CN-370000-CN803-T2.pdf
PDF 970 KB Posted
- Contract number
- CN803
- Issued by
- Florida
About this file
This is a Consultant's Task Assignment Notification (Form DRP-084) issued by the Florida Department of Environmental Protection (FDEP), Division of Recreation and Parks, for the Cayo Costa State Park Hurricane Ian Redevelopment project. The contract involves the FDEP as the state agency, Weiler Engineering Corporation as the consultant, and identifies specific FDEP representatives including Contract Manager Vu Nguyen and Project Manager Terry McCullum Jr. The document is dated April 22, 2025, and represents Task Assignment 02 under FDEP Contract No. CN803, Project Number 6I408C.
The task assignment covers the transferral of incomplete design, permitting, and construction administration subtasks from a previous contract (CN230 TA61) and includes additional design and permitting work for three sites at Cayo Costa State Park: upland improvements with new buildings at Site 1, residential improvements at Site 2, and storage building improvements at Site 3, along with waterside dredge and fill work. The contract encompasses 15 subtasks including permit approvals, 100% design development, pre-bid and pre-construction meetings, submittal reviews, contractor RFI responses, 16 monthly construction inspections, substantial and final completion inspections, electrical investigation, and generator platform design at 60% and 100% levels with permitting. The fixed price cost totals $187,761.04 with reimbursable costs of $973.00, for a total task amount of $188,734.04. The contract period runs from execution through December 31, 2026, with deliverables including signed and sealed plans, permits, inspection reports, and certifications provided in PDF and hard copy formats. Payment is contingent upon FDEP approval of deliverables for each subtask.
View the file
Other files
Show all 34
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Division of Recreation and Parks
Consultant�s Task Assignment Notification
FLORIDA DEPARTMENT OF
ENVIRONMENTAL PROTECTION
DRP-084
Rev. 0 /2025 of 2
FDEP Contract No: Project Number: Task Assignment No:
Project Location Project
Consultant�s Name:
Consultant�s Representative:
Phone: Email:
FDEP Contract Manager:
Phone: Email:
Task Description:
Project Manager:
Schedule:
Start Date: Completion Date:
Fixed Price Cost: Cost Reimbursement (Not to Exceed):
Total Task Amount:
Signatures and Date:
1.
Budget Representative, FDEP Signature Date
2.
Project Manager, FDEP Signature Date
3.
Signature Date
4.
Signature Date
5.
Contract Authority, FDEP Signature Date
CN803 6I408C 02
Cayo Costa State Park Hurricane Ian Redevelopment
Weiler Engineering Corporation
Michael J. Giardullo
(941) 505-1700 mgiardullo@weilerengineering.org
Vu Nguyen
(850) 245-2630 Vu.Nguyen@FloridaDEP.gov
Transferral of incomplete design, permitting, and construction administration subtasks (6B, 9-18) from CN230 TA61 and additional design and permitting tasks, per attached proposal dated April 10, 2025.
*Subtasks utilizing rates per CN230 are denoted with an asterisk (*) in the subtask heading.
Terry McCullum Jr.
Upon Execution 12/31/2026
$187,761.04 $973.00
$188,734.04
Tamika Bass
Terry McCullum Jr.
Michael J. Giardullo
Vu Nguyen
Tim Giesecke
04/22/2025
Tamika Bass Digitally signed by Tamika Bass Date: 2025.04.22 13:23:00 -04'00'
Terry McCullum Jr. Digitally signed by Terry McCullum Jr.
Date: 2025.04.22 14:10:36 -04'00'
Michael Giardullo Digitally signed by Michael Giardullo Date: 2025.04.22 16:43:47 -04'00'
Division of Recreation and Parks
Consultant�s Task Assignment Notification
FLORIDA DEPARTMENT OF
ENVIRONMENTAL PROTECTION
DRP-084
Rev. /2025 2 of 2
Encumbrance Information:
Project # Grant # Organization Code Category/Yr Fund Module Object EO Amount
Total:
6I408C FD091 37504003127 088040/23 675002 U3200 131500 XR $187,422.44
6I408C FD091 37504003127 088040/24 675002 U3200 131500 XR $1,311.60
$188,734.04
April 10, 2025
Mr. Terry McCullum, Jr Project Manager Bureau of Design and Construction Florida Department of Environmental Protection 3900 Commonwealth Boulevard 260-L, MS 520 Tallahassee, FL 32399
RE: Cayo Costa State Park - Hurricane Damage Repairs � Construction Assistance, Electrical Investigation, and Generator Platform, CN - 803, TA - 2
Dear Mr. McCullum, Thank you for the opportunity to provide this proposal to assist the Department to provide engineering assistance during construction, complete an electrical assessment, and complete design plans for the generator platform. The 100% plans and permit approvals for the waterside Dredge/Fill portion of the project has been transferred over to this contract from CN 230/TA61
Site 1: Proposed Conditions - Upland � Maintenance Building (Building 1), Pole Barn (Building 2), Gift Shop (Building 3) (See below) & Waterside - Dredge Cayo Costa Marina (See below 2nd picture below)
PUNTA GORDA OFFICE: 201 WEST MARION AVENUE - SUITE 1306 | PUNTA GORDA | FL 33950 | TEL 941-505 -1700 | FAX 941-505 - 1702 MARATHON OFFICE: 6805 OVERSEAS HIGHWAY | MARATHON | FL 33050 | TEL 305 -289 -4161 | FAX 305 - 289-
416 2 WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT
INFO@WEILERENGINEERING.ORG
Mr. Terry McCullum, Jr
Cayo Costa State Park Hurricane Repairs CA, Electrical Investigation, & Generator Platform
CN 803/TA2
Site 2 - Upland � Construction Assistance for new Residence designed under Cn230/TA61. (No in-water work this site).
