atch 6 Contractor Bid Schedules Base Year.pdf
PDF 90 KB Posted
- Attached to
- Paving Requirements Joint Base Elmendorf-Richardson AK Federal contract opportunity
- Solicitation number
- FA5000-12-R-0001
About this file
atch 6 Contractor Bid Schedule Base Year
View the file
Other files for this federal contract opportunity
Show all 50
Paving Requirements Joint Base Elmendorf-Richardson AK has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ESTIMATED
WORK ITEM ESTIMATED UNIT BID UNIT DOLLAR
QUANTITY PRICE AMOUNT
Removal for Roads and Airfields:
A 001 Remove Existing Asphalt to On-Base / On-Post Site 10,000 TONS A 002 Remove Existing Asphalt to Off-Base / Off-Post Site 2,500 TONS A 003 Remove Existing Asphalt [< 2,500 Tons] 6,250 TONS A 004 Cold Plane Existing Asphalt 20,000 SY-IN A 005 Cold Plane Existing Asphalt [< 50,000 SY-IN] 10,000 SY-IN A 006 Sawcut Existing/New Asphalt 15,000 IN-LF A 007 Sawcut Existing/New Concrete 12,200 IN-LF A 008 Remove Existing Base/Subbase 1,500 CY A 009 Remove Existing Base/Subbase [<3,000 CY] 750 CY A 010 Remove Unusable Soil / On-Base / On-Post Site 3,500 CY A 011 Remove Unsuitable Soil / On-Base / On-Post Site 2,500 CY A 012 Remove Unuseable/Unsuitable/ Soil [< 2000 CY] 2,000 CY A 013 Trench Excavation/Backfill 500 CY A 014 Excavation/Backfill Existing Underground Utilities 100 CY A 015 Locates/Potholing for Underground Utilities 50 HR A 016 Soil Excavation/Backfill 40 HR A 017 Drainage Ditch Grading 80 HR A 018 Clearing and Grubbing 10 MSF A 019 Clearing and Grubbing [< 10 MSF] 5 MSF A 020 Clearing and Grubbing / Tree Removal 2 MSF A 021 Remove Underground Storage Tanks 1 EA A 022 Remove Materials to MOA Landfill (Dumping Fees) 50 TONS A 023 Remove Materials to MOA Landfill (No Dumping Fees) 150 TONS A 024 Remove Conduits/Concrete Encased 100 LF A 025 Remove Concrete Vaults 2 EA New Materials for Roads and Airfields:
A 026 New Classified Backfill/Fill [2" minus] 2,000 TON A 027 New Subbase [3" minus] 4,000 TON A 028 New Pit Run Gravel 2,000 TON A 029 New Subbase/Classified /Pit Run [< 7,500 Tons] 4,000 TONS Site Work:
A 030 Re-Use Existing Base as Subbase On-site 6,000 CY A 031 Re-Use Exist Base as Subbase On-site [<7,500 CY] 3,000 CY A 032 New Geotextile Fabric 2,000 SY A 033 Surface Prep Existing Subbase/Subgrade 16,500 SY A 034 Surface Prep Existing Base Course 10,500 SY A 035 Surface Prep [<5,000 SY] 2,000 SY A 036 Spray Asphalt Emulsion 2,000 SY Work Items Predominately for Airfields (AF):
A 037 New Airfield Base Course / Processing 12,500 TONS A 038 New Airfield Base Course / Placement 9,500 TONS A 039 New Airfield Base Course / Drainage Layer 3,000 TONS A 040 New Airfield Base Course / [< 3,500 Tons] 6,250 TONS
A 041 New AF Base Course / [First 10,000 Tons] 10,000 TONS A 042 New AF Base Course / [ > 20,000 Tons] 5,000 TONS
A 043 New AF Asphalt Pavement / Processing 8,500 TONS A 044 New AF Asphalt Pavement (PG52-28) / Placement 2,000 TONS A 045 New AF Asphalt Pavement (PG58-28) / Placement 6,500 TONS A 046 New AF Asphalt Pavement / AF Shoulders / Lights 1,000 TONS A 047 New AF Asphalt Pavement / Runway Patches 1,000 TONS A 048 New AF Asphalt Pavement / Transitions 200 TONS A 049 New AF Asphalt Pavement / [< 2,500 Tons] 5,500 TONS
A 050 New AF AC Pavement / Cold Joint Removal 5,000 LF A 051 Runway Grooving 33,300 SY
Pavements - IDIQ
BID
Item #
Section B
JBER Elmendorf-Richardson
FA5000-12-R-0001
Bid Schedule / Base Year
FXSB 11-2102 Attachment 6 /Exhibit A
WORK ITEM ESTIMATED UNIT BID UNIT DOLLAR
QUANTITY PRICE AMOUNT
Pavements - IDIQ
BID
Item #
Section B
JBER Elmendorf-Richardson
FA5000-12-R-0001
Bid Schedule / Base Year
FXSB 11-2102 Attachment 6 /Exhibit A
A 052 AC Crack Sealing (Routing) 75,000 LF A 053 AC Crack Sealing (No Routing) 7,500 LBS A 054 AC/PCC and AC/AC Joint Sealing 5,000 LF A 055 New JFR Seal Coat (Squeegee-on) 1,000 SY A 056 New JFR Seal Coat (Trowel-on) 250 SY
A 057 Remove Existing Concrete Slabs (Isolated) 750 CY A 058 Remove Existing Concrete Slabs (Continuous) 3,000 CY A 059 Remove Concrete [> 12" Thick] 2,000 CY A 060 Remove Concrete [< 1,200 CY] 1,500 CY A 061 Remove Existing Concrete [Reinforced] 500 CY A 062 Remove Existing Concrete / Sawcutting 5,000 IN-LF
A 063 New Concrete Slabs (Isolated)-Replacement 750 CY A 064 New Concrete Slabs (Continuous)-Replacement 2,000 CY A 065 New Concrete Slabs (Continuous) 1,000 CY A 066 New Concrete Slabs [Crushed Rock] 500 CY A 067 New Concrete Slabs [15% Fly Ash] 500 CY A 068 New Concrete Slabs [25% Fly Ash] 500 CY A 069 New Concrete Slabs [< 12" Thick] 500 CY A 070 New Concrete Slabs [< 600 CY] 600 CY A 071 New Dowels Into Existing Concrete 2,000 EA
A 072 Cold Plane Exist PCC / AC Overlay / Continuous 10,000 SY-IN A 073 Cold Plane Exist PCC / AC Overlay [< 50,000 SY-IN] 5,000 SY-IN A 074 Repair Deteriorated Concrete Joints 2,500 SF
A 075 Concrete Spall Repairs (Isolated) 555 SF A 076 Concrete Spall Repairs (Continuous) 975 SF A 077 Concrete Spall Repairs (Quartz) 275 SF A 078 Concrete Spall Repairs [<250 SF] 250 SF A 079 Concrete Spall Repairs/Sawcutting 500 IN-LF
A 080 Concrete Crack Sealing 1,100 LF A 081 ReSeal Existing Concrete Joints 20,000 LF A 082 New Concrete Joint Sealing 5,000 LF A 083 Replace Grounding / Anchor Rods 25 EA A 084 Pavement Surface Repairs 200 SF A 085 Airfield FOD Clean-up 50 HR A 086 New Blast Deflectors-Taxi Power 200 LF A 087 New Blast Deflectors-Engine Run-up 200 LF A 088 New Pavement Markings for Airfields 20,000 LF A 089 Remove Pavement Markings for Airfields 5,000 LF Work Items Predominately for Roads:
A 090 Pulverize Existing Asphalt in Place 10,000 SY
A 091 New D-1 Base Course / Processing 13,000 TONS A 092 New D-1 Base Course / Placement 13,000 TONS A 093 New D-1 Base Course / 2"-4" Leveling Course 2,000 TONS A 094 New D-1 Base Course / AF Shoulders Placement 2,000 TONS A 095 New D-1 Base Course / Parking Lots [< 4,000 Tons] 3,000 TONS A 096 New D-1 Base Course / Roads [< 2,500 Tons] 2,500 TONS A 097 New D-1 Base Course / [First 10,000 Tons] 10,000 TONS A 098 New D-1 Base Course / [> 20,000 Tons] 5,000 TONS
A 099 New Road/Parking Lot Asphalt Pavement / Processing 6,500 TONS A 100 New Asphalt Pavement (PG52-28) / Placement 2,000 TONS A 101 New Asphalt Pavement (PG58-28) / Placement 4,500 TONS A 102 New Asphalt Pavement / [Transitions] 200 TONS
WORK ITEM ESTIMATED UNIT BID UNIT DOLLAR
QUANTITY PRICE AMOUNT
Pavements - IDIQ
BID
Item #
Section B
JBER Elmendorf-Richardson
FA5000-12-R-0001
Bid Schedule / Base Year
FXSB 11-2102 Attachment 6 /Exhibit A
