This is a Consultant's Task Assignment Notification issued by the Florida Department of Environmental Protection (FDEP), Division of Recreation and Parks, for the John Pennekamp Coral Reef State Park Mangrove Trail Boardwalk project. The document authorizes Weiler Engineering Corp., represented by Michael J. Giardullo, P.E., to perform construction administration services under FDEP Contract No. CN803, Project No. 61489C, Task Assignment No. 20. The contract manager is Vu Nguyen, and the FDEP project manager is James Post. The document was executed in September 2025 with a completion date of January 31, 2026.
The scope of work involves performing the balance of construction administration services remaining from the previous contract CN203 TA69, using the same hourly rates established in the original proposal dated September 2, 2025. The work comprises two subtasks: reviewing contractor submittals with a fixed price of $2,680.00, and conducting a substantial completion walk-through with punchlist services for $1,950.00. The total task amount is $4,630.00 on a fixed-price basis with no cost reimbursement component. Payment is contingent upon FDEP approval of deliverables for each subtask. The encumbrance information indicates funding from Grant No. 37505018015 under Category/Year 080039/23, Fund 423001, Module U3200, and Object 131500.
View the file
Other files
Show all 34
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DDivision oof RRecreation aand PParks
CConsultant’s TTask AAssignment NNotification
FFLORIDA DEPARTMENT OF
EENVIRONMENTAL PPROTECTION
DRP-084
Rev. 0 /2025 of 2
FDEP Contract No: Project Number: Task Assignment No:
Project Location Project
Consultant’s Name:
Consultant’s Representative:
Phone: Email:
FDEP Contract Manager:
Phone: Email:
Task Description:
Project Manager:
Schedule:
Start Date: Completion Date:
Fixed Price Cost: Cost Reimbursement (Not to Exceed):
Total Task Amount:
Signatures and Date:
1.
Budget Representative, FDEP Signature Date
2.
Project Manager, FDEP Signature Date
3.
Signature Date
4.
Signature Date
5.
Contract Authority, FDEP Signature Date
CN803 61489C 20
John Pennekamp Coral Reef State Park Mangrove Trail Boardwalk
Weiler Engineering Corp.
Michael J. Giardullo, P.E.
(941) 505-1700 mgiardullo@weilerengineering.org
Vu Nguyen
(850) 245-2630 Vu.Nguyen@FloridaDEP.gov
Perform the balance of CA services remaining from CN203 TA69 using the same hourly rates* as per the proposal dated September 2, 2025.
* Hourly rates from old TA
James Post
Upon Execution 01/31/2026
$4,630.00 $0.00 $4,630.00
Tamika Bass
James Post
Michael Giardullo, P.E.
Vu Nguyen
Michael W. Foster, Jr., P.E.
Tamika Bass Digitally signed by Tamika Bass Date: 2025.09.03 15:08:16 -04'00'
James Post Digitally signed by James Post Date: 2025.09.09 15:08:40 -04'00'
Michael J. Giardullo Digitally signed by Michael J. Giardullo Date: 2025.09.10 07:46:58 -04'00'
Vu Nguyen Digitally signed by Vu Nguyen Date: 2025.09.11 15:59:46 -04'00'
Michael W. Foster Jr., P.E.
Digitally signed by Michael W. Foster Jr., P.E.
Date: 2025.09.16 14:06:24 -04'00'
DDivision oof RRecreation aand PParks
CConsultant’s TTask AAssignment NNotification
FFLORIDA DEPARTMENT OF
EENVIRONMENTAL PPROTECTION
DRP-084
Rev. /2025 2 of 2
Encumbrance Information:
Project # Grant # Organization Code Category/Yr Fund Module Object EO Amount
Total:
61489C 37505018015 080039/23 423001 U3200 131500 QK $4,630.00
$4,630.00
September 2, 2025
Mr. Jim Post Bureau of Design and Construction Division of Recreation and Parks Project Manager 3 LaCroix Court Key Largo, FL 33037
RE: John Pennekamp State Park - Boardwalk Replacement, CN - 803, TA -
Dear Mr. Post, Thank you for the opportunity to provide this proposal for construction administration services to demolish and replace the existing boardwalk and accessory structures identified below.
PUNTA GORDA OFFICE: 201 WEST MARION AVENUE - SUITE 1306 | PUNTA GORDA | FL 33950 | TEL 941-505 -1700 | FAX 941-505 - 1702 MARATHON OFFICE: 6805 OVERSEAS HIGHWAY | MARATHON | FL 33050 | TEL 305 -289-4161 | FAX 305 -289-
416 2 WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT
INFO@WEILERENGINEERING.ORG
Mr. Jim Post John Pennekamp State Park Boardwalk
CN 803/TA
Our services will include:
Construction administration services to remove the existing +/- 1500 ft. long wood boardwalk and replace it as shown on the construction plans. For clarity, items with an asterisk (*) are items transferred over from the previous CN and use the old rates approved under CN 230.
For your review, the Weiler Engineering Corporation, has provided a proposal summary and man-hour documentation for the tasks identified below:
Please review the attached Proposal Summary and deliverables.
Sincerely, Michael J. Giardullo, P.E.
Director of Civil Engineering The Weiler Engineering Corporation- An Apex Company
Mr. Jim Post John Pennekamp State Park Boardwalk
CN 803/TA
Boardwalk Replacement John Pennekamp State Park
Contract Number 803, Task Assignment Number
*Subtask 1: Review Contractor submittals
Description: WEC will review and comment on Contractor submittal package within 14 days of receipt.
Deliverable: Stamped acceptance of final submittals in PDF digital form to FDEP Project Manager within 7 days of final approvals.
Fixed Price Cost:
Subtask 1 - Review Submittals
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Weiler Engineering Project Manager 145 2 290
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 0 0
Weiler Engineering Registered Engineer Intern 115 8 920
Weiler Engineering Senior Engineering Designer 100 12 1200
Weiler Engineering Engineering Technician 80 2 160
Weiler Engineering Clerical 55 2 110
Total 2680
*Subtask 2: Substantial Completion Walk-Through w/Punchlist
Description: WEC will assist Client with the Substantial Completion inspection and punchlist, with WEC representative attending the Substantial Completion inspection and providing engineer input related to the punchlist.
Deliverable: WEC will provide comments and input on punchlist and Certification provided by FDEP Project Manager via PDF within one (1) day of Substantial Completion inspection.
Fixed Price Cost:
Subtask 2 Substantial
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Weiler Engineering Project Manager 145 6 870
Mr. Jim Post John Pennekamp State Park Boardwalk
CN 803/TA
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 2 290
Weiler Engineering Registered Engineer Intern 115 6 690
Weiler Engineering Senior Engineering Designer 100 1 100
Weiler Engineering Engineering Technician 80 0 0
Weiler Engineering Clerical 55 0 0
Total 1950
Project Schedule:
Activity Duration (Calendar Days) Days from Execution
Subtask 1: Review Submittals TBD TBD
Subtask 4I: Substantial Completion Walk-Through w/ Punchlist
TBD TBD
Summary of Fees:
Subtask Subtask Fixed Price Cost Subtask Reimbursable
Subtask 1: Review Submittals $2680.00 $0.00
Subtask 4I: Substantial Completion Walk-Through w/ Punchlist
$1950.00 $0.00
Total during Construction $4,630.00 $0.00
Total Fixed Price Cost: $4,630.00
Overall Total Cost: $4,630.00
Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified. (Please do not alter this language)