This document is a Consultant's Task Assignment Notification (DRP-084) issued by the Florida Department of Environmental Protection (FDEP), Division of Recreation and Parks, for the Indian Key Historic State Park Dock and Pavilion Replacement project. The task assignment is executed under FDEP Contract No. CN803, Project Number 6i506C, and Task Assignment No. 8. The consultant performing the work is Weiler Engineering Corp. (WEC), with Michael J. Giardullo, P.E., serving as the consultant's representative. The FDEP Contract Manager is Vu Nguyen, and the Project Manager is James Post. The work is located at Indian Key Historic State Park in Florida.

The task assignment requires WEC to provide Construction Administration (CSA) services during the construction phase of the dock and pavilion replacement project, with a completion date of June 30, 2026. The scope includes fourteen subtasks: pre-construction meeting attendance, contractor submittal review, building department comment responses, contractor RFI responses, pile driving inspections (up to three), monthly construction inspections over eight months, and substantial completion walkthrough with punchlist development. All services are on a fixed-price basis totaling $24,049.35, with no reimbursable costs. Compensation is broken down by subtask, with individual costs ranging from $1,004.02 to $4,105.27. The funding is encumbered under Grant FD073, utilizing Fund 423001, Module U3200, and Object 131500. All work is scheduled to commence upon contract execution, with task durations and specific start dates to be determined by the project timeline.

View the file

Other files

File Type Posted
CN-370000-CN803-T10.pdf PDF
CN-370000-CN803-T10CO1.pdf PDF
CN-370000-CN803-T14.pdf PDF
CN-370000-CN803-T16.pdf PDF
CN-370000-CN803-T19.pdf PDF
CN-370000-CN803-T3.pdf PDF
CN-370000-CN803-T1.pdf PDF
CN-370000-CN803-T10.pdf.crdownload CRDOWNLOAD file
CN-370000-CN803-T11.pdf PDF
CN-370000-CN803-T13.pdf PDF
CN-370000-CN803-T2.pdf PDF
CN-370000-CN803-T22.pdf PDF
CN-370000-CN803-T23.pdf PDF
CN-370000-CN803-T25.pdf PDF
CN-370000-CN803-T26.pdf PDF
CN-370000-CN803-T4.pdf PDF
CN-370000-CN803.pdf PDF
CN-370000-CN803.pdf.crdownload CRDOWNLOAD file
CN-370000-CN803-CMC1.pdf PDF
CN-370000-CN803-T12.pdf PDF
CN-370000-CN803-T15.pdf PDF
CN-370000-CN803-T18.pdf PDF
CN-370000-CN803-T20.pdf PDF
CN-370000-CN803-T21.pdf PDF
CN-370000-CN803-T24.pdf PDF
CN-370000-CN803-T2CO1.pdf PDF
CN-370000-CN803-T30.pdf PDF
CN-370000-CN803-T6.pdf PDF
CN-370000-CN803-T6CO1.pdf PDF
CN-370000-CN803-T9.pdf PDF
CN-370000-CN803-T17.pdf PDF
CN-370000-CN803-T5.pdf PDF
CN-370000-CN803-T7.pdf PDF
CN-370000-CN803-T8CO1.pdf PDF
Show all 34

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Division of Recreation and Parks

Consultant’s Task Assignment Notification

FLORIDA DEPARTMENT OF

ENVIRONMENTAL PROTECTION

DRP-084

Rev. 0 /2025 of 2

FDEP Contract No: Project Number: Task Assignment No:

Project Location Project

Consultant’s Name:

Consultant’s Representative:

Phone: Email:

FDEP Contract Manager:

Phone: Email:

Task Description:

Project Manager:

Schedule:

Start Date: Completion Date:

Fixed Price Cost: Cost Reimbursement (Not to Exceed):

Total Task Amount:

Signatures and Date:

1.

Budget Representative, FDEP Signature Date

2.

