CN-370000-CN803-T1.pdf

PDF 933 KB Posted

Attached to
Master Agreement FL|CN803|e94021f7c01ffff2157f4f8cc3027b61
Contract number
CN803
Issued by
Florida

About this file

Consultant's Task Assignment Notification Summary

This is a Consultant's Task Assignment Notification (Form DRP-084) issued by the Florida Department of Environmental Protection (FDEP), Division of Recreation and Parks. The document establishes Task Assignment 1 (TA1) under FDEP Contract No. CN803 for the Gasparilla Island State Park Road Paving project located in Lee County, Florida. The consultant is Weiler Engineering Corporation, represented by Robin Palmer, with FDEP Contract Manager Vu Nguyen and Project Manager Meenakshi Senthilkumar overseeing the work. The task assignment represents the continuation and consolidation of incomplete subtasks previously initiated under Contract CN230, Task Assignment 89, with added construction administration services as outlined in the proposal dated March 12, 2025.

The contract encompasses comprehensive design, permitting, and construction administration services for paving the state park's access road and parking lots, including entry/exit realignment at Belcher Road, utility reconfiguration, stormwater management system design, and site grading. The total task amount is $118,739.13, consisting of a fixed price cost of $112,739.13 and cost reimbursement (not to exceed) of $6,000.00 for permit application fees. The fixed price is allocated across eight primary subtasks: concept planning ($5,823.75), 30% preliminary design ($17,838.75), survey ($9,946.09), geotechnical report ($7,819.29), 60% design plans ($17,478.75), 100% design plans ($14,232.50), permitting ($22,480.00), and construction phase services ($17,120.00). The work is scheduled to commence upon execution and conclude by December 31, 2026. Payment will be made upon FDEP approval of deliverables for each subtask, with funding encumbered against Project 61509C, Grant 37504003191, Organization Code 37504003191, under Category 080039/23, Fund 423001, Module U3200, Object 131500, with an EO designation of QK.

View the file

Other files

File Type Posted
CN-370000-CN803-T10.pdf.crdownload CRDOWNLOAD file
CN-370000-CN803-T11.pdf PDF
CN-370000-CN803-T13.pdf PDF
CN-370000-CN803-T2.pdf PDF
CN-370000-CN803-T22.pdf PDF
CN-370000-CN803-T23.pdf PDF
CN-370000-CN803-T25.pdf PDF
CN-370000-CN803-T26.pdf PDF
CN-370000-CN803-T4.pdf PDF
CN-370000-CN803.pdf PDF
CN-370000-CN803.pdf.crdownload CRDOWNLOAD file
CN-370000-CN803-T10.pdf PDF
CN-370000-CN803-T10CO1.pdf PDF
CN-370000-CN803-T14.pdf PDF
CN-370000-CN803-T16.pdf PDF
CN-370000-CN803-T19.pdf PDF
CN-370000-CN803-T3.pdf PDF
CN-370000-CN803-CMC1.pdf PDF
CN-370000-CN803-T12.pdf PDF
CN-370000-CN803-T15.pdf PDF
CN-370000-CN803-T18.pdf PDF
CN-370000-CN803-T20.pdf PDF
CN-370000-CN803-T21.pdf PDF
CN-370000-CN803-T24.pdf PDF
CN-370000-CN803-T2CO1.pdf PDF
CN-370000-CN803-T30.pdf PDF
CN-370000-CN803-T6.pdf PDF
CN-370000-CN803-T6CO1.pdf PDF
CN-370000-CN803-T9.pdf PDF
CN-370000-CN803-T17.pdf PDF
CN-370000-CN803-T5.pdf PDF
CN-370000-CN803-T7.pdf PDF
CN-370000-CN803-T8.pdf PDF
CN-370000-CN803-T8CO1.pdf PDF
Show all 34

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DDivision oof RRecreation aand PParks

CConsultant’s TTask AAssignment NNotification

FFLORIDA DEPARTMENT OF

EENVIRONMENTAL PPROTECTION

DRP-084

Rev. 0 /2025 of 2

FDEP Contract No: Project Number: Task Assignment No:

Project Location Project

Consultant’s Name:

Consultant’s Representative:

Phone: Email:

FDEP Contract Manager:

Phone: Email:

Task Description:

Project Manager:

Schedule:

Start Date: Completion Date:

Fixed Price Cost: Cost Reimbursement (Not to Exceed):

Total Task Amount:

Signatures and Date:

1.

Budget Representative, FDEP Signature Date

2.

Project Manager, FDEP Signature Date

3.

Signature Date

4.

Signature Date

5.

Contract Authority, FDEP Signature Date

CN803 61509C TA1

Gasparilla Island State Park Road Paving

Weiler Engineering Corporation Robin Palmer

(941) 646-8612 rpalmer@weilerengineering.org

Vu Nguyen

(850) 245-2630 Vu.Nguyen@FloridaDEP.gov

Moving incomplete subtasks (1,2,3,4) from CN230 TA89 and adding CA services, per proposal dated 03/12/25. Subtasks utilizing rates per CN230 are indicated with an asterisk (*) in the subtask heading.

Meenakshi Senthilkumar or successor

Upon Execution 12/31/2026

$112,739.13 $6,000.00 $118,739.13

Tamika Bass

Meenakshi Senthilkumar

Michael Giardullo, P.E.

Vu Nguyen

Tim Giesecke

Tamika Bass Digitally signed by Tamika Bass Date: 2025.04.10 09:39:52 -04'00'

Meenakshi Senthilkumar Digitally signed by Meenakshi Senthilkumar Date: 2025.04.10 13:48:50 -04'00'

Michael J. Giardullo Digitally signed by Michael J. Giardullo Date: 2025.04.11 09:17:50 -04'00'

Vu Nguyen Digitally signed by Vu Nguyen Date: 2025.04.14 09:22:03 -04'00'

Tim Giesecke Digitally signed by Tim Giesecke Date: 2025.04.16 11:12:27 -04'00'

DDivision oof RRecreation aand PParks

CConsultant’s TTask AAssignment NNotification

FFLORIDA DEPARTMENT OF

EENVIRONMENTAL PPROTECTION

DRP-084

Rev. /2025 2 of 2

Encumbrance Information:

Project # Grant # Organization Code Category/Yr Fund Module Object EO Amount

Total:

61509C 37504003191 080039/23 423001 U3200 131500 QK $118,739.13

$118,739.13

March 12, 2025

Ms. Meen Senthil Design Project Manager Bureau of Design and Construction Florida Department of Environmental Protection 3900 Commonwealth Boulevard 260-L, MS 520 Tallahassee, FL 32399

RE: Gasparilla Island State Park – Road Paving, CN - 803, TA - 01

Dear Ms. Senthil, Thank you for the opportunity to provide this proposal to prepare the plans and documentation necessary to relocate the state park’s access and reconfigure the parking lots within the boundary of the park.

PUNTA GORDA OFFICE: 201 WEST MARION AVENUE - SUITE 1306 | PUNTA GORDA | FL 33950 | TEL 941-505 -1700 | FAX 941-505 -1702 MARATHON OFFICE: 6805 OVERSEAS HIGHWAY | MARATHON | FL 33050 | TEL 305 -289-4161 | FAX 305 -289- 416 2 WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG

Ms. Meena Senthil Gasparilla Island State Park Road Paving

CN 803 / TA 01

Our services will include:

Design, permitting, and construction administration services to pave the state park's access and parking lots and provide the design of a stormwater management system. This includes the re-alignment of the park's entry / exit at Belcher Rd, main driveway, utilities reconfiguration, and paving of main parking lot and South parking lot

For your review, the Weiler Engineering Corporation, has provided a proposal summary and man-hour documentation for the tasks identified below:

Please review the attached Proposal Summary and deliverables.

Sincerely, Michael J. Giardullo, P.E.

