This is a Consultant's Task Assignment Notification (Form DRP-084) issued by the Florida Department of Environmental Protection (FDEP), Division of Recreation and Parks, for the Gasparilla Island State Park Sea Grape Day-Use Restroom project. The document formalizes Task Assignment No. 13 under FDEP Contract No. CN803 (Project No. 6G932) between FDEP and Weiler Engineering Corp (WEC). The key parties include FDEP Contract Manager Vu Nguyen, FDEP Project Manager Gage Marmolejo, WEC's consultant representative Robin Palmer, and five signatory officials representing FDEP budget, project management, contract management, and contract authority functions. The task assignment was executed on July 16-17, 2025, with a completion date of March 18, 2026.

The task encompasses construction administration and inspection services for the restroom facility construction, consisting of 14 subtasks (1A through 1N) transferred from the previous contract CN230 Task Assignment 63, utilizing the approved rates from that contract. Services include pre-construction meeting attendance, contractor submittal review, building department comment responses, request for information (RFI) responses, eight monthly construction inspections, substantial completion walk-through with punchlist review, and final completion certification. The contract is structured as a fixed-price agreement with a total task amount of $22,180.00 and zero cost reimbursement. All costs are encumbered against Project 6G932, Grant 37504003191, Organization Code 080039/25, Fund 408001, Module U3100, Object 134000, with payment contingent upon FDEP approval of deliverables for each subtask.

View the file

Other files

File Type Posted
CN-370000-CN803-T10.pdf PDF
CN-370000-CN803-T10CO1.pdf PDF
CN-370000-CN803-T14.pdf PDF
CN-370000-CN803-T16.pdf PDF
CN-370000-CN803-T19.pdf PDF
CN-370000-CN803-T3.pdf PDF
CN-370000-CN803-T1.pdf PDF
CN-370000-CN803-T10.pdf.crdownload CRDOWNLOAD file
CN-370000-CN803-T11.pdf PDF
CN-370000-CN803-T2.pdf PDF
CN-370000-CN803-T22.pdf PDF
CN-370000-CN803-T23.pdf PDF
CN-370000-CN803-T25.pdf PDF
CN-370000-CN803-T26.pdf PDF
CN-370000-CN803-T4.pdf PDF
CN-370000-CN803.pdf PDF
CN-370000-CN803.pdf.crdownload CRDOWNLOAD file
CN-370000-CN803-CMC1.pdf PDF
CN-370000-CN803-T12.pdf PDF
CN-370000-CN803-T15.pdf PDF
CN-370000-CN803-T18.pdf PDF
CN-370000-CN803-T20.pdf PDF
CN-370000-CN803-T21.pdf PDF
CN-370000-CN803-T24.pdf PDF
CN-370000-CN803-T2CO1.pdf PDF
CN-370000-CN803-T30.pdf PDF
CN-370000-CN803-T6.pdf PDF
CN-370000-CN803-T6CO1.pdf PDF
CN-370000-CN803-T9.pdf PDF
CN-370000-CN803-T17.pdf PDF
CN-370000-CN803-T5.pdf PDF
CN-370000-CN803-T7.pdf PDF
CN-370000-CN803-T8.pdf PDF
CN-370000-CN803-T8CO1.pdf PDF
Show all 34

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DDivision oof RRecreation aand PParks

CConsultant’s TTask AAssignment NNotification

FFLORIDA DEPARTMENT OF

EENVIRONMENTAL PPROTECTION

DRP-084

Rev. 0 /2025 of 2

FDEP Contract No: Project Number: Task Assignment No:

Project Location Project

Consultant’s Name:

Consultant’s Representative:

Phone: Email:

FDEP Contract Manager:

Phone: Email:

Task Description:

Project Manager:

Schedule:

Start Date: Completion Date:

Fixed Price Cost: Cost Reimbursement (Not to Exceed):

Total Task Amount:

Signatures and Date:

1.

Budget Representative, FDEP Signature Date

2.

