This is a Consultant's Task Assignment Notification (Form DRP-084) issued by the Florida Department of Environmental Protection (FDEP), Division of Recreation and Parks, for Project RM2301 at Rookery Bay Research Reserve. The consultant assigned is TheWeiler Engineering Corporation – An Apex Company, with Michael Giardullo, P.E., serving as the consultant's representative. The FDEP contract manager is Vu Nguyen. This task assignment represents modifications to the design of the Briggs Boardwalk replacement project to relocate all piles to match existing conditions, incorporating work previously initiated under CN 230, TA 54 (Including CO1).
The scope of work comprises two design phases and multiple construction-phase services. Subtask 1 involves 100% document revisions delivering revised plans in digital PDF and hard copy format. Subtask 2 covers assistance during the bidding phase with responses to bidder questions. Subtasks 3A through 3N encompass pre-construction and construction-phase services including pre-construction meeting attendance, contractor submittal review, regulatory responses, RFI responses, eight monthly construction inspections, substantial completion walk-through with punchlist, and final completion certification. The total task amount is $31,387.53, consisting of $29,917.53 in fixed price costs and $1,424.00 in cost reimbursement (not to exceed). The project schedule extends from upon execution through July 1, 2026. Funding is allocated through Grant F1076, Organization Code 37538020000, with the 29-digit FLAIR code 37202261019375004000010208000. All work is to be performed using rates established under the prior contract (CN 230, TA 54, CO1).
View the file
Other files
Show all 34
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DDivision oof RRecreation aand PParks
CConsultant’s TTask AAssignment NNotification
FFLORIDA DEPARTMENT OF
EENVIRONMENTAL PPROTECTION
DRP-084
Rev. 0 /2025 of 2
FDEP Contract No: Project Number: Task Assignment No:
Project Location Project
Consultant’s Name:
Consultant’s Representative:
Phone: Email:
FDEP Contract Manager:
Phone: Email:
Task Description:
Project Manager:
Schedule:
Start Date: Completion Date:
Fixed Price Cost: Cost Reimbursement (Not to Exceed):
Total Task Amount:
Signatures and Date:
1.
Budget Representative, FDEP Signature Date
2.
Project Manager, FDEP Signature Date
3.
Signature Date
4.
Signature Date
5.
Contract Authority, FDEP Signature Date
803 RM2301 6
Rookery Bay Research Reserve Briggs Boardwalk, TheWeiler Engineering Corporation- An Apex Company Michael Giardullo, P.E.,
(941) 505-1700 mgiardullo@weilerengineering.org
Vu Nguyen
(850) 245-2630 Vu.Nguyen@FloridaDEP.gov
Revisions to modify the design to have the piles in the same location as existing conditions. Proposal dated
4.14.25. CN 230, TA 54 (Including CO1) * all old rates.
Garland Sandel
Upon Execution 07/01/2026
$29,917.53 $1,424.00
$31,3 .53
Lisa Yarborough
Garland Sandel
Michael Giardullo, P.E., Vu Nguyen
Michael W. Foster Jr., P.E
04/30/2025Lisa Yarborough Digitally signed by Lisa Yarborough Date: 2025.04.30 14:24:28 -04'00'
Garland Sandel Digitally signed by Garland Sandel Date: 2025.04.30 14:45:07 -04'00'
Michael J. Giardullo Digitally signed by Michael J. Giardullo Date: 2025.05.02 14:27:05 -04'00'
Vu Nguyen Digitally signed by Vu Nguyen Date: 2025.05.06 13:59:38 -04'00'
Michael W. Foster Jr., P.E. Digitally signed by Michael W. Foster Jr., P.E.
Date: 2025.05.07 13:36:29 -04'00'
DDivision oof RRecreation aand PParks
CConsultant’s TTask AAssignment NNotification
FFLORIDA DEPARTMENT OF
EENVIRONMENTAL PPROTECTION
DRP-084
Rev. /2025 2 of 2
Encumbrance Information:
Project # Grant # Organization Code Category/Yr Fund Module Object EO Amount
Total:
RM2301 F1076 37538020000 083643/24 261019 U3210 241000 LQ $31, .53
$31,3 .53
102080/00 LH
3720226101937500400001020800029-Digit FLAIR Code 05/21/2025
05/21/202505/21/2025
Yarborough_L Highlight
Yarborough_L Highlight
Yarborough_L Highlight
April 14, 2025
Mr. Garland Sandel Project Manager Bureau of Design and Construction Florida Department of Environmental Protection 3900 Commonwealth Boulevard 260-L, MS 520 Tallahassee, FL 32399
RE: Rookery Bay Reserve - Briggs Boardwalk, CN - 803, TA - 06
Dear Mr. Sandel, Thank you for the opportunity to provide this proposal to adjust the current design and plans to reconstruct the existing boardwalk using the same pile locations.
PUNTA GORDA OFFICE: 201 WEST MARION AVENUE - SUITE 1306 | PUNTA GORDA | FL 33950 | TEL 941-505 -1700 | FAX 941-505 -1702 MARATHON OFFICE: 6805 OVERSEAS HIGHWAY | MARATHON | FL 33050 | TEL 305 -289-4161 | FAX 305 -289- 416 2 WE INVITE
YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG
Mr. Garland Sandel Rookery Bay Reserve Briggs Boardwalk- Plan Revisions
CN 803/TA03
WEC designed and permitted the replacement boardwalk under CN 230, TA 54 (Including CO1).
Subtasks 5-6N of the previous contract are being moved over to this proposal, as well as the plan revisions to modify the design to have the piles in the same location as existing conditions. The subtasks under CN 230, TA 54, CO1 have been completed and are not part of this scope.
For your review, the Weiler Engineering Corporation, has provided a proposal summary and man-hour documentation for the tasks identified below:
Please review the attached Proposal Summary and deliverables.
Sincerely, Michael J. Giardullo, P.E.
Director of Civil Engineering The Weiler Engineering Corporation- An Apex Company
Mr. Garland Sandel Rookery Bay Reserve Briggs Boardwalk- Plan Revisions
CN 803/TA06
Briggs Boardwalk Replacement- Plan Revisions Rookery Bay Reserve
Contract Number 803, Task Assignment Number 06
Subtask 1: 100% Document Revisions Description: Consultant will update the plans to relocate all piles to the location of the existing piles.
Deliverable: Plans consultant shall deliver 100% Plans (digital PDF + 1 Hard Copy) including:
Opinion of Probable Cost Cover sheet Survey/Existing Conditions Best Management Plan Demolition Plan Site & Grading Plan Site Details and General Notes Foundation/Piling Plans and details Exterior Elevations Ramp Cross-Sections and Details
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 1 - 100% Plan Revisions
Firm Name Position Classification Hourly Rate Hours Total
Fixed Price Cost
Weiler Engineering Project Manager 160.83 6 964.98
Weiler Engineering Principal in Charge 319.2 0.25 79.81
Weiler Engineering
Registered Professional Engineer 168.20 4 672.80
Weiler Engineering Registered Engineer Intern 115.45 5 577.25
Weiler Engineering Senior Engineering Designer 115.13 15 1,726.95
Weiler Engineering Engineering Technician 90.40 20 1,808.00
Weiler Engineering Clerical 62.74 1 62.74
Mr. Garland Sandel Rookery Bay Reserve Briggs Boardwalk- Plan Revisions
CN 803/TA06
Total 5,892.53
Total for Subtask 1 5,892.53
Reimbursable Cost:
Description Number @ Total Postage 0
Printing 20 2.3 46
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Reimbursable Total Cost 0
Total Subtask 1 5,938.53
Subtask 2: Assistance During Bidding
Description: Consultant will respond to bidder questions.