Project Manager, FDEP Signature Date

3.

Contract Manager, FDEP Signature Date

4.

Consultant Signature Date

5.

Contract Authority, FDEP Signature Date

CN803 6i506C 8

Indian Key Historic State Park Dock and Pavilion Replacement

Weiler Engineering Corp.

Michael J. Giardullo, P.E.

(941) 245-2630 mgiardullo@weilerengineering.com

Vu Nguyen

(850) 245-2630 Vu.Nguyen@FloridaDEP.gov

Provide CSA services during the construction of project as per the attached proposal dated May19, 2025.

James Post

Upon Execution 06/30/2026

$24,049.35 $0.00

$24,049.35

Tamika Bass

James Post

Vu Nguyen

Michael J. Giardullo, P. E.

Michael W. Foster Jr., P.E.

09/03/2025

09/03/2025

09/03/2025

09/03/2025

09/03/2025

Division of Recreation and Parks

Consultant’s Task Assignment Notification

FLORIDA DEPARTMENT OF

ENVIRONMENTAL PROTECTION

DRP-084

Rev. /2025 2 of 2

Encumbrance Information:

Project # Grant # Organization Code Category/Yr Fund Module Object EO Amount

Total: $24,049.35

April 18, 2025- Rev 2 May 19, 2025

Mr. James Post Construction Project Consultant II Bureau of Design and Construction Florida Department of Environmental Protection 3 LaCroix Court Key Largo, Florida 33037

RE: Indian Key Dock and Pavilion Replacement CA Services - CN 803, TA 0

Dear Mr. Post, Thank you for the opportunity to provide this proposal for Construction Administration services for the replacement of the dock at Indian Key Historic State Park.

For your review, the Weiler Engineering Corporation, has provided a proposal summary and man-hour documentation for the services tasks identified below.

Please review the attached Proposal Summary and deliverables.

Sincerely, Michael J. Giardullo, P.E.

Director of Civil Engineering Weiler Engineering Corporation- An Apex Company

April 18, 2025, REV 1: May 12, 2025 Mr. Jim Post Indian Key Dock Replacement CA Services CN 803 TN 0

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702 Marathon: 6805 Overseas Highway, Marathon, Florida 33050 | Tel 305-289-4161 | Fax 305-289-4162

Indian Key Dock and Pavilion Replacement CA Services Contract Number 803, Task Assignment 0

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Subtask 1A: Attend Pre-Construction Meeting

Description: WEC will provide representation at the Pre-Construction Meeting.

Deliverable: Meeting notes within 2 days from meeting date for inclusion by FDEP Project Manager in Meeting Minutes.

Fixed Price Cost:

Subtask 1A - Pre-Construction Mtg

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

Weiler Engineering Senior Project Manager 160.83 0.5 80.42

Weiler Engineering Principal 319.24 0 0

Weiler Engineering Professional Engineer 168.20 0 0

Weiler Engineering Engineer Intern 115.45 8 923.60

Weiler Engineering Senior Engineering Designer 115.13 0 0

Weiler Engineering Engineering Designer 90.40 0 0

Weiler Engineering Clerical 62.74 0 0

Total 1,004.02

Reimbursable Cost:

Description Number @ Total

Postage 0

Printing 2.3 0

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile)

Reimbursable Total Cost 0

Total Subtask 1A 1,004.02

Mr. Jim Post Indian Key Dock Replacement CA Services CN 803 TN 0

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702 Marathon: 6805 Overseas Highway, Marathon, Florida 33050 | Tel 305-289-4161 | Fax 305-289-4162

Subtask 1B: Review Contractor Submittals

Description: Consultant will review and comment on Contractor submittal package within 14 days of receipt.

Deliverable: Stamped acceptance of final submittals in PDF digital form to FDEP Project Manager within 7 days of final approvals.

Fixed Price Cost:

Subtask 1B - Review Submittals

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

Weiler Engineering Senior Project Manager 160.83 3 482.49

Weiler Engineering Principal 319.24 0 0

Weiler Engineering Professional Engineer 168.20 0 0

Weiler Engineering Engineer Intern 115.45 8 923.60

Weiler Engineering Senior Engineering Designer 115.13 12 1,381.56

Weiler Engineering Engineering Designer 90.40 2 180.80

Weiler Engineering Clerical 62.74 2 125.48

Total 3,093.93

Reimbursable Cost:

Description Number @ Total

Postage 0 35 0

Printing 0

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile)

Reimbursable Total Cost

Total Subtask 1B 3,093.93

Mr. Jim Post Indian Key Dock Replacement CA Services CN 803 TN 0

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702 Marathon: 6805 Overseas Highway, Marathon, Florida 33050 | Tel 305-289-4161 | Fax 305-289-4162

Subtask 1C: Respond to Building Department Comments

Description: WEC will assist Client and/or Client's Contractor in responding to comments from the Building Department, and revise plans accordingly within 14 days of receipt of comments. Specifically, when WEC's involvement is required for RFI responses, WEC will prepare a draft and send to FDEP Project Manager for review and comment. WEC will then discuss and/or revise accordingly prior to formal submittal of RFI response to Building Department.

Deliverable: RFI response documents submitted to Building Department.

Fixed Price Cost:

Subtask 1C

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

Weiler Engineering Senior Project Manager 160.83 4 643.32

Weiler Engineering Principal 319.24 0 0

Weiler Engineering Professional Engineer 168.20 4 672.80

Weiler Engineering Engineer Intern 115.45 6 692.70

Weiler Engineering Senior Engineering Designer 115.13 10 1,151.30

Weiler Engineering Engineering Designer 90.40 0 0

Weiler Engineering Clerical 62.74 1 62.74

Total 3,222.86

Reimbursable Cost:

Description Number @ Total

Postage 35 0

Printing 2.30 0.00

Overnight Travel

(if applicable)

Not anticipated

Mileage (@ $0.445 per mile)

Not anticipated

Reimbursable Total Cost

Total Subtask 1C 3,222.86

Mr. Jim Post Indian Key Dock Replacement CA Services CN 803 TN 0

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702 Marathon: 6805 Overseas Highway, Marathon, Florida 33050 | Tel 305-289-4161 | Fax 305-289-4162

Subtask 1D: Respond to Contractor RFl's

Description: WEC will respond to RFI's from Contractor within 7 days throughout the course of the construction phase.

Deliverable: WEC will provide copies of all RFI responses to FDEP Project

Manager in PDF digital format.

Fixed Price Cost:

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

Weiler Engineering Senior Project Manager 160.83 4 643.32

Weiler Engineering Principal 319.24 0 0

Weiler Engineering Professional Engineer 168.20 2 336.40

Weiler Engineering Engineer Intern 115.45 6 692.70

Weiler Engineering Senior Engineering Designer 115.13 4 460.52

Weiler Engineering Engineering Designer 90.40 0 0

Weiler Engineering Clerical 62.74 2 125.48

Total 2,258.42

Reimbursable Cost:

Description Number @ Total

Postage 0

Printing 0

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile)

Reimbursable Total Cost

Total Subtask 1D 2,258.42

Subtask 1D- Respond to RF's

Mr. Jim Post Indian Key Dock Replacement CA Services CN 803 TN 0

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702 Marathon: 6805 Overseas Highway, Marathon, Florida 33050 | Tel 305-289-4161 | Fax 305-289-4162

Subtask 1E: Pile Driving Inspection

Description: WEC will provide up to (3) Pile Inspections during the duration of the pile construction. Contractor is required to submit daily pile reports to EOR during the pile installation in order for the EOR to produce a Pile Inspection Report for the Village of Islamorada.

Deliverable: WEC will provide a signed and sealed reports to the FDEP Project Manager in PDF format. The inspection report will be submitted within 7 days upon the completion of the pile installation.

Fixed Price Cost:

Subtask 1E Pile Driving Inspection

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

Weiler Engineering Senior Project Manager 160.83 3 482.49

Weiler Engineering Principal 319.24 0 0

Weiler Engineering Professional Engineer 168.20 2 336.40

Weiler Engineering Engineer Intern 115.45 0 0

Weiler Engineering Senior Engineering Designer 115.13 28 3,223.64

Weiler Engineering Engineering Designer 90.40 0 0

Weiler Engineering Clerical 62.74 1 62.74

Total 4,105.27

Reimbursable Cost:

Description Number @ Total

Postage 35 0

Printing 0

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile)

0 0.445 0

Reimbursable Total Cost

Total Subtask 1E 4,105.27

Mr. Jim Post Indian Key Dock Replacement CA Services CN 803 TN 0

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702 Marathon: 6805 Overseas Highway, Marathon, Florida 33050 | Tel 305-289-4161 | Fax 305-289-4162

Subtask 1F: Construction Inspection (Month 1) Description: WEC will provide a monthly inspection (NLT every 30 days) during construction.

Deliverable: WEC will provide two (2) original signed and sealed reports to the FDEP Project Manager, as well as a digital version in PDF format. The inspection report will be submitted within 3 days of each inspection.

Fixed Price Cost:

Subtask 1F

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

Weiler Engineering Senior Project Manager 160.83 1 160.83

Weiler Engineering Principal 319.24 0 0

Weiler Engineering Professional Engineer 168.20 .5 84.10

Weiler Engineering Engineer Intern 115.45 6 692.70

Weiler Engineering Senior Engineering Designer 115.13 1 115.13

Weiler Engineering Engineering Designer 90.40 0 0

Weiler Engineering Clerical 62.74 0 0

Total 1,052.76

Reimbursable Cost:

Description Number @ Total

Postage 0 35 0

Printing 0

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile)

0 0.445 0

Reimbursable Total Cost

Total Subtask 1F 1,052.76

Mr. Jim Post Indian Key Dock Replacement CA Services CN 803 TN 0

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702 Marathon: 6805 Overseas Highway, Marathon, Florida 33050 | Tel 305-289-4161 | Fax 305-289-4162

Subtask 1G: Construction Inspection (Month 2)

Description: WEC will provide a monthly inspection (NLT every 30 days) during construction.

Deliverable: WEC will provide two (2) original signed and sealed reports to the FDEP Project Manager, as well as a digital version in PDF format. The inspection report will be submitted within 3 days of each inspection.

Fixed Price Cost:

Subtask 1G

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

Weiler Engineering Senior Project Manager 160.83 1 160.83

Weiler Engineering Principal 319.24 0 0

Weiler Engineering Professional Engineer 168.20 .5 84.10

Weiler Engineering Engineer Intern 115.45 6 692.70

Weiler Engineering Senior Engineering Designer 115.13 1 115.13

Weiler Engineering Engineering Designer 90.40 0 0

Weiler Engineering Clerical 62.74

Total 1,052.76

Reimbursable Cost:

Description Number @ Total

Postage 0 35 0

Printing 0

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile)

0 0.445 0

Reimbursable Total Cost

Total Subtask 1G 1,052.76

Mr. Jim Post Indian Key Dock Replacement CA Services CN 803 TN 0

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702 Marathon: 6805 Overseas Highway, Marathon, Florida 33050 | Tel 305-289-4161 | Fax 305-289-4162

Subtask 1H: Construction Inspection (Month 3)

Description: WEC will provide a monthly inspection (NLT every 30 days) during construction.

Deliverable: WEC will provide two (2) original signed and sealed reports to the FDEP Project Manager, as well as a digital version in PDF format. The inspection report will be submitted within 3 days of each inspection.