Project Manager, FDEP Signature Date

3.

Signature Date

4.

Signature Date

5.

Contract Authority, FDEP Signature Date

CN803 6G932 13

Gasparilla Island State Park Sea Grape Day-Use Restroom

Weiler Engineering Corp (WEC) Robin Palmer

(941) 646-8612 rpalmer@weilerengineering.org

Vu Nguyen

(850) 245-2630 vu.nguyen@floridadep.gov

Transferral of incomplete sub-tasks from CN230 TA63 (6A-6N) per attached proposal dated June 16, 2025 *Subtasks utilizing rates per CN230 are denoted with an asterisk (*) in the subtask heading.

Gage Marmolejo

Upon Execution 03/18/2026

$22,180.00 $0.00 $22,180.00

Tamika Bass

Gage Marmolejo

Robin Palmer

Vu Nguyen

Michael W. Foster Jr., P.E.

Tamika Bass Digitally signed by Tamika Bass Date: 2025.07.16 08:44:57 -04'00'

Digitally signed by Gage Marmolejo Date: 2025.07.16 09:01:07 -04'00'

Robin C. Palmer Digitally signed by Robin C. Palmer Date: 2025.07.16 11:24:34 -04'00'

Vu Nguyen Digitally signed by Vu Nguyen Date: 2025.07.16 15:43:36 -04'00'

Michael W. Foster Jr., P.E.

Digitally signed by Michael W. Foster Jr., P.E.

Date: 2025.07.17 09:05:44 -04'00'

DDivision oof RRecreation aand PParks

CConsultant’s TTask AAssignment NNotification

FFLORIDA DEPARTMENT OF

EENVIRONMENTAL PPROTECTION

DRP-084

Rev. /2025 2 of 2

Encumbrance Information:

Project # Grant # Organization Code Category/Yr Fund Module Object EO Amount

Total:

6G932 37504003191 080039/25 408001 U3100 134000 PF $22,180.00

$22,180.00

June 16, 2025

John Goss Construction Project Manager Bureau of Design and Construction Florida Department of Environmental Protection 1843 S. Tamiami Trail Osprey, FL 34229

RE: Gasparilla State Park - Seagrape Day Use Restroom, CN - 803, TA

Dear Mr. Goss, Thank you for the opportunity to provide this proposal for Construction Administration services during the construction of a new restroom at the Seagrape Day Use Area at Gasparilla State Park.

For clarity, items with an asterisk (*) are items transferred over from the previous CN and use the old rates approved under CN 230.

For your review, the Weiler Engineering Corporation, has provided a proposal summary and man-hour documentation for the tasks identified below:

Please review the attached Proposal Summary and deliverables.

Sincerely, Michael J. Giardullo, P.E.

Director of Civil Engineering The Weiler Engineering Corporation- An Apex Company

PUNTA GORDA OFFICE: 201 WEST MARION AVENUE - SUITE 1306 | PUNTA GORDA | FL 33950 | TEL 941-505 -1700 | FAX 941-505 -1702 MARATHON OFFICE: 6805 OVERSEAS HIGHWAY | MARATHON | FL 33050 | TEL 305 -289-4161 | FAX 305 -289- 416 2 WE INVITE YOU TO

VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG

Gasparilla State Park Seagrape Day Use Restroom CA

CN 803/TA

Gasparilla State Park Seagrape Day Use Restroom

Contract Number 803, Task Assignment Number

Subtask 1A - 1N: Construction Phase Services

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Subtask 1A: Attend Pre-Construction Meeting

Description: WEC will provide representation at the Pre-Construction Meeting.

Deliverable: Meeting notes within 2 days from meeting date for inclusion by FDEP Project Manager in Meeting Minutes.

Fixed Price Cost:

Subtask 1A - Pre-Construction Mtg

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 9 1305

Principal in Charge 195 0 0

Registered Professional Engineer 145 0 0

Registered Engineer Intern 115 8 920

Senior Engineering Designer 100 0 0

Engineering Technician 80 0 0

Clerical 55 0 0

Total 2225

Subtask 1B: Review Contractor Submittals

Description: WEC will review and comment on Contractor submittal package within 14 days of receipt.

Deliverable: Stamped acceptance of final submittals in PDF digital form to FDEP Project Manager within 7 days of final approvals.

Gasparilla State Park Seagrape Day Use Restroom CA

CN 803/TA

Fixed Price Cost:

Subtask 1B - Review Submittals

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 2 290

Principal in Charge 195 0 0

Registered Professional Engineer 145 0 0

Registered Engineer Intern 115 8 920

Senior Engineering Designer 100 12 1200

Engineering Technician 80 2 160

Clerical 55 2 110

Total 2680

Subtask 1 : Respond to Building Department comments

Description: WEC will assist Client and/or Client's Contractor in responding to comments from the Building Department, and revise plans accordingly within 14 days of receipt of comments.

Specifically, when WEC's involvement is required for RFI responses, WEC will prepare a draft and send to FDEP Project Manager for review and comment. WEC will then discuss and/or revise accordingly prior to formal submittal of RFI response to Building Department.

Deliverable: RFI response documents submitted to Building Department.

Fixed Price Cost:

Subtask 1C

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 2 290

Principal in Charge 195 0 0

Registered Professional Engineer 145 1 145

Registered Engineer Intern 115 6 690

Senior Engineering Designer 100 8 800

Engineering Technician 80 0 0

Clerical 55 1 55

Total 1980

Gasparilla State Park Seagrape Day Use Restroom CA

CN 803/TA

Subtask D: Respond to Contractor RFI's

Description: WEC will respond to RFI's from Contractor within 7 days throughout the course of the construction phase.

Deliverable: WEC will provide copies of all RFI responses to FDEP Project Manager in PDF digital format.

Fixed Price Cost:

Subtask 1D- Respond to RFI’s

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 2 290

Principal in Charge 195 0 0

Registered Professional Engineer 145 2 290

Registered Engineer Intern 115 8 920

Senior Engineering Designer 100 8 800

Engineering Technician 80 0 0

Clerical 55 4 220

Total 2520

Subtask 1E: Provide Construction Inspections (Month 1)

Description: WEC will provide a monthly inspection (NLT every 30 days) during construction.

Deliverable: WEC will provide two (2) original signed and sealed reports to the FDEP Project Manager, as well as a digital version in PDF format. The inspection report will be submitted within 3 days of each inspection.

Gasparilla State Park Seagrape Day Use Restroom CA

CN 803/TA

Fixed Price Cost:

Subtask 1E - Month 1 Inspection

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 2 290

Principal in Charge 195 0 0

Registered Professional Engineer 145 .5 72.5

Registered Engineer Intern 115 6 690

Senior Engineering Designer 100 1 100

Engineering Technician 80 0 0

Clerical 55 0 0

Total 1152.50

Subtask 1F: Construction Inspection (Month 2)

Description: WEC will provide a monthly inspection (NLT every 30 days) during construction.

Deliverable: WEC will provide two (2) original signed and sealed reports to the FDEP Project Manager, as well as a digital version in PDF format. The inspection report will be submitted within 3 days of each inspection.

Fixed Price Cost:

Subtask 1F

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 2 290

Principal in Charge 195 0 0

Registered Professional Engineer 145 .5 72.5

Registered Engineer Intern 115 6 690

Senior Engineering Designer 100 1 100

Engineering Technician 80 0 0

Clerical 55 0 0

Total 1152.50

Gasparilla State Park Seagrape Day Use Restroom CA

CN 803/TA

Subtask 1G: Construction Inspection (Month 3)

Description: WEC will provide a monthly inspection (NLT every 30 days) during construction.

Deliverable: WEC will provide two (2) original signed and sealed reports to the FDEP Project Manager, as well as a digital version in PDF format. The inspection report will be submitted within 3 days of each inspection.

Fixed Price Cost:

Subtask 1G Month 3 Inspection

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 2 290

Principal in Charge 195 0 0

Registered Professional Engineer 145 .5 72.5

Registered Engineer Intern 115 6 690

Senior Engineering Designer 100 1 100

Engineering Technician 80 0 0

Clerical 55 0 0

Total 1152.50

Subtask 1H: Construction Inspection (Month 4)

Description: WEC will provide a monthly inspection (NLT every 30 days) during construction.

Deliverable: WEC will provide two (2) original signed and sealed reports to the FDEP Project Manager, as well as a digital version in PDF format. The inspection report will be submitted within 3 days of each inspection.

Fixed Price Cost:

Subtask 1H - Inspection Month 4

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 2 290

Principal in Charge 195 0 0

Registered Professional Engineer 145 .5 72.5

Registered Engineer Intern 115 6 690

Senior Engineering Designer 100 1 100

Gasparilla State Park Seagrape Day Use Restroom CA

CN 803/TA

Engineering Technician 80 0 0

Clerical 55 0 0

Total 1152.50

Subtask 1I: Construction Inspection (Month 5)

Description: WEC will provide a monthly inspection (NLT every 30 days) during construction.

Deliverable: WEC will provide two (2) original signed and sealed reports to the FDEP Project Manager, as well as a digital version in PDF format. The inspection report will be submitted within 3 days of each inspection.

Fixed Price Cost:

Subtask 1I Month 5 Inspection

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 2 290

Principal in Charge 195 0 0

Registered Professional Engineer 145 .5 72.5

Registered Engineer Intern 115 6 690

Senior Engineering Designer 100 1 100

Engineering Technician 80 0 0

Clerical 55 0 0

Total 1152.50

Subtask 1J: Construction Inspection (Month 6)

Description: WEC will provide a monthly inspection (NLT every 30 days) during construction.

Deliverable: WEC will provide two (2) original signed and sealed reports to the FDEP Project Manager, as well as a digital version in PDF format. The inspection report will be submitted within 3 days of each inspection.

Gasparilla State Park Seagrape Day Use Restroom CA

CN 803/TA

Fixed Price Cost:

Subtask 1J Month 6 Inspection

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 2 290

Principal in Charge 195 0 0

Registered Professional Engineer 145 .5 72.5

Registered Engineer Intern 115 6 690

Senior Engineering Designer 100 1 100

Engineering Technician 80 0 0

Clerical 55 0 0

Total 1152.50

Subtask 1K: Construction Inspection (Month 7)

Description: WEC will provide a monthly inspection (NLT every 30 days) during construction.

Deliverable: WEC will provide two (2) original signed and sealed reports to the FDEP Project Manager, as well as a digital version in PDF format. The inspection report will be submitted within 3 days of each inspection.

Fixed Price Cost:

Subtask 1K Month 7 Inspection

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 2 290

Principal in Charge 195 0 0

Registered Professional Engineer 145 .5 72.5

Registered Engineer Intern 115 6 690

Senior Engineering Designer 100 1 100

Engineering Technician 80 0 0

Clerical 55 0 0

Total 1152.50

Gasparilla State Park Seagrape Day Use Restroom CA

CN 803/TA

Subtask 1L: Construction Inspection (Month 8)

Description: WEC will provide a monthly inspection (NLT every 30 days) during construction.

Deliverable: WEC will provide two (2) original signed and sealed reports to the FDEP Project Manager, as well as a digital version in PDF format. The inspection report will be submitted within 3 days of each inspection.

Fixed Price Cost:

Subtask 1L Month 8 Inspection

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 2 290

Principal in Charge 195 0 0

Registered Professional Engineer 145 .5 72.5

Registered Engineer Intern 115 6 690

Senior Engineering Designer 100 1 100

Engineering Technician 80 0 0

Clerical 55 0 0

Total 1152.50

Subtask 1M: Substantial Completion Walk-Through w/Punchlist

Description: WEC will assist Client with the Substantial Completion inspection and punchlist, with WEC representative attending the Substantial Completion inspection and providing engineer input related to the punchlist.

Deliverable: WEC will provide comments and input on punchlist within one (1) day of Substantial Completion inspection.

Gasparilla State Park Seagrape Day Use Restroom CA

CN 803/TA

Fixed Price Cost:

Subtask 1M substantial

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 6 870

Principal in Charge 195 0 0

Registered Professional Engineer 145 1 145

Registered Engineer Intern 115 7 805

Senior Engineering Designer 100 1 100

Engineering Technician 80 0 0

Clerical 55 1 55

Total 1975

Subtask 1N: Final Completion w/ Certification

Description: WEC will assist Client with the Final Completion inspection, with WEC representative attending the Final Completion inspection.

Deliverable: WEC will also provide complete the final completion certification form required by FDEP Project Manager.

Fixed Price Cost:

Subtask 1N - Final

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 3 435

Principal in Charge 195 0 0

Registered Professional Engineer 145 1 145

Registered Engineer Intern 115 6 690

Senior Engineering Designer 100 2 200

Engineering Technician 80 0 0

Clerical 55 2 110

Total 1580

Gasparilla State Park Seagrape Day Use Restroom CA

CN 803/TA

Project Schedule:

Activity Duration (Calendar Days) Days from Execution

Subtask 1A - Pre Construction TBD TBD

Subtask 1B: Review Submittals TBD TBD

Subtask 1C: Respond to RAI's TBD TBD

Subtask 1D: Respond to Contractor RFI's

TBD TBD

Subtask 1E: Provide Construction Inspections w/ (Month 1)

TBD TBD

Subtask 1F: Provide Construction Inspections w/ Report (Month 2)

TBD TBD

Subtask 1G: Provide Construction Inspections w/ Report (Month 3)

TBD TBD

Subtask 1H: Provide Construction Inspections w/ (Month 4)

TBD TBD

Subtask 1I: Provide Construction Inspections w/ Report (Month 5)

TBD TBD

Subtask 1J: Provide Construction Inspections w/ (Month 6)

TBD TBD

Subtask 1K: Provide Construction Inspections w/ (Month 7)

TBD TBD

Subtask 1L: Provide Construction Inspections w/ (Month 8)

TBD TBD

Subtask 1M: Substantial Completion Walk-Through w/ Punchlist

TBD TBD

Subtask 1N: Final Completion w/ Certification

TBD TBD

Summary of Fees:

Subtask Subtask Fixed Price Cost Subtask Reimbursable

Subtask 1A - Pre Construction 2225 0

Subtask 1B: Review Submittals 2680 0

Subtask 1C: Respond to RAI's 1980 0

Subtask 1D: Respond to Contractor RFI's

2520 0

Subtask 1E: Provide Construction Inspections w/ (Month 1)

1152.50 0

Subtask 1F: Provide Construction Inspections w/ Report (Month 2)

1152.50 0

Gasparilla State Park Seagrape Day Use Restroom CA

CN 803/TA

Subtask 1G: Provide Construction Inspections w/ Report (Month 3)

1152.50 0

Subtask 1H: Provide Construction Inspections w/ (Month 4)

1152.50 0

Subtask 1I: Provide Construction Inspections w/ Report (Month 5)

1152.50 0

Subtask 1J: Provide Construction Inspections w/ (Month 6)

1152.50 0

Subtask 1K: Provide Construction Inspections w/ (Month 7)

1152.50 0

Subtask 1L: Provide Construction Inspections w/ (Month 8)

1152.50 0

Subtask 1M: Substantial Completion Walk-Through w/ Punchlist

1975.00 0

Subtask 1N: Final Completion w/ Certification

1580.00 0

Total during Construction $22180.00 $0

Total Fixed Price Cost: $22180.00

Total Fixed Price Cost: $0

Overall Total Cost: $22180.00

Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified. (Please do not alter this language)

File details come from the government source that posted it. Updated .