atch 1 2560 Asphalt Tack.pdf

PDF 84 KB Posted

Attached to
Paving Requirements Joint Base Elmendorf-Richardson AK Federal contract opportunity
Solicitation number
FA5000-12-R-0001
Issued by
Department of the Air Force Pacific Air Forces

About this file

atch 1 2560 Asphalt Tack

View the file

Other files for this federal contract opportunity

Other files attached to Paving Requirements Joint Base Elmendorf-Richardson AK, newest first.
File Type Posted
Atch 6 Option Year 6.pdf PDF
Atch 6 Option Year 5.pdf PDF
Atch 6 Option Year 1.pdf PDF
Atch 6 Option Year 2.pdf PDF
Atch 6 Option Year 4.pdf PDF
Atch 6 Option Year 3.pdf PDF
Bid Questions 8 May 12.pdf PDF
atch 1 1020 scope —
atch 4 Wage 20 Apr 12.pdf PDF
FA5000-12-R-0001 solicitation.doc DOC document
FA5000-12-R-0001 Sol 18 Apr 12.doc DOC document
atch 7 EPA CLINS.pdf PDF
atch 6 Contractor Bid Schedules Option 4.pdf PDF
atch 1 2530 Asphalt Pavemnet Crack Seal.pdf PDF
atch 6 Contractor Bid Schedules Option 3.pdf PDF
atch 1 2572 Re-Sealing.pdf PDF
atch 1 2576 Hydraulic Cement Repair.pdf PDF
atch 1 2515 Concrete Pavements.pdf PDF
atch 6 Contractor Bid Schedules Option 1.pdf PDF
atch 6 Contractor Bid Schedules Option 2.pdf PDF
atch 1 16370 Electrical Distribution Systems Aerial.pdf PDF
atch 1 2510 Concrete Sidewalks.pdf PDF
atch 1 2100 Asphalt pavements.pdf PDF
atch 10 Subcontractor Teaming Partner Consent Form.pdf PDF
atch 1 1010 General Requirements.pdf PDF
atch 1 1120 Environmental.pdf PDF
atch 1 16375 Electrical Distribution System Underground.pdf PDF
atch 1 2570 Joint Sealing.pdf PDF
atch 1 2567 Rubberized Tar Seal Coat.pdf PDF
atch 9 Past Performance Questionnaire.pdf PDF
Atch 2 drawings Apt 11.pdf PDF
atch 6 Contractor Bid Schedules Summary.pdf PDF
atch 6 Contractor Bid Schedules option 5.pdf PDF
atch 1 1121 Accumulation.pdf PDF
atch 4 Wage AK1 13 Apr 12.pdf PDF
atch 1 2550 Hot Mix Asphalt.pdf PDF
atch 1 2590 Pavement Markings for Airfields.pdf PDF
atch 1 2575 Spall Repair.pdf PDF
atch 8 Past Performance Instruction.pdf PDF
atch 1 1020 scope.pdf PDF
Atch 5 WeDateElm.pdf PDF
atch 1 2936 Hydro Seeding.pdf PDF
atch 1 2230 Crusher Agg Base Airfields.pdf PDF
atch 6 Contractor Bid Schedules option 6.pdf PDF
atch 1 2595 Pavement Markings for Roads.pdf PDF
atch 3 Form66.pdf PDF
atch 1 2540 Cold Planing.pdf PDF
atch 1 2225 Sub Base.pdf PDF
atch 1 2235 Crusher Agg Base roads.pdf PDF
atch 6 Contractor Bid Schedules Base Year.pdf PDF
Show all 50

Paving Requirements Joint Base Elmendorf-Richardson AK has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Asphalt Tack & Prime Coat FA5000-12-R-0001 Attachment 1

2560- 1

1. SCOPE:

1.1 This section covers asphalt tack and prime coats.

2. REFERENCED SPECIFICATIONS:

2.1 Alaska Department of Highways "Standard Specification for Highway Construction, "most current version, is included as part of these specifications to the extent noted hereinafter. Where the referenced specifications conflict with requirements noted in these specifications, these specifications will take procedures. Contractor shall submit one complete set of the referenced specifications to the Government to aid in evaluating the Contractor's submittals.

3. SUBMITTALS:

3.1 Contractor shall submit the most recent Laboratory Report - Certificate of Analysis for the tack coat and prime coat to the Contracting Officer for approval prior to placement.

4. MATERIALS: Materials shall conform to the following grades and types:

4.1 Prime Coat: ASTM D 2397, Grade CSS-1

4.2 Tack Coat: Type STE-1 (Snap Tack Emulsion), no dilution.

5. CONSTRUCTION REQUIREMENTS:

5.1 Shall conform to Alaska Department of Highways specifications Sections 402-3.01 to 3.05, and 403-3.01 to 3.05. The application temperature range for CSS-1 shall be between 165 degrees F to 190 degrees F or the manufacturer’s instructions. The application temperature range for STE-1 shall be between 150 degrees F to 180 degrees F or the manufacturer’s instructions. The tack or prime coat material shall not be covered until full curing has been accomplished (95 percent evaporation of base liquid). Curing time for the prime coat shall be a minimum of 24 hours. Curing time for the tack coat shall be a minimum of 2 hours or as per manufacturer’s recommendations.

6. APPLICATION RATES:

6.1 Application rates for STE-1 mixture shall be .03 to .09 gal/sy for tack coats as determined by the project engineer. Application rates for the CSS-1 for prime coats shall be .1 to .35 gal/sy as determined by the project engineer. The tack coat and prime coat shall uniformly cover the entire surface of the area to be resurfaced.

7. CONTRACTOR’S QUALITY CONTROL:

Pavements - IDIQ

FXSB 11-2102

Section 2560

Asphalt Tack & Prime Coat

Asphalt Tack & Prime Coat FA5000-12-R-0001 Attachment 1

2560- 2

7.1 Assure that application is uniform over the entire surface and at proper application rates.

Assure that a hand wand is used to apply the tack coat uniformly at the proper application rate on all vertical surfaces. Assure that the contractor does not pave until the tack coat or prime coat has properly cured or "broken". Assure that the contractor cleans up any tack coat or prime coat that has not properly cured. Assure that amount of tack coat placed is for one day's paving operation.

Assure that tack coat and prime coat that is picked up and tracked by vehicles is cleaned up.

8. PAYMENT:

8.1 Tack coat application is not paid separately, but is included under appropriate asphalt paving pay item. Prime coat application is not paid separately, but is included under appropriate BASE course pay item.

End of Section