ei nf or ced. Openi ngs ar e di agonal l y r ei nf or ced. Mesh over l aps mi ni mum 65 mm ( 2- 1/ 2 i nches) .

n. Base coat t hi ckness i s wi t hi n speci f i ed l i mi t s. _ ____

o. The base coat / r ei nf or ci ng f abr i c mesh must be al l owed t o _ ____ dr y ( a mi ni mum of 24- hour s) pr i or t o t he appl i cat i on of t he f i ni sh coat .

p. Fi ni sh coat i s appl i ed wi t h suf f i c i ent number of _ ____ per sonnel and st opped at sui t abl e poi nt s. Fl oat s and met hods of t ext ur i ng ar e uni f or m.

q. Al l f l ashi ngs ar e pr oper l y i nst al l ed. _ ____ r . Al l j oi nt s ar e pr oper l y seal ed i n t hei r ent i r e l engt h _ ____ at t i me and under envi r onment al condi t i ons as speci f i ed by t he manuf act ur er .

Apr i l 2019 Page 15 SECTI ON 07 24 00

CHECK LI ST

Item Description Appr'd/Date_

s. Al l scaf f ol di ng, equi pment , mat er i al s, debr i s _ ____ and t empor ar y pr ot ect i on ar e r emoved f r om si t e upon compl et i on.

Name of I nspect or : ________________ Si gned: __________________ Date:________

3. 6 CLEANUP

Upon compl et i on, r emove al l scaf f ol di ng, equi pment , mat er i al s and debr i s f r om si t e. Remove al l t empor ar y pr ot ect i on i nst al l ed t o f aci l i t at e i nst al l at i on of EI FS.

- - End of Sect i on - -