Mr. Terry McCullum, Jr
Cayo Costa State Park Hurricane Repairs CA, Electrical Investigation, & Generator Platform
CN 803/TA2
Site 3 - Upland � Construction assistance for the new storage building at Jug Creek & Waterside - Dredge Jug Creek access (100% Dredge/Fill Plans & Permit Approvals transferred from CN230/TA61)
For your review, the Weiler Engineering Corporation- An Apex Company, has provided a proposal summary and man-hour documentation for the services and tasks identified.
Please feel free to contact me if you have any questions or wish to discuss matters further.
Sincerely, Michael J. Giardullo, P.E.
Director of Civil Engineering The Weiler Engineering Corporation- An Apex Company
Mr. Terry McCullum, Jr
Cayo Costa State Park Hurricane Repairs CA, Electrical Investigation, & Generator Platform
CN 803/TA2
Hurricane Repairs - Design & Permitting Cayo Costa State Park
Contract Number 8 3, Task Assignment Number 2
Subtask 1: Site 1 & 3 Dredge & Fill Permitting Approval*
Description:
Depends on agencies but anticipate at least 180 days after submittal. Consultant will respond to agency requests for additional information and copy Client on all responses. Upon approval, Consultant will provide Client with permits and revised (if necessary) plans and documentation in PDF format.
Deliverable:
6) B � Permit Approvals
Consultant will provide Client with permits and revised (if necessary) plans and documentation in PDF format.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 1 Sites 1 & 3 Dredge & Fill Permit Approvals
Firm Name Position Classification Hourly Rate Hours
Total Fixed Price Cost
Weiler Engineering Project Manager 145 10 1,450
Weiler Engineering Principal in Charge 195 2 390
Weiler Engineering Registered Professional Engineer 145 7 1,015
Weiler Engineering Registered Engineer Intern 115 12 1,380
Weiler Engineering Senior Engineering Designer 100 20 2,000
Weiler Engineering Engineering Technician 80 20 1,600
Weiler Engineering Clerical 55 1 55
Total 1 - Sites 1 & 3 Dredge & Fill Approvals 7,890
Mr. Terry McCullum, Jr
Cayo Costa State Park Hurricane Repairs CA, Electrical Investigation, & Generator Platform
CN 803/TA2
Reimbursable Cost:
Description Number @ Total
Postage 1 35 0
Printing 0 2.3 0
Permit application fees estimate
1 0 0
Reimbursable Total Cost for 6A
Total for Subtask 1
7,890
Subtask 2: 100% Site 1 & 3 Site/Civil Documents (In-Water Work) Description*:
Description: Development plans completed to 100% for in-water work (dredging).
Deliverable: Incorporate Client review of 100% plans, Consultant shall deliver two sets of 100% signed and sealed plans, digital 1-PDF and 1-CAD including:
Updated Opinion of Probable Cost (Broken down by site, with tabled project total summary)
Cover sheet Survey Existing Conditions Best Management Plan Demolition Plan Site, Utility & Grading Plans Dredging Plan & Details incl. spoil location & BMP Site Details and General Notes Sections
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Mr. Terry McCullum, Jr
Cayo Costa State Park Hurricane Repairs CA, Fixed Price Cost:
Subtask 2 - 100% Site 3 Site & Development Plans
Firm Name Position Classification Hourly Rate Hours
Total Fixed Price Cost
Weiler Engineering Project Manager 145 20 2,900
Weiler Engineering Principal in Charge 195 2 390
Weiler Engineering Registered Professional Engineer 145 18 2,610
Weiler Engineering Registered Engineer Intern 115 28 3,220
Weiler Engineering Senior Engineering Designer 100 68 6,800
Weiler Engineering Engineering Technician 80 94 7,520
Weiler Engineering Clerical 55 8 440
Total 23,880
Postage 1 35 35
Printing 60 2.30 138
Overnight Travel
(if applicable)
Reimbursable Total Cost
Subtask 2 Site 3 100% S/Civil Plans (In- Water)
24,053.00
Mr. Terry McCullum, Jr
Cayo Costa State Park Hurricane Repairs CA, Electrical Investigation, & Generator Platform
CN 803/TA2
Subtask 3: Attend a Pre-Bid meeting on-site*
Description: Consultant will attend one pre-bid meeting on site to respond to questions and prepare minutes.
