CN-370000-CN803-T23.pdf

PDF 417 KB Posted

Attached to
Master Agreement FL|CN803|e94021f7c01ffff2157f4f8cc3027b61
Contract number
CN803
Issued by
Florida

About this file

Document Summary

This is a Consultant's Task Assignment Notification issued by the Florida Department of Environmental Protection (FDEP), Division of Recreation and Parks. The assignment, designated as FDEP Contract No. CN803, Project Number 61231C, Task Assignment No. 23, involves The Weiler Engineering Corporation serving as the consultant for the Myakka River State Park Concession Building Floor Repairs project. The consultant's representative is Michael J. Giardullo, P.E., with Vu Nguyen serving as the FDEP Contract Manager.

The task involves transferral of incomplete construction administration subtasks from a previous contract (CN230 TA25) to support design and construction services for the Park Improvements project at Myakka River State Park. The assignment encompasses 13 subtasks including inspection services, substantial and final completion meetings, contractor submittal reviews, requests for information (RFI) responses, mechanical-electrical-plumbing (MEP) reviews and inspections, framing inspections, and various project monitoring activities. The total fixed price cost is $28,594.25 with no cost reimbursement component. The task is effective upon execution with a completion date of December 30, 2026. Payment is contingent upon FDEP approval of deliverables for each subtask. The funding is encumbered across two grant codes (37504000056) with amounts of $25,848.83 and $2,745.42 respectively.

View the file

Other files

File Type Posted
CN-370000-CN803-T10.pdf PDF
CN-370000-CN803-T10CO1.pdf PDF
CN-370000-CN803-T14.pdf PDF
CN-370000-CN803-T16.pdf PDF
CN-370000-CN803-T19.pdf PDF
CN-370000-CN803-T3.pdf PDF
CN-370000-CN803-T1.pdf PDF
CN-370000-CN803-T10.pdf.crdownload CRDOWNLOAD file
CN-370000-CN803-T11.pdf PDF
CN-370000-CN803-T13.pdf PDF
CN-370000-CN803-T2.pdf PDF
CN-370000-CN803-T22.pdf PDF
CN-370000-CN803-T25.pdf PDF
CN-370000-CN803-T26.pdf PDF
CN-370000-CN803-T4.pdf PDF
CN-370000-CN803.pdf PDF
CN-370000-CN803.pdf.crdownload CRDOWNLOAD file
CN-370000-CN803-CMC1.pdf PDF
CN-370000-CN803-T12.pdf PDF
CN-370000-CN803-T15.pdf PDF
CN-370000-CN803-T18.pdf PDF
CN-370000-CN803-T20.pdf PDF
CN-370000-CN803-T21.pdf PDF
CN-370000-CN803-T24.pdf PDF
CN-370000-CN803-T2CO1.pdf PDF
CN-370000-CN803-T30.pdf PDF
CN-370000-CN803-T6.pdf PDF
CN-370000-CN803-T6CO1.pdf PDF
CN-370000-CN803-T9.pdf PDF
CN-370000-CN803-T17.pdf PDF
CN-370000-CN803-T5.pdf PDF
CN-370000-CN803-T7.pdf PDF
CN-370000-CN803-T8.pdf PDF
CN-370000-CN803-T8CO1.pdf PDF
Show all 34

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DDivision oof RRecreation aand PParks

CConsultant’s TTask AAssignment NNotification

FFLORIDA DEPARTMENT OF

EENVIRONMENTAL PPROTECTION

DRP-084

Rev. 0 /2025 of 2

FDEP Contract No: Project Number: Task Assignment No:

Project Location Project

Consultant’s Name:

Consultant’s Representative:

Phone: Email:

FDEP Contract Manager:

Phone: Email:

Task Description:

Project Manager:

Schedule:

Start Date: Completion Date:

Fixed Price Cost: Cost Reimbursement (Not to Exceed):

Total Task Amount:

Signatures and Date:

1.

Budget Representative, FDEP Signature Date

2.

Project Manager, FDEP Signature Date

3.

Signature Date

4.

Signature Date

5.

Contract Authority, FDEP Signature Date

CN803 61231C 23

Myakka River State Park Concession Building Floor Repairs

The Weiler Engineering Corporation Michael J. Giardullo

(941) 916-8073 mgiardullo@weilerengineering.org

Vu Nguyen

(850) 245-2630 Vu.Nguyen@floridaDEP.gov

Transferral of incomplete construction administration subtasks from CN230 TA25 to support the design and construction of the Park Improvements project at Myakka River State Park, per attached proposal dated September 3, 2025.*Subtasks utilizing rates per CN230 are denoted with an asterisk (*) in the subtask heading.

John Goss

Upon Execution 12/30/2026

$28,594.25 $0.00 $28,594.25

Tamika Bass

John Goss

Michael J. Giardullo, P.E.