Director of Civil Engineering The Weiler Engineering Corporation- An Apex Company

Ms. Meena Senthil Gasparilla Island State Park

Gasparilla Island State Park

Contract Number 803, Task Assignment Number 01

Subtask 1: 30% Preliminary Design

1) A – Concept Planning

a) Consultant will prepare (2) Concept Plans showing the parking lot layout options.

1) B – 30% Preliminary Design

a) WEC will conduct one site visit.

b) Consultant will conduct a pre-application meeting with the Water Management District, FDEP

CCCL, and Lee County. No USACE permitting is anticipated for this project.

c) Consultant will prepare Preliminary Design Plans.

1) C – Surveys

a) Consultant will coordinate with Survey Sub-Consultant to prepare a special Purpose Survey with topographic information for the project area.

1) D –Geotechnical Reports

a) Consultant will coordinate with Geotechnical Sub-Consultant to prepare a geotechnical Report recommending piling depths

Deliverable:

1) A – Concept Planning

Consultant shall deliver (2) concept site plans to the client via digital PDF. Plans will include:

Site Plan 1: Parking Layout with Park Entrance Remaining the Same (if FDEP to acquire neighboring parcel) Site Plan 2: Parking Layout with Park Entrance Relocated onto State Lands

1) B – 30% Preliminary Design

Meeting minutes from the site visit and all permitting pre-application meeting minutes will be provided in PDF format. For the 30% Design Plans, Consultant shall deliver 30% design plans to the client via digital PDF. Plans will include:

Cover sheet Existing Conditions Site Plan Opinion of Probable Cost

1) C - Survey

Completed Survey – Sixty days from execution of Task Assignment, consultant shall deliver a Special Purpose Survey via digital PDF, and CAD.

Ms. Meena Senthil Gasparilla Island State Park

1) D –Geotechnical Report

Geotechnical Report – Sixty days from execution of task assignment, consultant shall deliver a completed geotechnical Report with (2) Standard Penetration Test (SPT) borings and (60 hand auger borings to a depth of 6ft within the area to be paved. Deliverable shall be via digital PDF.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Fixed Price Cost:

Subtask 1A: Concept

Firm Name Position Classification Hourly Rate Hours Total Fixed Price

Cost

Weiler Engineering Project Manager 145 8 1160.00

Weiler Engineering Principal in Charge 195 .25 48.75

Weiler Engineering

Registered Professional Engineer 145 3 435.00

Weiler Engineering Registered Engineer Intern 115 15 1725.00

Weiler Engineering Senior Engineering Designer 100 20 2000.00

Weiler Engineering Engineering Technician 80 5 400.00

Weiler Engineering Clerical 55 1 55.00

Total: Concept Design

5,823.75

Ms. Meena Senthil Gasparilla Island State Park

Subtask 1B: 30% Preliminary Design

Rate Hours Total Fixed Price

Cost

Weiler Engineering Project Manager 145 14 2030.00

Weiler Engineering Principal in Charge 195 .25 48.75

Weiler Engineering

Registered Professional Engineer 145 26 3770.00

Weiler Engineering Registered Engineer Intern 115 32 3680.00

Weiler Engineering Senior Engineering Designer 100 50 5000.00

Weiler Engineering Engineering Technician 80 40 3200.00

Weiler Engineering Clerical 55 2 110.00

Total: 30% Preliminary Design

17,838.75

Subtask 1C: Survey

Firm Name Position Classification Unit Unit Rate Number Units

Total Fixed Price Cost

Weiler Engineering Project Manager Hr 145 9 1305.00

CHW 3 Person Field Crew Hr 177.54 26 4616.04

CHW Project Surveyor Hr 74.75 23 1719.25

CHW Senior CAD/GIS Hr 103.13 16 1650.08

CHW Professional Surveyor & Mapper

Hr 163.93 4 655.72

Total: Survey 9,946.09

Ms. Meena Senthil Gasparilla Island State Park

Subtask 1D: Geotechnical Report

Firm Name Position Classification Unit Unit Rate Number Units

Total Fixed Price Cost

Weiler Engineering Project Manager Hr 145 7 1015.00

Geotech Tierra

Tierra Senior Engineer Hr 178.60 12 2143.20

Tierra Senior Project Engineer Hr 146.53 16 2344.48

Tierra Geotechnical Technician Hr 68.45 25 1711.25

Tierra Clerical Hr 75.67 8 605.36 Total: Geotech 7,819.29

Reimbursable Cost: (if applicable)