Fixed Price Cost:

Subtask 1H Month 3 Inspection

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

Weiler Engineering Senior Project Manager 160.83 1 160.83

Weiler Engineering Principal 319.24 0 0

Weiler Engineering Professional Engineer 168.20 .5 84.10

Weiler Engineering Engineer Intern 115.45 6 692.70

Weiler Engineering Senior Engineering Designer 115.13 1 115.13

Weiler Engineering Engineering Designer 90.40 0 0

Weiler Engineering Clerical 62.74 0 0

Total 1,052.76

Reimbursable Cost:

Description Number @ Total

Postage 0 35 0

Printing 0

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile)

0 0.445 0

Reimbursable Total Cost

Total Subtask 1H 1,052.76

Mr. Jim Post Indian Key Dock Replacement CA Services CN 803 TN 0

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702 Marathon: 6805 Overseas Highway, Marathon, Florida 33050 | Tel 305-289-4161 | Fax 305-289-4162

Subtask 1I: Construction Inspection (Month 4)

Description: WEC will provide a monthly inspection (NLT every 30 days) during construction.

Deliverable: WEC will provide two (2) original signed and sealed reports to the FDEP Project Manager, as well as a digital version in PDF format. The inspection report will be submitted within 3 days of each inspection.

Fixed Price Cost:

Subtask 1I - Inspection Month 4

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

Weiler Engineering Senior Project Manager 160.83 1 160.83

Weiler Engineering Principal 319.24 0 0

Weiler Engineering Professional Engineer 168.20 .5 84.10

Weiler Engineering Engineer Intern 115.45 6 692.70

Weiler Engineering Senior Engineering Designer 115.13 1 115.13

Weiler Engineering Engineering Designer 90.40 0 0

Weiler Engineering Clerical 62.74 0 0

Total 1,052.76

Reimbursable Cost:

Description Number @ Total

Postage 0 35 0

Printing 0

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile)

0 0.445 0

Reimbursable Total Cost

Total Subtask 1I 1,052.76

Mr. Jim Post Indian Key Dock Replacement CA Services CN 803 TN 0

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702 Marathon: 6805 Overseas Highway, Marathon, Florida 33050 | Tel 305-289-4161 | Fax 305-289-4162

Subtask 1J: Construction Inspection (Month 5)

Description: WEC will provide a monthly inspection (NLT every 30 days) during construction.

Deliverable: WEC will provide two (2) original signed and sealed reports to the FDEP Project Manager, as well as a digital version in PDF format. The inspection report will be submitted within 3 days of each inspection.

Fixed Price Cost:

Subtask 1J Month 5 Inspection

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

Weiler Engineering Senior Project Manager 160.83 1 160.83

Weiler Engineering Principal 319.24 0 0

Weiler Engineering Professional Engineer 168.20 .5 84.10

Weiler Engineering Engineer Intern 115.45 6 692.70

Weiler Engineering Senior Engineering Designer 115.13 1 115.13

Weiler Engineering Engineering Designer 90.40 0 0

Weiler Engineering Clerical 62.74 0 0

Total 1,052.76

Reimbursable Cost:

Description Number @ Total

Postage 0 35 0

Printing 0

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile)

0 0.445 0

Reimbursable Total Cost

Total Subtask 1J 1,052.76

Mr. Jim Post Indian Key Dock Replacement CA Services CN 803 TN 0

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702 Marathon: 6805 Overseas Highway, Marathon, Florida 33050 | Tel 305-289-4161 | Fax 305-289-4162

Subtask 1K: Construction Inspection (Month 6)

Description: WEC will provide a monthly inspection (NLT every 30 days) during construction.

Deliverable: WEC will provide two (2) original signed and sealed reports to the FDEP Project Manager, as well as a digital version in PDF format. The inspection report will be submitted within 3 days of each inspection.