Deliverable: Consultant will provide digital responses to contractor questions.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 2- Assistance During Bidding Firm Name Position Classification Hourly
Rate Hours Total
Fixed Price Cost
Weiler Engineering Project Manager 145 8 $1,160.00
Weiler Engineering Principal in Charge 195 0 $0.00
Weiler Engineering Registered Professional Engineer
145 0 $0.00
Mr. Garland Sandel Rookery Bay Reserve Briggs Boardwalk- Plan Revisions
CN 803/TA06
Weiler Engineering Registered Engineer Intern 115 8 $920.00
Weiler Engineering Senior Engineering Designer
100 8 $800.00
Weiler Engineering Engineering Technician 80 8 $640.00
Weiler Engineering Clerical 55 0 $0.00 Total $3,520.00
Reimbursable Cost:
Description Number @ Total Postage Not anticipated
Overnight Travel (if applicable)
Not anticipated
Mileage (@ $0.445 per mile)
$0.00
Reimbursable Total Cost $0.00
Total Subtask 2 $3,520.00
Subtask 3A - 3N: Construction Phase Services
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. {Please do not alter this language)
Subtask 3A: Attend Pre-Construction Meeting
Description: WEC will provide representation at the Pre-Construction Meeting.
Deliverable: Meeting notes within 2 days from meeting date for inclusion by FDEP Project Manager in Meeting Minutes.
Mr. Garland Sandel Rookery Bay Reserve Briggs Boardwalk- Plan Revisions
CN 803/TA06
Fixed Price Cost:
Subtask 3A - Pre-Construction Mtg Firm Name Position Classification Hourly Rate Hours Total Fixed
Price Cost Weiler Engineering Project Manager 145 8 1,160
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer
145 0 0
Weiler Engineering Registered Engineer Intern 115 8 920
Weiler Engineering Senior Engineering Designer 100 0 0
Weiler Engineering Engineering Technician 80 0 0
Weiler Engineering Clerical 55 0 0
Total 2,080
Reimbursable Cost:
Description Number @ Total Postage 0
Printing 2.3 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Reimbursable Total Cost 0
Total Subtask 3A 2,080
Subtask 3B: Review Contractor Submittals
Description: Consultant will review and comment on Contractor submittal package within 14 days of receipt.
Deliverable: Stamped acceptance of final submittals in PDF digital form to FDEP Project Manager within 7 days of final approvals.
Mr. Garland Sandel Rookery Bay Reserve Briggs Boardwalk- Plan Revisions
CN 803/TA06
Fixed Price Cost:
Subtask 3B - Review Submittals Firm Name Position Classification Hourly Rate Hours Total Fixed
Price Cost Weiler Engineering Project Manager 145 2 290
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer
145 0 0
Weiler Engineering Registered Engineer Intern 115 8 920
Weiler Engineering Senior Engineering Designer 100 12 1200
Weiler Engineering Engineering Technician 80 2 160
Weiler Engineering Clerical 55 2 110
Total 2,680
Reimbursable Cost:
Description Number @ Total Postage 0 35 0 Printing 0
Overnight Travel {if applicable)
Mileage {@ $0.445 per mile)
Reimbursable Total Cost
Total Subtask 3B 2,680
Subtask 3C: Respond to Building Department comments
Description: WEC will assist Client and/or Client's Contractor in responding to comments from the Building Department, and revise plans accordingly within 14 days of receipt of comments.
Specifically, when WEC's involvement is required for RFI responses, WEC will prepare a draft and send to FDEP Project Manager for review and comment. WEC will then discuss and/or revise accordingly prior to formal submittal of RFI response to Building Department.
Mr. Garland Sandel Rookery Bay Reserve Briggs Boardwalk- Plan Revisions
CN 803/TA06
Deliverable: RFI response documents submitted to Building Department.
Fixed Price Cost:
Subtask 3C Firm Name Position Classification Hourly Rate Hours Total Fixed
Price Cost Weiler Engineering Project Manager 145 2 290
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer
145 1 145
Weiler Engineering Registered Engineer Intern 115 6 690
Weiler Engineering Senior Engineering Designer 100 8 800
Weiler Engineering Engineering Technician 80 0 0
Weiler Engineering Clerical 55 1 55
Total 1,980
Reimbursable Cost:
Description Number @ Total Postage 35 0
Printing 2.30 0.00
Overnight Travel {if applicable)
Not anticipated
Mileage {@ $0.445 per mile)
Not anticipated
Reimbursable Total Cost
Total Subtask 3C 1,980
Mr. Garland Sandel Rookery Bay Reserve Briggs Boardwalk- Plan Revisions
CN 803/TA06
Subtask 3D: Respond to Contractor RFl's
Description: WEC will respond to RFI's from Contractor within 7 days throughout the course of the construction phase.
Deliverable: WEC will provide copies of all RFI responses to FDEP Project Manager in PDF digital format.
Fixed Price Cost:
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Weiler Engineering Project Manager 145 2 290
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer
145 2 290
Weiler Engineering Registered Engineer Intern 115 8 920
Weiler Engineering Senior Engineering Designer 100 8 800
Weiler Engineering Engineering Technician 80 0 0
Weiler Engineering Clerical 55 4 220
Total 2,520
Reimbursable Cost:
Description Number @ Total Postage 0
Printing 0
Overnight Travel {if applicable)
Mileage (@ $0.445 per mile)
Reimbursable Total Cost
Total Subtask 3D 2,520
Subtask 3D- Respond to RFI's
Mr. Garland Sandel Rookery Bay Reserve Briggs Boardwalk- Plan Revisions
CN 803/TA06
Subtask 3E: Provide Construction Inspections (Month 1)
Description: WEC will provide a monthly inspection (NLT every 30 days) during construction.
Deliverable: WEC will provide two (2) original signed and sealed reports to the FDEP Project Manager, as well as a digital version in PDF format. The inspection report will be submitted within 3 days of each inspection.
Fixed Price Cost:
Subtask 3E - Month 1 Inspection Firm Name Position Classification Hourly Rate Hours Total Fixed
Price Cost Weiler Engineering Project Manager 145 1 145
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer
145 .5 72.5
Weiler Engineering Registered Engineer Intern 115 6 690
Weiler Engineering Senior Engineering Designer 100 1 100
Weiler Engineering Engineering Technician 80 0 0
Weiler Engineering Clerical 55 0 0
Total 1,007.5
Reimbursable Cost:
Description Number @ Total Postage 35 0
Printing 0
Overnight Travel {if applicable)
Mileage (@ $0.445 per mile)
320 0.445 142.40
Reimbursable Total Cost
142.40
Total Subtask 3E 1,149.90
Mr. Garland Sandel Rookery Bay Reserve Briggs Boardwalk- Plan Revisions
CN 803/TA06
Subtask 3F: Construction Inspection (Month 2)
Description: WEC will provide a monthly inspection (NLT every 30 days) during construction.
Deliverable: WEC will provide two (2) original signed and sealed reports to the FDEP Project Manager, as well as a digital version in PDF format. The inspection report will be submitted within 3 days of each inspection.
Fixed Price Cost:
Subtask 3F Firm Name Position Classification Hourly Rate Hours Total Fixed
Price Cost Weiler Engineering Project Manager 145 1 145
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer
145 .5 72.5
Weiler Engineering Registered Engineer Intern 115 6 690
Weiler Engineering Senior Engineering Designer 100 1 100
Weiler Engineering Engineering Technician 80 0 0
Weiler Engineering Clerical 55 0 0
Total 1007.50
Reimbursable Cost:
Description Number @ Total Postage 0 35 0 Printing 0
Overnight Travel {if applicable)
Mileage (@ $0.445 per mile)
320 0.445 142.40
Reimbursable Total Cost
Total Subtask 3F 1,149.90
Mr. Garland Sandel Rookery Bay Reserve Briggs Boardwalk- Plan Revisions
CN 803/TA06
Subtask 3G: Construction Inspection (Month 3)
Description: WEC will provide a monthly inspection (NLT every 30 days) during construction.
Deliverable: WEC will provide two (2) original signed and sealed reports to the FDEP Project Manager, as well as a digital version in PDF format. The inspection report will be submitted within 3 days of each inspection.
Fixed Price Cost:
Subtask 3G Month 3 Inspection Firm Name Position Classification Hourly Rate Hours Total Fixed
Price Cost Weiler Engineering Project Manager 145 1 145
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer
145 .5 72.5
Weiler Engineering Registered Engineer Intern 115 6 690
Weiler Engineering Senior Engineering Designer 100 1 100
Weiler Engineering Engineering Technician 80 0 0
Weiler Engineering Clerical 55 0 0
Total 1007.5
Reimbursable Cost:
Description Number @ Total Postage 0 35 0 Printing 0
Overnight Travel {if applicable)
Mileage (@ $0.445 per mile)
320 0.445 142.40
Reimbursable Total Cost
Mr. Garland Sandel Rookery Bay Reserve Briggs Boardwalk- Plan Revisions
CN 803/TA06
Total Subtask 3G 1,149.90
Subtask 3H: Construction Inspection (Month 4)
Description: WEC will provide a monthly inspection (NLT every 30 days) during construction.
Deliverable: WEC will provide two (2) original signed and sealed reports to the FDEP Project Manager, as well as a digital version in PDF format. The inspection report will be submitted within 3 days of each inspection.
Fixed Price Cost:
Subtask 3H - Inspection Month 4 Firm Name Position Classification Hourly Rate Hours Total Fixed
Price Cost Weiler Engineering Project Manager 145 1 145
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer
145 .5 72.5
Weiler Engineering Registered Engineer Intern 115 6 690
Weiler Engineering Senior Engineering Designer 100 1 100
Weiler Engineering Engineering Technician 80 0 0
Weiler Engineering Clerical 55 0 0
Total 1007.5
Reimbursable Cost:
Description Number @ Total Postage 0 35 0 Printing 0
Overnight Travel {if applicable)
Mileage (@ $0.445 per mile)
320 0.445 142.40
Mr. Garland Sandel Rookery Bay Reserve Briggs Boardwalk- Plan Revisions
CN 803/TA06
Reimbursable Total Cost
142.40
Total Subtask 3H 1,149.90
Subtask 3l: Construction Inspection (Month 5)
Description: WEC will provide a monthly inspection (NLT every 30 days) during construction.
Deliverable: WEC will provide two (2) original signed and sealed reports to the FDEP Project Manager, as well as a digital version in PDF format. The inspection report will be submitted within 3 days of each inspection.
Fixed Price Cost:
Subtask 3I Month 5 Inspection Firm Name Position Classification Hourly Rate Hours Total Fixed
Price Cost Weiler Engineering Project Manager 145 1 145
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer
145 .5 72.5
Weiler Engineering Registered Engineer Intern 115 6 690
Weiler Engineering Senior Engineering Designer 100 1 100
Weiler Engineering Engineering Technician 80 0 0
Weiler Engineering Clerical 55 0 0
Total 1007.5
Mr. Garland Sandel Rookery Bay Reserve Briggs Boardwalk- Plan Revisions
CN 803/TA06
Reimbursable Cost:
Description Number @ Total Postage 0 35 0 Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
320 0.445 142.40
Reimbursable Total Cost
142.40
Total Subtask 3I 1,149.90
Subtask 3J: Construction Inspection (Month 6)
Description: WEC will provide a monthly inspection (NLT every 30 days) during construction.
Deliverable: WEC will provide two (2) original signed and sealed reports to the FDEP Project Manager, as well as a digital version in PDF format. The inspection report will be submitted within 3 days of each inspection.
Fixed Price Cost:
Subtask 3J Month 6 Inspection Firm Name Position Classification Hourly Rate Hours Total Fixed
Price Cost Weiler Engineering Project Manager 145 1 145
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer
145 .5 72.5
Weiler Engineering Registered Engineer Intern 115 6 690
Weiler Engineering Senior Engineering Designer 100 1 100
Weiler Engineering Engineering Technician 80 0 0
Total 1007.5
Mr. Garland Sandel Rookery Bay Reserve Briggs Boardwalk- Plan Revisions
CN 803/TA06
Reimbursable Cost:
Description Number @ Total Postage 0 35 0 Printing 0
Overnight Travel {if applicable)
Mileage {@ $0.445 per mile)
320 0.445 142.40
Reimbursable Total Cost
142.40
Total Subtask 3J 1,149.90
Subtask 3K: Construction Inspection (Month 7)
Description: WEC will provide a monthly inspection (NLT every 30 days) during construction.
Deliverable: WEC will provide two (2) original signed and sealed reports to the FDEP Project Manager, as well as a digital version in PDF format. The inspection report will be submitted within 3 days of each inspection.
Fixed Price Cost:
Subtask 3K Month 7 Inspection Firm Name Position Classification Hourly Rate Hours Total Fixed
Price Cost Weiler Engineering Project Manager 145 1 145
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer
145 .5 72.5
Weiler Engineering Registered Engineer Intern 115 6 690
Weiler Engineering Senior Engineering Designer 100 1 100
Weiler Engineering Engineering Technician 80 0 0
Total 1,007.5
Mr. Garland Sandel Rookery Bay Reserve Briggs Boardwalk- Plan Revisions
CN 803/TA06
Reimbursable Cost:
Description Number @ Total Postage 0 35 0 Printing 0
Overnight Travel {if applicable)
Mileage (@ $0.445 per mile)
320 0.445 142.40
Reimbursable Total Cost
142.40
Total Subtask 3K 1,149.90
Subtask 3L: Construction Inspection (Month 8)
Description: WEC will provide a monthly inspection (NLT every 30 days) during construction.
Deliverable: WEC will provide two (2) original signed and sealed reports to the FDEP Project Manager, as well as a digital version in PDF format. The inspection report will be submitted within 3 days of each inspection.
Fixed Price Cost:
Subtask 3L Month 8 Inspection Firm Name Position Classification Hourly Rate Hours Total Fixed
Price Cost Weiler Engineering Project Manager 145 1 145
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer
145 .5 72.5
Weiler Engineering Registered Engineer Intern 115 6 690
Weiler Engineering Senior Engineering Designer 100 1 100
Weiler Engineering Engineering Technician 80 0 0
Total 1,007.50
Mr. Garland Sandel Rookery Bay Reserve Briggs Boardwalk- Plan Revisions
CN 803/TA06
Reimbursable Cost:
Description Number @ Total Postage 0 35 0 Printing 0
Overnight Travel {if applicable)
Mileage {@ $0.445 per mile)
320 0.445 142.40
Reimbursable Total Cost
142.40
Total Subtask 3L 1,149.90
Subtask 3M: Substantial Completion Walk-Through w/Punchlist
Description: WEC will assist Client with the Substantial Completion inspection and punchlist, with WEC representative attending the Substantial Completion inspection and providing engineer input related to the punchlist.
Deliverable: WEC will provide comments and input on punchlist within one {1) day of Substantial Completion inspection.
Fixed Price Cost:
Subtask 3M substantial Firm Name Position Classification Hourly Rate Hours Total Fixed
Price Cost Weiler Engineering Poject Manager 145 6 870
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer
145 1 145
Weiler Engineering Registered Engineer Intern 115 6 690
Weiler Engineering Senior Engineering Designer 100 1 100
Mr. Garland Sandel Rookery Bay Reserve Briggs Boardwalk- Plan Revisions
CN 803/TA06
Weiler Engineering Engineering Technician 80 0 0
Weiler Engineering Clerical 55 0 0
Total 1,805
Reimbursable Cost:
Description Number @ Total Postage 0 35 0 Printing 0
Overnight Travel {if applicable)
Mileage {@ $0.445 per mile)
320 0.445 142.40
Reimbursable Total Cost
142.40
Total Subtask 3M 1,947.40
Subtask 3N: Final Completion w/ Certification
Description: WEC will assist Client with the Final Completion inspection, with WEC representative attending the Final Completion inspection.