Vu Nguyen

Michael W. Foster, Jr., P.E.

Tamika Bass Digitally signed by Tamika Bass Date: 2025.09.08 13:21:49 -04'00'

John Goss Digitally signed by John Goss Date: 2025.09.08 15:38:18 -04'00'

Michael J. Giardullo Digitally signed by Michael J. Giardullo Date: 2025.09.11 07:37:04 -04'00'

Vu Nguyen Digitally signed by Vu Nguyen Date: 2025.09.11 10:19:16 -04'00'

Michael W. Foster Jr., P.E.

Digitally signed by Michael W. Foster Jr., P.E.

Date: 2025.09.16 14:03:51 -04'00'

DDivision oof RRecreation aand PParks

CConsultant’s TTask AAssignment NNotification

FFLORIDA DEPARTMENT OF

EENVIRONMENTAL PPROTECTION

DRP-084

Rev. /2025 2 of 2

Encumbrance Information:

Project # Grant # Organization Code Category/Yr Fund Module Object EO Amount

Total:

61231C 37504000056 080039/21 675002 U3200 131500 XR $25,848.83

61231C 37504000056 088040/24 675002 U3200 131500 XR $2,745.42

$28,594.25

September 3, 2025

Mr. John Goss Construction Project Manager Bureau of Design and Construction Florida Department of Environmental Protection 1843 S. Tamiami Trail Osprey, FL 34229

RE: Myakka River State Park Concession Building – CEI, Contract 803, TA

Dear Mr. Goss, We are pleased to offer this proposal to provide services during construction. For clarity, items with an asterisk (*) are items transferred over from the previous CN and use the old rates approved under CN 230.

For your review, the Weiler Engineering Corporation, has provided a proposal summary and man-hour documentation for the services and tasks identified.

Please feel free to contact me if you have any questions or wish to discuss matters further.

Sincerely, Michael J. Giardullo, P.E.

Director of Civil Engineering The Weiler Engineering Corporation- An Apex Company

Mr. John Goss Myakka River State Park Concession Building

CN 803 T

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702 Marathon: 6805 Overseas Highway, Marathon, Florida 33050 | Tel 305-289-4161 | Fax 305-289-4162

Myakka River State Park Concession Building CA Services

Contract Number 803, Task Assignment Number

Subtask 1: Inspection 3

Description: WEC staff will assist Client with engineering representation at (1) Progress Meeting.

Deliverable: Consultant will provide digital pdf of with meeting notes/inspection report via email within 4 days of the meeting to the FDEP Project Manager.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Fixed Price Cost:

Subtask 1: Inspection 3 Position Classification Hourly Rate

Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 2.5 $362.50

Principal in Charge 195 0 $0.00 Registered Professional Engineer

145 0.5 $72.50

Registered Engineer Intern 115 0 $0.00

Senior Engineering Designer 100 7 $700.00

Engineering Technician 80 0 $0.00

Clerical 55 0.25 $13.75

Total $1,148.75

Subtask 2: Substantial Completion Description: WEC staff will assist Client with engineering representation at one (1) Substantial Completion meeting.

Deliverable: WEC will provide representation at the Substantial Completion Meeting and deliver meeting notes/inspection report via email within 4 days of the meeting to the FDEP Project Manager.

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702 Marathon: 6805 Overseas Highway, Marathon, Florida 33050 | Tel 305-289-4161 | Fax 305-289-4162

September 3, 2025 Mr. John Goss Myakka River State Park Concession Building

CN 803 T

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Subtask 2: Substantial Completion

Position Classification Hourly Rate

Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 2.5 $362.50

Principal in Charge 195 0 $0.00 Registered Professional Engineer

145 0.5 $72.50

Registered Engineer Intern 115 0 $0.00

Senior Engineering Designer 100 7 $700.00

Engineering Technician 80 0 $0.00

Clerical 55 0.25 $13.75

Total $1,148.75

Subtask 3: Final Completion

Description: WEC staff will assist Client with engineering representation at one (1) Final Completion meeting.

Deliverable: WEC will provide representation at the Substantial Completion Meeting and deliver meeting notes/inspection report via email within 4 days of the meeting to the FDEP Project Manager.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Subtask 3: Final Completion Position Classification Hourly Rate

Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 2.5 $362.50

Principal in Charge 195 0 $0.00

Mr. John Goss Myakka River State Park Concession Building

CN 803 T

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702 Marathon: 6805 Overseas Highway, Marathon, Florida 33050 | Tel 305-289-4161 | Fax 305-289-4162

Registered Professional Engineer

145 0.5 $72.50

Registered Engineer Intern 115 0 $0.00

Senior Engineering Designer 100 7 $700.00

Engineering Technician 80 0 $0.00

Clerical 55 0.25 $13.75

Total $1,148.75

Subtask 4: Contractor Submittals

Description: WEC will assist Client in reviewing product submittals including alternates and shop drawings during construction. Where WEC’s involvement is required for submittal reviews, WEC will prepare a draft and send to the FDEP Construction Project Manager for review and comment.

