This is a Consultant's Task Assignment Notification (Form DRP-084) issued by the Florida Department of Environmental Protection (FDEP), Division of Recreation and Parks, assigning Task 12 under FDEP Contract CN803 to Weiler Engineering Corporation. The task pertains to the Yulee Sugar Mill Ruins Historic State Park Historic Ruins Preservation project located in Yulee, Florida. Robin Palmer, P.E., serves as the consultant's representative, with Vu Nguyen as the FDEP Contract Manager and Richard Marcil as the project manager. All required parties executed the notification on or before June 24, 2025.
The task encompasses the transfer of design, permitting, and construction administration services from the previous CN230 TA84 contract. The work includes 60% and 100% structural restoration plans for the Sugar Mill's components (Kettle Train, Boiler, Rolling Press, and Well), with a combined design cost of $25,147.50. Construction phase services—including bidding assistance, pre-construction meeting attendance, contractor submittal review, regulatory permitting support, RFI responses, site inspections, and substantial and final completion certifications—total $18,228.75. The overall fixed-price contract amount is $43,376.25 with no cost reimbursement provisions. The task is effective upon execution with a completion date of June 1, 2026. Payment will be made upon FDEP approval of deliverables for each subtask. Encumbrance information indicates funding from Grant 37502000017, Organization Code 100718/00, Fund 675005, Module U1300, and Object 131500.
View the file
Other files
Show all 34
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DDivision oof RRecreation aand PParks
CConsultant’s TTask AAssignment NNotification
FFLORIDA DEPARTMENT OF
EENVIRONMENTAL PPROTECTION
DRP-084
Rev. 0 /2025 of 2
FDEP Contract No: Project Number: Task Assignment No:
Project Location Project
Consultant’s Name:
Consultant’s Representative:
Phone: Email:
FDEP Contract Manager:
Phone: Email:
Task Description:
Project Manager:
Schedule:
Start Date: Completion Date:
Fixed Price Cost: Cost Reimbursement (Not to Exceed):
Total Task Amount:
Signatures and Date:
1.
Budget Representative, FDEP Signature Date
2.
Project Manager, FDEP Signature Date
3.
Signature Date
4.
Signature Date
5.
Contract Authority, FDEP Signature Date
CN803 61543 12
Yulee Sugar Mill Ruins Historic State Park Historic Ruins Preservation
Weiler Engineering Corporation Robin Palmer, P.E.
(941) 646-8612 rpalmer@weilerengineering.org
Vu Nguyen
(850) 245-2630 vu.nguyen@floridadep.gov
Transferring design, permitting, and construction administration tasks from CN230 TA84 per the attached proposal dated June 8, 2025. Subtasks using CN230 rates indicated by *.
Richard Marcil
Upon Execution 06/01/2026
$25,147.50 $0.00 $25,147.50
Tamika Bass
Richard Marcil
Robin Palmer, P.E.
Vu Nguyen
Michael W. Foster Jr., P.E.
Tamika Bass Digitally signed by Tamika Bass Date: 2025.06.12 10:15:38 -04'00'
Richard Rene Marcil, III Digitally signed by Richard Rene Marcil, III Date: 2025.06.13 14:53:22 -04'00'
Robin C. Palmer Digitally signed by Robin C. Palmer Date: 2025.06.13 15:53:30 -04'00'
Vu Nguyen Digitally signed by Vu Nguyen Date: 2025.06.16 11:39:24 -04'00'
Michael W. Foster Jr., P.E.
Digitally signed by Michael W. Foster Jr., P.E.
Date: 2025.06.24 22:34:41 -04'00'
DDivision oof RRecreation aand PParks
CConsultant’s TTask AAssignment NNotification
FFLORIDA DEPARTMENT OF
EENVIRONMENTAL PPROTECTION
DRP-084
Rev. /2025 2 of 2
Encumbrance Information:
Project # Grant # Organization Code Category/Yr Fund Module Object EO Amount
Total:
61543 37502000017 100718/00 675005 U1300 131500 X2 $25,147.50
$25,147.50
PUNTA GORDA OFFICE: 201 WEST MARION AVENUE- SUITE 1306 | PUNTA GORDA | FL 33950 | TEL 941-505-1700 | FAX 941-505-1702 MARATHON OFFICE: 6805 OVERSEAS HIGHWAY | MARATHON | FL 33050 | TEL 305 -289-4161 | FAX 305 -289-41 6 2 KEY W EST OFF I CE: 663 0 FRONT STREE T | KE Y W EST | FL 33 04 0 | TEL 3 05 - 289 -4 16 1 | FAX 30 5 -28 9 - 41 6 2 WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG
June 8, 2025
Mr. Richard Marcil Project Manager Bureau of Design and Construction Florida Department of Environmental Protection 3900 Commonwealth Boulevard 260-L, MS 520 Tallahassee, FL 32399
RE: Yulee Mill Ruins State Park – Historic Preservation, CN - 803, TA -
Dear Mr. Marcil, Thank you for the opportunity to provide this proposal to prepare the plans and documentation necessary to provide reports, plans, and permits to perform Historic Preservation services on the Sugar Mill. The items below have been transferred over from the previous CN230 contract using the previous rates and previous rates are indicated by asterisks.
1. 60% Structural Restoration Plans.
• Kettle Train (#5 on Exhibit Below)
• Remove sod and soil to expose grate + add a product/treatment to the grate to protect it.
• Flue is to remain as-is. No work is proposed on the flue.
• Boiler (#1 on Exhibit Below)
• Add structural support to the boiler to keep boiler, boiler run, stonework.
• Add a grate to prevent visitors from climbing into boiler run., and stack component intact.
• Replace any bricks with matching, local stonework.
• Rolling Press (#2 on Exhibit Below)
• Remove stone façade and add an access hole to allow inspections, maintenance, and air flow using a metal grate and lock. (Access hole should not be on the roadside face).
• Remove 1 face of façade and aging wooden structure. Replacement stabilization with cast-in-place foundation.
Mr. Richard Marcil Yulee Sugar Mill
CN 803/TA
May 13, 2025- Rev 1 June 8, 2025
PUNTA GORDA OFFICE: 201 WEST MARION AVENUE - SUITE 1306 | PUNTA GORDA | FL 33950 | TEL 941-505 -1700 | FAX 941-505 -1702 MARATHON OFFICE: 6805 OVERSEAS HIGHWAY | MARATHON | FL 33050 | TEL 305 -289-4161 | FAX 305 -289-4 1 6 2 KEY W EST OFF I CE: 663 0 FRONT STREE T | KE Y W EST | FL 33 04 0 | TEL 3 05 - 289 -4 16 1 | FAX 30 5 - 28 9 - 41 6 2 WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG
• Well (#4 on Exhibit Below)
• Add a grate for protection using a heavy-duty metal grate similar to other locations.
2. 100% Structural Restoration Plans
CN 803/TA
May 13, 2025- Rev 1 June 8, 2025
PUNTA GORDA OFFICE: 201 WEST MARION AVENUE - SUITE 1306 | PUNTA GORDA | FL 33950 | TEL 941-505 -1700 | FAX 941-505 -1702 MARATHON OFFICE: 6805 OVERSEAS HIGHWAY | MARATHON | FL 33050 | TEL 305 -289-4161 | FAX 305 -289-4 1 6 2 KEY W EST OFF I CE: 663 0 FRONT STREE T | KE Y W EST | FL 33 04 0 | TEL 3 05 - 289 -4 16 1 | FAX 30 5 - 28 9 - 41 6 2 WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG
Areas that do NOT require any attention at this time:
Steam Well (#3) Cooling Vat (#6) Engine (#7) Stack (#8)
For your review, the Weiler Engineering Corporation, has provided a proposal summary and man-hour documentation for the tasks identified below:
Please review the attached Proposal Summary and deliverables.
Sincerely, Michael J. Giardullo, P.E.
Director of Civil Engineering The Weiler Engineering Corporation- An Apex Company
CN 803/TA
May 13, 2025- Rev 1 June 8, 2025
PUNTA GORDA OFFICE: 201 WEST MARION AVENUE - SUITE 1306 | PUNTA GORDA | FL 33950 | TEL 941-505 -1700 | FAX 941-505 -1702 MARATHON OFFICE: 6805 OVERSEAS HIGHWAY | MARATHON | FL 33050 | TEL 305 -289-4161 | FAX 305 -289-4 1 6 2 KEY W EST OFF I CE: 663 0 FRONT STREE T | KE Y W EST | FL 33 04 0 | TEL 3 05 - 289 -4 16 1 | FAX 30 5 - 28 9 - 41 6 2 WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG
Yulee Ruins State Park
Contract Number 803, Task Assignment Number XX
*Subtask 1: 60% Design
Description: Plans completed to 60% incorporating comments from preliminary investigation and report.
Deliverable: Plans consultant shall deliver 60% Plans (digital PDF only) including:
Opinion of Probable Cost Cover sheet Plan Sheet Identifying the General Location of the Mill and Facilities Larger Scale Sheets Identifying Kettle Train, Boiler, Rolling Press, and Well with damaged areas and specific repairs Details General Notes
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
*Subtask 1: 60% Design
Firm Name Position Classification Hourly Rate Hours Total Fixed
Price Cost Weiler Engineering Project Manager 145 13 1,885.00
Principal in Charge 195 .25 48.75
Registered Professional Engineer
145 11 1,595.00
Registered Engineer Intern 115 18 2,070.00
Senior Engineering Designer 100 45 4,500.00
Engineering Technician 80 61 4,880.00
CN 803/TA
May 13, 2025- Rev 1 June 8, 2025
PUNTA GORDA OFFICE: 201 WEST MARION AVENUE - SUITE 1306 | PUNTA GORDA | FL 33950 | TEL 941-505 -1700 | FAX 941-505 -1702 MARATHON OFFICE: 6805 OVERSEAS HIGHWAY | MARATHON | FL 33050 | TEL 305 -289-4161 | FAX 305 -289-4 1 6 2 KEY W EST OFF I CE: 663 0 FRONT STREE T | KE Y W EST | FL 33 04 0 | TEL 3 05 - 289 -4 16 1 | FAX 30 5 - 28 9 - 41 6 2 WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG
Clerical 55 2 110.00
Total 15,088.75
*Subtask 2: 100% Design
Description: Plans completed to 100% incorporating comments from 60%.
Deliverable: Plans consultant shall deliver 100% Plans (digital PDF only) including:
Opinion of Probable Cost Cover sheet Plan Sheet Identifying the General Location of the Mill and Facilities.
Larger Scale sheets identifying Kettle Train, Boiler, Rolling Press, and Well with damaged areas and specific repairs Details General Notes Specifications
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
*Subtask 2: 100% Design
Firm Name Position Classification Hourly Rate Hours Total Fixed
Price Cost Weiler Engineering Project Manager 145 8 1,160.00
Principal in Charge 195 .25 48.75
Registered Professional Engineer
145 8 1,160.00
Registered Engineer Intern 115 12 1,380.00
Senior Engineering Designer 100 30 3,000.00
Engineering Technician 80 40 3,200.00
Clerical 55 2 110.00
Total 10,058.75
CN 803/TA
May 13, 2025- Rev 1 June 8, 2025
PUNTA GORDA OFFICE: 201 WEST MARION AVENUE - SUITE 1306 | PUNTA GORDA | FL 33950 | TEL 941-505 -1700 | FAX 941-505 -1702 MARATHON OFFICE: 6805 OVERSEAS HIGHWAY | MARATHON | FL 33050 | TEL 305 -289-4161 | FAX 305 -289-4 1 6 2 KEY W EST OFF I CE: 663 0 FRONT STREE T | KE Y W EST | FL 33 04 0 | TEL 3 05 - 289 -4 16 1 | FAX 30 5 - 28 9 - 41 6 2 WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG
*Subtask 3A – 3H: Construction Phase Services **(Note: Not activated until the construction Phase)
*Subtask 3A: Assistance During Bidding
Description: WEC will provide assistance during the bidding process. Responses to the FDEP on bidder RFIs will be responded to within 7 days.
Deliverable: Responses to bidder questions will be provided in PDF format to the FDEP Project Manager within 7 days.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
*Subtask 3A: Assistance During Bidding
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Weiler Engineering Project Manager 145 6 870.00
Weiler Engineering Senior Engineering Designer 100 4 400.00 Total 1,270.00
*Subtask 3B: Attend Pre-Construction Meeting
Description: WEC will provide representation at the Pre-Construction Meeting.
Deliverable: Meeting notes within 2 days from meeting date for inclusion by FDEP Project Manager in Meeting Minutes.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
CN 803/TA
May 13, 2025- Rev 1 June 8, 2025
PUNTA GORDA OFFICE: 201 WEST MARION AVENUE - SUITE 1306 | PUNTA GORDA | FL 33950 | TEL 941-505 -1700 | FAX 941-505 -1702 MARATHON OFFICE: 6805 OVERSEAS HIGHWAY | MARATHON | FL 33050 | TEL 305 -289-4161 | FAX 305 -289-4 1 6 2 KEY W EST OFF I CE: 663 0 FRONT STREE T | KE Y W EST | FL 33 04 0 | TEL 3 05 - 289 -4 16 1 | FAX 30 5 - 28 9 - 41 6 2 WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG
*Subtask 3B: Attend Pre-Construction Meeting
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Weiler Engineering Project Manager 145 8 1,160.00
Weiler Engineering Registered Engineer Intern 115 8 920.00 Total 2,080.00
*Subtask 3C: Review Contractor Submittals
Description: WEC will review and comment on Contractor submittal package within 14 days of receipt.
Deliverable: Stamped acceptance of final submittals in PDF digital form to FDEP Project Manager within 7 days of final approvals.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
*Subtask 3C: Review Contractor Submittals Firm Name Position Classification Hourly Rate Hours Total Fixed
Price Cost Weiler Engineering Project Manager 145 2 290.00
Weiler Engineering Registered Engineer Intern 115 6 690.00
Weiler Engineering Senior Engineering Designer 100 8 800.00
Weiler Engineering Engineering Technician 80 2 160.00 Total 1,940.00
CN 803/TA
May 13, 2025- Rev 1 June 8, 2025
PUNTA GORDA OFFICE: 201 WEST MARION AVENUE - SUITE 1306 | PUNTA GORDA | FL 33950 | TEL 941-505 -1700 | FAX 941-505 -1702 MARATHON OFFICE: 6805 OVERSEAS HIGHWAY | MARATHON | FL 33050 | TEL 305 -289-4161 | FAX 305 -289-4 1 6 2 KEY W EST OFF I CE: 663 0 FRONT STREE T | KE Y W EST | FL 33 04 0 | TEL 3 05 - 289 -4 16 1 | FAX 30 5 - 28 9 - 41 6 2 WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG
Subtask 3D: Assistance With Regulatory Permitting
Description: WEC will assist the contractor with the permitting process for the Citrus County Historic Review Board as well as any regulatory comments from Citrus County.
Deliverable: WEC will provide any plan revisions/exhibits needed for Citrus County to FDEP Project Manager in PDF digital format within 14 days.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 3D: Assistance With Regulatory Permitting Firm Name Position Classification Hourly Rate Hours Total Fixed
Price Cost Weiler Engineering Project Manager 145 12 1,740.00
Weiler Engineering Principal 195 0.25 48.75
Weiler Engineering Registered Professional Engineer
145 2 290.00
Weiler Engineering Registered Engineer Intern 115 12 1,380.00
Weiler Engineering Senior Engineering Designer 100 14 1,400.00
Weiler Engineering Engineering Technician 80 2 160.00
Weiler Engineering Clerical 55 0.5 27.50 Total 5,046.25
*Subtask 3E: Respond to Contractor RFIs
Description: WEC will respond to RFIs from Contractor within 7 days throughout the course of the construction phase. If any plan changes are required, these changes will be completed within 14 days.
Deliverable: WEC will provide copies of all RFI responses to FDEP Project Manager in PDF digital format within 7 days.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are
CN 803/TA
May 13, 2025- Rev 1 June 8, 2025
PUNTA GORDA OFFICE: 201 WEST MARION AVENUE - SUITE 1306 | PUNTA GORDA | FL 33950 | TEL 941-505 -1700 | FAX 941-505 -1702 MARATHON OFFICE: 6805 OVERSEAS HIGHWAY | MARATHON | FL 33050 | TEL 305 -289-4161 | FAX 305 -289-4 1 6 2 KEY W EST OFF I CE: 663 0 FRONT STREE T | KE Y W EST | FL 33 04 0 | TEL 3 05 - 289 -4 16 1 | FAX 30 5 - 28 9 - 41 6 2 WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG
Fixed Price Cost:
*Subtask 3E: Respond to Contractor RFIs Firm Name Position Classification Hourly Rate Hours Total Fixed
Price Cost Weiler Engineering Project Manager 145 2 290.00
Weiler Engineering Registered Professional Engineer
145 2 290.00
Weiler Engineering Registered Engineer Intern 115 6 690.00
Weiler Engineering Senior Engineering Designer 100 6 600.00
Weiler Engineering Clerical 55 1 55.00 Total 1,925.00
*Subtask 3F: Interim Site Inspection
Description: WEC will provide an interim inspection during construction upon request from BDC.
Deliverable: WEC will provide a site visit report to the FDEP Project Manager in PDF format.
The inspection report will be submitted within 3 days of the site visit.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
*Subtask 3F: Interim Site Inspection Firm Name Position Classification Hourly Rate Hours Total Fixed
Price Cost Weiler Engineering Project Manager 145 1 145.00
Weiler Engineering Registered Professional Engineer
145 .5 72.50
Weiler Engineering Registered Engineer Intern 115 10 1,150.00 Total 1,367.50
CN 803/TA
May 13, 2025- Rev 1 June 8, 2025
PUNTA GORDA OFFICE: 201 WEST MARION AVENUE - SUITE 1306 | PUNTA GORDA | FL 33950 | TEL 941-505 -1700 | FAX 941-505 -1702 MARATHON OFFICE: 6805 OVERSEAS HIGHWAY | MARATHON | FL 33050 | TEL 305 -289-4161 | FAX 305 -289-4 1 6 2 KEY W EST OFF I CE: 663 0 FRONT STREE T | KE Y W EST | FL 33 04 0 | TEL 3 05 - 289 -4 16 1 | FAX 30 5 - 28 9 - 41 6 2 WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG
*Subtask 3G: Substantial Completion w/ Certification
Description: WEC will assist Client with the Substantial Completion inspection, with WEC representative attending the Substantial Completion inspection with punchlist. WEC will assist the FDEP with any permit closeout.
Deliverable: WEC will provide complete the substantial completion certification form required by FDEP Project Manager.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
*Subtask 3G: Substantial Completion w/ Certification Firm Name Position Classification Hourly Rate Hours Total Fixed
Price Cost Weiler Engineering Project Manager 145 3 435.00
Weiler Engineering Registered Professional Engineer
145 1 145.00
Weiler Engineering Registered Engineer Intern 115 8 920.00
Weiler Engineering Senior Engineering Designer 100 8 800.00 Total 2,300.00
*Subtask 3H: Final Completion
Description: WEC will assist Client with the Final Completion inspection, with WEC representative attending the Final Completion inspection.
Deliverable: WEC will provide a final completion inspection report to the FDEP Project Manager.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are
CN 803/TA
May 13, 2025- Rev 1 June 8, 2025
PUNTA GORDA OFFICE: 201 WEST MARION AVENUE - SUITE 1306 | PUNTA GORDA | FL 33950 | TEL 941-505 -1700 | FAX 941-505 -1702 MARATHON OFFICE: 6805 OVERSEAS HIGHWAY | MARATHON | FL 33050 | TEL 305 -289-4161 | FAX 305 -289-4 1 6 2 KEY W EST OFF I CE: 663 0 FRONT STREE T | KE Y W EST | FL 33 04 0 | TEL 3 05 - 289 -4 16 1 | FAX 30 5 - 28 9 - 41 6 2 WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG
Fixed Price Cost:
*Subtask 3H: Final Completion Firm Name Position Classification Hourly Rate Hours Total Fixed
Price Cost Weiler Engineering Project Manager 145 3 435.00
Weiler Engineering Registered Professional Engineer
145 1 145.00
Weiler Engineering Registered Engineer Intern 115 8 920.00
Weiler Engineering Senior Engineering Designer 100 8 800.00 Total 2,300.00
Project Schedule:
Subtasks 3A - 3H are not yet to be activated.
Activity Duration (Calendar Days) Days from Execution *Subtask 1: 60% Design 45 - includes 7 days for Client review
*Subtask 2: 100% Plans 45 – includes 7 days for Client review
*Subtask 3A: Assistance During Bidding
TBD TBD
*Subtask 3B: Attend A Pre- Construction Meeting
TBD TBD
*Subtask 3C: Review Contractor Submittals
TBD TBD
Subtask 3D: Assistance with Regulatory Permitting
TBD TBD
*Subtask 3E: Respond to Contractor RFIs
TBD TBD
*Subtask 3F: Interim Site Inspection
TBD TBD
*Subtask 3G: Substantial Completion w/ Certification
TBD TBD
CN 803/TA
May 13, 2025- Rev 1 June 8, 2025
PUNTA GORDA OFFICE: 201 WEST MARION AVENUE - SUITE 1306 | PUNTA GORDA | FL 33950 | TEL 941-505 -1700 | FAX 941-505 -1702 MARATHON OFFICE: 6805 OVERSEAS HIGHWAY | MARATHON | FL 33050 | TEL 305 -289-4161 | FAX 305 -289-4 1 6 2 KEY W EST OFF I CE: 663 0 FRONT STREE T | KE Y W EST | FL 33 04 0 | TEL 3 05 - 289 -4 16 1 | FAX 30 5 - 28 9 - 41 6 2 WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG
*Subtask 3H: Final Completion
TBD TBD
Summary of Fees:
Subtask Subtask Fixed Price Cost Subtask Reimbursable *Subtask 1: 60% Design $15,088.75 $0.00 *Subtask 2: 100% Plans $10,058.75 $0.00
Total Design Cost: $25,147.50 $0.00 *Subtask 3A: Assistance During Bidding
$1,270.00 $0.00
*Subtask 3B: Attend A Pre- Construction Meeting
$2,080.00 $0.00
*Subtask 3C: Review Contractor Submittals
$1,940.00 $0.00
Subtask 3D: Assistance with Regulatory Permitting
$5,046.25 $0.00
*Subtask 3E: Respond to Contractor RFIs
$1,925.00 $0.00
*Subtask 3F: Interim Site Inspection
$1,367.50 $0.00
*Subtask 3F: Substantial Completion w/ Certification
$2,300.00 $0.00
*Subtask 3H: Final Completion $2,300.00 $0.00 Total Construction Costs: $18,228.75 $0.00
Total Fixed Price Cost: $43,376.25 Total Price Cost: $0.00
Overall Total Cost: $43,376.25
Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified.