Addendum__1.pdf

PDF 53 KB Posted

Attached to
Malmstrom AFB Multiple Award Task Order Contract (MATOC) Federal contract opportunity
Solicitation number
FA462619RA014
Issued by
Department of the Air Force Global Strike Command

About this file

This addendum provides fifteen revisions to construction documents for repair work at Malmstrom Air Force Base under solicitation number FA462619RA014. Key changes include replacing flooring materials at stairwell landings and vending areas, substituting solid surface for tile in showers, removing references to carpet and rubber base installation in storage rooms, updating fixture quantities in general notes, and adding a hatch pattern to denote rubber flooring in stairwells. The solicitation is for a multiple award task order contract to be awarded by the Department of the Air Force Global Strike Command for repair and construction services at Malmstrom AFB.

Dated 19 Aug 2019.

View the file

Other files for this federal contract opportunity

Other files attached to Malmstrom AFB Multiple Award Task Order Contract (MATOC), newest first.
File Type Posted
Q&A__5.docx DOCX document
Q&A__4.pdf PDF
Q&A__4_Attachment_2_-_09_72_00_FL_-_Wall_Coverings.pdf PDF
Specifications_-_Table_of_contents_(Amended).pdf PDF
Q&A__4_Attachment_1_-_Cabinet_Bottom.pdf PDF
Amendment_1_FA462619RA0140001.pdf PDF
Q&A__3_Attachment_1_-_Irrigation_mainline_as-builts.PDF PDF
Q&A__3.docx DOCX document
PreProposal_SiteVisit_Minutes.pdf PDF
Pre-Proposal_Conference_Sign-in_Roster.pdf PDF
Q&A__2.docx DOCX document
Q&A__2_Attachment_1_-_Asbestos_Survey.pdf PDF
Q&A__2_Attachment_3_-_Drawing_M1.4_Bid_Docs_-_MAFB_Dorm_655.pdf PDF
Q&A__2_Attachment_2_-_08_14_16_FL_-_FLUSH_WOOD_DOORS.pdf PDF
Attach_6_Drawing_M1.3.pdf PDF
Q&A__1.docx DOCX document
Attach_6_Drawing_FULL_Set_Repair_Dorm_655_Part_2.pdf PDF
Attach_6_Drawing_FULL_Set_Repair_Dorm_655_Part_8.pdf PDF
Attach_6_Drawing_FULL_Set_Repair_Dorm_655_Part_6.pdf PDF
Attach_6_Drawing_FULL_Set_Repair_Dorm_655_Part_3.pdf PDF
Attach_6_Drawing_FULL_Set_Repair_Dorm_655_Part_4.pdf PDF
Attach_6_Drawing_FULL_Set_Repair_Dorm_655_Part_7.pdf PDF
Attach_6_Drawing_FULL_Set_Repair_Dorm_655_Part_5.pdf PDF
Attach_2_Specifications_Repair_Dorm_655_Part_2.pdf PDF
Attach_6_Drawing_FULL_Set_Repair_Dorm_655_Part_1.0.pdf PDF
Attach_2_Specifications_Repair_Dorm_655_Part_4.pdf PDF
Attach_4_Full_Submittal_Schedule_Repair_Dorm_655.xls XLS spreadsheet
Attach_14_MATOC_Task_Order_Procedures_Rev4.docx DOCX document
Attach_10_On-Off_Ramp_Procedures_Rev1.docx DOCX document
Attach_7_Installation_Perimeter_Access_Control.pdf PDF
Attach_2_Specifications_Repair_Dorm_655_Part_1.pdf PDF
Attach_3_Bid_Schedule_Repair_Dorm_655.xlsx XLSX spreadsheet
Attach_9_Subcontractor_Consent_Rev_1.doc DOC document
Attach_1_MATOC_Statement_of_Work_Rev2.doc DOC document
Attach_5__Schedule_of_Drawings_Repair_Dorm_655.doc DOC document
Attach_8_Past_Performance_Questionaire_Rev1.docx DOCX document
Attach_2_Specifications_Repair_Dorm_655_Part_3.pdf PDF
Attach_11_SECTION_L_Rev1.docx DOCX document
Attach_12_SECTION_M_Revision_5.docx DOCX document
Solicitation_-_FA462619RA014.pdf PDF
Attach_13_Wage_Determinations.docx DOCX document
Show all 41

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ADDENDUM #1

Repair B-655

Malmstrom AFB, MT

NZAS 04-1042

19 AUG 2019

FA4626-19-R-A014

ITEM REFERENCE DESCRIPTION

A1.02

ADD: At stairwell landings, demo existing flooring. Some landings are rubber flooring and some are sheet vinyl

2 A1.00 and A1.01, Detail 1

CHANGE: Change the keynote for stairwell landings from 7 to 6.

Also note that some landings are sheet vinyl and some are rubber flooring

3 A2.03 thru A2.05 At Finish Schedule Note 2, delete painting of wood rail and instead re-stain

4 A2.04 thru A2.05 Change flooring for vending areas 2111 and 3111 from CPT to QT 5 A2.00 thru A2.02, Keynote 3 Change shower from tile finish to solid surface

6 A1.00 thru A1.02 Delete removal of carpet in rooms 1004,1055,2002,2053,3002, and 3053 (Storage rooms). Existing floors are concrete

7 A2.03 thru A2.05 Delete install of carpet in rooms 1004,1055, 2002, 2053, 3002, and 3053 (Storage rooms).

8 A4.00, Detail 10 Delete reference to Keynote 9 that re-installs rubber wall base. Install carpet base cove instead

9 General Finishes In all carpeted areas, install carpet base cove. Do not install rubber wall base

10 A2.03 thru A2.05 Delete floor finish legend item “calculating” and associated hatch symbol

11 A2.0 Change Keynote 7 to “Install (N) sink in (N) solid surface top.”

12 Spec 08 71 10 para 3.5 Change in Set 3.0 “1 Exit Device” to “2 Exit Device” 13 E1.1 Delete General Demolition Note 9 14 A1.00 Change quantities under General Notes – Fixtures and Furnishings for kitchen table, microwave, refrigerator, and range to read “48 (1per unit)”

15 A2.04 and A2.05 Add: In the stairwells, all stairs and landings should be hatched for rubber flooring

File details come from the government source that posted it. Updated .