Description Number @ Total

Postage Not Anticipated

Printing Not

Overnight Travel (if applicable)

Not

Mileage (@ $0.445 per mile)

0.445 0

Reimbursable Total Cost 1

Total Subtask 1 41,427.88

Ms. Meena Senthil Gasparilla Island State Park

Subtask 2: 60% Design Plans

Subtask 2: 60% Design Plans Description: Plans completed to 60% incorporating comments from 30%.

Deliverable: Plans consultant shall deliver 60% Plans (digital PDF only) including:

Opinion of Probable Cost Cover sheet Survey Existing Conditions Best Management Plan Demolition Plan Site & Grading Plan Site Details and General Notes

Rate Hours Total Fixed

Price Cost

Weiler Engineering Project Manager 145 14 2030.00

Weiler Engineering Principal in Charge 195 0.25 48.75

Weiler Engineering

Registered Professional Engineer 145 30 4350.00

Weiler Engineering Registered Engineer Intern 115 30 3450.00

Weiler Engineering Senior Engineering Designer 100 45 4500.00

Weiler Engineering Engineering Technician 80 36 2880.00

Weiler Engineering Clerical 55 4 220.00

Total: 60% Design Plans 17478.75

Total for Subtask 2

17,478.75

Ms. Meena Senthil Gasparilla Island State Park

Subtask 3: 100% Design Plans

Description: Plans completed to 100%.

Deliverable: Incorporate Client review of 60% plans, Consultant shall deliver two sets of 100% signed and sealed plans, digital 1-PDF and 1-CAD including:

Updated Opinion of Probable Cost Cover sheet Survey Existing Conditions Best Management Plan Demolition Plan Site & Grading Plan Site Details and General Notes

Subtask 3: 100% Design Plans

Rate Hours Total Fixed

Price Cost

Weiler Engineering Project Manager 145 14 2030.00

Weiler Engineering Principal in Charge 195 .5 97.50

Weiler Engineering

Registered Professional Engineer 145 22 3190.00

Weiler Engineering Registered Engineer Intern 115 26 2990.00

Weiler Engineering Senior Engineering Designer 100 32 3200.00

Weiler Engineering Engineering Technician 80 32 2560.00

Weiler Engineering Clerical 55 3 165.00

Total: 100% Design Plans 14,232.50

Ms. Meena Senthil Gasparilla Island State Park

Reimbursable Cost:

Postage Not anticipated

35 0

Printing Not anticipated

2.30 0

Overnight Travel (if applicable)

Reimbursable Total Cost

Total for Subtask 3

14,232.50

Subtask 4: Permitting

Description:

4) A – Permit Applications

Consultant will assist Client to submit permit applications for Local and State approvals. WEC will complete applications for the Water Management District for an Individual or General Permit, the FDEP for a CCCL Permit, and coordinate with the Lee County on a Limited Development Order.

4) B – Permit Approvals

Consultant will coordinate with agencies and respond to agencies for additional information.

Depending on the agencies, the anticipated timeline for approval is 90 days after submittal.

Consultant will respond to agency requests for additional information and copy Client on all responses. Upon approval, Consultant will provide Client with approvals and revised (if necessary) plans and documentation. Permit approvals will include: FDEP CCCL and SWFWMD ERP/General Permit, and Lee County LDO.

Deliverable:

4) A – Permit Applications

Incorporate Client review comments from 60% plans and deliver a digital set of the permit applications for signature. Deliverable will be in PDF format.

4) B – Permit Approvals

Approvals will be obtained from SWFWMD (Individual or General Permit), FDEP CCCL Permit, and Lee County LDO. Deliverable will be in PDF format.