Fixed Price Cost:

Subtask 1K Month 6 Inspection

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

Weiler Engineering Senior Project Manager 160.83 1 160.83

Weiler Engineering Principal 319.24 0 0

Weiler Engineering Professional Engineer 168.20 .5 84.10

Weiler Engineering Engineer Intern 115.45 6 692.70

Weiler Engineering Senior Engineering Designer 115.13 1 115.13

Weiler Engineering Engineering Designer 90.40 0 0

Weiler Engineering Clerical 62.74 0 0

Total 1,052.76

Reimbursable Cost:

Description Number @ Total

Postage 0 35 0

Printing 0

Overnight Travel {if applicable)

Mileage (@ $0.445 per mile)

0 0.445 0

Reimbursable Total Cost

Total Subtask 1K 1,052.76

Mr. Jim Post Indian Key Dock Replacement CA Services CN 803 TN 0

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702 Marathon: 6805 Overseas Highway, Marathon, Florida 33050 | Tel 305-289-4161 | Fax 305-289-4162

Subtask 1L: Construction Inspection (Month 7)

Description: WEC will provide a monthly inspection (NLT every 30 days) during construction.

Deliverable: WEC will provide two (2) original signed and sealed reports to the FDEP Project Manager, as well as a digital version in PDF format. The inspection report will be submitted within 3 days of each inspection.

Fixed Price Cost:

Subtask 1L Month 7 Inspection

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

Weiler Engineering Senior Project Manager 160.83 1 160.83

Weiler Engineering Principal 319.24 0 0

Weiler Engineering Professional Engineer 168.20 .5 84.10

Weiler Engineering Engineer Intern 115.45 6 692.70

Weiler Engineering Senior Engineering Designer 115.13 1 115.13

Weiler Engineering Engineering Designer 90.40 0 0

Weiler Engineering Clerical 62.74 0 0

Total 1,052.76

Reimbursable Cost:

Description Number @ Total

Postage 0 35 0

Printing 0

Overnight Travel {if applicable)

Mileage (@ $0.445 per mile)

0 0.445 0

Reimbursable Total Cost

Total Subtask 1L 1,052.76

Mr. Jim Post Indian Key Dock Replacement CA Services CN 803 TN 0

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702 Marathon: 6805 Overseas Highway, Marathon, Florida 33050 | Tel 305-289-4161 | Fax 305-289-4162

Subtask 1M: Construction Inspection (Month 8)

Description: WEC will provide a monthly inspection (NLT every 30 days) during construction.

Deliverable: WEC will provide two (2) original signed and sealed reports to the FDEP Project Manager, as well as a digital version in PDF format. The inspection report will be submitted within 3 days of each inspection.

Fixed Price Cost:

Subtask 1M Month 8 Inspection

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

Weiler Engineering Senior Project Manager 160.83 1 160.83

Weiler Engineering Principal 319.24 0 0

Weiler Engineering Professional Engineer 168.20 .5 84.10

Weiler Engineering Engineer Intern 115.45 6 692.70

Weiler Engineering Senior Engineering Designer 115.13 1 115.13

Weiler Engineering Engineering Designer 90.40 0 0

Weiler Engineering Clerical 62.74 0 0

Total 1,052.76

Reimbursable Cost:

Description Number @ Total

Postage 0 35 0

Printing 0

Overnight Travel {if applicable)

Mileage (@ $0.445 per mile)

0 0.445 0

Reimbursable Total Cost

Total Subtask 1M 1,052.76

Mr. Jim Post Indian Key Dock Replacement CA Services CN 803 TN 0

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702 Marathon: 6805 Overseas Highway, Marathon, Florida 33050 | Tel 305-289-4161 | Fax 305-289-4162

Subtask 1N: Substantial Completion Walk-Through w/Punchlist

Description: WEC will assist Client with the Substantial Completion inspection and punchlist, with WEC representative attending the Substantial Completion inspection and providing engineer input related to the punchlist. WEC will also submit permit closeout documents to the permitting agencies, as applicable.

