DD2794 COST AND SOFTWARE DATA REPORTING PLAN.xls

DoD Form XLS spreadsheet 201 KB Posted

Attached to
KC-135 Center Console Refresh (CCR)
Solicitation number
FA810523RB004
Issued by

About this file

This document is a Cost and Software Data Reporting (CSDR) plan for the KC-135 Center Console Refresh solicitation from the Air Force Materiel Command Lifecycle Management Center. Key details include:

  • The solicitation is for aircraft systems integration, assembly, test and checkout, airframe components, propulsion, vehicle subsystems including electrical and fuel, avionics, and program management.

  • The contractor must report costs for all contract line items, including over and above work, long lead materials, and foreign military sales. Costs should not be omitted based on contract structure and must be tagged to discrete delivery orders.

  • Technical data, quantity data, and cost reports are due initially by June 2024 and annually through final contract completion reports due by June 2033.

  • Technical parameters include new design percentages, volumes, weights, connection counts, material mixes, and computing specifications for hardware and software at different work breakdown structure levels.

View the file

Other versions and copies of DD Form 2794

File Revision Posted Attached to
9. DD2794_Cost and Software Reporting Plan_AF-24-M-C1_20240510.xls May 10, 2024 Space Development Agency (SDA) Advanced Fire Control Ground Infrastructure (AFCGI)
Attachment_21_DD2794 Avionics CSDR Plan_21 Nov 2022.xlsx Nov 21, 2022 T-6A Avionics Replacement Program
Attachment 0005 DD2794 Sustainment CSDR Standard Plan 23-R-0075 PRID 2022H018.xlsx 2022 Fuel Tank Combo-Pack for the Apache AH-64
Attachment 9 - RMWT LEO GEPs DD2794 CSDR Plan.xlsx Revision not stated Request for Proposal (RFP) - Resilient Missile Warning Tracking (RMWT) Low Earth Orbit (LEO) Ground Entry Points (GEPs)
DHMS Deployment DD2794 CSDR Plan.xlsx Revision not stated Program Executive Office (PEO) Defense Healthcare Management Systems (DHMS) Deployment Solutions
DRAFT SOW Appendix D DD2794_KC-135 CCR.pdf Revision not stated KC-135 Center Console Refresh (CCR) Revision 2
Attachment 0004 - DD2794 CSDR.xls Revision not stated Head, Rotary Wing for the Apache AH-64
Attachment 0005 - DD2794 Sustainment CSDR Standard Plan 23-B-0037.cplan.XML_Finalized.pdf Revision not stated Head, Rotary Wing for the Apache AH-64
ATTACHMENT 8 DD 2794 IDIQ CSDR Plan v2.xlsx Revision not stated RFP - Space Test Experiments Platform (STEP) 2. 0
J-16 DD 2794 CSDR Plan for BVY-1 ISIS TI-26-28-30 (2023-08-04) FINALIZED MEMO.pdf Revision not stated BVY-1 ISIS TI-26 TI-28 TI-30 Solicitation
DRAFT CSDR Plan F100 RDN DD Form 2794.xls Revision not stated Regional Depot Network (RDN) Re-manufacture of F100-PW-220/-220E/-229/-229EEP Series Engine Modules
TMIP-J Attachment 7 DD2794 CSDR Standard Plan.xls Revision not stated Theater Medical Information Program Joint (TMIP-J) Sustainment
Attachment 15 - DD2794 MK41 VLS Launcher.xls Revision not stated FY 22-27 MK 41 Vertical Launching System (VLS) Production
Attachment_0001_DD2794_CSDR_Plan.xls Revision not stated F-16 Brake Control System Redesign (BCSR)
Exhibit A1 A004 DD Form 2794 DISC_CSDR_Plan.xls Revision not stated Directorate for Test Resources (DTR) Instrumentation Support Contract (DISC) Draft RFP
N0010419RK082 Attach 1 - CSDR Co-Plan, DD Form 2794.pdf Revision not stated JSF C/P Cartridges IDIQ
APPENDIX_C_CSDR__DD2794_Attachment.xlsx Revision not stated KC-135 Aero-I SATCOM Replacement
Attachment_J-5_DD_2794_Co-Plan_for_MMM-_Procurement.xlsx Revision not stated Multifunction Modular Mast
Attachment_J-6_-_DD_2794_Co-Plan_for_MMM-_Development.xlsx Revision not stated Multifunction Modular Mast
ATT 54 CSDR DD 2794.xls Revision not stated T-34/T-44/T-6 Aircraft Maintenance and Contractor Logistics Support
Show all 20

Who attaches DD Form 2794

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DD Form 2794, Pg 1 (METADATA)

COST AND SOFTWARE DATA REPORTING PLANOMB No. 0704-0188
The public reporting burden for this collection of information is estimated to average 8 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number.

PLEASE DO NOT RETURN YOUR COMPLETED FORM TO THE ABOVE ORGANIZATION.

1a. PROGRAM NAME
KC-135 Center Console Refresh (CCR)
1b. PHASE/MILESTONE (check all that apply)
Pre-A
A
XB
C-LRIP
C-FRP
O&S
1c. PRIME MISSION PRODUCT
Aircraft
1d. ACQUISITION CATEGORY (ACAT)
Pre-ACAT
ACAT I (MDAP)
ACAT IA (MAIS)
ACAT II
XACAT III
Other
2. COMMODITY TYPE
Aircraft System
3. PLAN ITERATION TYPE
XINITIAL
REVISION
4. CURRENT SUBMISSION DATE (YYYYMMDD)
5. LAST APPROVED PLAN DATE (YYYYMMDD)
6a. GOVERNMENT PLAN POINT OF CONTACT (POC) NAME (Last, First, M.)
Shotnokoff, Erica D.
6b. ADDRESS (Include ZIP Code)
3001 Staff Drive STE 2AE1-88G, Tinker AFB, OK 73145
6c. TELEPHONE NUMBER (Include Area Code)
256-285-0095
6d. E-MAIL ADDRESS
erica.shotnokoff.3@us.af.mil
7. PLAN TYPE
GOVERNMENT
XCONTRACT (PRIME)
CONTRACT (SUB)
8. PLAN GOVERNMENT PREPARING ORGANIZATION
AFLCMC/WLTMA
9a. CONTRACTOR NAME/ADDRESS
i. REPORTING ORGANIZATION NAME
TBD
ii. DIVISION NAME
iii. LOCATION
iv. CONTRACTOR BUSINESS DATA REPORT (CBDR 1921-3) REQUIREMENT:
XCBDR REQUIRED FOR THIS ORGANIZATION
9b. CONTRACT NUMBER (List all that apply, separated by commas)
TBD
9c. APPROPRIATION (check all that apply)
XRDT&E
XPROCUREMENT
O&M
FMS
WCF
OTHER
10a. APPROVED PLAN NUMBER
AF-23-C1
10b. APPROVED PLAN REVISION NUMBER
10c. APPROVED PLAN REQUIREMENTS
XAT COMPLETION COSTS FOR STANDARD FUNCTIONAL CATEGORIES (FlexFile or Legacy)
XAT COMPLETION COSTS FOR RECURRING/NONRECURRING (FlexFile only)
XTECHNICAL DATA REQUIRED
10d. COST REPORT TYPE
XFLEXFILE
LEGACY DD 1921 SERIES
DRAFT DD FORM 2794 (PAGE 1), METADATA, JANUARY 2019PREVIOUS EDITION IS OBSOLETE

erica.shotnokoff.3@us.af.mil

DD Form 2794, Pg 2 (REPORTING)

COST AND SOFTWARE DATA REPORTING PLANCOST, SOFTWARE, & TECHNICAL DATA REPORTING/EARNED VALUE MANAGEMENT CO-PLAN
11. WORK BREAKDOWN STRUCTURE (WBS)12. COST13. TECHNICAL DATA
a. WBS
CODEb. WBS
LEVELc. WBS ELEMENT NAMEa. ACTUALS TO
DATE (ATD)b. LEGACY
1921-1c. LEGACY
1921-2d. LEGACY
1921-5e. EAC/FAC
(See item 10d)a. QUANTITYb. SRDR
FORMATSc.

MAINT. &

REPAIR

PARTS

i. QUANTITY
DATAii. GFE

QUANTITY

1.01Aircraft SystemX
1.12Aircraft System, Integration, Assembly, Test, and CheckoutX
1.22Air VehicleX
1.2.13Air Vehicle Integration, Assembly, Test, and CheckoutX
1.2.1.14Integration and AssemblyXXX
1.2.1.24Test and CheckoutXXX
1.2.1.34Rate ToolingXXX
1.2.23AirframeX
1.2.2.14Airframe Integration, Assembly, Test, and CheckoutX
1.2.2.24FuselageX
1.2.2.2.15Forward FuselageXXX
1.2.2.2.25Center FuselageXXX
1.2.2.2.35Aft FuselageXXX
1.2.2.2.45Other Fuselage (specify)XXX
1.2.2.34WingXXX
1.2.2.44EmpennageXXX
1.2.2.54NacelleXXX
1.2.2.64Other Airframe Components 1..n (Specify)XXX
1.2.33PropulsionXX
1.2.43Vehicle SubsystemsX
1.2.4.14Vehicle Subsystem Integration, Assembly, Test, and CheckoutXXX
1.2.4.24Flight Control SubsystemX
1.2.4.2.15Flight Control Hardware Integration, Assembly, Test and CheckoutXXX
1.2.4.2.25Flight Control Hardware 1..n (Specify)XXX
1.2.4.2.35Flight Control Software Release 1..n (Specify)XXX
1.2.4.34Auxiliary Power SubsystemX
1.2.4.3.15Auxiliary Power Hardware Integration, Assembly, Test, and CheckoutXXX
1.2.4.3.25Auxiliary Power Hardware 1..n (Specify)XXX
1.2.4.3.35Auxiliary Power Software Release 1..n (Specify)XXX
1.2.4.44Hydraulic SubsystemXX
1.2.4.54Electrical SubsystemX
1.2.4.5.15Electrical Hardware Integration, Assembly, Test, and CheckoutXXX
1.2.4.5.25Electrical Hardware 1..n (Specify)XXX
1.2.4.5.35Electrical Software Release 1..n (Specify)XXX
1.2.4.64Crew Station SubsystemX
1.2.4.6.15Crew Station Hardware Integration, Assembly, Test, and CheckoutXXX
1.2.4.6.25Canopy /Cockpit SystemXXX
1.2.4.6.35Mechanical SystemXXX
1.2.4.6.45Fire Protection SystemXXX
1.2.4.6.55Crew Station Software Release 1..n (Specify)XXX
1.2.4.74Environmental Control SubsystemXX
1.2.4.84Fuel SubsystemX
1.2.4.8.15Fuel Hardware Integration, Assembly, Test, and CheckoutXXX
1.2.4.8.25Fuel Subsystem Hardware 1..n (Specify)XXX
1.2.4.8.35Fuel Subsystem Software Release 1..n (Specify)XXX
1.2.4.94Landing GearXX
1.2.4.104Rotor GroupXX
1.2.4.114Drive GroupXX
1.2.4.124Vehicle Subsystem Software Release 1..n (Specify)XXX
1.2.4.134Other Subsystems 1...n (Specify)X
1.2.4.13.15Other Vehicle Subsystem Hardware Integration, Assembly, Test, and CheckoutXXX
1.2.4.13.25Other Vehicle Subsystem Hardware 1..n (Specify)XXX
1.2.4.13.35Other Vehicle Subsystems Software Release 1..n (Specify)XXX
1.2.53AvionicsX
1.2.5.14Avionics Integration, Assembly, Test And CheckoutXXX
1.2.5.24Communication/IdentificationX
1.2.5.2.15Communication/Identification Hardware Integration, Assembly, Test, and CheckoutXXX
1.2.5.2.25Communication/Identification Hardware 1..n (Specify)XXX
1.2.5.2.35Communication/Identification Software Release 1..n (Specify)XXX
1.2.5.34Navigation/GuidanceX
1.2.5.3.15Navigation/Guidance Hardware Integration, Assembly, Test, and CheckoutXXX
1.2.5.3.25Navigation/Guidance Hardware 1..n (Specify)XXX
1.2.5.3.35Navigation/Guidance Software Release 1..n (Specify)XXX
1.2.5.44Mission Computer/ProcessingX
1.2.5.4.15Mission Computer/Processing Hardware Integration, Assembly, Test, and CheckoutXXX
1.2.5.4.25Mission Computer/Processing Hardware 1..n (Specify)XXX
1.2.5.4.35Mission Computer/Processing Software Release 1..n (Specify)XXX
1.2.5.54Fire ControlXX
1.2.5.64Data Display & ControlX
1.2.5.6.15Data Display and Control Hardware Integration, Assembly, Test And CheckoutXXX
1.2.5.6.25Data Display & Control Hardware 1..n (Specify)XXX
1.2.5.6.35Data Display & Control Software Release 1..n (Specify)XXX
1.2.5.74SurvivabilityX
1.2.5.7.15Survivability Hardware Integration, Assembly, Test, and CheckoutXXX
1.2.5.7.25Survivability Hardware 1..n (Specify)XXX
1.2.5.7.35Survivability Software Release 1..n (Specify)XXX
1.2.5.84ReconnaissanceXX
1.2.5.94Electronic WarfareXX
1.2.5.104Automatic Flight ControlXX
1.2.5.114Health Monitoring SystemX
1.2.5.11.15Health Monitoring Hardware Integration, Assembly, Test, and CheckoutXXX
1.2.5.11.25Health Monitoring System Hardware 1..n (Specify)XXX
1.2.5.11.35Health Monitoring System Software Release 1..n (Specify)XXX
1.2.5.124Stores ManagementXX
1.2.5.134Avionics Software Release 1..n (Specify)XXX
1.2.5.144Other Avionics Subsystems 1...n (Specify)X
1.2.5.14.15Other Avionics Subsystem Hardware Integration, Assembly, Test, and CheckoutXXX
1.2.5.14.25Other Avionics Subsystem Hardware 1..n (Specify)XXX
1.2.5.14.35Other Avionics Subsystem Software Release 1..n (Specify)XXX
1.2.63Armament/Weapons DeliveryXX
1.2.73Auxiliary EquipmentXXX
1.2.83Furnishings and EquipmentXXX
1.2.93Air Vehicle Software Release 1..n (Specify)XXX
1.2.103Other Air Vehicle 1...n (Specify)XXX
1.32Payload/Mission SystemXX
1.42Ground/Host SegmentXX
1.52Aircraft System Software Release 1...n (Specify)XXX
1.62Systems Engineering
1.6.13Software Systems EngineeringXXX
1.6.23Integrated Logistics Support (ILS) Systems EngineeringXX
1.6.33Cybersecurity Systems EngineeringXX
1.6.43Core Systems EngineeringXX
1.6.53Other Systems Engineering 1...n (Specify)XX
1.72Program Management
1.7.13Software Program ManagementXXX
1.7.23Integrated Logistics Support (ILS) Program ManagementXX
1.7.33Cybersecurity ManagementXX
1.7.43Core Program ManagementXX
1.7.53Other Program Management 1...n (Specify)XX
1.82System Test and Evaluation
1.8.13Development Test and Evaluation
1.8.1.14System Acceptance Test (SAT)XX
1.8.1.24Wind TunnelXX
1.8.1.34Structural TestXX
1.8.1.44Flight TestXX
1.8.1.54Ground TestXX
1.8.1.64Cybersecurity Test and Evaluation
1.8.1.6.15Cybersecurity Development TestXX
1.8.1.6.25Cybersecurity Operational TestXX
1.8.1.6.35Cybersecurity Other (1...n)XX
1.8.1.74Service/Agency DT&E 1...n (Specify) (GOV ONLY)XX
1.8.1.84Other DT&E Tests 1...n (Specify)XX
1.8.23Operational Test and Evaluation
1.8.2.14Limited User Evaluation (LUE/M-LUT/FUE)XX
1.8.2.24Interoperability Testing (IOP with IA/OT&E)XX
1.8.2.34Flight TestsXX
1.8.2.44Ground TestsXX
1.8.2.54Cybersecurity Test and Evaluation
1.8.2.5.15Cybersecurity Development TestXX
1.8.2.5.25Cybersecurity Operational TestXX
1.8.2.5.35Cybersecurity Other (1...n)XX
1.8.2.64Other OT&E Tests 1...n (Specify)XX
1.8.33Live Fire Test and EvaluationXX
1.8.43Mock-ups/System Integration Labs (SILs)XX
1.8.53Test and Evaluation SupportXX
1.8.63Test Facilities
1.8.6.14Commercial (GOV ONLY)XX
1.8.6.24Government (Pay-as-You-Go) (GOV ONLY)XX
1.92Training
1.9.13EquipmentX
1.9.1.14Operator Instructional EquipmentXXX
1.9.1.24Maintainer Instructional EquipmentXXX
1.9.23Services
1.9.2.14Operator Instructional Services
1.9.2.1.15Development of Training MaterialsXX
1.9.2.1.25Provide TrainingXX
1.9.2.24Maintainer Instructional Services
1.9.2.2.15Development of Training MaterialsXX
1.9.2.2.25Provide TrainingXX
1.9.33FacilitiesXX
1.9.43Training Software 1...n (Specify)XX
1.102Data
1.10.13Data Deliverables 1...n (Specify)XX
1.10.23Data RepositoryXX
1.10.33Data Rights 1...n (Specify)XX
1.112Peculiar Support EquipmentX
1.11.13Test and Measurement EquipmentXX
1.11.23Support and Handling EquipmentXX
1.122Common Support EquipmentX
1.12.13Test and Measurement EquipmentXX
1.12.23Support and Handling EquipmentXX
1.132Operational/Site Activation by Site 1...n (Specify)
1.13.13System Assembly, Installation and Checkout on Site
1.13.1.14Deployment HW and SWXX
1.13.1.24Site ActivationXX
1.13.23Contractor Technical SupportXX
1.13.33Site ConstructionXX
1.13.43Site/Ship/Vehicle ConversionXX
1.13.53Interim Contractor Support (ICS)XX
1.142Contractor Logistics Support (CLS)XX
1.152Industrial FacilitiesX
1.162Initial Spares and Repair PartsX
1.16.13PMP Spare and Repair 1...n (Specify)XXX
1.16.23Support Equipment Spare and Repair PartsXXX
1.16.33Training Equipment Spare and Repair PartsXXX
1.16.43Packaging, Handling, Storage, and Transportation (PHS&T)X
1.16.4.14ContainersXXX
1.16.4.24TransportationXXX
Subtotal CostXX
Reporting Contractor G&AXX
Reporting Contractor Undistributed BudgetXX
Reporting Contractor Management ReserveXX
Reporting Contractor FCCMXX
Total CostXX
Reporting Contractor Profit/Loss or FeeXX
Total PriceXX
DRAFT DD FORM 2794 (PAGE 2), REPORTING, JANUARY 2019

DD Form 2794, Pg 3 (EVENTS)

COST AND SOFTWARE DATA REPORTING PLAN
14. CSDR SUBMISSION EVENTS
a.
EVENT IDb.
DATA REPORT(S)c.
SUBMISSION EVENT NAMEd.
REPORT CYCLEe. AS OF DATEf. DUE DATE
(YYYYMMDD)(YYYYMMDD)
1Cost and Hour Report (FlexFile), Quantity Data ReportContract AwardInitial2024040120240601
2Technical Data ReportContract AwardInitial2024040120240601
5Cost and Hour Report (FlexFile), Quantity Data ReportAnnual Report 1Interim2025040120250601
6Technical Data ReportAnnual Report 1Interim2025040120250601
7Cost and Hour Report (FlexFile), Quantity Data ReportAnnual Report 2Interm2026040120260601
8Technical Data ReportAnnual Report 2Interim2026040120260601
9Cost and Hour Report (FlexFile), Quantity Data ReportAnnual Report 3Interim2027040120270601
10Technical Data ReportAnnual Report 3Interim2027040120270601
11Cost and Hour Report (FlexFile), Quantity Data ReportAnnual Report 4Interim2028040120280601
12Technical Data ReportAnnual Report 4Interim2028040120280601
13Cost and Hour Report (FlexFile), Quantity Data ReportAnnual Report 5Interim2029040120290601
14Technical Data ReportAnnual Report 5Interim2029040120290601
15Cost and Hour Report (FlexFile), Quantity Data ReportAnnual Report 6Interim2030040120300601
16Technical Data ReportAnnual Report 6Interim2030040120300601
17Cost and Hour Report (FlexFile), Quantity Data ReportAnnual Report 7Interim2031040120310601
18Technical Data ReportAnnual Report 7Interim2031040120310601
19Cost and Hour Report (FlexFile), Quantity Data ReportAnnual Report 8Interim2032040120320601
20Technical Data ReportAnnual Report 8Interim2032040120320601
21Cost and Hour Report (FlexFile), Quantity Data ReportContract Completion (60 days from completion)Final2033040123360601
22Technical Data ReportContract Completion (60 days from completion)Final2033040120330601
DRAFT DD FORM 2794 (PAGE 3), SUBMISSION EVENTS, JANUARY 2019PREVIOUS EDITION IS OBSOLETE

DD Form 2794, Pg 4 (REMARKS)

COST AND SOFTWARE DATA REPORTING PLAN
15. REMARKS
The contractor must report costs on all CLINs associated with the KC-135 Center Console Refresh contract including Over and Above, Advance Procurement, Long Lead Materials, Multiyear Procurement, Inter-Division or Inter-Company Work Orders (IWOs), Foreign Military Sales (FMS), Warranty, etc. Costs should not be omitted based on contract CLIN structure or definition.
FAC vs EAC
The checkmarks for EAC/FAC in column 12e at the WBS level shall be reported as "Forecast at Completion" (FAC). The Forecast At Completion (FAC) required here is not subject to the standards established in ANSI/EIA-748 guideline #27 (Estimate at Complete); therefore, the FAC does not need to be, but may be, derived from Industry Earned Value Management (EVM) processes.
NON-RECURRING/RECURRING DEFINITIONS
Recurring and Non-Recurring Costs required for all levels:
Recurring costs. Repetitive elements of development, investment or sustainment costs that may vary with the quantity being produced or maintained, irrespective of system life cycle phase and appropriation. Recurring cost categories include procurement, and production and maintenance activities; acceptance testing; maintenance and support equipment, training, and data; test articles built to an operational configuration; and certain elements of systems engineering and program management.
Examples of Prime Mission Product activities include repetitive costs incurred when building prototype, test systems, or production units to an operational configuration. Examples of Prime Mission Product Hardware activities include Fabrication and assembly of partial/full prototype, test, or production units whether for customer or contractor use; Raw material, purchased parts, equipment associated with the fabrication and assembly of partial/full prototype or test units whether for customer or contractor use; Touch labor, integration and assembly, installation and check out; Engineering support for production unit fabrication, assembly and check out.
Examples of Prime Mission Product Software activities include Procurement of stand-alone or bundled COTS software licenses used in an operational system and installation and checkout of developed software into production units. Examples of Systems Engineering activities include Sustaining engineering, logistics support, planning, organizing, monitoring and reporting activities, document maintenance. Examples of Program Management activities include programmatic, financial, contractual, schedule, planning, organizing, and monitoring (quality information assurance, configuration management) activities in support of production unit fabrication, assembly and check out; meetings & efforts in support of supplier, manufacturing & production activities.
Nonrecurring costs. Non-repetitive elements of development, investment or sustainment costs that generally do not vary with the quantity being produced or maintained, irrespective of system life cycle phase and the appropriation. Nonrecurring cost categories include product design and development (PD&D) activities, including those for modifications; system test and evaluation (ST&E) including ST&E for modifications; tooling; pre-production or pre-maintenance activities; design and development of support equipment, training, and data; and certain elements of systems engineering and program management.
Examples of Prime Mission Product PD&D activities are: Requirements definition, engineering design, analysis & development; Redesign, rework & retest due to design flaws & first time corrective actions; test articles built for testing purposes only (i.e., units that are not production-representative) such as wind tunnel models, and bench and coupon test articles; structural development, static, fatigue, software, and ballistics testing; stress analysis; flight, ground, or sea testing of system properties; redesign as a result of testing; and retesting efforts; All configuration, quality, and data management efforts supporting release activity for first article configuration, delivery & certification; System safety plan, manuals, tech services, & maintenance manual development in support of first article delivery.
Examples of hardware design and development activities include material, purchased parts and labor associated with engineering models, operational models, bench, lab articles or partially built units (i.e. units that are not production representative), tooling, and ground support equipment for qualification, structural, static, fatigue or stress testing, and refurbishment of test units; and engineering support including manufacturing engineering, quality engineering, and tool engineering for development unit fabrication, assembly & tests.
Examples of software design and development activities include design and development of all software; delivered operational software and software developed to correct deficiencies and add capabilities; Initial integration of COTS and GOTS products into operational configuration; Support for HW-SW integration and test, system level testing; initial integration of COTS and GOTS products into operational configuration; and commercial software licenses for development facilities. System Engineering, Program Management, and Data activities occur throughout the system life cycle and are supportive in nature; as such, these costs take on the characteristics of the underlying activities being performed.
Examples of Systems Engineering activities include installation plans or quality inspection plans; requirements definition, allocation and flow-down; creation of specification and Interface Control Documents (ICDs); design and implementation of system security; top level design trade-offs; analyses, studies, and simulations for system performance and effectiveness, reliability, availability, maintainability or survivability; internal & external design review, IPT coordination & integration meetings; Certification & Control documentation; and supplier selection & coordination. Examples of Program Management activities include programmatic, financial, contractual, schedule, planning, organizing, and monitoring (quality information assurance, configuration management) activities in support of development, design & testing efforts.
Examples of System Test and Evaluation activities include development of test plans/procedures; subsystem and system level test and integration for developmental articles; test equipment in support of development including for static & fatigue testing, test stands, wind tunnel models, stress analysis, ballistics testing, flight, ground or sea testing of system, redesign from testing, retesting; System/Software Integration Laboratory (SIL) development; and analysis to support verification, validation & certification. Examples of Training activity include initial courseware development and simulator development. Examples of Initial Spares and Repair Parts activity include spare parts and material in support of the nonrecurring subsystem/system level articles.
Examples of Support Equipment activity include initial equipment design and test efforts, and test program sets development. Examples of Tooling activity include special test equipment, special tooling, procurement of initial & rate tooling, tool replacement (with the exact same tool) & tool modification (to accommodate product configuration changes). Examples of Operational/Site Activation activity include site planning efforts.
IRAD EFFORT
The contractor should list the major relevant IRAD projects leveraged for this development effort, provide a brief description of the cost of the projects, and provide/attach any more detailed actual cost information at the level available.
WBS INDEX AND DICTIONARY
The WBS Dictionary is a living document and must match the technical content, cost content, and work content of each end item (see Block 17) for all WBS elements for each Cost and Hour (FlexFile) submission. The dictionary shall contain a disclosure statement detailing any differences between the CSDR reporting methodology and the reporting entity's Cost Accounting Standards. The dictionary shall include a section detailing how parts are procured under this contract and any limitations of the parts procurement cost data or allocation of cost data for the WBS element.

The reporting entity must maintain and update the WBS Dictionary throughout the life of the contract, IAW DI-FNCL-82162, if changes to the WBS occur, the reporting entity shall annotate and track changes by adding the “As of Date” of the submitted FlexFile report and indicate the changes to the WBS Index and Dictionary Definitions.

For WBS elements identified in block 11 of the CSDR plan that is not within the contract's scope of work, the reporting entity shall report in the dictionary that “This CSDR WBS element is not associated with this contract’s scope of work”, and zero costs will be associated for ATD and FAC for these WBS elements.

COST ACCOUNTING STANDARDS (CAS) DISCLOSURE STATEMENT DIFFERENCES
Describe significant accounting changes from previous accounting period in the Remarks section of the reports, if applicable.
1921-3 CONTRACTOR BUSINESS DATA REPORT
a. The Contractor Business Data Report is prepared by and for the business entity (e.g., business unit, segment, or site) responsible for submitting the Forward Pricing RateProposal (FPRP) representing the basis for Forward Pricing Rate Agreement (FPRA) negotiations with the government.

b. Reports are submitted annually at the end of the contractor's fiscal year.

c. Data for Future Years should be reflective of the number of years contained in the most current document, i.e., the FPRP or the FPRA.If the document applies to more than three future years, attach additional future year sheets as required. In the absence of these documents, estimates should be provided for three future years.

d. The existing 1921-3 requires strictly formatted data and necessitates mappings to a government standard, the new DRAFT 1921-3 may be submitted in the contractor’s own format and according to the contractor’s own rate structure, so long as it meets the data requirements in the DRAFT 1921-3 Data Item Description DI-FNCL-81765.

END ITEMS/ORDER LOTS SCOPE IDIQ
Block 16 Orders/Lots is meant to capture the discrete Delivery Orders/Task Orders exercised on the contract. If a Delivery Order/Task Order is exercised on the contract and the CSDR plan has not been updated, it is the Reporting Entity's responsibility to still submit the dollars and hours in the FlexFile tagged to the appropriate Delivery Orders/Task Orders. The CSDR plan will be revised accordingly to include all exercised Delivery Orders/Task Orders.
COST AND HOUR REPORT UNIT/SUBLOT REPORTING
The Reporting Entity is required to provide unit or sublot (specify) reporting for any given Order/Lot and End Item as outlined in block 18 of the DD Form 2794. If Unit Reporting is selected in item 18c (Unit Reporting), it is expected that all touch labor costs and hours that are associated with the discrete units or sublots be tagged as Touch Manufacturing or Touch Maintenance as defined in Data Group E, Item 7.
QUANTITY REPORTING
a. If the quantity for a given element differs from the quantity reported for the full system, provide a comment in the WBS Element Remarks section.

b. The Reporting Entity shall provide meaningful quantity information lower than the summary level in the remarks for WBS elements Peculiar Support Equipment, Common Support Equipment, and Initial Spares and Repair Parts, if applicable.

FINAL COST REPORT
Final Cost Report to be submitted when final end item has been delivered and accepted by the government (e.g., as evidenced by a completed DD 250) and 95% or more of total costs for each Order/Lot (see Block 16) and each End Item (see Block 17) has been incurred.
CSDR READINESS REVIEW (CSDR-RR) also known as Post Award Conference (PAC)
The Reporting Entity shall attend and participate in a CSDR Readiness Review meeting (also known as the Post award CSDR conference) which will be held with the Cost Working Group Integrated Product Team (CWIPT) IAW DFARS 242.503-2(b) and DoDM 5000.04 (CSDR Manual). During this meeting, the CWIPT and contractor will review the Reporting Entity's process for data collection and reporting to ensure it satisfies the guidelines outlined in the DoDM 5000.04, CSDR Manual, the approved CSDR plan reporting requirement, and the Resource Distribution Table. The Reporting Entity shall demonstrate how costs will be based, to the maximum extent possible, upon actual cost transactions and not cost allocations; describe how recurring vs. nonrecurring costs will be segregated; demonstrate how the data from its accounting system will be mapped into the reporting categories in the approved CSDR plan. The Reporting Entity shall present the methodologies used for mapping internal cost accounts to the agreed upon WBS, specifically illustrating how individual WBS elements and standard functional categories in the FlexFile (functional data elements in the 1921 series) codes will be populated. The review shall include any reporting issue corrections and identify proposed changes to the approved CSDR Plan as necessary.
RESOURCE DISTRIBUTION TABLE (RDT)
The Reporting Entity is instructed to provide a Resource Distribution Table upon contract award, which identifies the value and work assigned to the Reporting Entity and its subcontractors. The Reporting Entity shall provide an updated RDT when additional quantities/scope are added to the contract to ensure that no major sub-contract(s) breach the direct CSDR reporting threshold specified in DoDI 5000.02 and DoDM 5000.04-M-1.
PERIOD OF PERFORMANCE (POP)
If contract Period of Performance is extended, the contractor shall submit an additional cost report for each additional year of extension. The final report will be moved to the revised end of the Period of Performance.
DRAFT DD FORM 2794 (PAGE 4), REMARKS, JANUARY 2019 PREVIOUS EDITION IS OBSOLETE

DD Form 2794, Pg 5 (SCOPE DEF)

COST AND SOFTWARE DATA REPORTING PLAN
INTRA-CONTRACT SCOPE REPORTING DEFINITION
16. ORDERS/LOTS
a. IDb. NAMEc. PHASE/MILESTONE
1TBD Contract Number
17. END ITEMS
a. IDb. NAME
1Prototype 1 - A Kits
2Prototype 1 - B Kits
3Prototype 2 - A Kits
4Prototype 2 - B Kits
5Common
18. OPTIONAL REQUIREMENTS
a. ORDER/LOT IDb. END ITEM IDc. UNIT REPORTING
(X if applicable)d. SEQUENCING

(X if applicable)

11XX
12XX
DRAFT DD FORM 2794 (PAGE 5), INTRA-CONTRACT SCOPE, JANUARY 2019

DD Form 2794, Pg 8 (TECH RQTS)

COST AND SOFTWARE DATA REPORTING PLAN - TECHNICAL PARAMETER REQUIREMENTS
TECHNICAL PARAMETER REQUIREMENTS
26. WBS
ELEMENT CODE27. WBS ELEMENT NAME28. ITEM TYPE29. TECHNICAL PARAMETER
a. PARAMETER NAMEb. UNIT OF MEASUREc. UNIT OF MEASURE QUALIFIERd. REPEATABLEe. REMARKS
1.2.1Air Vehicle Integration, Assembly, Test, and CheckoutHeritageNew DesignPercent
1.2.1Air Vehicle Integration, Assembly, Test, and CheckoutHeritagePredecessor SystemDescriptor
1.2.1Air Vehicle Integration, Assembly, Test, and CheckoutIAT&CONumber of Electrical ConnectionsQuantityElectrical Connections
1.2.1Air Vehicle Integration, Assembly, Test, and CheckoutIAT&CONumber of Mechanical ConnectionsQuantityMechanical Connections
1.2.4Vehicle SubsystemsHeritageNew DesignPercent
1.2.4Vehicle SubsystemsHeritagePredecessor SystemDescriptor
1.2.4.1Vehicle Subsystem Integration, Assembly, Test, and CheckoutHeritageNew DesignPercent
1.2.4.1Vehicle Subsystem Integration, Assembly, Test, and CheckoutHeritagePredecessor SystemDescriptor
1.2.4.1Vehicle Subsystem Integration, Assembly, Test, and CheckoutIAT&CONumber of Electrical ConnectionsQuantityElectrical Connections
1.2.4.1Vehicle Subsystem Integration, Assembly, Test, and CheckoutIAT&CONumber of Mechanical ConnectionsQuantityMechanical Connections
1.2.4.5.1Electrical Hardware Integration, Assembly, Test, and CheckoutIAT&CONumber of Electrical ConnectionsQuantityElectrical Connections
1.2.4.5.1Electrical Hardware Integration, Assembly, Test, and CheckoutIAT&CONumber of Mechanical ConnectionsQuantityMechanical Connections
1.2.4.5.2Electrical Hardware 1..n (Specify)PhysicalOtherMaterial Mix 1…nPercent of Total WeightMaterial NameY
1.2.4.5.2Electrical Hardware 1..n (Specify)PhysicalStrucVolumeCubic Inches
1.2.4.5.2Electrical Hardware 1..n (Specify)PhysicalStrucWeightPounds
1.2.4.5.2Electrical Hardware 1..n (Specify)PowerPower - Subsystem TotalWatts
1.2.4.5.2Electrical Hardware 1..n (Specify)PowerPower - Subsystem PeakWatts
1.2.4.5.2Electrical Hardware 1..n (Specify)PowerPower - Supply Performance PeriodSeconds
1.2.4.5.2Electrical Hardware 1..n (Specify)PowerPower - Supply AverageVolts
1.2.4.5.2Electrical Hardware 1..n (Specify)PowerVolume of Electrical Power SystemCubic Inches
1.2.4.5.2Electrical Hardware 1..n (Specify)PowerNumber of Power Supply Inputs - Alternating Current (AC)QuantityInputs
1.2.4.5.2Electrical Hardware 1..n (Specify)PowerNumber of Power Supply Inputs - Direct Current (DC)QuantityInputs
1.2.4.5.2Electrical Hardware 1..n (Specify)PowerNumber of Power Supply Outputs - Direct Current (DC)QuantityOutputs
1.2.4.5.2Electrical Hardware 1..n (Specify)PowerType of PowerList
1.2.4.5.2Electrical Hardware 1..n (Specify)PowerType of BatteryList
1.2.4.5.2Electrical Hardware 1..n (Specify)PowerNumber of Stages CoveredQuantityStages
1.2.4.5.2Electrical Hardware 1..n (Specify)BatteryBattery CapacityAmpere Hours
1.2.4.5.2Electrical Hardware 1..n (Specify)BatteryOutput VoltageVolts
1.2.4.5.2Electrical Hardware 1..n (Specify)BatteryType of BatteryList
1.2.4.5.2Electrical Hardware 1..n (Specify)BatteryNumber of Battery CellsQuantity
1.2.4.5.2Electrical Hardware 1..n (Specify)ComputerSimultaneous Multi-Mode OperationList
1.2.4.5.2Electrical Hardware 1..n (Specify)ComputerProcessor TypeDescriptor
1.2.4.5.2Electrical Hardware 1..n (Specify)ComputerComputing PerformanceMillions of Instructions per Second
1.2.4.5.2Electrical Hardware 1..n (Specify)ElecBoxCircuit Cards - Number ofQuantity
1.2.4.5.2Electrical Hardware 1..n (Specify)ElecBoxApplication Specific Integrated Circuit (ASIC) DesignsQuantityASICs
1.2.4.5.2Electrical Hardware 1..n (Specify)ElecBoxField Programmable Gate Array (FPGA) DesignsQuantityFPGAs
1.2.4.6.1Crew Station Hardware Integration, Assembly, Test, and CheckoutIAT&CONumber of Electrical ConnectionsQuantityElectrical Connections
1.2.4.6.1Crew Station Hardware Integration, Assembly, Test, and CheckoutIAT&CONumber of Mechanical ConnectionsQuantityMechanical Connections
1.2.4.6.2Canopy /Cockpit SystemPhysicalOtherMaterial Mix 1…nPercent of Total WeightMaterial NameY
1.2.4.6.2Canopy /Cockpit SystemPhysicalStrucVolumeCubic Inches
1.2.4.6.2Canopy /Cockpit SystemPhysicalStrucWeightPounds
1.2.4.8.1Fuel Hardware Integration, Assembly, Test, and CheckoutIAT&CONumber of Electrical ConnectionsQuantityElectrical Connections
1.2.4.8.1Fuel Hardware Integration, Assembly, Test, and CheckoutIAT&CONumber of Mechanical ConnectionsQuantityMechanical Connections
1.2.4.8.2Fuel Subsystem Hardware 1..n (Specify)PhysicalOtherMaterial Mix 1…nPercent of Total WeightMaterial NameY
1.2.4.8.2Fuel Subsystem Hardware 1..n (Specify)PhysicalStrucVolumeCubic Inches
1.2.4.8.2Fuel Subsystem Hardware 1..n (Specify)PhysicalStrucWeightPounds
1.2.4.8.2Fuel Subsystem Hardware 1..n (Specify)FuelSystemFuel CapacityGallons
1.2.4.13.1Other Vehicle Subsystem Hardware Integration, Assembly, Test, and CheckoutIAT&CONumber of Electrical ConnectionsQuantityElectrical Connections
1.2.4.13.1Other Vehicle Subsystem Hardware Integration, Assembly, Test, and CheckoutIAT&CONumber of Mechanical ConnectionsQuantityMechanical Connections
1.2.4.13.2Other Vehicle Subsystem Hardware 1..n (Specify)PhysicalOtherMaterial Mix 1…nPercent of Total WeightMaterial NameY
1.2.4.13.2Other Vehicle Subsystem Hardware 1..n (Specify)PhysicalStrucVolumeCubic Inches
1.2.4.13.2Other Vehicle Subsystem Hardware 1..n (Specify)PhysicalStrucWeightPounds
1.2.4.13.2Other Vehicle Subsystem Hardware 1..n (Specify)ComputerSimultaneous Multi-Mode OperationList
1.2.4.13.2Other Vehicle Subsystem Hardware 1..n (Specify)ComputerProcessor TypeDescriptor
1.2.4.13.2Other Vehicle Subsystem Hardware 1..n (Specify)ComputerComputing PerformanceMillions of Instructions per Second
1.2.4.13.2Other Vehicle Subsystem Hardware 1..n (Specify)ElecBoxCircuit Cards - Number ofQuantity
1.2.4.13.2Other Vehicle Subsystem Hardware 1..n (Specify)ElecBoxApplication Specific Integrated Circuit (ASIC) DesignsQuantityASICs
1.2.4.13.2Other Vehicle Subsystem Hardware 1..n (Specify)ElecBoxField Programmable Gate Array (FPGA) DesignsQuantityFPGAs
1.2.5AvionicsHeritageNew DesignPercent
1.2.5AvionicsHeritagePredecessor SystemDescriptor
1.2.5.1Avionics Integration, Assembly, Test And CheckoutHeritageNew DesignPercent
1.2.5.1Avionics Integration, Assembly, Test And CheckoutHeritagePredecessor SystemDescriptor
1.2.5.1Avionics Integration, Assembly, Test And CheckoutIAT&CONumber of Electrical ConnectionsQuantityElectrical Connections
1.2.5.1Avionics Integration, Assembly, Test And CheckoutIAT&CONumber of Mechanical ConnectionsQuantityMechanical Connections