Deliverable: WEC will provide digital PDFs of submittals stamped within 5 business days.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Subtask 4: Contractor Submittals

Position Classification Hourly Rate

Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 2 $290.00

Principal in Charge 195 0 $0.00 Registered Professional Engineer

145 2 $290.00

Registered Engineer Intern 115 6 $690.00

Senior Engineering Designer 100 4 $400.00

Engineering Technician 80 0 $0.00

Clerical 55 1 $55.00

Total $1,725.00

Mr. John Goss Myakka River State Park Concession Building

CN 803 T

Subtask 5: Contractor RFIs

Description: WEC will assist Client in responding to Client’s Contractor regarding any requests for additional information throughout the construction process.

Deliverable: RFI responses will be issued by WEC as digital PDFs within 3 business days.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Subtask 5: Contractor RFIs Position Classification Hourly Rate

Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 12 $1,740.00

Principal in Charge 195 0 $0.00 Registered Professional Engineer

145 1 $145.00

Registered Engineer Intern 115 4 $460.00

Senior Engineering Designer 100 4 $400.00

Engineering Technician 80 0 $0.00

Clerical 55 1 $55.00

Total $2,800.00

Subtask 6: MEP Review

Description: WEC will coordinate with Atlas Design & Engineering, Inc. who will assist the Client in responding to Client’s Contractor regarding any requests for additional information, submittal review, and general consulting throughout the construction process.

Deliverable: RFI responses will be issued by WEC as digital PDFs within 5 business days.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702

Mr. John Goss Myakka River State Park Concession Building

CN 803 T

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702 Marathon: 6805 Overseas Highway, Marathon, Florida 33050 | Tel 305-289-4161 | Fax 305-289-4162

Subtask 6: MEP Review Position Classification Hourly Rate

Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145.00 4 $580.00

Atlas Design & Engineering Inc.

Professional Engineer 249.20 6 $1,495.20

Atlas Design & Engineering Inc.

Show Drawing Review 200.20 10 $2,002.00

Atlas Design & Engineering Inc.

Project Manager 200.20 2 $400.40

Atlas Design & Engineering Inc.

Administrative 74.90 2 $149.80

Total $4,627.40

Subtask 7: MEP Inspection 2

Description: Consultant shall coordinate with Atlas Design & Engineering Inc. who will visit the site to perform a site inspection.

Deliverable: A written report will be provided in PDF format within 5 business days.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Subtask 7: MEP Inspection 2 Position Classification Hourly Rate

Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145.00 1 $145.00

Weiler Engineering Registered Engineer Intern 115.00 1 $115.00

Weiler Engineering Clerical 55.00 1 $55.00 Atlas Design & Engineering Inc.

Professional Engineer 249.20 8 $1,993.60

Atlas Design & Engineering Inc.

Project Manager 200.20 2 $400.40

Atlas Design & Engineering Inc.

Administrative 74.90 1 $74.90

Total $2,783.90

Mr. John Goss Myakka River State Park Concession Building

CN 803 T

Subtask 8: MEP Inspection 3

Description: Consultant shall coordinate with Atlas Design & Engineering Inc. who will visit the site to perform a site inspection.

Deliverable: A written report will be provided in PDF format within 5 business days.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Subtask 8: MEP Inspection 3 Position Classification Hourly Rate

Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145.00 1 $145.00

Weiler Engineering Registered Engineer Intern 115.00 1 $115.00

Weiler Engineering Clerical 55.00 1 $55.00 Atlas Design & Engineering Inc.

Professional Engineer 249.20 8 $1,993.60

Atlas Design & Engineering Inc.

Project Manager 200.20 2 $400.40

Atlas Design & Engineering Inc.

Administrative 74.90 1 $74.90

Total $2,783.90

Subtask 9: Contractor Submittals- Part II

Description: WEC will assist Client in reviewing product submittals including alternates and shop drawings during construction. Where WEC’s involvement is required for submittal reviews, WEC will prepare a draft and send to the FDEP Construction Project Manager for review and comment.