Deliverable: WEC will provide comments and input on punchlist within one (1) day of Substantial Completion inspection.

Fixed Price Cost:

Subtask 1N substantial

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

Weiler Engineering Senior Project Manager 160.83 1 160.83

Weiler Engineering Principal 319.24 0 0

Weiler Engineering Professional Engineer 168.20 1 168.20

Weiler Engineering Engineer Intern 115.45 6 692.70

Weiler Engineering Senior Engineering Designer 115.13 8 921.04

Weiler Engineering Engineering Designer 90.40 0 0

Weiler Engineering Clerical 62.74 0 0

Total 1,942.77

Reimbursable Cost:

Description Number @ Total

Postage 0 35 0

Printing 0

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile)

0 0.445 0

Reimbursable Total Cost

Total Subtask 1N 1,942.77

Mr. Jim Post Indian Key Dock Replacement CA Services CN 803 TN 0

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702 Marathon: 6805 Overseas Highway, Marathon, Florida 33050 | Tel 305-289-4161 | Fax 305-289-4162

Project Schedule:

Activity Duration (Calendar Days)

Days from Execution

Subtask 1A: Pre-Construction TBD TBD

Subtask 1B: Review Submittals TBD TBD

Subtask 1C: Respond to Building Department Comments

TBD TBD

Subtask 1D: Respond to Contractor RFI's TBD TBD

Subtask 1E: Pile Driving Inspection TBD TBD

Subtask 1F: Provide Construction Inspections w/ (Month 1)

TBD TBD

Subtask 1G: Provide Construction Inspections w/ Report (Month 2)

TBD TBD

Subtask 1H: Provide Construction Inspections w/ Report (Month 3)

TBD TBD

Subtask 1I: Provide Construction Inspections w/ (Month 4)

TBD TBD

Subtask 1J: Provide Construction Inspections w/ Report (Month 5)

TBD TBD

Subtask 1K: Provide Construction Inspections w/ (Month 6)

TBD TBD

Subtask 1L: Provide Construction Inspections w/ (Month 7)

TBD TBD

Subtask 1M: Provide Construction Inspections w/ (Month 8)

TBD TBD

Subtask 1N: Substantial Completion Walk-Through w/ Punchlist

TBD TBD

Mr. Jim Post Indian Key Dock Replacement CA Services CN 803 TN 0

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702 Marathon: 6805 Overseas Highway, Marathon, Florida 33050 | Tel 305-289-4161 | Fax 305-289-4162

Summary of Fees:

Subtask Subtask Fixed Price Cost

Subtask Reimbursable

Subtask 1A: Pre-Construction $1,004.02 $0.00

Subtask 1B: Review Submittals $3,093.93 $0.00

Subtask 1C: Respond to Building Department Comments

$3,222.86 $0.00

Subtask 1D: Respond to Contractor RFI's $2,258.42 $0.00

Subtask 1E: Pile Driving Inspection $4,105.27 $0.00

Subtask 1F: Provide Construction Inspections w/ (Month 1)

$1,052.76 $0.00

Subtask 1G: Provide Construction Inspections w/ Report (Month 2)

$1,052.76 $0.00

Subtask 1H: Provide Construction Inspections w/ Report (Month 3)

$1,052.76 $0.00

Subtask 1I: Provide Construction Inspections w/ (Month 4)

$1,052.76 $0.00

Subtask 1J: Provide Construction Inspections w/ Report (Month 5)

$1,052.76 $0.00

Subtask 1K: Provide Construction Inspections w/ (Month 6)

$1,052.76 $0.00

Subtask 1L: Provide Construction Inspections w/ (Month 7)

$1,052.76 $0.00

Subtask 1M: Provide Construction Inspections w/ (Month 8)

$1,052.76 $0.00

Subtask 1N: Substantial Completion Walk-Through w/ Punchlist

$1,942.77 $0.00

Total during Construction $24,049.35 $0.00 Project Grand Total: $24,049.35