1.2.5.2.1Communication/Identification Hardware Integration, Assembly, Test, and CheckoutIAT&CONumber of Electrical ConnectionsQuantityElectrical Connections
1.2.5.2.1Communication/Identification Hardware Integration, Assembly, Test, and CheckoutIAT&CONumber of Mechanical ConnectionsQuantityMechanical Connections
1.2.5.2.2Communication/Identification Hardware 1..n (Specify)PhysicalOtherMaterial Mix 1…nPercent of Total WeightMaterial NameY
1.2.5.2.2Communication/Identification Hardware 1..n (Specify)PhysicalStrucVolumeCubic Inches
1.2.5.2.2Communication/Identification Hardware 1..n (Specify)PhysicalStrucWeightPounds
1.2.5.2.2Communication/Identification Hardware 1..n (Specify)ComputerSimultaneous Multi-Mode OperationList
1.2.5.2.2Communication/Identification Hardware 1..n (Specify)ComputerProcessor TypeDescriptor
1.2.5.2.2Communication/Identification Hardware 1..n (Specify)ComputerComputing PerformanceMillions of Instructions per Second
1.2.5.2.2Communication/Identification Hardware 1..n (Specify)ElecBoxCircuit Cards - Number ofQuantity
1.2.5.2.2Communication/Identification Hardware 1..n (Specify)ElecBoxApplication Specific Integrated Circuit (ASIC) DesignsQuantityASICs
1.2.5.2.2Communication/Identification Hardware 1..n (Specify)ElecBoxField Programmable Gate Array (FPGA) DesignsQuantityFPGAs
1.2.5.2.2Communication/Identification Hardware 1..n (Specify)AmplifierPeak Output PowerWatts
1.2.5.2.2Communication/Identification Hardware 1..n (Specify)AmplifierAverage Output PowerWatts
1.2.5.2.2Communication/Identification Hardware 1..n (Specify)AmplifierFrequency - MaximumMegahertz
1.2.5.2.2Communication/Identification Hardware 1..n (Specify)AmplifierFrequency - MinimumMegahertz
1.2.5.2.2Communication/Identification Hardware 1..n (Specify)AmplifierAmplifier EfficiencyPercent
1.2.5.2.2Communication/Identification Hardware 1..n (Specify)AntennaFrequency BandList
1.2.5.2.2Communication/Identification Hardware 1..n (Specify)AntennaFrequency RangeMegahertz
1.2.5.2.2Communication/Identification Hardware 1..n (Specify)AntennaAperture - AntennaInches
1.2.5.2.2Communication/Identification Hardware 1..n (Specify)AntennaNumber of Sub ArraysQuantityPer Antenna Face
1.2.5.2.2Communication/Identification Hardware 1..n (Specify)AntennaTunable BandwidthGigahertz
1.2.5.2.2Communication/Identification Hardware 1..n (Specify)AntennaType of SteeringList
1.2.5.2.2Communication/Identification Hardware 1..n (Specify)AntennaPattern TypeList
1.2.5.2.2Communication/Identification Hardware 1..n (Specify)AntennaTechnology TypeDescriptor
1.2.5.2.2Communication/Identification Hardware 1..n (Specify)AntennaOperational ModeList
1.2.5.2.2Communication/Identification Hardware 1..n (Specify)AntennaBandwidthGigahertzInstantaneous
1.2.5.2.2Communication/Identification Hardware 1..n (Specify)TransReceivRFTransmitter Power Output - PeakWatts
1.2.5.2.2Communication/Identification Hardware 1..n (Specify)TransReceivRFTransmitter Power Output - AverageWatts
1.2.5.2.2Communication/Identification Hardware 1..n (Specify)TransReceivRFBandwidthMegahertz
1.2.5.3.1Navigation/Guidance Hardware Integration, Assembly, Test, and CheckoutIAT&CONumber of Electrical ConnectionsQuantityElectrical Connections
1.2.5.3.1Navigation/Guidance Hardware Integration, Assembly, Test, and CheckoutIAT&CONumber of Mechanical ConnectionsQuantityMechanical Connections
1.2.5.3.2Navigation/Guidance Hardware 1..n (Specify)PhysicalOtherMaterial Mix 1…nPercent of Total WeightMaterial NameY
1.2.5.3.2Navigation/Guidance Hardware 1..n (Specify)PhysicalStrucVolumeCubic Inches
1.2.5.3.2Navigation/Guidance Hardware 1..n (Specify)PhysicalStrucWeightPounds
1.2.5.3.2Navigation/Guidance Hardware 1..n (Specify)ComputerSimultaneous Multi-Mode OperationList
1.2.5.3.2Navigation/Guidance Hardware 1..n (Specify)ComputerProcessor TypeDescriptor
1.2.5.3.2Navigation/Guidance Hardware 1..n (Specify)ComputerComputing PerformanceMillions of Instructions per Second
1.2.5.3.2Navigation/Guidance Hardware 1..n (Specify)ElecBoxCircuit Cards - Number ofQuantity
1.2.5.3.2Navigation/Guidance Hardware 1..n (Specify)ElecBoxApplication Specific Integrated Circuit (ASIC) DesignsQuantityASICs
1.2.5.3.2Navigation/Guidance Hardware 1..n (Specify)ElecBoxField Programmable Gate Array (FPGA) DesignsQuantityFPGAs
1.2.5.3.2Navigation/Guidance Hardware 1..n (Specify)AmplifierPeak Output PowerWatts
1.2.5.3.2Navigation/Guidance Hardware 1..n (Specify)AmplifierAverage Output PowerWatts
1.2.5.3.2Navigation/Guidance Hardware 1..n (Specify)AmplifierFrequency - MaximumMegahertz
1.2.5.3.2Navigation/Guidance Hardware 1..n (Specify)AmplifierFrequency - MinimumMegahertz
1.2.5.3.2Navigation/Guidance Hardware 1..n (Specify)AmplifierAmplifier EfficiencyPercent
1.2.5.3.2Navigation/Guidance Hardware 1..n (Specify)AntennaFrequency BandList
1.2.5.3.2Navigation/Guidance Hardware 1..n (Specify)AntennaFrequency RangeMegahertz
1.2.5.3.2Navigation/Guidance Hardware 1..n (Specify)AntennaAperture - AntennaInches
1.2.5.3.2Navigation/Guidance Hardware 1..n (Specify)AntennaNumber of Sub ArraysQuantityPer Antenna Face
1.2.5.3.2Navigation/Guidance Hardware 1..n (Specify)AntennaTunable BandwidthGigahertz
1.2.5.3.2Navigation/Guidance Hardware 1..n (Specify)AntennaType of SteeringList
1.2.5.3.2Navigation/Guidance Hardware 1..n (Specify)AntennaPattern TypeList
1.2.5.3.2Navigation/Guidance Hardware 1..n (Specify)AntennaTechnology TypeDescriptor
1.2.5.3.2Navigation/Guidance Hardware 1..n (Specify)AntennaOperational ModeList
1.2.5.3.2Navigation/Guidance Hardware 1..n (Specify)AntennaBandwidthGigahertzInstantaneous
1.2.5.3.2Navigation/Guidance Hardware 1..n (Specify)TransReceivRFTransmitter Power Output - PeakWatts
1.2.5.3.2Navigation/Guidance Hardware 1..n (Specify)TransReceivRFTransmitter Power Output - AverageWatts
1.2.5.3.2Navigation/Guidance Hardware 1..n (Specify)TransReceivRFBandwidthMegahertz
1.2.5.4.1Mission Computer/Processing Hardware Integration, Assembly, Test, and CheckoutIAT&CONumber of Electrical ConnectionsQuantityElectrical Connections
1.2.5.4.1Mission Computer/Processing Hardware Integration, Assembly, Test, and CheckoutIAT&CONumber of Mechanical ConnectionsQuantityMechanical Connections
1.2.5.4.2Mission Computer/Processing Hardware 1..n (Specify)PhysicalOtherMaterial Mix 1…nPercent of Total WeightMaterial NameY
1.2.5.4.2Mission Computer/Processing Hardware 1..n (Specify)PhysicalStrucVolumeCubic Inches
1.2.5.4.2Mission Computer/Processing Hardware 1..n (Specify)PhysicalStrucWeightPounds
1.2.5.4.2Mission Computer/Processing Hardware 1..n (Specify)ComputerSimultaneous Multi-Mode OperationList
1.2.5.4.2Mission Computer/Processing Hardware 1..n (Specify)ComputerProcessor TypeDescriptor
1.2.5.4.2Mission Computer/Processing Hardware 1..n (Specify)ComputerComputing PerformanceMillions of Instructions per Second
1.2.5.4.2Mission Computer/Processing Hardware 1..n (Specify)ElecBoxCircuit Cards - Number ofQuantity
1.2.5.4.2Mission Computer/Processing Hardware 1..n (Specify)ElecBoxApplication Specific Integrated Circuit (ASIC) DesignsQuantityASICs
1.2.5.4.2Mission Computer/Processing Hardware 1..n (Specify)ElecBoxField Programmable Gate Array (FPGA) DesignsQuantityFPGAs
1.2.5.6.1Data Display and Control Hardware Integration, Assembly, Test And CheckoutIAT&CONumber of Electrical ConnectionsQuantityElectrical Connections
1.2.5.6.1Data Display and Control Hardware Integration, Assembly, Test And CheckoutIAT&CONumber of Mechanical ConnectionsQuantityMechanical Connections
1.2.5.6.2Data Display & Control Hardware 1..n (Specify)PhysicalOtherMaterial Mix 1…nPercent of Total WeightMaterial NameY
1.2.5.6.2Data Display & Control Hardware 1..n (Specify)PhysicalStrucVolumeCubic Inches
1.2.5.6.2Data Display & Control Hardware 1..n (Specify)PhysicalStrucWeightPounds
1.2.5.6.2Data Display & Control Hardware 1..n (Specify)ComputerSimultaneous Multi-Mode OperationList
1.2.5.6.2Data Display & Control Hardware 1..n (Specify)ComputerProcessor TypeDescriptor
1.2.5.6.2Data Display & Control Hardware 1..n (Specify)ComputerComputing PerformanceMillions of Instructions per Second
1.2.5.6.2Data Display & Control Hardware 1..n (Specify)ElecBoxCircuit Cards - Number ofQuantity
1.2.5.6.2Data Display & Control Hardware 1..n (Specify)ElecBoxApplication Specific Integrated Circuit (ASIC) DesignsQuantityASICs
1.2.5.6.2Data Display & Control Hardware 1..n (Specify)ElecBoxField Programmable Gate Array (FPGA) DesignsQuantityFPGAs
1.2.5.6.2Data Display & Control Hardware 1..n (Specify)DisplayType of DisplayList
1.2.5.6.2Data Display & Control Hardware 1..n (Specify)DisplaySize of monitor (diagonal)Inches
1.2.5.6.2Data Display & Control Hardware 1..n (Specify)DisplayHeightInches
1.2.5.6.2Data Display & Control Hardware 1..n (Specify)DisplayApplicable TSOsDescriptor
1.2.5.6.2Data Display & Control Hardware 1..n (Specify)DisplayCivil Airspace Access FunctionsList
1.2.5.7.1Survivability Hardware Integration, Assembly, Test, and CheckoutIAT&CONumber of Electrical ConnectionsQuantityElectrical Connections
1.2.5.7.1Survivability Hardware Integration, Assembly, Test, and CheckoutIAT&CONumber of Mechanical ConnectionsQuantityMechanical Connections
1.2.5.7.2Survivability Hardware 1..n (Specify)PhysicalOtherMaterial Mix 1…nPercent of Total WeightMaterial NameY
1.2.5.7.2Survivability Hardware 1..n (Specify)PhysicalStrucVolumeCubic Inches
1.2.5.7.2Survivability Hardware 1..n (Specify)PhysicalStrucWeightPounds
1.2.5.7.2Survivability Hardware 1..n (Specify)ElecBoxCircuit Cards - Number ofQuantity
1.2.5.7.2Survivability Hardware 1..n (Specify)ElecBoxApplication Specific Integrated Circuit (ASIC) DesignsQuantityASICs
1.2.5.7.2Survivability Hardware 1..n (Specify)ElecBoxField Programmable Gate Array (FPGA) DesignsQuantityFPGAs
1.2.5.7.2Survivability Hardware 1..n (Specify)CountermeasuresRange - MaximumKilometers
1.2.5.11.1Health Monitoring Hardware Integration, Assembly, Test, and CheckoutIAT&CONumber of Electrical ConnectionsQuantityElectrical Connections
1.2.5.11.1Health Monitoring Hardware Integration, Assembly, Test, and CheckoutIAT&CONumber of Mechanical ConnectionsQuantityMechanical Connections
1.2.5.11.2Health Monitoring System Hardware 1..n (Specify)PhysicalOtherMaterial Mix 1…nPercent of Total WeightMaterial NameY
1.2.5.11.2Health Monitoring System Hardware 1..n (Specify)PhysicalStrucVolumeCubic Inches
1.2.5.11.2Health Monitoring System Hardware 1..n (Specify)PhysicalStrucWeightPounds
1.2.5.11.2Health Monitoring System Hardware 1..n (Specify)ComputerSimultaneous Multi-Mode OperationList
1.2.5.11.2Health Monitoring System Hardware 1..n (Specify)ComputerProcessor TypeDescriptor
1.2.5.11.2Health Monitoring System Hardware 1..n (Specify)ComputerComputing PerformanceMillions of Instructions per Second
1.2.5.11.2Health Monitoring System Hardware 1..n (Specify)ElecBoxCircuit Cards - Number ofQuantity
1.2.5.11.2Health Monitoring System Hardware 1..n (Specify)ElecBoxApplication Specific Integrated Circuit (ASIC) DesignsQuantityASICs
1.2.5.11.2Health Monitoring System Hardware 1..n (Specify)ElecBoxField Programmable Gate Array (FPGA) DesignsQuantityFPGAs
1.2.5.14.1Other Avionics Subsystem Hardware Integration, Assembly, Test, and CheckoutIAT&CONumber of Electrical ConnectionsQuantityElectrical Connections
1.2.5.14.1Other Avionics Subsystem Hardware Integration, Assembly, Test, and CheckoutIAT&CONumber of Mechanical ConnectionsQuantityMechanical Connections
1.2.5.14.2Other Avionics Subsystem Hardware 1..n (Specify)PhysicalOtherMaterial Mix 1…nPercent of Total WeightMaterial NameY
1.2.5.14.2Other Avionics Subsystem Hardware 1..n (Specify)PhysicalStrucVolumeCubic Inches
1.2.5.14.2Other Avionics Subsystem Hardware 1..n (Specify)PhysicalStrucWeightPounds
1.2.5.14.2Other Avionics Subsystem Hardware 1..n (Specify)ElecBoxCircuit Cards - Number ofQuantity
1.2.5.14.2Other Avionics Subsystem Hardware 1..n (Specify)ElecBoxApplication Specific Integrated Circuit (ASIC) DesignsQuantityASICs
1.2.5.14.2Other Avionics Subsystem Hardware 1..n (Specify)ElecBoxField Programmable Gate Array (FPGA) DesignsQuantityFPGAs
1.2.10Other Air Vehicle 1...n (Specify)HeritageNew DesignPercent
1.2.10Other Air Vehicle 1...n (Specify)HeritagePredecessor SystemDescriptor
1.6Systems EngineeringSysEngNumber of Requirement Document - "Shalls"QuantityShallsYG
1.6Systems EngineeringSysEngNumber of Platforms - IntegratedQuantityPlatforms
1.7Program ManagementProgMgmtFrequency of Government Program ReviewsQuantityReviews per Year
1.7Program ManagementProgMgmtNumber of Contract Line Item Number (CLIN)sQuantityCLINs
1.7Program ManagementProgMgmtNumber of SubcontractorsQuantitySubcontractors
1.7Program ManagementProgMgmtNumber of Customer StakeholdersQuantityStakeholders
1.8.4Mock-ups/System Integration Labs (SILs)SILModeling TypeListYG
1.8.4Mock-ups/System Integration Labs (SILs)SILMock-up / SIL - SizeSquare Feetby Facility / SuiteYG
1.8.4Mock-ups/System Integration Labs (SILs)SILMock-up / SIL - Primary PurposeListYG
1.9.1.1Operator Instructional EquipmentTrainDeviceTraining Device NameDescriptorTraining Device NameYG

This is the start of the file's text. The full file is on GovTribe.