Addendum__1.pdf
PDF 53 KB Posted
- Attached to
- Malmstrom AFB Multiple Award Task Order Contract (MATOC) Federal contract opportunity
- Solicitation number
- FA462619RA014
About this file
This addendum provides fifteen revisions to construction documents for repair work at Malmstrom Air Force Base under solicitation number FA462619RA014. Key changes include replacing flooring materials at stairwell landings and vending areas, substituting solid surface for tile in showers, removing references to carpet and rubber base installation in storage rooms, updating fixture quantities in general notes, and adding a hatch pattern to denote rubber flooring in stairwells. The solicitation is for a multiple award task order contract to be awarded by the Department of the Air Force Global Strike Command for repair and construction services at Malmstrom AFB.
Dated 19 Aug 2019.
View the file
Other files for this federal contract opportunity
Show all 41
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ADDENDUM #1
Repair B-655
Malmstrom AFB, MT
NZAS 04-1042
19 AUG 2019
FA4626-19-R-A014
ITEM REFERENCE DESCRIPTION
A1.02
ADD: At stairwell landings, demo existing flooring. Some landings are rubber flooring and some are sheet vinyl
2 A1.00 and A1.01, Detail 1
CHANGE: Change the keynote for stairwell landings from 7 to 6.
Also note that some landings are sheet vinyl and some are rubber flooring
3 A2.03 thru A2.05 At Finish Schedule Note 2, delete painting of wood rail and instead re-stain
4 A2.04 thru A2.05 Change flooring for vending areas 2111 and 3111 from CPT to QT 5 A2.00 thru A2.02, Keynote 3 Change shower from tile finish to solid surface
6 A1.00 thru A1.02 Delete removal of carpet in rooms 1004,1055,2002,2053,3002, and 3053 (Storage rooms). Existing floors are concrete
7 A2.03 thru A2.05 Delete install of carpet in rooms 1004,1055, 2002, 2053, 3002, and 3053 (Storage rooms).
8 A4.00, Detail 10 Delete reference to Keynote 9 that re-installs rubber wall base. Install carpet base cove instead
9 General Finishes In all carpeted areas, install carpet base cove. Do not install rubber wall base
10 A2.03 thru A2.05 Delete floor finish legend item “calculating” and associated hatch symbol
11 A2.0 Change Keynote 7 to “Install (N) sink in (N) solid surface top.”
12 Spec 08 71 10 para 3.5 Change in Set 3.0 “1 Exit Device” to “2 Exit Device” 13 E1.1 Delete General Demolition Note 9 14 A1.00 Change quantities under General Notes – Fixtures and Furnishings for kitchen table, microwave, refrigerator, and range to read “48 (1per unit)”
15 A2.04 and A2.05 Add: In the stairwells, all stairs and landings should be hatched for rubber flooring