Deliverable: WEC will also provide complete the final completion certification form required by FDEP Project Manager.
Fixed Price Cost:
Subtask 3N - Final Firm Name Position Classification Hourly Rate Hours Total Fixed
Price Cost Weiler Engineering Project Manager 145 2 290
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer
145 1 145
Weiler Engineering Registered Engineer Intern 115 6 690
Mr. Garland Sandel Rookery Bay Reserve Briggs Boardwalk- Plan Revisions
CN 803/TA06
Weiler Engineering Senior Engineering Designer 100 2 200
Weiler Engineering Engineering Technician 80 0 0
Weiler Engineering Clerical 55 1 55
Total 1,380
Reimbursable Cost:
Description Number @ Total Postage 0 35 0 Printing 0
Overnight Travel {if applicable)
Mileage {@ $0.445 per mile)
320 0.445 142.40
Reimbursable Total Cost
142.40
Total Subtask 3N 1,522.40
Project Schedule:
Activity Duration (Calendar Days) Days from Execution Subtask 1: 100% Plan Revisions
30 – includes 7 days for Client review
Subtask 2: Assistance During Bidding
TBD TBD
Subtask 3A: Pre-Construction TBD TBD Subtask 3B: Review Submittals
TBD TBD
Subtask 3C: Respond to RAI's TBD TBD Subtask 3D: Respond to Contractor RFI's
TBD TBD
Subtask 3E: Provide Construction Inspections w/ (Month 1)
TBD TBD
Mr. Garland Sandel Rookery Bay Reserve Briggs Boardwalk- Plan Revisions
CN 803/TA06
Subtask 3F: Provide Construction Inspections w/ Report (Month 2)
TBD TBD
Subtask 3G: Provide Construction Inspections w/ Report (Month 3)
TBD TBD
Subtask 3H: Provide Construction Inspections w/ (Month 4)
TBD TBD
Subtask 3I: Provide Construction Inspections w/ Report (Month 5)
TBD TBD
Subtask 3J: Provide Construction Inspections w/ (Month 6)
TBD TBD
Subtask 3K: Provide Construction Inspections w/ (Month 7)
TBD TBD
Subtask 3L: Provide Construction Inspections w/ (Month 8)
TBD TBD
Subtask 3M: Substantial Completion Walk-Through w/ Punchlist
TBD TBD
Subtask 3N: Final Completion w/ Certification
TBD TBD
Mr. Garland Sandel Rookery Bay Reserve Briggs Boardwalk- Plan Revisions
CN 803/TA06
Summary of Fees:
Subtask Subtask Fixed Price Cost Subtask Reimbursable Subtask 1: 100% Plan Revisions
$5,892.53 $46.00
Total Design & Permitting $5,892.53 $46.00
Subtask 2 Pre-Bid $3,520.00 $0.00 Subtask 3A - Pre-Construction Meeting
$2,080.00 $0.00
Subtask 3B - Submittal Review $2,680.00 $0.00 Subtask 3C - Regulatory Response
$1,980.00 $0.00
Subtask 3D Assistance during construction
$2,520.00 $0.00
Subtask 3E Inspection 1 $1,007.50 $142.40 Subtask 3F Inspection 2 $1,007.50 $142.40 Subtask 3G Inspection 3 $1,007.50 $142.40 Subtask 3H Inspection 4 $1,007.50 $142.40 Subtask 3I Inspection 5 $1,007.50 $142.40 Subtask 3J Inspection 6 $1,007.50 $142.40 Subtask 3K Inspection 7 $1,007.50 $142.40 Subtask 3L Inspection 8 $1,007.50 $142.40 Subtask 3M Substantial Completion
$1,805.00 $142.40
Subtask 3N Final Completion $1,380.00 $142.40 Total during Construction $24,025.00 $1,424.00
Total: $29,917.53 $1,470.00