Deliverable: WEC will provide digital PDFs of submittals stamped within 5 business days.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702

Mr. John Goss Myakka River State Park Concession Building

CN 803 T

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702 Marathon: 6805 Overseas Highway, Marathon, Florida 33050 | Tel 305-289-4161 | Fax 305-289-4162

Subtask 9: Contractor Submittals- Part II

Position Classification Hourly Rate

Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 2 $290.00

Principal in Charge 195 0 $0.00 Registered Professional Engineer

145 2 $290.00

Registered Engineer Intern 115 6 $690.00

Senior Engineering Designer 100 4 $400.00

Engineering Technician 80 0 $0.00

Clerical 55 1 $55.00

Total $1,725.00

Subtask 10: Contractor RFI- Part II

Description: WEC will assist Client in responding to Client’s Contractor regarding any requests for additional information throughout the construction process.

Deliverable: RFI responses will be issued by WEC as digital PDFs within 3 business days.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Subtask 10: Contractor RFIs- Part II

Position Classification Hourly Rate

Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 2 $290.00

Principal in Charge 195 0 $0.00 Registered Professional Engineer

145 2 $290.00

Registered Engineer Intern 115 6 $690.00

Senior Engineering Designer 100 4 $400.00

Engineering Technician 80 0 $0.00

Clerical 55 1 $55.00

Total $1,725.00

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702

September 3, 2025 Mr. John Goss Myakka River State Park Concession Building

CN 803 T

Subtask 11: Post Demo MEP

Description: Consultant shall coordinate with Atlas Design & Engineering Inc. who will visit the site to perform a site inspection.

Deliverable: A written report will be provided in PDF format within 5 business days.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Subtask 11: Post Demo MEP Position Classification Hourly Rate

Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145.00 1 $145.00

Weiler Engineering Registered Engineer Intern 115.00 1 $115.00

Weiler Engineering Clerical 55.00 1 $55.00 Atlas Design & Engineering Inc.

Professional Engineer 249.20 8 $1,993.60

Atlas Design & Engineering Inc.

Project Manager 200.20 2 $400.40

Atlas Design & Engineering Inc.

Administrative 74.90 1 $74.90

Total $2,783.90

Subtask 12: Framing Inspection

Description: WEC will complete (1) site visit to complete a framing inspection.

Deliverable: Consultant shall deliver an inspection report as a digital PDF within 3 business days.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Subtask 12: Framing Inspection Position Classification Hourly Rate

Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 1 $145.00

Principal in Charge 195 0 $0.00

Mr. John Goss Myakka River State Park Concession Building

CN 803 T

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702 Marathon: 6805 Overseas Highway, Marathon, Florida 33050 | Tel 305-289-4161 | Fax 305-289-4162

Registered Professional Engineer

145 2 $290.00

Registered Engineer Intern 115 8 $920.00

Senior Engineering Designer 100 0 $0.00

Engineering Technician 80 0 $0.00

Clerical 55 1 $55.00

Total $1,410.00

Subtask 13: MEP Substantial Completion Inspection

Description: Consultant shall coordinate with Atlas Design & Engineering Inc. who will visit the site to perform a site inspection and provide a punchlist.

Deliverable: A written report and punchlist will be provided in PDF format within 5 business days.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Subtask 13: MEP Substantial Completion

Position Classification Hourly Rate

Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145.00 1 $145.00 Weiler Engineering Registered Engineer Intern 115.00 1 $115.00

Weiler Engineering Clerical 55.00 1 $55.00 Atlas Design & Engineering Inc.

Professional Engineer 249.20 8 $1,993.60

Atlas Design & Engineering Inc.

Project Manager 200.20 2 $400.40

Atlas Design & Engineering Inc.

Administrative 74.90 1 $74.90

Total $2,783.90

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702

September 3, 2025 Mr. John Goss Myakka River State Park Concession Building

CN 803 T

Project Schedule:

Activity Duration (Calendar Days) Dates to be based on date of execution of task order

Subtask’s 1-13 TBD TBD

Summary of Fees:

Subtask Subtask Fixed Price Cost Subtask Reimbursable Subtask 1: Inspection 3 $1,148.75 $0.00

Subtask 2: Substantial Completion

$1,148.75 $0.00

Subtask 3: Final Completion $1,148.75 $0.00

Subtask 4: Contractor Submittals

$1,725.00 $0.00

Subtask 5: Contractor RFIs $2,800.00 $0.00

Subtask 6: MEP Review $4,627.40 $0.00

Subtask 7: MEP Inspection 2 $2,783.90 $0.00 Subtask 8: MEP Inspection 3 $2,783.90 $0.00 Subtask 9: Contractor Submittals- Part II

$1,725.00 $0.00

Subtask 10: Contractor RFIs- Part II

$1,725.00 $0.00

Subtask 11: Post Demo MEP $2,783.90 $0.00 Subtask 12: Framing Inspection $1,410.00 $0.00 Subtask 13: MEP Substantial Completion

$2,783.90 $0.00

Total during Construction $28,594.25 $0.00 Overall Total Cost: $28,594.25

Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified. (Please do not alter this language)

File details come from the government source that posted it. Updated .