This is a Task Assignment (TA) Document DC-002A issued under Contract HW682 between the State of Florida Department of Environmental Protection (FDEP) and Environmental Consulting and Technology, Inc. (ECT). The Task Assignment was effective February 20, 2023, with a completion date of August 4, 2023, and authorizes ECT to perform Soil Vapor Extraction (SVE) system electrical testing and SVE Verification Testing at the Town & Country Cleaners facility located at 1005 NW 76th Boulevard, Gainesville, Florida 32608 (Project Number ERIC_3985). The Department Project Manager is Kelly Crain, and the Contractor's Project Manager is Mark A. Culbreth.
The total Task Assignment value is $16,131.95 on a Fixed Unit Rate basis. The contract consists of three subtasks: SubTask 1 (Project Management) at $1,087.57; SubTask 2 (SVE System Electrical Testing and Analysis Memo) at $7,304.85, due May 3, 2023; and SubTask 3 (SVE Verification Testing Report) at $7,739.53, due June 23, 2023. Invoicing is contingent upon FDEP approval of deliverables. The scope includes system electrical evaluation by a licensed electrician, generator-powered SVE verification testing with soil vapor sample collection, preparation of a system analysis memorandum and verification testing report, and recommendations for repair or replacement. Subcontractor costs include generator rental ($2,200.00), electrical control panel services ($1,125.00), diesel fueling ($350.00), laboratory analysis ($1,200.00), and field supplies.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Funding Information:
Org. Code E.O. Object Code Budget Entity Appropriation
Category Grant # Project # Year Amount
Additional Funding Information attached on separate page.
Rev. 8/26/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .
1. TA Number: TA Completion Date:
TA Description:
2. Parties State of Florida Department of Environmental Protection (Department)
Department Project Manager: Department Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number)
Project Location(s):
Project Name:
4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:
Fixed Price:
Fixed Unit Rate: (Extended Price)
Cost Reimbursement:
Total TA Value:
5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:
Attachment 1:
Additional Attachments (if necessary):
IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.
State of Florida Department of Environmental Protection
CONTRACTOR Department Name:
Title: Secretary or Designee
(Authorized Signature) (Authorized Signature) Date:
Additional signatures attached on separate page.
HW682
DC002A Completion August 4, 2023
ECT will perform a Soil Vapor Extraction (SVE) system electrical testing and SVE Verification Testing in accordance with the scope of work and cost proposal submitted on February 7, 2023.
Kelly Crain 850-245-8953 Contractor Environmental Consulting and Technology, Inc. (ECT) Contractor
Contractor Mark A. Culbreth Contractor 813-289-9338
ERIC_3985
1005 NW 76th Blvd. Gainesville, FL 32608
Town & Country Cleaners
Contractor Contractor
✔ $ 16,131.95
$ 16,131.95
Select One
Environmental Consulting and Technology, Inc. (ECT Contractor Mark A. Culbreth
Contract Manager Digitally signed by Mark Culbreth DN: CN=Mark Culbreth, E=mculbreth@ectinc.com Reason: I am approving this document Location: your signing location here Date: 2023.02.20 08:44:25-05'00' Foxit PhantomPDF Version: 10.1.6
Mark Culbreth Kelly Crain Digitally signed by Kelly Crain Date: 2023.02.20 08:39:36 -05'00'
N/A
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WC TAFORM
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
SVE System Analysis Memo (Subtask 2) 05/03/2023
SVE Verification Testing Report and PM (Subtask 3 and 1) 06/23/2023
FDEP Approval of SVE System Analysis Memo (Subtask 2) $ 7,304.85
FDEP Approval of SVE Verification Testing Report and PM (Subtask 3 and 1) $ 8,827.10
$ 16,131.95
HW682
DC002A
FFLORIDAA DEPARTMENTT OF
EEnvironmentall Protection
Bob Martinez Center 2600 Blair Stone Road
Tallahassee, FL 32399-2400
Ronn DeSantis Governor
Jeanette Nuñez Lt. Governor
Shawnn Hamilton Secretary
Memorandum
TO:
FROM:
SUBJECT:
DATE:
HW682 Contract File Cleaners
ERIC_3985
Kelly Crain, Project Manager Negotiation Summary Task Assignment DC-002A February 10, 2022
This Task Assignment authorizes ECT to conduct Soil Vapor Extraction (SVE) system electrical testing and SVE Verification Testing in accordance with the scope of work and cost proposal submitted on February 7, 2023. ECT will perform testing and troubleshooting of the SVE system with a licensed electrician, and if the system is operable will use a generator to perform SVE Verification testing including collection of soil vapor samples after 60-minutes of run-time per well based on the pore volume calculations.
ECT will provide a memorandum summarizing the condition of the system, whether the system is operable and recommendations for repair or replacement. A SVE Verification Testing Report will be prepared detailing the results of the test and recommendations for next steps.
ECT will ensure that the Department has a current site access agreement in place prior to initiating field activities.
The final costs associated with this Task Assignment are $1 . ECT may invoice according to the attached schedule.
FDEP COST ESTIMATEContractor: Environmental Consulting & Technology, Inc.
Date: 7-Feb-23
Task #: SubTask 1 Project Management
Site: Town & Country Cleaners SubTask 2 SVE System Electrical Testing
Activity/Phase: SubTask 3 SVE System Verification Testing
Project Manager: Mark Culbreth SubTask 4
SubTask 5
TTotals 1 2 3 4 Labor Rate Category
$80.12 PProject Manager 4.5 4.5 $80.12 Senior Principal Scientist (MC) 2 0.0 2.0 0 $52.89 Senior Engineer / Scientist (GS) 34 18.0 16.0 0 $26.54 GIS Analyst / Graphics (JV) 6 0.0 6.0 0 $22.44 Technician (BC) 21.5 13.0 8.5 0 $31.45 Administrative (BJ) 6 0.0 6.0 0
Total Hours 74.5 5 31.0 38.5 0
Direct Labor $3,151.46 $362.56 $1,243.74 $1,545.16 $0.00
Overhead 125.30% $3,948.79 $454.29 $1,558.41 $1,936.09 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 47.40% $1,493.79 $171.85 $589.53 $732.41 $0.00 Total Labor $8,594.04 $988.70 $3,391.68 $4,213.66 $0.00
Travel Vehicle Rental $240.00 $120.00 $120.00 $0.00 Per diem + Hotel $414.00 $414.00 $0.00 $0.00 Total Travel $654.00 $534.00 $120.00 $0.00
Subcontractor (Equipment Procurement) Generator Rental $2,200.00 $1,100.00 $1,100.00 $0.00 Diesel Fueling $350.00 $175.00 $175.00 $0.00 Electrical Control Panel Subcontractor $1,125.00 $1,125.00 $0.00 $0.00 Subcontractor Subtotal $3,675.00 $2,400.00 $1,275.00 $0.00 Procurement Fee $367.50 $240.00 $127.50 $0.00 Total Subcontractor Cost $4,042.50 $2,640.00 $1,402.50 $0.00
Subcontractor (Services Procurement) Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 Handling Fee $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00
Laboratory Analytical Costs $1,200.00 $0.00 $1,200.00 $0.00 Sample Shipping $52.00 $0.00 $52.00 $0.00 Total Laboratory $1,252.00 $0.00 $1,252.00 $0.00
Field Expenses Expendables $80.00 $40.00 $40.00 $0.00 Construction/O&M/Pilot Test Kit $360.00 $360.00 $0.00 $0.00 Soil Vapor Sampling Kit $290.00 $0.00 $290.00 $0.00 Total Field Expenses $730.00 $400.00 $330.00 $0.00
Subtotal $15,272.54 $988.70 $6,965.68 $7,318.16 $0.00 Completion Fee $859.41 $98.87 $339.17 $421.37 $0.00
Total Estimated Cost $16,131.95 $1,087.57 $7,304.85 $7,739.53 $0.00
Soil Vapor Extraction Verification Testing
REV: 02/03 CEF ECT Page 1
LEVEL OF EFFORT/EXPENSE WORKSHEET
SITE : Town & County Cleaners SUBTASK SVE System Electrical Testing
DATE: 2/7/2023
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
G. Sattler Senior Engineer Verify and Notify RPO of field activities 2 Prepare Health and Safety Plan 2 Round trip Mobilize to Gainesville 5 Troubleshooting System 8 Prepare memorandum 1
Total hours 18 Total hours 0
B. Carrick Technician Prepare for the SVE event 0.5 Round trip Mobilize to Gainesville 4 Setup, opening and closing calibration of equipment 0.5 Troubleshooting System for SVE operation 8
Total hours 13
TOTAL LABOR 31
VEHICLE TYPE RATE UNIT USEAGE
G. Sattler Rental Truck $120.00 day 1 $120.00 B. Carrick Rental Truck
TOTAL VEHICLE $120.00
PER DIEM STAFF RATE UNIT USEAGE
Per Diem B. Carrick $36.00 day 2 $72.00 Hotel B. Carrick $135.00 day 1 $135.00
Per Diem G. Sattler $36.00 day 2 $72.00 Hotel G. Sattler $135.00 day 1 $135.00
TOTAL PER DIEM $414.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST UNIT
Equipment with Experience Generator Rental $1,100.00 1 $1,100.00 Equipment with Experience Diesel Fuel $175.00 1 $175.00 Electrical Control Panel Subcontractor System Troubleshooting $1,125.00 1 $1,125.00
TOTAL $2,400.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
TOTAL LAB $0.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Expendables $40.00 Event 1 $40.00 Construction/O&M/Pilot Test Kit $360.00 Day 1 $360.00
TOTAL EQUIPMENT $400.00
FINAL --7/24/96
LEVEL OF EFFORT/EXPENSE WORKSHEET
SITE : Town & County Cleaners SUBTASK:SVE System Verification Testing
DATE: 2/7/2023
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
M. Culbreth Sr. Principal Scientist Develop conclusions and recommendations to prepare final SVE System Verification Test Report 2 Total hours 2
G. Sattler System Verification test and collect SVE well Samples 8 Prepare SVE Verification Resting Report 8
Total hours 16 J. Von Borstel GIS Analyst Update Figure 6
Total hours 6 B. Carrick Technician Prepare for the SVE event 0.5
System Verification test and collect SVE well Samples 8 Total hours 8.5
B. Jarvis Administrative Recreate Tables and report production 6 Total hours 6
TOTAL LABOR 38.5
VEHICLE TYPE RATE UNIT USEAGE
B. Carrick Rental Truck $120.00 day 1 $120.00 G. Sattler
TOTAL VEHICLE $120.00
PER DIEM STAFF RATE UNIT USEAGE
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
Equipment with Experience Generator Rental $1,100.00 $1,100.00 Equipment with Experience Diesel Fuel $175.00 $175.00
TOTAL $1,275.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
TO-15 $200.00 6 $1,200.00
Sample Shipping $52.00 1 $52.00
TOTAL LAB $1,252.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Expendables $40.00 Event 1 $40.00 Soil Vapor Sampling Kit $290.00 Day 1 $290.00
TOTAL EQUIPMENT $330.00
FINAL --7/24/96
5315 56th Commerce Park Blvd.
Tampa, FL 33610
Phone (813) 413-7760 eWe – Your Partner in Remediation Fax (813) 413-7761
- 1 - EWE-2346
January 4, 2023
Ms. Greg Sattler, P.E.
Environmental Consulting Technologies, Inc.
3660 Maguire Blvd., Suite 234 Orlando, FL 32803 VIA Email
RE: 8 Hr SVE Episodic Event Town & Country Cleaners 1005 NW 76th Boulevard Gainesville, FL
EWE-2346
Dear Ms. Sattler:
Equipment with Experience (EWE) is pleased to submit this proposal to provide the generator and wires for the 8 Hr SVE Episodic Event at the above-referenced location. EWE proposes to provide the generator and services as per information provided by Environmental Consulting Technologies, Inc. The cost to provide this equipment/service is detailed on the attached Proposal.
Equipment and services to be provided:
20 KW Generator/Fuel and operation (wires to control panel) Transportation, setup, well connections, and operation
If there are questions or comments concerning the above, please call Tom Twitmyer at (813) 413-7760. If you would like to proceed with scheduling the above referenced work please sign and return one copy of the proposal to EWE. EWE thanks you for this opportunity to be of service; we look forward to working with you in the future.
Sincerely, Equipment with Experience, LLC
Thomas F. Twitmyer, P.G.
Attachments: Proposal, Standard Terms/Conditions
- 2 - EWE-2346
PROPOSAL
8 Hr SVE Episodic Event
Environmental Consulting Technologies, Inc.
Town & Country Cleaners 1005 NW 76th Boulevard
Gainesville, FL
Please initial and return to the attention of: Thomas Twitmyer – Tomt@ewithe.net
APPROVED ITEM DESCRIPTION RATES UNIT QUANTITY COST
3 phase wires $150 /job 1 $150
Transportation and operation $450 /job 1 $450
Power Supply 55 KW three phase generator $500 /job 1 $500
TOTAL ESTIMATED COSTS $1,100
NOTES:
Estimate valid for 90 days
DATE SERVICES NEEDED: PROPOSAL PREPARED: 1/4/2023
START TIME: ESTIMATED HOURS ON SITE:
PURCHASE ORDER NO.: EWE JOB NO.: EWE -2346
PAYMENT TERMS: Net 30 Days APPROVED COST
BILLING INFORMATION: Officer* Date *Signature Acts as Notice to Proceed at Contract Price
Payment Remitted to: ATTENTION: Ms. Greg Sattler , P.E.
Equipment with Experience, LLC Environmental Consulting Technologies, Inc.
5315 56th Commerce Park Blvd 3660 Maguire Blvd., Suite 234 Tampa, FL 33610 Orlando, FL 32803
PHONE: (407) 367-3064
FAX:
Email: gsattler@ectinc.com
Thomas F. Twitmyer, EWE Environmental Consulting Technologies, Inc.
- 3 - EWE-2346
Standard Terms/Conditions ACCEPTANCE: This proposal is an invitation for an offer and will become a binding contract when accepted.
LIMITATION OF PROPOSAL: The prices and terms quoted in this proposal are subject to acceptance by the Purchaser within a period of (30) calendar days from the date hereon.
EXCLUSIONS: This proposal is based solely and completely on specifications submitted to Equipment with Experience, Inc. (EWE) at the time of the writing of the proposal. General plans and specification not actually submitted shall not apply. This proposal, together with all annexed specifications, when accepted, shall be the complete agreement between the parties; and any alternations or unusual and undisclosed conditions or deviations from the above specifications involving extra costs shall be agreed upon in writing by both parties and shall become an additional charge over and above the proposal price set forth herein. Delays or impossibility of performance by EWE because of reasons beyond the control of EWE shall relieve us from all liability herein.
TERMS OF PAYMENT: Subject to the payment terms described in the General Conditions section in the proposal. We reserve the right to cancel the contract or cease work if payments thereon are not received when due. 1.5% per month shall be charged on all unpaid balances.
TAXES: The Purchaser shall pay any local, state or federal sales, excise or use tax imposed on the equipment in addition to the prices quoted.
WARRANTY LIMITATION: There are no warranties that extend beyond the warranties herein after expressed.
WARRANTIES: All work shall be done in a workmanlike manner according to standard practices. We agree to pass on to the Purchaser such warranties, if any, as may be extended by the manufacturer for material supplied. Labor for replacing defective materials shall not be provided by us unless it is specifically spelled out in the proposal. We shall not be responsible for materials damaged, lost or stolen after delivery, through no fault of ours, or for failure to deliver and perform because of reasons beyond our control.
EXCLUSIVE REMEDIES: Remedies are limited to the repair or replacement at FOB point of delivery. Consequential damages are excluded. In no event shall EWE be responsible for consequential damages of any such defective material or workmanship including, but not limited to, the Purchaser's loss of material or profits, increased expenses of operation, downtime or reconstruction of the work, and in no event shall EWE ' obligation under this warranty exceed the original contract price of the defective item.
DISCLAIMER: EWE will not be responsible for damage to equipment or materials through improper installation, storage, improper services, or through attempts to operate it in excess of its rated capacity or recommended use, intentional or otherwise, by parties other than EWE or its authorized representatives.
CONDITIONS OF SALE: Prices quoted are those now in effect. Seller reserves the right to bill at the prices in effect at the time of shipment if the proposal is not accepted in writing within thirty (30) days, unless a longer term of validity is in writing on the proposal.
LIMITATIONS OF LIABILITY
A. Neither Seller nor its suppliers of any tier will be liable to Purchaser, whether in contract, in tort (including negligence and strict liability), under any warranty or otherwise, for any special, indirect, incidental, or consequential loss or damage whatsoever, or for loss of or to the plant, loss of use of equipment or power system, cost of capital, loss of profits or revenue or the loss of use thereof, cost of environmental damage or clean-up, or claims of customers of Purchaser. The remedies set forth herein are exclusive, and the total cumulative liability of seller and it suppliers under any purchase order or any act or omission in connection therewith or related thereto, whether in contract, in tort (including negligence and strict liability), under any warranty, or otherwise, will be limited to the price of the contract.