Ms. Meena Senthil Gasparilla Island State Park

Subtask 4A:

Permit Applications

Rate Hours Total Fixed

Price Cost

Weiler Engineering Project Manager 145 14 2030.00

Weiler Engineering Principal in Charge 195 .25 48.75

Weiler Engineering Registered Professional Engineer 145 28 4060.00

Weiler Engineering Registered Engineer Intern 115 60 6900.00

Weiler Engineering Senior Engineering Designer 100 32 3200.00

Weiler Engineering Engineering Technician 80 36 2880.00

Weiler Engineering Clerical 55 1 55.00

Total: Permit Applications 19,173.75

Subtask 4B Permit Approvals

Rate Hours Total Fixed

Price Cost

Weiler Engineering Project Manager 145 2 290.00

Weiler Engineering Principal in Charge 195 .25 48.75

Weiler Engineering Registered Professional Engineer 145 4 580.00

Weiler Engineering Registered Engineer Intern 115 8 920.00

Weiler Engineering Senior Engineering Designer 100 8 800.00

Weiler Engineering Engineering Technician 80 8 640.00

Weiler Engineering Clerical 55 0.5 27.50

Total: Permit Approvals 3,306.25

Ms. Meena Senthil Gasparilla Island State Park

Postage Not anticipated 35 0

Printing Not anticipated 2.3 0

SFWMD

Application Fees

1 3500 3500.00

Lee County

LDO

1 2500 2500.00

Reimbursable Total Cost for 4A

6000.00

Total for Subtask 4

28,480.00

Subtask 5A – 5H: Construction Phase Services

Subtask 5A: Assistance during bidding

Description: Consultant will respond to bidders’ questions and provide clarifications during bidding.

Deliverable: Consultant will provide digital pdf of all responses and communication with bidders.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Firm Name Position Classification Hourly Rate Hours Total Fixed Price

Cost

Weiler Engineering Project Manager 145 6 870

Weiler Engineering Principal in Charge 195 0 0

Weiler Engineering Registered Professional Engineer

145 0 0

Weiler Engineering Registered Engineer Intern 115 8 920

Weiler Engineering Senior Engineering Designer 100 0 0

Weiler Engineering Engineering Technician 80 0 0

Weiler Engineering Clerical 55 0 0 Total: Attend Pre-Construction

Meeting

Ms. Meena Senthil Gasparilla Island State Park

Postage 0

Printing 2.3 0

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile)

Reimbursable Total Cost 0

Total Subtask 5A 1790

Subtask 5B: Attend Pre-Construction Meeting

Description: WEC will provide representation at the Pre-Construction Meeting.

Deliverable: Meeting notes within 2 days from meeting date for inclusion by FDEP Project Manager in Meeting Minutes.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Firm Name Position Classification Hourly Rate Hours Total Fixed Price

Cost

Weiler Engineering Project Manager 145 8 1160

Weiler Engineering Principal in Charge 195 0 0

Weiler Engineering Registered Professional Engineer

145 0 0

Weiler Engineering Registered Engineer Intern 115 8 920

Weiler Engineering Senior Engineering Designer 100 0 0

Weiler Engineering Engineering Technician 80 0 0

Weiler Engineering Clerical 55 0 0 Total: Attend Pre-Construction

Meeting

Ms. Meena Senthil Gasparilla Island State Park

Printing 2.3 0

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile)

Total Subtask 5B 2080

Subtask 5C: Review Contractor submittals

Description: WEC will review and comment on Contractor submittal package within 14 days of receipt.

Deliverable: Stamped acceptance of final submittals in PDF digital form to FDEP Project Manager within 7 days of final approvals.

accurate, and timely. (Please do not alter this language)

Subtask 5C: Review Submittals

Cost

Weiler Engineering Project Manager 145 2 290

Weiler Engineering Principal in Charge 195 0 0

Weiler Engineering Registered Professional Engineer

145 0 0

Weiler Engineering Registered Engineer Intern 115 8 920

Weiler Engineering Senior Engineering Designer 100 12 1200

Weiler Engineering Engineering Technician 80 2 160

Weiler Engineering Clerical 55 2 110 Total Review Submittals 2680

Ms. Meena Senthil Gasparilla Island State Park

Postage Not Anticipated 35 0

Printing 0

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile)

Reimbursable Total Cost

Total Subtask 5C 2680.00

Subtask 5D: Respond to Building Department Comments

Description: WEC will assist Client and/or Client's Contractor in responding to comments from the Building Department within 7 days, and revise plans accordingly within 14 days of receipt of comments.

Specifically, when WEC's involvement is required for RFI responses, WEC will prepare a draft and send to FDEP Project Manager for review and comment. WEC will then discuss and/or revise accordingly prior to formal submittal of RFI response to Building Department.

Deliverable: RFI response documents submitted to Building Department within 7 days (14 days for plan revisions) in PDF format.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, Subtask 5D: Respond to Building Department Comments

Cost

Weiler Engineering Project Manager 145 2 290

Weiler Engineering Principal in Charge 195 0 0

Weiler Engineering Registered Professional Engineer

145 1 145

Weiler Engineering Registered Engineer Intern 115 6 690

Weiler Engineering Senior Engineering Designer 100 8 800

Weiler Engineering Engineering Technician 80 0 0

Weiler Engineering Clerical 55 1 55 Total 1980

Ms. Meena Senthil Gasparilla Island State Park

Postage 35 0

Printing 2.30 0.00

Overnight Travel

(if applicable)

Not anticipated

Mileage (@ $0.445 per mile)

Not anticipated

Reimbursable Total Cost

Total: 5D 1980

Subtask 5E: Respond to Contractor RFI's

Description: WEC will respond to RFI's from Contractor within 7 days throughout the course of the construction phase. If any plan changes are required, these changes will be completed within 14 days.

Deliverable: WEC will provide copies of all RFI responses to FDEP Project Manager in PDF digital format within 7 days.

Subtask 5E: Respond to RFI’s

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 2 290

Weiler Engineering Principal in Charge 195 0 0

Weiler Engineering Registered Professional Engineer

145 2 290

Weiler Engineering Registered Engineer Intern 115 8 920

Weiler Engineering Senior Engineering Designer 100 8 800

Weiler Engineering Engineering Technician 80 0 0

Weiler Engineering Clerical 55 4 220 Total Respond to RFI’s 2520

Ms. Meena Senthil Gasparilla Island State Park

Printing 0

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile)

Total Subtask 5E 2520

Subtask 5F: Interim Site Inspection # 1

Description: WEC will provide an interim inspection during construction upon request from BDC.

Deliverable: WEC will provide a site visit report to the FDEP Project Manager in PDF format. The inspection report will be submitted within 3 days of the site visit.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, Subtask 5F – Interim Site Inspection #1

Cost

Weiler Engineering Project Manager 145 1 145.00

Weiler Engineering Principal in Charge 195 0 0.00

Weiler Engineering Registered Professional Engineer

145 .5 72.50

Weiler Engineering Registered Engineer Intern 115 10 1150.00

Weiler Engineering Senior Engineering Designer 100 1 100.00

Weiler Engineering Engineering Technician 80 0 0.00

Weiler Engineering Clerical 55 0 0.00 Total Interim Site Inspection #1 1467.50

Ms. Meena Senthil Gasparilla Island State Park

Postage 35 0

Printing 0

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile)

Reimbursable Total Cost

Total Subtask 5F 1467.50

Subtask 5G: Interim Site Inspection #2

Description: WEC will provide an interim inspection during construction upon request from BDC.

Deliverable: WEC will provide a site visit report to the FDEP Project Manager in PDF format. The inspection report will be submitted within 3 days of the site visit.

Subtask 5G: Interim Site Inspection #2

Cost

Weiler Engineering Project Manager 145 1 145.00

Weiler Engineering Principal in Charge 195 0 0.00

Weiler Engineering Registered Professional Engineer

145 .5 72.50

Weiler Engineering Registered Engineer Intern 115 10 1150.00

Weiler Engineering Senior Engineering Designer 100 1 100.00

Weiler Engineering Engineering Technician 80 0 0.00

Total 1467.50

Ms. Meena Senthil Gasparilla Island State Park

Postage 0 35 0

Printing 0

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile)

0.445 0

Reimbursable Total Cost

Total Subtask 5G 1467.50

Subtask 5H: Substantial Completion w/ Certification

Description: WEC will assist Client with the Substantial Completion inspection, with WEC representative attending the Substantial Completion inspection with punchlist.

Deliverable: WEC will also provide complete the substantial completion certification form required by FDEP Project Manager.

Subtask 5H: Substantial Completion

Cost

Weiler Engineering Project Manager 145 3 435.00

Weiler Engineering Principal in Charge 195 0 0.00

Weiler Engineering Registered Professional Engineer

145 2 290.00

Weiler Engineering Registered Engineer Intern 115 14 1610.00

Weiler Engineering Senior Engineering Designer 100 8 800.00

Weiler Engineering Engineering Technician 80 0 0.00

Total 3135.00

Ms. Meena Senthil Gasparilla Island State Park

Postage 0 35 0

Printing 0

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile)

Reimbursable Total Cost

Total Subtask 5H 3135.00

Project Schedule:

Activity Duration (Calendar Days) Days from Execution

Subtask 1A: Concept Plan 30 30

Subtask 1B: 30% Preliminary Design

60 60

Subtask 1C: Survey 60 60

Subtask 1D: Geotechnical Report 60 60

Subtask 2: 60% Design 30 - includes 7 days for Client review

Subtask 3: 100% Design 30 – includes 7 days for Client review

Subtask 4A: Permit Applications 30 – includes 7 days for Client review

Subtask 4B: Permit Approvals 60 – includes response for additional information

Subtask 5A: Assistance During Bidding

TBD TBD

Subtask 5B: Pre-Construction TBD TBD

Subtask 5C: Review Submittals TBD TBD

Subtask 5D: Respond to RAI's TBD TBD

Subtask 5E: Respond to Contractor RFI's

TBD TBD

Subtask 5F: Interim Site Inspection #1

TBD TBD

Ms. Meena Senthil Gasparilla Island State Park

Subtask 5G: Interim Site Inspection #2

TBD TBD

Subtask 5H: Substantial Completion Walk-Through w/ Punchlist

TBD TBD

Summary of Fees:

Subtask Subtask Fixed Price Cost Subtask Reimbursable

Subtask 1A: Concept Plans $5823.75 $0.00

Subtask 1B: 30% Preliminary Design

$17838.75 $0.00

Subtask 1C: Survey $9946.09 $0.00

Subtask 1D: Geotech $7819.29 $0.00

Subtask 2: 60% Design $17478.75 $0.00

Subtask 3: 100% Design $14232.50 $0.00

Subtask 4A: Permit Applications $19173.75 $6000.00

Subtask 4B: Permit Approvals $3306.25 $0.00

Total Design & Permitting $95,619.13 $6,000.00

Subtask 5A: Assistance during Bidding

$1790.00 $0.00

Subtask 5B: Pre-Construction Meeting

$2080.00 $0.00

Subtask 5C: Submittal Review $2680.00 $0.00

Subtask 5D: Regulatory Response

$1980.00 $0.00

Subtask 5E: Assistance during construction

$2520.00 $0.00

Subtask 5F: Interim Site Inspection #1

$1467.50 $0.00

Subtask 5G: Interim Site Inspection #2

$1467.50 $0.00

Subtask 5H: Substantial Completion

$3135.00 $0.00

Total during Construction 17,120.00 $0.00

Total Fixed Price Cost: $112,739.13

Total Fixed Price Cost: $6000.00

Overall Total Cost: $118,739.13

Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified. (Please do not alter this language)

File details come from the government source that posted it. Updated .