Deliverable: Consultant will provide digital minutes of meeting and responses to contractor questions.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 3 - Pre-bid
Firm Name Position Classification Hourly Rate
Hours Total Fixed Price Cost
Weiler Engineering Project Manager 145 8 $1160.00
Weiler Engineering Principal in Charge 195 0 $0.00
Weiler Engineering Registered Professional Engineer
145 0 $0.00
Weiler Engineering Registered Engineer Intern 115 8 $920.00
Weiler Engineering Senior Engineering Designer 100 8 $800.00
Weiler Engineering Engineering Technician 80 8 $640.00
Weiler Engineering Clerical 55 0 $0.00
Total $3520.00
Reimbursable Cost:
Description Number @ Total
Postage Not anticipated
Overnight Travel
(if applicable)
Not anticipated
Mileage (@ $0.445 per mile) Reimbursable Total Cost
$0.00
$0.00
Mr. Terry McCullum, Jr
Cayo Costa State Park Hurricane Repairs CA, Total Subtask 3 $3520.00
Subtask 4: Attend Pre-Construction Meeting*
Description: WEC will provide representation at the Pre-Construction Meeting.
Deliverable: Meeting notes within 2 days from meeting date for inclusion by FDEP Project Manager in Meeting Minutes.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are
Subtask 4 - Pre-Construction Mtg
Firm Name Position Hourly Rate Hours Total Fixed Price Cost
Weiler Engineering Project Manager 145 8 1160
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 0 0
Weiler Engineering Registered Engineer Intern 115 8 920
Weiler Engineering Senior Engineering Designer 100 8 800
Weiler Engineering Engineering Technician 80 0 0
Weiler Engineering Clerical 55 2 110
Total 2990
Postage 0
Printing 2.3 0
Mr. Terry McCullum, Jr
Cayo Costa State Park Hurricane Repairs CA, Overnight Travel (if applicable)
Mileage (@ $0.445 per mile) 0
Reimbursable Total Cost 0
Total subtask 4 2990
Subtask 5: Review Contractor Submittals*
Description: WEC will review and comment on Contractor submittal package within 14 days of receipt.
Deliverable:, Stamped acceptance of submittals in PDF digital form to FDEP Project
Subtask 5 - Review Submittals
Cost
Weiler Engineering Project Manager 145 2 290
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 0 0
Weiler Engineering Registered Engineer Intern 115 16 1840
Weiler Engineering Senior Engineering Designer 100 16 1600
Weiler Engineering Engineering Technician 80 6 480
Weiler Engineering Clerical 55 2 110
Total 4320
Mr. Terry McCullum, Jr
Cayo Costa State Park Hurricane Repairs CA, Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Reimbursable Total Cost
Total Subtask 5 4320
Subtask 6: Respond to Contractor RFI's*
Description: WEC will respond to RFI's from Contractor within 7 days throughout the course of the construction phase 18 months.
Deliverable: WEC will provide copies of all RFI responses to FDEP Project Manager in PDF digital format.
Subtask 6- Respond to RFI�s
Cost
Weiler Engineering Project Manager 145 77 11165
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 18 2610
Weiler Engineering Registered Engineer Intern 115 24 2760
Weiler Engineering Senior Engineering Designer 100 20 2000
Weiler Engineering Engineering Technician 80 20 1600
Weiler Engineering Clerical 55 4 220
Total 20355
Mr. Terry McCullum, Jr
Cayo Costa State Park Hurricane Repairs CA, Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Total Subtask 6 20355
Subtask 7A: Provide Construction Inspections (Month 1)*
Description: WEC will provide a monthly inspection (NLT every 30 days) during construction.
Deliverable: WEC will provide two (2) original signed and sealed reports to the FDEP Project Manager, as well as a digital version in PDF format. The inspection report will be submitted within 3 days of each inspection.
Subtask 7A - Month 1 Inspection
Cost
Weiler Engineering Project Manager 145 8 1160
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 .5 72.5
Weiler Engineering Registered Engineer Intern 115 8 920
Weiler Engineering Senior Engineering Designer 100 1 100
Weiler Engineering Engineering Technician 80 0 0
Weiler Engineering Clerical 55 0 0
Total 2252.5
Mr. Terry McCullum, Jr
Cayo Costa State Park Hurricane Repairs CA, Electrical Investigation, & Generator Platform
CN 803/TA2
Reimbursable Cost:
Description Number @ Total
Postage 35 0
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Reimbursable Total Cost
Total Subtask 7A 2252.5
Subtask 7B: Construction Inspection (Month 2)*
Description: WEC will provide a monthly inspection (NLT every 30 days) during construction.
Deliverable: WEC will provide original digitally signed and sealed reports to the FDEP Project Manager, in PDF format. The inspection report will be submitted within 3 days of each inspection.
Fixed Price Cost:
Subtask 7B
Firm Name Position Hourly Rate Hours Total Fixed Price Cost
Weiler Engineering Project Manager 145 8 1160
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 .5 72.5
Weiler Engineering Registered Engineer Intern 115 8 920
Weiler Engineering Senior Engineering Designer 100 1 100
Weiler Engineering Engineering Technician 80 0 0
Total 2252.5
Mr. Terry McCullum, Jr
Cayo Costa State Park Hurricane Repairs CA, Electrical Investigation, & Generator Platform
Postage 35 0
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
0.445 0
Reimbursable Total Cost
Total Subtask 7B 2252.5
Subtask 7C: Construction Inspection (Month 3)*
Deliverable: WEC will provide original digitally signed and sealed reports to the FDEP Project Manager, in PDF format. The inspection report will be submitted within 3 days of each inspection.