B. The provisions of this Article shall survive termination, cancellation or expiration of the purchase order and shall apply, notwithstanding any other provisions of this Agreement or any related document thereto, to the fullest extent permitted by law. Prior to the transfer of any equipment or material furnished or for which work is furnished hereunder from the project site (except temporarily for repair work or permanently for disposal), or the transfer of any interest therein or in the plant, Purchaser shall obtain for Seller written assurances from the transferee of limitation of and protection against liability following the proposed transfer at least equivalent to that afforded seller and its suppliers under the purchase order.
REFERENCE: REF. NO. TERMS: DATE:
Gainesville, FL 4454-23 Net 30 1/4/2023
ITEM RATE QUANTITY TOTAL
Generator Rental to operate SVE system 500.00 Day 1 $500.00 Cord to connect generator to the trailer 50.00 ls 1 $50.00 Delivery & Pick up of generator 750.00 ls 1 $750.00
Total cost for rental $1,300.00 Does not include fuel, fueling or servicing
Fuel estimated at 2 gallons an hour
This price will remain firm for ninety days from the proposal date.
We appreciate the opportunity of offering this proposal and trust we may be favored with your most valued business.
ECT Kenneth P. Richard Company Name Sales Representative
Petroleum Resources & Development, Inc.
Signature Date
Title
(321) 986-6036
PR&D Quote # 4454-23
Petroleum Resources & Development, Inc.
2460 N Courtenay Pkwy, Suite 212
Merritt Island, Florida 32953
(321) 986-6026
U1INVPDF
This is not an invoice Please do not pay from this document
RENTAL QUOTE
POWER & HVAC
Page: 1
RENTAL ITEMS:
_____ ___________ _______________________________________ _____________________________________________ _______________ Qty Equipment Description Minimum Day Week 4 Week Estimated Amt.
1 2403137 GENERATOR 30-39 KVA TIER 4 299.64 599.27 1,648.00 299.64
1 241/7275 CABLE 6/4 50 AMP 50' 47.95 47.95 59.93 164.80 47.95
BARE END
Rental Subtotal: 347.59
SALES/MISCELLANEOUS ITEMS:
_______ ______________________________________________________________ _____________ _________________ _______________ Qty Item Price Unit of Measure Extended Amt.
1 ENVIRONMENTAL SERVICE CHARGE [ENV/MCI] 5.990 EACH 5.99
1 DELIVERY CHARGE 694.560 EACH 694.56
1 PICKUP CHARGE 694.560 EACH 694.56
Sales/Misc Subtotal: 1,395.11
Agreement Subtotal: 1,742.70 Tax: 26.52 Estimated Total: 1,769.22
COMMENTS/NOTES:
CONTACT: GREG SATTLER
CELL#: 321-245-2124
DLV/PKU LOC SELECTED BY MAP PIN OPTION
GAINSEVILLE
1005 NW 76TH BLVD
GAINESVILLE FL 32608
Office: 352-332-0444 Cell: 321-245-2124
ENVIRONMENTAL CONSULTING &
7027 SW 24TH AVE
GAINESVILLE FL 32607-3704
BRANCH G80
5856 MINING TER
JACKSONVILLE FL 32257-3233
904-731-5545
904-731-5255 FAX
# 214240970
J o b
S i t e
J o b
S i b
S i b
S i b
S i b
S i b
S i b
S i b
S i b
S i b
S i b
S i b
S i b
S i b
S i b
S i
Customer # :
Quote Date :
Estimated Out :
Estimated In :
UR Job Loc :
UR Job # :
Customer Job ID:
P.O. # :
Ordered By :
Written By :
Salesperson :
2005009 12/20/22
01/05/23 03:00 PM
01/06/23 03:00 PM
1005 NW 76TH BLVD, G
TBD
GREG SATTLER
KEVIN CHMELA
KEVIN CHMELA
This proposal may be withdrawn if not accepted within 30 days. The above referenced Rental Protection Plan, environmental, and tax charges are estimates and are subject to change.
NOTICE: This is not a rental agreement. The rental of equipment and any items listed above is subject to availability and subject to the terms and conditions of the Rental and Service Agreement, which are available at https://www.unitedrentals.com/legal/rental-service-terms-US and which are incorporated herein by reference. A COPY OF THE RENTAL AND SERVICE
AGREEMENT TERMS ARE AVAILABLE IN PAPER FORM UPON REQUEST.
Partnership for A Cleaner Tomorrow
495 Oak Road Ocala, FL 34472 Phone (800) 277-3279 Fax (352) 680-9278
Mr. Greg Sattler, PE January 13, 2023 Sr. Remediation Engineer ECT, Inc.
3751 Maguire Boulevard, Suite 234 Orlando, FL 32803
RE: Electrical Evaluation and Startup Procedures Quote - Proposal # AP011323-01
Town & Country Cleaners - 1005 NW 75th Boulevard, Gainesville, Florida 32608
Dear Mr. Sattler, ESD Waste2Water is pleased to submit the following cost estimate for the above referenced project, per your Request for Quote. The general scope of services and associated costs are summarized below.
Electrical evaluation of the existing Control Panel and SVE System.
Assist with developing the electrical startup procedures for the referenced SVE System.
Price includes mobilization, truck, tools and 6 hours of on-site support from one ESD’s Qualified Field Services Technicians, that has experience with troubleshooting control panels and SVE electrical components.
PROJECT COST $1,125.00
Exceptions, Clarifications, General Terms and Conditions Proposal pricing is valid for 30 days from date of proposal.
Payment terms: Net 30 Days and will be Invoiced upon completion.
Pricing is limited to only those services describe herein and based on 6 Hours of On-Site support.
Any additional time or materials/components requested and required, will be billed on a time-and-materials basis, and will be pre-approved by ECT.
Pricing does not include any sales tax, if applicable.
No permitting services or costs are included.
Greg, Thank You for the opportunity to provide you with this cost proposal. Please call/reply with any questions, comments or requests. If agreeable, please sign below and return at your convenience.
Best Regards, Alan K. Pierce
Authorized and Approved by ECT, Inc.
Authorized By: _____________________________ Date: __________________ Signature
Name: _____________________________________ P.O. #: __________________ Print
Gregory Sattler
From: abpelectric1@verizon.net Sent: Wednesday, January 18, 2023 2:25 PM To: Gregory Sattler Subject: RE: Town & Country Cleaners Electrical System Evaluation
Good afternoon Greg, Thank you for the opportunity to bid on your project. At this time I will need to decline bidding on this project due to our very busy schedule and time constraints. Please keep ABP in mind for future projects.
Thank you for your understanding.
Sincerely, Brad Plough 8717 Park Byrd Road Lakeland, FL 33810 863-816-7313 Office 863-581-7879 Cell 863-853-2694 Fax abpelectric1@verizon.net
From: Gregory Sattler <gsattler@ectinc.com> Sent: Thursday, January 12, 2023 4:52 PM To: Brad Plough (ABPelectric1@verizon.net) <abpelectric1@verizon.net> Subject: Town & Country Cleaners Electrical System Evaluation
Good evening Brad, ECT is requesting quotes for electrical evaluation and electrical startup procedures for a soil vapor extraction system owned by the Florida Department of Environmental Protection (FDEP) Waste Cleanup Division. The site is known as Town & Country Cleaners (D496), located at 1005 NW 75th Boulevard, Gainesville, Florida 32608. ECT has assumed responsibility for the system for the FDEP from a previous consultant. The system and control panel have been exposed to the elements and some water intrusion has been identified. ECT will provide a 3-phase generator to power the system to determine whether it is operable in the current state or whether repairs will be required. In your quote, please include mobilization and 6 hours for a technician that has experience with troubleshooting control panels and SVE electrical components.
ECT would like to perform the electrical evaluation, troubleshooting, and minor repairs to operate the SVE system the following day.
Attached are photos of the system. If you have any additional questions, you may contact me at the below information.
Best Regards, Gregory Sattler, P.E.
Senior Remediation Engineer| Site Assessment & Remediation
Environmental Consulting & Technology, Inc.
3751 Maguire Boulevard | Suite 234 | Orlando, Florida 32803 C: 321.245.2124 | gsattler@ectinc.com
Follow us: