atch 7 EPA CLINS.pdf

PDF 44 KB Posted

Attached to
Paving Requirements Joint Base Elmendorf-Richardson AK Federal contract opportunity
Solicitation number
FA5000-12-R-0001
Issued by
Department of the Air Force Pacific Air Forces

About this file

atch 7 EPA CLINS

View the file

Other files for this federal contract opportunity

Other files attached to Paving Requirements Joint Base Elmendorf-Richardson AK, newest first.
File Type Posted
Atch 6 Option Year 2.pdf PDF
Atch 6 Option Year 4.pdf PDF
Atch 6 Option Year 1.pdf PDF
Atch 6 Option Year 3.pdf PDF
Atch 6 Option Year 6.pdf PDF
Atch 6 Option Year 5.pdf PDF
atch 1 1020 scope —
Bid Questions 8 May 12.pdf PDF
atch 4 Wage 20 Apr 12.pdf PDF
FA5000-12-R-0001 solicitation.doc DOC document
FA5000-12-R-0001 Sol 18 Apr 12.doc DOC document
atch 6 Contractor Bid Schedules Summary.pdf PDF
atch 6 Contractor Bid Schedules option 5.pdf PDF
atch 1 1121 Accumulation.pdf PDF
atch 4 Wage AK1 13 Apr 12.pdf PDF
atch 1 2550 Hot Mix Asphalt.pdf PDF
atch 1 2590 Pavement Markings for Airfields.pdf PDF
atch 1 2575 Spall Repair.pdf PDF
atch 8 Past Performance Instruction.pdf PDF
atch 1 1020 scope.pdf PDF
atch 1 1010 General Requirements.pdf PDF
atch 1 1120 Environmental.pdf PDF
atch 1 16375 Electrical Distribution System Underground.pdf PDF
atch 1 2570 Joint Sealing.pdf PDF
atch 1 2567 Rubberized Tar Seal Coat.pdf PDF
atch 9 Past Performance Questionnaire.pdf PDF
Atch 2 drawings Apt 11.pdf PDF
Atch 5 WeDateElm.pdf PDF
atch 1 2936 Hydro Seeding.pdf PDF
atch 1 2560 Asphalt Tack.pdf PDF
atch 1 2230 Crusher Agg Base Airfields.pdf PDF
atch 6 Contractor Bid Schedules option 6.pdf PDF
atch 1 2595 Pavement Markings for Roads.pdf PDF
atch 3 Form66.pdf PDF
atch 1 2540 Cold Planing.pdf PDF
atch 1 2225 Sub Base.pdf PDF
atch 1 2235 Crusher Agg Base roads.pdf PDF
atch 6 Contractor Bid Schedules Base Year.pdf PDF
atch 1 1 title and table of contents.pdf PDF
atch 6 Contractor Bid Schedules Option 4.pdf PDF
atch 1 2530 Asphalt Pavemnet Crack Seal.pdf PDF
atch 6 Contractor Bid Schedules Option 3.pdf PDF
atch 1 2572 Re-Sealing.pdf PDF
atch 1 2576 Hydraulic Cement Repair.pdf PDF
atch 1 2515 Concrete Pavements.pdf PDF
atch 6 Contractor Bid Schedules Option 1.pdf PDF
atch 6 Contractor Bid Schedules Option 2.pdf PDF
atch 1 16370 Electrical Distribution Systems Aerial.pdf PDF
atch 1 2510 Concrete Sidewalks.pdf PDF
atch 1 2100 Asphalt pavements.pdf PDF
Show all 50

Paving Requirements Joint Base Elmendorf-Richardson AK has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

EPA CLINS FA5000-12-R-0001

Attachment 7

ESTIMATED Material

WORK ITEM ESTIMATED UNIT BID UNIT DOLLAR Material Affected Unit Price Material Qty

QUANTITY PRICE AMOUNT By EPA Base Year Unit Per CLIN Qty

Asphalt Adjustment:

#44 New Airfield PG 52-28 Asphalt Pavement (Placement)

#45 New Airfield 3% SBS Asphalt Pavement (Placement)

#52 Asphalt Crack Sealing (Routing)

#53 Asphalt Crack Sealing (No routing)

#54 Asphalt/Concrete & AC/AC Joint Sealing

#81 Reseal Existing Concrete Joints Sealing

#82 New Concrete Joint Sealing

#100 New Road/Parking Lot PG 52-28 Asphalt Pavement (Placement)

#101 New Road/Parking Lot 3% SBS Asphalt Pavement (Placement)

#102 New Asphalt Transitions/Radius Work (Placement)

#103 New Asphalt Leveling Course (Placement)

#139 Minor Asphalt Repairs

#149 New Bike Trails/Paths

#224 New Air Force Hot Mix PG-52-28 Asphalt for BCE (On-base)

Fuel Adjustment:

#001 Remove Existing Asphalt to On-Base / On-Post Site

#004 Cold Plane Existing Asphalt

#008 Remove Existing Base/Sub-base

#010 Remove Unusable Soil / On-Base / On-Post Site

#018 Clearing and Grubbing

#020 Clearing and Grubbing / Tree Removal

#026 New Classified Backfill/Fill [2" minus]

#027 New Sub base [3" minus]

#028 New Pit Run Gravel

#029 New Sub base/Classified /Pit Run [< 7,500 Tons]

#033 Surface Prep Existing Sub base/Sub grade

#034 Surface Prep Existing Base Course

#037 New Airfield Base Course / Processing

#038 New Airfield Base Course / Placement

#039 New Airfield Base Course / Drainage Layer

#041 New AF Base Course / [First 10,000 Tons]

#043 New AF Asphalt Pavement / Processing

#044 New AF Asphalt Pavement (PG52-28) / Placement

#045 New AF Asphalt Pavement (PG58-28) / Placement

#057 Remove Existing Concrete Slabs (Isolated)

#058 Remove Existing Concrete Slabs (Continuous)

#059 Remove Concrete [> 12" Thick]

#060 Remove Concrete [< 1,200 CY]

#061 Remove Existing Concrete [Reinforced]

#090 Pulverize Existing Asphalt in Place

#091 New D-1 Base Course / Processing

#092 New D-1 Base Course / Placement

#093 New D-1 Base Course / 2"-4" Leveling Course

#099 New Road/Parking Lot Asphalt Pavements / Processing

#100 New Asphalt Pavements (PG52-28) / Placement

#101 New Asphalt Pavements (PG58-28) / Placement

#107 New AC Pavement (AF & Roads) / [First 10,000 Tons]

#181 Hauling Material

#186 Remove Unusable Soil (North End of North/South Runway)

BID

Item

Sheet1