Subtask 7C Month 3 Inspection
Cost
Weiler Engineering Project Manager 145 8 1160
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 .5 72.5
Weiler Engineering Registered Engineer Intern 115 8 920
Weiler Engineering Senior Engineering Designer 100 8 800
Weiler Engineering Engineering Technician 80 0 0
Total 2952.5
Mr. Terry McCullum, Jr
Cayo Costa State Park Hurricane Repairs CA, Electrical Investigation, & Generator Platform
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Total Subtask 7C 2952.5
Subtask 7D: Construction Inspection (Month 4)*
Deliverable: WEC will provide original digitally signed and sealed reports to the FDEP Project
Subtask 7D - Inspection Month 4
Cost
Weiler Engineering Project Manager 145 1 145
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 .5 72.5
Weiler Engineering Registered Engineer Intern 115 8 920
Weiler Engineering Senior Engineering Designer 100 8 800
Weiler Engineering Engineering Technician 80 0 0
Total 1937.5
Mr. Terry McCullum, Jr
Cayo Costa State Park Hurricane Repairs CA, Electrical Investigation, & Generator Platform
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
0.445 0
Total Subtask 7D 1937.5
Subtask 7E: Construction Inspection (Month 5)*
Subtask 7E Month 5 Inspection
Cost
Weiler Engineering Project Manager 145 1 145
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 .5 72.5
Weiler Engineering Registered Engineer Intern 115 8 920
Weiler Engineering Senior Engineering Designer 100 8 800
Weiler Engineering Engineering Technician 80 0 0
Mr. Terry McCullum, Jr
Cayo Costa State Park Hurricane Repairs CA, Electrical Investigation, & Generator Platform
CN 803/TA2
Reimbursable Cost:
Description Number @ Total
Postage 35 0
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Reimbursable Total Cost 0
Total Subtask 7E 1937.5
Subtask 7F: Construction Inspection (Month 6)*
Description: WEC will provide a monthly inspection (NLT every 30 days) during construction.
Deliverable: WEC will provide original digitally signed and sealed reports to the FDEP Project Manager, in PDF format. The inspection report will be submitted within 3 days of each inspection.
Fixed Price Cost:
Subtask 7F Month 6 Inspection
Firm Name Position Hourly Rate Hours Total Fixed Price Cost
Weiler Engineering Project Manager 145 1 145
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 .5 72.5
Weiler Engineering Registered Engineer Intern 115 8 920
Weiler Engineering Senior Engineering Designer 100 8 800
Weiler Engineering Engineering Technician 80 0 0
Mr. Terry McCullum, Jr
Cayo Costa State Park Hurricane Repairs CA, Electrical Investigation, & Generator Platform
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Total Subtask 7F 1937.5
Subtask 7G: Construction Inspection (Month 7)*
Subtask 7G Month 7 Inspection
Cost
Weiler Engineering Project Manager 145 1 145
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 .5 72.5
Weiler Engineering Registered Engineer Intern 115 8 920
Weiler Engineering Senior Engineering Designer 100 8 800
Weiler Engineering Engineering Technician 80 0 0
Mr. Terry McCullum, Jr
Cayo Costa State Park Hurricane Repairs CA, Electrical Investigation, & Generator Platform
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Total Subtask 7G 1937.5
Subtask 7H: Construction Inspection (Month 8)*
Subtask 7H Month 8 Inspection
Cost
Weiler Engineering Project Manager 145 1 145
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 .5 72.5
Weiler Engineering Registered Engineer Intern 115 8 920
Weiler Engineering Senior Engineering Designer 100 8 800
Weiler Engineering Engineering Technician 80 0 0
Mr. Terry McCullum, Jr
Cayo Costa State Park Hurricane Repairs CA, Electrical Investigation, & Generator Platform
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Total Subtask 7H 1937.5
Subtask 7I: Construction Inspection (Month 9)*
Deliverable: WEC will provide original digitally signed and sealed reports to the FDEP Project
Subtask 7I Month 9 Inspection
Cost
Weiler Engineering Project Manager 145 1 145
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 .5 72.5
Weiler Engineering Registered Engineer Intern 115 8 920
Weiler Engineering Senior Engineering Designer 100 8 800
Weiler Engineering Engineering Technician 80 0 0
Mr. Terry McCullum, Jr
Cayo Costa State Park Hurricane Repairs CA, Electrical Investigation, & Generator Platform
CN 803/TA2
Reimbursable Cost:
Description Number @ Total
Postage 0
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Reimbursable Total Cost 0
Total Subtask 7I 1937.5
Subtask 7J: Construction Inspection (Month 10)*
Description: WEC will provide a monthly inspection (NLT every 30 days) during construction.
Deliverable: WEC will provide original digitally signed and sealed reports to the FDEP Project Manager, in PDF format. The inspection report will be submitted within 3 days of each inspection.
