Summary

This is a Consultant's Task Assignment Notification (Form DRP-084) issued by the Florida Department of Environmental Protection's Division of Recreation and Parks. The document formalizes a task assignment under Contract CN803 between the State of Florida (FDEP) and Weiler Engineering Corporation, an Apex Company. Garland Sandel serves as the FDEP Project Manager, while Michael Giardullo, P.E., represents the consultant. The contract manager is Laurinda Micheels. The task assignment was executed on January 7, 2027, as referenced in the notification dated January 6, 2026.

The task consists of design plans, permitting, and construction assistance for modifications to the existing Gasparilla Island State Park Armory Chapel into an open-air structure. The work is organized into 21 subtasks spanning design phases (30%, 60%, and 100%), permitting, and construction oversight. The fixed price cost is $139,582.03, with cost reimbursement not to exceed $6,500.00 for permit application fees, bringing the total task amount to $146,082.03. The project is funded through grant FD097 under organization code 37504003191 with fiscal year allocation 088040/25. Design and permitting subtasks are scheduled to conclude by day 315 from execution, while construction inspection and assistance activities are scheduled as needed through final completion. Payment is contingent upon FDEP approval of deliverables for each subtask.

View the file

Other files

File Type Posted
CN-370000-CN803-T1.pdf PDF
CN-370000-CN803-T10.pdf.crdownload CRDOWNLOAD file
CN-370000-CN803-T11.pdf PDF
CN-370000-CN803-T13.pdf PDF
CN-370000-CN803-T2.pdf PDF
CN-370000-CN803-T22.pdf PDF
CN-370000-CN803-T23.pdf PDF
CN-370000-CN803-T25.pdf PDF
CN-370000-CN803-T26.pdf PDF
CN-370000-CN803-T4.pdf PDF
CN-370000-CN803.pdf PDF
CN-370000-CN803.pdf.crdownload CRDOWNLOAD file
CN-370000-CN803-CMC1.pdf PDF
CN-370000-CN803-T12.pdf PDF
CN-370000-CN803-T15.pdf PDF
CN-370000-CN803-T18.pdf PDF
CN-370000-CN803-T20.pdf PDF
CN-370000-CN803-T21.pdf PDF
CN-370000-CN803-T24.pdf PDF
CN-370000-CN803-T2CO1.pdf PDF
CN-370000-CN803-T6.pdf PDF
CN-370000-CN803-T6CO1.pdf PDF
CN-370000-CN803-T9.pdf PDF
CN-370000-CN803-T10.pdf PDF
CN-370000-CN803-T10CO1.pdf PDF
CN-370000-CN803-T14.pdf PDF
CN-370000-CN803-T16.pdf PDF
CN-370000-CN803-T19.pdf PDF
CN-370000-CN803-T3.pdf PDF
CN-370000-CN803-T17.pdf PDF
CN-370000-CN803-T5.pdf PDF
CN-370000-CN803-T7.pdf PDF
CN-370000-CN803-T8.pdf PDF
CN-370000-CN803-T8CO1.pdf PDF
Show all 34

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DDivision oof RRecreation aand PParks

CConsultant’s TTask AAssignment NNotification

FFLORIDA DEPARTMENT OF

EENVIRONMENTAL PPROTECTION

DRP-084

Rev. /2025 of 2

FDEP Contract No: Project Number: Task Assignment No:

Project Location Project

Consultant’s Name:

Consultant’s Representative:

Phone: Email:

FDEP Contract Manager:

Phone: Email:

Task Description:

Project Manager:

Schedule:

Start Date: Completion Date:

Fixed Price Cost: Cost Reimbursement (Not to Exceed):

Total Task Amount:

Signatures and Date:

1.

Budget Representative, FDEP Signature Date

2.

Project Manager, FDEP Signature Date

3.

Signature Date

4.

Signature Date

5.

Contract Authority, FDEP Signature Date

CN803 6M40 C 30

Gasparilla Island State Park Chapel

Weiler Engineering Corporation- An Apex Company Michael Giardullo, P.E.,

(941) 505-1700 mgiardullo@weilerengineering.org

Laurinda Micheels

(850) 245-2781 Laurinda.Micheels@FloridaDEP.gov

The TA consist of design plans, permitting, and construction assistance for modifications to the existing Gasparilla Island State Park Armory Chapel into an open-air structure. See proposal dated 1/6/2026.

Garland Sandel

Upon Execution 01/07/2027

$139,582.03 $6,500.00 $146,082.03

Tamika Bass

Garland Sandel

Michael Giardullo, P.E., Laurinda Micheels

Michael W. Foster Jr., P.E

Tamika Bass Digitally signed by Tamika Bass Date: 2026.01.08 10:57:04 -05'00'

Garland Sandel Digitally signed by Garland Sandel Date: 2026.01.08 11:21:05 -05'00'

Michael Giardullo Digitally signed by Michael Giardullo DN: E=mgiardullo@weilerengineering.org, CN=Michael Giardullo, OU=Users, OU=Apex-FL-PTG, OU=Apex-Offices, DC=ApexCos, DC=local Date: 2026.01.08 14:44:01-05'00'

Laurinda Micheels Digitally signed by Laurinda Micheels Date: 2026.01.08 14:50:50 -05'00'

Michael W. Foster Jr., P.E. Digitally signed by Michael W. Foster Jr., P.E.

Date: 2026.01.13 09:47:39 -05'00'

DDivision oof RRecreation aand PParks

CConsultant’s TTask AAssignment NNotification

FFLORIDA DEPARTMENT OF

EENVIRONMENTAL PPROTECTION

DRP-084

Rev. /2025 2 of 2

Encumbrance Information:

Project # Grant # Organization Code Category/Yr Fund Module Object EO Amount

Total:

6M40 C FD097 37504003191 088040/25 675002 U3200 131500 XR $146,082.03

$146,082.03

January 6, 2026

Garland Sandel Project Manager Bureau of Design and Construction Florida Department of Environmental Protection 3900 Commonwealth Boulevard 260-L, MS 520 Tallahassee, FL 32399

RE: Gasparilla Island State Park Chapel Design CN 803, TA

Mr. Sandel, Thank you for the opportunity to provide this proposal to assist the Department to prepare design plans, permitting, and construction assistance for modifications to the existing Gasparilla Island State Park Armory Chapel into an open-air structure.

PUNTA GORDA OFFICE: 201 WEST MARION AVENUE - SUITE 1306 | PUNTA GORDA | FL 33950 | TEL 941-505 -1700 | FAX 941-505 - 1702 MARATHON OFFICE: 6805 OVERSEAS HIGHWAY | MARATHON | FL 33050 | TEL 305 -289-4161 | FAX 305 -

289- 416 2 WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT

INFO@WEILERENGINEERING.ORG

Mr. Garland Sandel Gasparilla Island State Park Chapel Design

CN 803, TA

For your review, the Weiler Engineering Corporation, has provided a proposal summary and man-hour documentation for the tasks identified below. Please review the attached proposal summary and deliverables.

Sincerely, Michael J. Giardullo, P.E.

Director of Civil Engineering The Weiler Engineering Corporation- An Apex Company

Mr. Garland Sandel Gasparilla Island State Park Chapel Design

CN 803, TA

Gasparilla Island State Park Chapel Contract Number 803, Task Assignment Number

Subtask 1: Pre-Application Meetings Description: Consultant will complete pre-application meetings with SWFWMD and Lee County, a meeting with Lee County historic board, and a site visit.

Deliverable: Consultant shall deliver the following:

1. Meeting Minutes from Pre-Application Meetings (SWFWMD and Lee

County)

2. Meeting with Lee County historic board.

3. Site Visit: On-site presentation to Lee County historic board.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Fixed Price Cost:

Subtask 1 – Pre-Application Meetings Firm Name Position Classification Hourly

Rate Hours Total

Fixed Price Cost

Weiler Engineering

Senior Project Manager 160.83 7 1,125.81

Weiler Engineering

Principal 319.24 0.25 79.81

Weiler Engineering

Professional Engineer 168.20 1 168.20

Weiler Engineering

Engineer Intern 115.45 4 461.80

Weiler Engineering

Senior Engineering Designer 115.13 13 1,496.69

Weiler Engineering

Engineering Designer 90.40 10 904.00

Weiler Engineering

Clerical 62.74 1 62.74

Total 4,299.05

Total for Subtask 1

4,299.05

Mr. Garland Sandel Gasparilla Island State Park Chapel Design CN

803, TA

Subtask 2: CRAS

Cultural Resource Assessment (CRAS)

a) Consultant will complete a 1A-32 Florida Permit Application

b) Consultant will complete a review of historic records for the site

c) Consultant will complete a cultural resource survey on-site

d) Consultant will update the Florida Master Site File (FMSF)

e) Consultant will provide a report in PDF format detailing the results

Deliverable:

Cultural Resource Assessment (CRAS)

a) Consultant will complete a 1A-32 Florida Permit Application

b) Consultant will complete a review of historic records for the site

c) Consultant will complete a cultural resource survey on-site

d) Consultant will update the Florida Master Site File (FMSF)

e) Consultant will provide a report in PDF format detailing the results

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Fixed Price Cost:

Subtask 2 - CRAS

Firm Name Position Classification Hourly Rate Hours Total Fixed

Price Cost Weiler Engineering Senior Project Manager 160.83 14 2,251.62

Archaeological and Historic Conservancy, Inc.

Historian 71.28 25 1,782.00

Archaeological and Historic Conservancy, Inc.

Project Lead Archaeologist 145.20 16 2,323.20

Archaeological and Historic Conservancy, Inc.

Field Archaeologist 97.68 25 2,442.00

Archaeological and Historic Conservancy, Inc.

Administrative 79.20 1 79.20

Total 8,878.02

Mr. Garland Sandel Gasparilla Island State Park Chapel Design

CN 803, TA

Subtask 3: 30% Design

A – 30% Design

f) WEC will conduct one site visit

g) Consultant will prepare 30% design plans

B – Surveys

h) Consultant will coordinate with Survey Sub-Consultant to prepare a special Purpose

Survey of the existing structure and topography for the project area.

C – Lead/Asbestos Reports

i) Consultant will coordinate with Geotechnical Sub-Consultant to conduct

NESHAP Asbestos and Lead Based paint screening (up to 50 samples for asbestos and 5 lead samples) on the existing structure.

Deliverable:

A – 30% Civil Design Plans

Consultant shall deliver 30% Civil Plans for the site to the client via digital PDF. Plans will include:

Cover Sheet Survey/Existing Conditions Best Management Plan Demolition Plan Site Plan

B - Survey Consultant will coordinate with Survey Sub-Consultant to prepare a special Purpose Survey of the existing structure and topography for the project area.

C – Lead/Asbestos Report

Consultant will coordinate with Geotechnical Sub-Consultant to conduct NESHAP Asbestos and Lead Based paint screening (up to 50 samples for asbestos and 5 lead samples) on the existing structure

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Mr. Garland Sandel Gasparilla Island State Park Chapel Design

CN 803, TA

Fixed Price Cost:

Subtask 3A - 30% Design Plans

Firm Name Position Classification Hourly Rate Hours Total Fixed

Price Cost Weiler Engineering Senior Project Manager 160.83 14 2,251.62

Weiler Engineering Principal 319.24 0.25 79.81

Weiler Engineering

Professional Engineer 168.20 14 2,354.80

Weiler Engineering Engineer Intern 115.45 25 2,886.25

Weiler Engineering Senior Engineering Designer 115.13 50 5,756.50

Weiler Engineering Engineering Designer 90.40 35 3,164.00

Weiler Engineering Clerical 62.74 5 313.70

Total 16,806.68

Subtask 3B - Survey Firm Name Position Classification Unit Unit

Rate Number Units

Total Fixed Price Cost

Weiler Engineering Senior Project Manager Hr 160.83 4 643.32 CHW 3 Person Field Crew Hr 166.59 5 832.95 CHW Project Surveyor Hr 70.14 2 140.28 CHW Professional Surveyor &

Mapper Hr 153.82 2 307.64

CHW Senior CAD/GIS Hr 96.78 2 193.56 Total Survey 2,117.75

Mr. Garland Sandel Gasparilla Island State Park Chapel Design

CN 803, TA

Subtask 3C Lead/Asbestos Testing

Firm Name Position Classification Unit Unit Rate

Number Units

Total Fixed Price Cost

Weiler Engineering Senior Project Manager Hr 160.83 8 1,286.64 Tierra Principal Engineer Hr 248.71 10 2,487.10 Tierra Chief Scientist Hr 182.01 12 2,184.12 Tierra Senior Engineering

Technician Hr 120.34 18 2,166.12

Tierra Secretary/Clerical Hr 114.16 2 228.32 Tierra Total Lead/Asbestos 8,352.30

Subtask 4: 60% Plans

Description: Design Plans completed to 60% incorporating comments from 30% design.

Deliverable: Consultant shall deliver 60% Plans (digital PDF only) including:

Opinion of Probable Cost Cover sheet Survey/Existing Conditions Best Management Plan Demolition Plan Site, Utility & Grading Plans Site Details and General Notes Floor Plan Foundation Plan Exterior Elevations Building Cross-Sections and Details

Mr. Garland Sandel Gasparilla Island State Park Chapel Design

CN 803, TA

Fixed Price Cost:

Subtask 4 - 60% Plans

Firm Name Position Classification Hourly Rate Hours Total

Fixed Price Cost

Weiler Engineering Senior Project Manager 160.83 14 2,251.62

Weiler Engineering Principal 319.24 0.25 79.81

Weiler Engineering

Professional Engineer 168.20 14 2,354.80

Weiler Engineering Engineer Intern 115.45 30 3,463.50

Weiler Engineering Senior Engineering Designer 115.13 60 6,907.80

Weiler Engineering Engineering Designer 90.40 30 2,712.00

Weiler Engineering Clerical 62.74 2 125.48

Total 17,895.01

Subtask 5: Permit Applications

Description:

5) A – Permit Applications Consultant will assist Client to submit permit applications for SWFWMD, Lee County LDO, Lee County Historic Preservation Board, State Fire Marshal, and DHR.

5) B – Permit Approvals:

Consultant will coordinate with SWFWMD, Lee County LDO, Lee County Historic Preservation Board, State Fire Marshal, and DHR and assist Client to respond to agencies for additional information.

Deliverable:

5) A – Permit Applications Incorporate Client review comments from 60% plans and deliver permit applications for SWFWMD, Lee County LDO, Lee County Historic Preservation Board, State Fire Marshal, and DHR applications in PDF format.

Mr. Garland Sandel Gasparilla Island State Park Chapel Design

CN 803, TA

5) B – Permit Approvals:

Consultant will respond to SWFWMD, Lee County LDO, Lee County Historic Preservation Board, State Fire Marshal, and DHR requests for additional information and copy Client on all responses. Upon approval, Consultant will provide Client with approval and revised (if necessary) plans and documentation. Approval will be provided in PDF format.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Fixed Price Cost:

Subtask 5A – Permit Applications

Firm Name Position Classification Hourly Rate Hours Total

Fixed Price Cost

Weiler Engineering Senior Project Manager 160.83 10 1,608.30

Weiler Engineering Principal 319.24 2 638.48

Weiler Engineering

Professional Engineer 168.20 12 2,018.40

Weiler Engineering Engineer Intern 115.45 45 5,195.25

Weiler Engineering Senior Engineering Designer 115.13 60 6,907.80

Weiler Engineering Engineering Designer 90.40 40 3,616.00

Weiler Engineering Clerical 62.74 2 125.48

Total 20,109.71

Subtask 5B – Permit Approvals:

Firm Name Position Classification Hourly Rate Hours Total

Fixed Price Cost

Weiler Engineering Senior Project Manager 160.83 6 964.98

Mr. Garland Sandel Gasparilla Island State Park Chapel Design

CN 803, TA

Weiler Engineering Principal 319.24 0.25 79.81

Weiler Engineering

Professional Engineer 168.20 2 336.40

Weiler Engineering Engineer Intern 115.45 4 461.80

Weiler Engineering Senior Engineering Designer 115.13 10 1,151.30

Weiler Engineering Engineering Designer 90.40 4 361.60

Weiler Engineering Clerical 62.74 1 62.74

Total 3,418.63

Reimbursable Cost:

Description Number @ Total

Postage Not Anticipated Printing Not Anticipated Permit application fees estimate

6,500 6,500

Reimbursable Total Cost for 5

6,500

Total for Subtask 5

30,028.34

Subtask 6: 100% Plans

Description: Plans completed to 100% incorporating comments from 60% design.

Deliverable: Consultant shall deliver 100% Plans (digital PDF only) including:

Opinion of Probable Cost Cover sheet Survey/Existing Conditions Best Management Plan Demolition Plan Site, Utility & Grading Plans Site Details and General Notes Sections

Mr. Garland Sandel Gasparilla Island State Park Chapel Design

CN 803, TA

Floor Plan Foundation Plans Beam Schedules Exterior Elevations Building Cross-Sections and Details

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Fixed Price Cost:

Subtask 6 - 100% Plans

Firm Name Position Classification Hourly Rate Hours Total

Fixed Price Cost

Weiler Engineering Senior Project Manager 160.83 8 1,286.64

Weiler Engineering Principal 319.24 .25 79.81

Weiler Engineering

Professional Engineer 168.20 8 1,345.60

Weiler Engineering Engineer Intern 115.45 20 2,309.00

Weiler Engineering Senior Engineering Designer 115.13 50 5,756.50

Weiler Engineering Engineering Designer 90.40 40 3,616.00

Weiler Engineering Clerical 62.74 0 0.00

Total 14,393.55

Subtask 7: Assistance During Bidding

Description: WEC will provide assistance with Contractor RFIs during the bidding process.

Deliverable: Answers to bidder’s questions will be provided to the FDEP Project Manager within 5 business days in PDF format.

Mr. Garland Sandel Gasparilla Island State Park Chapel Design

CN 803, TA

Fixed Price Cost:

Subtask 7 – Assistance During Bidding Firm Name Position Classi cation Hourly Rate Hours Total Fixed

Price Cost Weiler Engineering Senior Project Manager 160.83 6 964.98

Weiler Engineering Principal 319.24 0 0

Weiler Engineering Professional Engineer 168.20 4 672.80

Weiler Engineering Engineer Intern 115.45 8 923.60

Weiler Engineering Senior Engineering Designer 115.13 10 1,151.30

Weiler Engineering Engineering Designer 90.40 2 180.80

Weiler Engineering Clerical 62.74 1 62.74 Total 3,956.22

Subtask 8: Pre-Construction Meeting

Description: Consultant will either attend one pre-bid meeting on site to respond to questions and prepare minutes or assist with responses sent to Consultant via email.

Deliverable: Consultant will provide digital minutes of meeting and responses to contractor questions.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Fixed Price Cost:

Subtask 8 – Pre-Construction Meeting Firm Name Position Classification Hourly

Rate Hours Total

Fixed Price Cost

Weiler Engineering Senior Project Manager 160.83 8 1,286.64

Weiler Engineering Principal 319.24 0 0.00

Weiler Engineering Professional Engineer 168.20 0 0.00

Weiler Engineering Engineer Intern 115.45 8 923.60

Weiler Engineering Senior Engineering Designer 115.13 2 230.26

Weiler Engineering Engineering Designer 90.40 0 0.00

Weiler Engineering Clerical 62.74 1 62.74

Total $2,503.24

Mr. Garland Sandel Gasparilla Island State Park Chapel Design

CN 803, TA

Subtask 9: Building Department Comments

Description: Consultant will assist Client and Client’s Contractor with responding to any comments received from the Lee County Building Department.

Deliverable: Consultant will provide written responses to comments and provide any necessary plan changes in PDF format.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Fixed Price Cost:

Subtask 9 – Building Department Comments Firm Name Position Classification Hourly

Rate Hours Total

Fixed Price Cost

Weiler Engineering Senior Project Manager 160.83 6 964.98

Weiler Engineering Principal 319.24 0.25 79.81

Weiler Engineering Professional Engineer 168.20 6 1,009.20

Weiler Engineering Engineer Intern 115.45 8 923.60

Weiler Engineering Senior Engineering Designer

115.13 20 2,302.60

Weiler Engineering Engineering Designer 90.40 10 904.00

Weiler Engineering Clerical 62.74 1 62.74 Total $6,246.93

Subtask 10: Review Contractor Submittals

Description: WEC will review and comment on Contractor submittal package within 14 days of receipt.

Deliverable: Stamped acceptance of nal submittals in PDF digital form to FDEP Project Manager within 7 days of nal approvals.

Fixed Price Cost:

Subtask 10 - Review Submittals Firm Name Position Classi cation Hourly Rate Hours Total Fixed

Price Cost

Mr. Garland Sandel Gasparilla Island State Park Chapel Design

CN 803, TA

Weiler Engineering Senior Project Manager 160.83 8 1,286.64

Weiler Engineering Principal 319.24 0 0.00

Weiler Engineering Professional Engineer 168.20 6 1,009.20

Weiler Engineering Engineer Intern 115.45 8 923.60

Weiler Engineering Senior Engineering Designer 115.13 15 1,726.95

Weiler Engineering Engineering Designer 90.40 6 542.40

Weiler Engineering Clerical 62.74 2 125.48

Total $5,614.27

Subtask 11: Assistance During Construction

Description: WEC will respond to RFI's from Contractor within 7 days throughout the course of the construction phase.

Deliverable: WEC will provide copies of all RFI responses to FDEP Project Manager in PDF digital format.

Fixed Price Cost:

Subtask 11- Respond to RFI’s Firm Name Position Classi cation Hourly Rate Hours Total Fixed

Price Cost Weiler Engineering Senior Project Manager 160.83 8 1,286.64

Weiler Engineering Principal 319.24 0 0.00

Weiler Engineering Professional Engineer 168.20 8 1,345.00

Weiler Engineering Engineer Intern 115.45 12 1,385.40

Weiler Engineering Senior Engineering Designer 115.13 14 1,611.82

Weiler Engineering Engineering Designer 90.40 2 180.80

Weiler Engineering Clerical 62.74 1 62.74

Total $5,873.00

Subtask 12: Provide Construction Inspections (Month 1)

Description: WEC will provide a monthly inspection (NLT every 30 days) during construction.

Deliverable: WEC will provide two (2) original signed and sealed reports to the FDEP Project Manager, as well as a digital version in PDF format. The inspection report will be submitted within

Mr. Garland Sandel Gasparilla Island State Park Chapel Design

CN 803, TA

3 days of each inspection.

Fixed Price Cost:

Subtask 12 - Month 1 Inspection Firm Name Position Classi cation Hourly Rate Hours Total Fixed

Price Cost Weiler Engineering Senior Project Manager 160.83 2 321.66

Weiler Engineering Principal 319.24 0 0.00

Weiler Engineering Professional Engineer 168.20 0.5 84.10

Weiler Engineering Engineer Intern 115.45 4 461.80

Weiler Engineering Senior Engineering Designer 115.13 1 115.13

Weiler Engineering Engineering Designer 90.40 0 0.00

Weiler Engineering Construction Inspector 96.87 7 678.09

Weiler Engineering Clerical 62.74 0 0.00

Total $1,660.78

Subtask 13: Provide Construction Inspections (Month 2)

Description: WEC will provide a monthly inspection (NLT every 30 days) during construction.

Deliverable: WEC will provide two (2) original signed and sealed reports to the FDEP Project Manager, as well as a digital version in PDF format. The inspection report will be submitted within 3 days of each inspection.

Fixed Price Cost:

Subtask 13 - Month 2 Inspection Firm Name Position Classi cation Hourly Rate Hours Total Fixed

Price Cost Weiler Engineering Senior Project Manager 160.83 2 321.66

Weiler Engineering Principal 319.24 0 0.00

Weiler Engineering Professional Engineer 168.20 0.5 84.10

Weiler Engineering Engineer Intern 115.45 4 461.80

Weiler Engineering Senior Engineering Designer 115.13 1 115.13

Weiler Engineering Engineering Designer 90.40 0 0.00

Weiler Engineering Construction Inspector 96.87 7 678.09

Weiler Engineering Clerical 62.74 0 0.00

Mr. Garland Sandel Gasparilla Island State Park Chapel Design

CN 803, TA

Total $1,660.78

Subtask 14: Provide Construction Inspections (Month 3)

Description: WEC will provide a monthly inspection (NLT every 30 days) during construction.

Deliverable: WEC will provide two (2) original signed and sealed reports to the FDEP Project Manager, as well as a digital version in PDF format. The inspection report will be submitted within 3 days of each inspection.

Fixed Price Cost:

Subtask 14 - Month 3 Inspection Firm Name Position Classi cation Hourly Rate Hours Total Fixed

Price Cost Weiler Engineering Senior Project Manager 160.83 2 321.66

Weiler Engineering Principal 319.24 0 0.00

Weiler Engineering Professional Engineer 168.20 0.5 84.10

Weiler Engineering Engineer Intern 115.45 4 461.80

Weiler Engineering Senior Engineering Designer 115.13 1 115.13

Weiler Engineering Engineering Designer 90.40 0 0.00

Weiler Engineering Construction Inspector 96.87 7 678.09

Weiler Engineering Clerical 62.74 0 0.00

Total $1,660.78

Subtask 15: Provide Construction Inspections (Month 4)

Description: WEC will provide a monthly inspection (NLT every 30 days) during construction.

Deliverable: WEC will provide two (2) original signed and sealed reports to the FDEP Project Manager, as well as a digital version in PDF format. The inspection report will be submitted within 3 days of each inspection.

Fixed Price Cost:

Subtask 15 - Month 4 Inspection Firm Name Position Classi cation Hourly Rate Hours Total Fixed

Price Cost Weiler Engineering Senior Project Manager 160.83 2 321.66

Weiler Engineering Principal 319.24 0 0.00

Mr. Garland Sandel Gasparilla Island State Park Chapel Design

CN 803, TA

Weiler Engineering Professional Engineer 168.20 0.5 84.10

Weiler Engineering Engineer Intern 115.45 4 461.80

Weiler Engineering Senior Engineering Designer 115.13 1 115.13

Weiler Engineering Engineering Designer 90.40 0 0.00

Weiler Engineering Construction Inspector 96.87 7 678.09

Weiler Engineering Clerical 62.74 0 0.00

Total $1,660.78

Subtask 16: Provide Construction Inspections (Month 5)

Description: WEC will provide a monthly inspection (NLT every 30 days) during construction.

Deliverable: WEC will provide two (2) original signed and sealed reports to the FDEP Project Manager, as well as a digital version in PDF format. The inspection report will be submitted within 3 days of each inspection.

Fixed Price Cost:

Subtask 16 - Month 5 Inspection Firm Name Position Classi cation Hourly Rate Hours Total Fixed

Price Cost Weiler Engineering Senior Project Manager 160.83 2 321.66

Weiler Engineering Principal 319.24 0 0.00

Weiler Engineering Professional Engineer 168.20 0.5 84.10

Weiler Engineering Engineer Intern 115.45 4 461.80

Weiler Engineering Senior Engineering Designer 115.13 1 115.13

Weiler Engineering Engineering Designer 90.40 0 0.00

Weiler Engineering Construction Inspector 96.87 7 678.09

Weiler Engineering Clerical 62.74 0 0.00

Total $1,660.78

Subtask 17: Provide Construction Inspections (Month 6)

Description: WEC will provide a monthly inspection (NLT every 30 days) during construction.

Deliverable: WEC will provide two (2) original signed and sealed reports to the FDEP Project Manager, as well as a digital version in PDF format. The inspection report will be submitted within 3 days of each inspection.

Mr. Garland Sandel Gasparilla Island State Park Chapel Design

CN 803, TA

Fixed Price Cost:

Subtask 17 - Month 6 Inspection Firm Name Position Classi cation Hourly Rate Hours Total Fixed

Price Cost Weiler Engineering Senior Project Manager 160.83 2 321.66

Weiler Engineering Principal 319.24 0 0.00

Weiler Engineering Professional Engineer 168.20 0.5 84.10

Weiler Engineering Engineer Intern 115.45 4 461.80

Weiler Engineering Senior Engineering Designer 115.13 1 115.13

Weiler Engineering Engineering Designer 90.40 0 0.00

Weiler Engineering Construction Inspector 96.87 7 678.09

Weiler Engineering Clerical 62.74 0 0.00

Total $1,660.78

Subtask 18: Provide Construction Inspections (Month 7)

Description: WEC will provide a monthly inspection (NLT every 30 days) during construction.

Deliverable: WEC will provide two (2) original signed and sealed reports to the FDEP Project Manager, as well as a digital version in PDF format. The inspection report will be submitted within 3 days of each inspection.

Fixed Price Cost:

Subtask 18 - Month 7 Inspection Firm Name Position Classi cation Hourly Rate Hours Total Fixed

Price Cost Weiler Engineering Senior Project Manager 160.83 2 321.66

Weiler Engineering Principal 319.24 0 0.00

Weiler Engineering Professional Engineer 168.20 0.5 84.10

Weiler Engineering Engineer Intern 115.45 4 461.80

Weiler Engineering Senior Engineering Designer 115.13 1 115.13

Weiler Engineering Engineering Designer 90.40 0 0.00

Weiler Engineering Construction Inspector 96.87 7 678.09

Weiler Engineering Clerical 62.74 0 0.00

Total $1,660.78

Mr. Garland Sandel Gasparilla Island State Park Chapel Design

CN 803, TA

Subtask 19: Provide Construction Inspections (Month 8)

Description: WEC will provide a monthly inspection (NLT every 30 days) during construction.

Deliverable: WEC will provide two (2) original signed and sealed reports to the FDEP Project Manager, as well as a digital version in PDF format. The inspection report will be submitted within 3 days of each inspection.

Fixed Price Cost:

Subtask 19 - Month 8 Inspection Firm Name Position Classi cation Hourly Rate Hours Total Fixed

Price Cost Weiler Engineering Senior Project Manager 160.83 2 321.66

Weiler Engineering Principal 319.24 0 0.00

Weiler Engineering Professional Engineer 168.20 0.5 84.10

Weiler Engineering Engineer Intern 115.45 4 461.80

Weiler Engineering Senior Engineering Designer 115.13 1 115.13

Weiler Engineering Engineering Designer 90.40 0 0.00

Weiler Engineering Construction Inspector 96.87 7 678.09

Weiler Engineering Clerical 62.74 0 0.00

Total $1,660.78

Subtask 20: Substantial Completion Inspection

Description: WEC will assist Client with the Substantial Completion inspection and punchlist, with WEC representative attending the Substantial Completion inspection and providing engineer input related to the punchlist.

Deliverable: WEC will provide comments and input on punchlist within one (1) day of Substantial Completion inspection in PDF via email.

Fixed Price Cost:

Subtask 20 – Substantial Completion Inspection Firm Name Position Classi cation Hourly Rate Hours Total Fixed

Price Cost Weiler Engineering Senior Project Manager 160.83 4 643.32

Weiler Engineering Principal 319.24 0 0.00

Weiler Engineering Professional Engineer 168.20 0.5 84.10

Mr. Garland Sandel Gasparilla Island State Park Chapel Design

CN 803, TA

Weiler Engineering Engineer Intern 115.45 6 692.70

Weiler Engineering Senior Engineering Designer 115.13 6 690.78

Weiler Engineering Engineering Designer 90.40 0 0.00

Weiler Engineering Construction Inspector 96.87 12 1,162.44

Weiler Engineering Clerical 62.74 0 0.00

Total $3,273.34

Subtask 21: Final Completion Inspection

Description: WEC will assist Client with the Final Completion inspection, with WEC representative attending the Final Completion inspection and prepare the necessary record information based on WEC inspections and as-builts by contractor’s surveyor.

Deliverable: WEC will provide completed record drawings and certi cations to FDEP Project Manager in PDF via email.

Fixed Price Cost:

Subtask 21 – Final Completion Inspection Firm Name Position Classi cation Hourly Rate Hours Total Fixed

Price Cost Weiler Engineering Senior Project Manager 160.83 4 643.32

Weiler Engineering Principal 319.24 0 0.00

Weiler Engineering Professional Engineer 168.20 0.5 84.10

Weiler Engineering Engineer Intern 115.45 4 461.80

Weiler Engineering Senior Engineering Designer 115.13 6 690.78

Weiler Engineering Engineering Designer 90.40 0 0.00

Weiler Engineering Construction Inspector 96.87 7 678.09

Weiler Engineering Clerical 62.74 0 0.00

Total $2,558.09

Project Schedule:

Activity Duration (Calendar Days) Days from Execution Subtask 1: Pre-Application Meetings

60 60

Subtask 2: CRAS 60 60

Mr. Garland Sandel Gasparilla Island State Park Chapel Design

CN 803, TA

Subtask 3A: 30% Design 60 120 Subtask 3B: Survey 60 60 Subtask 3C: Lead/Asbestos Testing

60 60

Subtask 4: 60% Plans 60 – includes 14 days for Client review

Subtask 5A: Permit Applications

60 – includes 14 days for Client review

Subtask 5B: Permit Approvals 90 – includes response for additional information

Subtask 6: 100% Plans 45 - includes 14 days for Client review

Subtask 7: Assistance During Bidding

TBD TBD

Subtask 8: Pre-Construction Meeting

TBD TBD

Subtask 9: Building Department Comments

TBD TBD

Subtask 10: Submittal Review TBD TBD

Subtask 11: Assistance During Construction

TBD TBD

Subtask 12: Month 1 Inspection

TBD TBD

Subtask 13: Month 2 Inspection

TBD TBD

Subtask 14: Month 3 Inspection

TBD TBD

Subtask 15: Month 4 Inspection

TBD TBD

Subtask 16: Month 5 Inspection

TBD TBD

Subtask 17: Month 6 Inspection

TBD TBD

Subtask 18: Month 7 Inspection

TBD TBD

Subtask 19: Month 8 Inspection

TBD TBD

Subtask 20: Substantial Completion

TBD TBD

Subtask 21: Final Completion TBD TBD

Mr. Garland Sandel Gasparilla Island State Park Chapel Design

CN 803, TA

Summary of Fees:

Subtask Subtask Fixed Price Cost Subtask Reimbursable Subtask 1: Pre-Application Meetings

$4,299.05 $0.00

Subtask 2: CRAS $8,878.02 $0.00 Subtask 3A: 30% Design $16,806.68 $0.00 Subtask 3B: Survey $2,117.75 $0.00 Subtask 3C: Lead/Asbestos Testing

$8,352.30 $0.00

Subtask 4: 60% Plans $17,895.01 $0.00 Subtask 5A: Permit Applications

$20,109.71 $6,500.00

Subtask 5B: Permit Approvals $3,418.63 $0.00 Subtask 6: 100% Plans $14,393.55 $0.00

Sub-Totals Design and Permitting

$96,270.70 $6,500.00

Subtask 7: Assistance During Bidding

$3,956.22 $0.00

Subtask 8: Pre-Construction Meeting

$2,503.24 $0.00

Subtask 9: Building Department Comments

$6,246.93 $0.00

Subtask 10: Submittal Review $5,614.27 $0.00 Subtask 11: Assistance During Construction

$5,873.00 $0.00

Subtask 12: Month 1 Inspection

$1,660.78 $0.00

Subtask 13: Month 2 Inspection

$1,660.78 $0.00

Subtask 14: Month 3 Inspection

$1,660.78 $0.00

Subtask 15: Month 4 Inspection

$1,660.78 $0.00

Mr. Garland Sandel Gasparilla Island State Park Chapel Design

CN 803, TA

Subtask 16: Month 5 Inspection

$1,660.78 $0.00

Subtask 17: Month 6 Inspection

$1,660.78 $0.00

Subtask 18: Month 7 Inspection

$1,660.78 $0.00

Subtask 19: Month 8 Inspection

$1,660.78 $0.00

Subtask 20: Substantial Completion

$3,273.34 $0.00

Subtask 21: Final Completion $2,558.09 $0.00

Sub-Total during construction $43,311.33 $0.00

Overall Total Cost:

$146,082.03

Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified. (Please do not alter this language)