A 103 New Asphalt Pavement / [Leveling Course] 500 TONS A 104 New Asphalt Pavement / Parking Lots [< 2,000 Tons] 2,000 TONS A 105 New Asphalt Pavement / Roads [< 1,500 Tons] 1,500 TONS A 106 New Asphalt Pavement / [< 750 Tons] 500 TONS Asphalt Pavement Adjustment [Airfield & Roads]:
A 107 New AC Pavement (AF & Roads) / [First 10,000 Tons] 10,000 TONS A 108 New AC Pavement (AF & Roads) / [> 25,000 Tons] 5,000 TONS
A 109 5,000 TONS
A 110 5,000 TONS
A 111 5,000 TONS
A 112 5,000 TONS
A 113 New Asphalt Pavement / [PG64-28] 1,000 TONS A 114 New Asphalt Pavement / [PG64-34] 1,000 TONS Work Items Predominately for Roads:
A 115 New Pavement Markings for Roads/Parking Lots 15,150 LF A 116 New Road Pavement / Cold Joint Removal 5,000 LF A 117 Not Used
A 118 Remove Curbs/Gutters (Isolated) 1,500 LF A 119 Remove Curb/Gutter (Isolated)/Sawcutting 500 LF A 120 Remove Curbs/Gutters (Continuous) 6,000 LF A 121 New Concrete Curbs & Gutters (Isolated) 1,000 LF A 122 New Concrete Curbs & Gutters (Continuous) 2,000 LF A 123 New Concrete Curbs & Gutters (Radius) 500 LF A 124 New Concrete Curbs & Gutters [< 3,600 LF ] 4,000 LF A 125 Remove Concrete Sidewalks (Isolated) 2,000 SY A 126 Remove Sidewalks (Isolated)/Sawcutting 500 LF A 127 Remove Concrete Sidewalks (Continuous) 2,500 SY A 128 New Concrete Sidewalks (Isolated) 2,000 SF A 129 New Concrete Sidewalks (Continuous) 3,000 SF A 130 New Concrete Sidewalks [< 4000 SF] 4,000 SF
A 131 Repair Catch Basins 10 EA A 132 Remove Catch Basins 5 EA A 133 New Curb Opening Catch Basins 5 EA A 134 Replace/New Guard Rails 100 LF Work Items for Repairing Roads:
A 135 AC Crack Sealing (Routing) 25,000 LF A 136 AC Crack Sealing (No Routing) 2,500 LBS A 137 UPM Cold Patch Repair 100 SF A 138 Patching / Pothole Repair / Utility Trench Repairs 1,000 SY A 139 Minor Asphalt Repair 2,000 SY New Work Items :
A 140 New 4" Topsoil 10 MSF A 141 New 4" Topsoil [< 10 MSF] 5 MSF A 142 New Hydroseeding 10 MSF A 143 New Hydroseeding [< 10 MSF] 5 MSF A 144 New Grass Sod 500 SF A 145 New Trees Planted In Place 20 EA A 146 New Shrubs Planted In Place 50 EA A 147 New Shredded Bark Mulch 2,000 SF A 148 New Contour Grading for Landscaping 2,000 SY A 149 New Bike Trails / Paths 5,000 SY A 150 New Bike/Handicap Access Ramps 25 EA A 151 New Concrete Driveways 1,000 SF A 152 New Concrete Barrier Walls 200 LF A 153 New Concrete Wheel Stops 10 EA A 154 New Encase Conduits in Concrete 20 CY A 155 New Concrete Loading Docks/Handicap Platforms 100 CY
New AC Pavement (Non-Airfield) with 30% RAP Added New AC Pavement (Non-Airfield) with 40% RAP Added New AC Pavement (Non-Airfield) with 50% RAP Added
New AC Pavement (Non-Airfield) with 20% RAP Added
WORK ITEM ESTIMATED UNIT BID UNIT DOLLAR
QUANTITY PRICE AMOUNT
Pavements - IDIQ
BID
Item #
Section B
JBER Elmendorf-Richardson
FA5000-12-R-0001
Bid Schedule / Base Year
FXSB 11-2102 Attachment 6 /Exhibit A
A 156 New Metal Handrails 200 LF A 157 New Protective Pipe Bollards 8 EA A 158 New Traffic / Information Signs on Sign Posts 5 EA
A 159 New 4" diameter PVC Conduit 400 LF A 160 New 4" diameter GRC Conduit 700 LF A 161 New 2" diameter PVC Conduit 150 LF A 162 New 2" diameter GRC Conduit 150 LF A 163 New 4" diameter Split Duct Conduit 50 LF
A 164 New 12" diameter Culvert 200 LF A 165 New 12" diameter Drain Pipe 100 LF A 166 New 24" diameter Drain Pipe 120 LF A 167 New 36" diameter Drain Pipe 60 LF A 168 New Manholes/Catch Basins/Aircraft rated 2 EA A 169 New Drain Rock 200 TONS A 170 New Thaw Pipe In Culverts 100 LF A 171 New EPS Insulation Board 600 SF Miscellaneous Work Items :
A 172 Adjust Pavement Structures 25 EA A 173 Replace Manhole Covers and Rings 10 EA A 174 Adjust Existing Utilties 10 EA A 175 Relocate Fire Hydrants 2 EA A 176 Relocate POL Pit 1 EA
A 177 Asphalt Crushing 10,000 TONS A 178 Crush Existing Concrete in Place 20,000 TONS A 179 Recycled Asphalt Pavement (Placement) 5,000 TONS A 180 Flagging/Traffic Operation 50 MH A 181 Hauling Material 15,000 TON-MI A 182 Slope Reclamation Using Reject 2,500 TONS A 183 Silt Fencing 500 LF A 184 SWPP Plan 5 EA A 185 Free Zone Barriers 2,000 LF A 186 Remove Unusable Soil (North End of North/South Runway) 500,000 BCY Testing / Quality Control / Surveying :
A 187 Asphalt Cores 20 EA A 188 Concrete Cores 20 EA A 189 Construction Surveying 350 HOURS A 190 As-Built Survey on CAD 50 HOURS
A 191 Indep Quality Control-Base Course / Subbase 50 LOTS A 192 Indep Quality Control-AC Pavement 100 SUBLOTS A 193 Indep Quality Control-Concrete Pavement 8 LOTS A 194 Testing-Base Course / Subbase 50 LOTS A 195 Testing-Asphalt Pavement 100 SUBLOTS A 196 Testing-Concrete Pavement 8 LOTS Fuel Contaminated Soils:
A 197 Test Fuel-Contaminated Soil 20 EA A 198 Remediate Fuel-Contaminated Soil 50 TONS Traffic Lights and Control System:
A 199 Mast/Arm/Post Assembly 4 EA A 200 Extension Pole for Street Light & Photocell 2 EA A 201 Traffic Signal Head & Hardware Type I 2 EA A 202 Traffic Signal Head & Hardware Type II/III/IV 2 EA A 203 Pedestrian Signals, Push Buttons & Signs 4 EA SYS A 204 Traffic Signal Controller Sys / Intersection Style I 1 EA SYS A 205 Traffic Sensor Loop System 4 EA SYS A 206 Secondary Power Service 1 LS
WORK ITEM ESTIMATED UNIT BID UNIT DOLLAR
QUANTITY PRICE AMOUNT
Pavements - IDIQ
BID
Item #
Section B
JBER Elmendorf-Richardson
FA5000-12-R-0001
Bid Schedule / Base Year
FXSB 11-2102 Attachment 6 /Exhibit A
A 207 Directional Traffic Signs 6 EA Light Bases, Light Poles, Heater Outlets:
A 208 Remove Existing Concrete Light Bases 5 EA A 209 New Concrete Light Bases 5 EA A 210 Raise/Lower Concrete Light Bases in Place 10 EA A 211 New Airfield Light Fixtures / Existing Conc Base 10 EA A 212 Re-Use Existing Airfield Light Fixtures 20 EA A 213 New Airfield Lighting Fixtures-Flush / New Conc Bases 25 EA A 214 New Airfield Lighting Fixtures-Elevated/New Conc Bases 50 EA A 215 New Airfield Lighting Cabling 2,000 LF A 216 New Street/Parking Lot Light Poles 3 EA
A 217 5 EA
A 218 5 EA
A 219 5 EA
A 220 New Head Bolt Heater Outlet Posts / Multiple 16 EA A 221 New Head Bolt Heater Outlet Posts / Singular 4 EA A 222 Secondary Power Service 1 LS Borrow Pit Materials for Purchase A 223 D-1 Base Course for BCE (On-base Source) 20,000 TONS A 224 Hot Mix PG52-28 Asphalt for BCE (On-base Source) 5,000 TONS
Total of Line Items Bonding A 225 Bonding Premium 1 LS
PG 52-28 Asphalt oil cost per ton:
PG 58-28 Asphalt oil cost per ton:
Estimated Total for Base Year Bid Items A001 thru A225:
New Street/Parking Lot Light Pole Arm New Street/Parking Lot Light New Airfield Ramp Security Lighting