Fixed Price Cost:
Subtask 7J Month 10 Inspection
Firm Name Position Hourly Rate Hours Total Fixed Price Cost
Weiler Engineering Project Manager 145 1 145
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 .5 72.5
Weiler Engineering Registered Engineer Intern 115 8 920
Weiler Engineering Senior Engineering Designer 100 8 800
Weiler Engineering Engineering Technician 80 0 0
Mr. Terry McCullum, Jr
Cayo Costa State Park Hurricane Repairs CA, Electrical Investigation, & Generator Platform
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Total Subtask 7J 1937.5
Subtask 7K: Construction Inspection (Month 11)*
Subtask 7K Month 11 Inspection
Cost
Weiler Engineering Project Manager 145 1 145
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 .5 72.5
Weiler Engineering Registered Engineer Intern 115 8 920
Weiler Engineering Senior Engineering Designer 100 8 800
Weiler Engineering Engineering Technician 80 0 0
Mr. Terry McCullum, Jr
Cayo Costa State Park Hurricane Repairs CA, Electrical Investigation, & Generator Platform
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Total Subtask 7K 1937.5
Subtask 7L: Construction Inspection (Month 12)*
Subtask 7L Month 12 Inspection
Cost
Weiler Engineering Project Manager 145 1 145
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 .5 72.5
Weiler Engineering Registered Engineer Intern 115 8 920
Weiler Engineering Senior Engineering Designer 100 8 800
Weiler Engineering Engineering Technician 80 0 0
Mr. Terry McCullum, Jr
Cayo Costa State Park Hurricane Repairs CA, Electrical Investigation, & Generator Platform
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Total Subtask 7L 1937.5
Subtask 7M: Construction Inspection (Month 13)*
Subtask 7M Month 13 Inspection
Cost
Weiler Engineering Project Manager 145 1 145
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 .5 72.5
Weiler Engineering Registered Engineer Intern 115 8 920
Weiler Engineering Senior Engineering Designer 100 8 800
Weiler Engineering Engineering Technician 80 0 0
Mr. Terry McCullum, Jr
Cayo Costa State Park Hurricane Repairs CA, Electrical Investigation, & Generator Platform
CN 803/TA2
Reimbursable Cost:
Description Number @ Total
Postage 35 0
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Reimbursable Total Cost 0
Total Subtask 7M 1937.5
Subtask 7N: Construction Inspection (Month 14)*
Description: WEC will provide a monthly inspection (NLT every 30 days) during construction.
Deliverable: WEC will provide original digitally signed and sealed reports to the FDEP Project Manager, in PDF format. The inspection report will be submitted within 3 days of each inspection.
Fixed Price Cost:
Subtask 7N Month 14 Inspection
Firm Name Position Hourly Rate Hours Total Fixed Price Cost
Weiler Engineering Project Manager 145 1 145
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 .5 72.5
Weiler Engineering Registered Engineer Intern 115 8 920
Weiler Engineering Senior Engineering Designer 100 8 800
Weiler Engineering Engineering Technician 80 0 0
Mr. Terry McCullum, Jr
Cayo Costa State Park Hurricane Repairs CA, Electrical Investigation, & Generator Platform
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Total Subtask 7N 1937.5
Subtask 7O: Construction Inspection (Month 15)*
Subtask 7O Month 15 Inspection
Cost
Weiler Engineering Project Manager 145 1 145
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 .5 72.5
Weiler Engineering Registered Engineer Intern 115 8 920
Weiler Engineering Senior Engineering Designer 100 8 800
Weiler Engineering Engineering Technician 80 0 0
Mr. Terry McCullum, Jr
Cayo Costa State Park Hurricane Repairs CA, Electrical Investigation, & Generator Platform
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Total Subtask 7O 1937.5
Subtask 7P: Construction Inspection (Month 16)*
Deliverable: WEC will provide one digitally signed and sealed reports to the FDEP Project
Subtask 7P Month 16 Inspection
Cost
Weiler Engineering Project Manager 145 1 145
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 .5 72.5
Weiler Engineering Registered Engineer Intern 115 8 920
Weiler Engineering Senior Engineering Designer 100 8 800
Weiler Engineering Engineering Technician 80 0 0
Mr. Terry McCullum, Jr
Cayo Costa State Park Hurricane Repairs CA, Electrical Investigation, & Generator Platform
CN 803/TA2
Reimbursable Cost:
Description Number @ Total
Postage 35 0
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Reimbursable Total Cost 0
Total Subtask 7P 1937.5
Subtask 8A: Substantial Completion Walk-Through w/Punchlist Site�s 1, 2 & 3 Upland Improvements*
Description: WEC will assist Client with the Substantial Completion inspection and punchlist, with WEC representative attending the Substantial Completion inspection and providing engineer input related to the punchlist.
Deliverable: WEC will provide comments and input on punchlist within one (1) day of Substantial Completion inspection in PDF via email.
Fixed Price Cost:
Subtask 8 Substantial (Uplands)
Firm Name Position Hourly Rate Hours Total Fixed Price Cost
Weiler Engineering Project Manager 145 8 1160
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 4 580
Weiler Engineering Registered Engineer Intern 115 16 1840
Weiler Engineering Senior Engineering Designer 100 16 1600
Weiler Engineering Engineering Technician 80 0 0
Total 5400
Mr. Terry McCullum, Jr
Cayo Costa State Park Hurricane Repairs CA, Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Total Subtask 8A Substantial 1,2,3 Uplands
Subtask 8B: Substantial Completion Walk-Through w/Punchlist Buildings*
Description: WEC will assist Client with the Substantial Completion inspection and punchlist, with WEC representative attending the Substantial Completion inspection and providing engineer input related to the punchlist.
Deliverable: WEC will provide comments and input on punchlist within one (1) day of Substantial Completion inspection in PDF via email.
Subtask 8B Substantial Buildings
Cost
Weiler Engineering Project Manager 145 8 1160
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 6 870
Weiler Engineering Registered Engineer Intern 115 20 2300
Weiler Engineering Senior Engineering Designer 100 20 2000
Weiler Engineering Engineering Technician 80 0 0
Total 6550
Mr. Terry McCullum, Jr
Cayo Costa State Park Hurricane Repairs CA, Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Total Subtask 8B Substantial Buildings
Subtask 8C: Substantial Completion Walk-Through w/Punchlist Site�s 1 & 3 Dredge and Fill*
Description: WEC will assist Client with the Substantial Completion inspection and punchlist, with WEC representative attending the Substantial Completion inspection and providing engineer input related to the punchlist.
Deliverable: WEC will provide comments and input on punchlist within one (1) day of Substantial Completion inspection in PDF via email.
Subtask 8C Substantial Site�s 1 & 3 Dredge & Fill
Cost
Weiler Engineering Project Manager 145 8 1160
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 8 1160
Weiler Engineering Registered Engineer Intern 115 24 2760
Weiler Engineering Senior Engineering Designer 100 24 2400
Weiler Engineering Engineering Technician 80 0 0
Total 7700
Mr. Terry McCullum, Jr
Cayo Costa State Park Hurricane Repairs CA, Electrical Investigation, & Generator Platform
CN 803/TA2
Reimbursable Cost:
Description Number @ Total
Postage 35 0
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Reimbursable Total Cost 0
Total Subtask 8A Substantial 1,2,3 Uplands
Subtask 9: Final Completion w/ Sites 1,2 & 3 Upland Improvements*
Description: WEC will assist Client with the Final Completion inspection, with WEC representative attending the Final Completion inspection and prepare the necessary record information based on WEC inspections and as-builts by contractor�s surveyor.
Deliverable: WEC will provide completed record drawings and to FDEP Project Manager in PDF via email.
Fixed Price Cost:
Subtask 9 - Final Site�s 1,2 & 3 Site Upland Improvements
Firm Name Position Hourly Rate Hours Total Fixed Price Cost
Weiler Engineering Project Manager 145 10 1450
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 4 580
Weiler Engineering Registered Engineer Intern 115 20 2300
Weiler Engineering Senior Engineering Designer 100 20 2000
Weiler Engineering Engineering Technician 80 24 1920
Weiler Engineering Clerical 55 8 440
Total 8690
Mr. Terry McCullum, Jr
Cayo Costa State Park Hurricane Repairs CA, Electrical Investigation, & Generator Platform
CN 803/TA2
Reimbursable Cost:
Description Number @ Total
Postage 35 0
Printing 2.3 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Reimbursable Total Cost 0
Total Subtask 9 8690
Subtask 10: Final Completion w/ Buildings*
Description: WEC will assist Client with the Final Completion inspection, with WEC representative attending the Final Completion inspection and prepare the necessary record information based on WEC inspections and as-builts by contractor�s surveyor.
Deliverable: WEC will provide completed record drawings and to FDEP Project Manager via PDF.
Fixed Price Cost:
Subtask 10- Final Buildings
Firm Name Position Hourly Rate Hours Total Fixed Price Cost
Weiler Engineering Project Manager 145 8 1160
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 8 1160
Weiler Engineering Registered Engineer Intern 115 20 2300
Weiler Engineering Senior Engineering Designer 100 20 2000
Weiler Engineering Engineering Technician 80 24 1920
Total 8980
Mr. Terry McCullum, Jr
Cayo Costa State Park Hurricane Repairs CA, Electrical Investigation, & Generator Platform
CN 803/TA2
Reimbursable Cost:
Description Number @ Total
Postage 35 0
Printing 2.3 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Reimbursable Total Cost 0
Total Subtask 10 8980
Subtask 11: Final Completion w/ Site 1 & 3 Dredge & Fill*
Description: WEC will assist Client with the Final Completion inspection, with WEC representative attending the Final Completion inspection and prepare the necessary record information based on WEC inspections and as-builts by contractor�s surveyor.
Deliverable: WEC will also provide complete the completion form required by FDEP Project Manager via PDF.
Fixed Price Cost:
Subtask 11 - Final Site 3
Firm Name Position Hourly Rate Hours Total Fixed Price Cost
Weiler Engineering Project Manager 145 12 1740
Weiler Engineering Principal in Charge 195 1 195
Weiler Engineering Registered Professional Engineer 145 8 1160
Weiler Engineering Registered Engineer Intern 115 32 3680
Weiler Engineering Senior Engineering Designer 100 32 3200
Weiler Engineering Engineering Technician 80 48 3840
Total 14255
Mr. Terry McCullum, Jr
Cayo Costa State Park Hurricane Repairs CA, Electrical Investigation, & Generator Platform
CN 803/TA2
Reimbursable Cost:
Description Number @ Total
Postage 35 0
Printing 2.3 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Reimbursable Total Cost 0
Total Subtask 11 Final 1 & 3 Dredging
14255
Subtask 12: Electrical Investigation
Description: WEC staff will complete an electrical investigation and collect data available data on the current electrical usage and capabilities. WEC will provide a written summary of the results along with recommendations
Deliverable: Consultant will deliver a final report (digital PDF only).
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 12: Electrical Investigation
Firm Name Position Classification Hourly Rate Hours Total Fixed
Price Cost
Weiler Engineering
Project Manager 160.83 40 6,433.20
Weiler Engineering
Principal in Charge 319.2 0.25 79.81
Weiler Engineering
Professional Engineer 168.2 40 6,728.00
Weiler Engineering
Engineer Intern 115.45 60 6,927.00
Weiler Engineering
Senior Engineering Designer 115.13 10 1,151.30
Mr. Terry McCullum, Jr
Cayo Costa State Park Hurricane Repairs CA, Electrical Investigation, & Generator Platform
CN 803/TA2
Weiler Engineering Engineering 90.4 20 1,808.50
Weiler Engineering Clerical 62.74 2 125.48
Total: 60% Design Plans 23,252.79
Total for Subtask 12 23,252.79
Reimbursable Cost:
Description Number @ Total
Postage 35 0
Printing 2.3 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Reimbursable Total Cost 0
Total Subtask 12:
Electrical Investigation
23,252.79
Subtask 13: Generator Platform 60% Design
Description: WEC staff will complete 60% design plans for the new generator platform.
Deliverable: Consultant shall deliver 60% plans
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 13: Generator Platform 60% Design
Firm Name Position Classification Hourly Rate
Hours Total Fixed Price Cost
Weiler Engineering Project Manager 160.83 8 1 286.64
Mr. Terry McCullum, Jr
Cayo Costa State Park Hurricane Repairs CA, Electrical Investigation, & Generator Platform
CN 803/TA2
Weiler Engineering Principal in Charge 319.2 0.25 79.81
Weiler Engineering
Professional Engineer 168.2 10 1,682.00
Weiler Engineering Engineer Intern 115.45 16 1,847.20
Weiler Engineering
Senior Engineering Designer 115.13 10 1,151.30
Weiler Engineering Engineering 90.4 20 1,808.50
Weiler Engineering Clerical 62.74 1 62.74
Total: 60% Design Plans 7,917.69
Total for Subtask 13 7,917.69
Reimbursable Cost:
Description Number @ Total
Postage 35 0
Printing 2.3 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Reimbursable Total Cost 0
Total Subtask 13:
Generator Platform 60% Design
7,917.69
Subtask 14: Generator Platform Permitting
Description: WEC staff will complete permit applications for submittal to Lee County (LDO) and an Exemption from SFWMD.
Deliverable: Consultant shall copies of approved permits from Lee County and SFWMD (digital PDF only).
Performance Measure: Deliverables will be reviewed by the Department to confirm they are
Mr. Terry McCullum, Jr
Cayo Costa State Park Hurricane Repairs CA, Electrical Investigation, & Generator Platform
CN 803/TA2
Fixed Price Cost:
Subtask 14: Generator Platform Permitting
Firm Name Position Classification Hourly Rate Hours Total Fixed
Price Cost
Weiler Engineering
Project Manager 160.83 6 964.98
Weiler Engineering Principal in Charge 319.2 0.25 79.81
Weiler Engineering
Professional Engineer 168.2 4 672.80
Weiler Engineering
Engineer Intern 115.45 16 1,847.20
Weiler Engineering
Senior Engineering Designer 115.13 4 460.52
Weiler Engineering
Engineering 90.4 4 361.60
Weiler Engineering
Clerical 62.74 2 125.48
Total: 60% Design Plans 4,512.39
Total for Subtask 14 4,512.39
Reimbursable Cost:
Description Number @ Total
Postage 35 0
Printing 2.3 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Permit Application Total Cost
800.00
Reimbursable Total Cost 800.00
Total Subtask 14:
Generator Platform Permitting
5,312.39
Mr. Terry McCullum, Jr
Cayo Costa State Park Hurricane Repairs CA, Electrical Investigation, & Generator Platform
CN 803/TA2
Subtask 15: Generator Platform 100% Design
Description: WEC staff will incorporate comments on the 60% design plans for a 100% construction set.
Deliverable:
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 15: Generator Platform 100% Design
Firm Name Position Classification Hourly Rate Hours Total Fixed
Price Cost
Weiler Engineering
Project Manager 160.83 6 964.98
Weiler Engineering
Principal in Charge 319.2 0.25 79.81
Weiler Engineering
Professional Engineer 168.2 3 504.60
Weiler Engineering
Engineer Intern 115.45 8 923.60
Weiler Engineering Senior Engineering Designer 115.13 8 921.04
Weiler Engineering Engineering 90.4 16 1,446.40
Weiler Engineering
Clerical 62.74 1 62.74
Total: 100% Design Plans 4,903.17
Subtask 15 4,903.17
Mr. Terry McCullum, Jr
Cayo Costa State Park Hurricane Repairs CA, Electrical Investigation, & Generator Platform
CN 803/TA2
Reimbursable Cost:
Description Number @ Total
Postage 35 0
Printing 2.3 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Reimbursable Total Cost 0
Total Subtask 15:
Generator Platform 100% Design Plans
4,903.17
Project Schedule:
Activity Duration (Calendar Days) Days from Execution
Subtask 1: Waterside Dredge & fill Permit approvals Site 1 & 3
180 180
Subtask 2: 100% Waterside D & F Plans 100% Site�s 1 & 3
45 - includes 14 days for Client review 225
Subtask 3: Pre-bid 30 TBD
Subtask 4: Pre-construction Meeting 30 TBD
Subtask 5: Submittals 30 TBD
Subtask 6: RFI�s 525 TBD
Subtask 7A: Inspection 1 30 TBD
Subtask 7B: Inspection 2 30 TBD
Subtask 7C: Inspection 3 30 TBD
Subtask 7D: Inspection 4 30 TBD
Subtask 7E: Inspection 5 30 TBD
Subtask 7F: Inspection 6 30 TBD
Subtask 7G: Inspection 7 30 TBD
Subtask 7H: Inspection 8 30 TBD
Subtask 7I: Inspection 9 30 TBD
Subtask 7J: Inspection 10 30 TBD
Subtask 7K: Inspection 11 30 TBD
Mr. Terry McCullum, Jr
Cayo Costa State Park Hurricane Repairs CA, Electrical Investigation, & Generator Platform
CN 803/TA2
Subtask 7L: Inspection 12 30 TBD
Subtask 7M: Inspection 13 30 TBD
Subtask 7N: Inspection 14 30 TBD
Subtask 7O: Inspection 15 30 TBD
Subtask 7P: Inspection 16 30 TBD
Subtask 8A: Substantial Uplands 1,2&3
30 TBD
Subtask 8B: Substantial Buildings 30 TBD
Subtask 8C: Substantial 1 & 3 Waterside Dredge & Fill
30 TBD
Subtask 9: Final/Certifications Site�s 1,2 & 3 Uplands
30 TBD
Subtask 10: Final/Certifications Buildings
30 TBD
Subtask 11: Final/Certifications Site 1 & 3 Waterside Dredge & Fill
30 TBD
Subtask 12: Electrical Investigation 90 90
Subtask 13: Generator Platform 60% Design
21 21
Subtask 14: Generator Platform Permitting 60 81
Subtask 15: Generator Platform 100% Design
21 102
Summary of Fees:
Subtask Subtask Fixed Price Cost Subtask Reimbursable
Subtask 1: Waterside Dredge & fill Permit approvals Site 1 & 3
$7,890.00 $0.00
Subtask 2: 100% Waterside D & F Plans 100% Site�s 1 & 3
$23,880.00 $173.00
Sub-Totals In-Water Design & Permitting
$31,770.00 $173.00
Subtask 3: Pre-bid $3520.00 $0.00
Subtask 4: Pre-construction Meeting $2990.00 $0.00
Subtask 5: Submittals $4320.00 $0.00
Subtask 6: RFI�s $20355.00 $0.00
Subtask 7A: Inspection 1 $2252.50 $0.00
Subtask 7B: Inspection 2 $2252.50 $0.00
Subtask 7C: Inspection 3 $2952.50 $0.00
Subtask 7D: Inspection 4 $1937.50 $0.00
Mr. Terry McCullum, Jr
Cayo Costa State Park Hurricane Repairs CA, Electrical Investigation, & Generator Platform
CN 803/TA2
Subtask 7E: Inspection 5 $1937.50 $0.00
Subtask 7F: Inspection 6 $1937.50 $0.00
Subtask 7G: Inspection 7 $1937.50 $0.00
Subtask 7H: Inspection 8 $1937.50 $0.00
Subtask 7I: Inspection 9 $1937.50 $0.00
Subtask 7J: Inspection 10 $1937.50 $0.00
Subtask 7K: Inspection 11 $1937.50 $0.00
Subtask 7L: Inspection 12 $1937.50 $0.00
Subtask 7M: Inspection 13 $1937.50 $0.00
Subtask 7N: Inspection 14 $1937.50 $0.00
Subtask 7O: Inspection 15 $1937.50 $0.00
Subtask 7P: Inspection 16 $1937.50 $0.00
Subtask 8A: Substantial Uplands 1,2&3
$5400.00 $0.00
Subtask 8B: Substantial Buildings $6550.00 $0.00
Subtask 8C: Substantial 1 & 3 Waterside Dredge & Fill
$7700.00 $0.00
Subtask 9: Final/Certifications Site�s 1,2 & 3 Uplands
$8690.00 $0.00
Subtask 10: Final/Certifications Buildings
$8980.00 $0.00
Subtask 11: Final/Certifications Site 1 & 3 Waterside Dredge & Fill
$14255.00 $0.00
Sub-Total During Construction $115,405.00 $0.00
Subtask 12: Electrical Investigation $23,252.79 $0.00
Subtask 13: Generator Platform 60% Design
$7,917.69 $0.00
Subtask 14: Generator Platform Permitting
$4,512.39 $800.00
Subtask 15: Generator Platform 100% Design
$4,903.17 $0.00
Sub-Total Electrical and Platform $40,586.04 $800.00
Overall Total Cost: $188,734.04
Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified. (Please do not alter this language)
File details come from the government source that posted it. Updated .