This document is a Task Assignment Change Order Form (Change Order No. 4) issued by the Florida Department of Environmental Protection (FDEP) for Agreement CN331 with Humiston & Moore Engineers. The project involves seawall replacement and riverbank stabilization at Hillsborough River State Park in Florida. The change order was authorized by FDEP's Bureau of Design and Construction and signed by all required parties between October 22 and November 6, 2024.
Change Order No. 4 reinstates the original Subtask 4 (redesignated as Subtask 9) for processing of State and County environmental permits, including environmental support services from ESA. The subtask encompasses permit application preparation and filing with the Southwest Florida Water Management District (SWFWMD) and the Hillsborough County Environmental Protection Commission/Permit Technical Branch (HEPC/PTB). The work is budgeted at a fixed price of $10,043.80 with no reimbursable costs, comprised of Project Manager hours (15 hours at $206.00), Engineer II hours (25 hours at $96.00), AutoCAD Tech II hours (10 hours at $85.00), and ESA Chief Scientist hours (20 hours at $185.19). The maximum duration for permit processing is 150 calendar days from authorization, with the task end date established as July 27, 2026. Payment will be issued upon FDEP approval of deliverables, which include copies of all state and local authorizations provided to the Project Manager.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT CHANGE ORDER FORM
( ) Page 1 of 1
Required Signatures: Adobe Signature
FDEP Contract No.: Task Assignment No.: Change Order No.: Project No.:
Project Location: Project Name:
Consultant Name:
Consultant Representative: Phone: Email:
FDEP Contract Manager: Phone: Email:
Description and Justification of Change:
Change in Task Amount:
Item Reimbursement Fixed Fee Total
Original Task Amount:
Task amount including all previous Change Orders:
Net increase/decrease in task amount for this Change Order:
Total Amounts with all Change Orders:
Change in Task Time:
Original Task Execution Date:
Original Task End Date:
Present Task End Date:
Net Change in Days:
New Task End Date:
Approval Signatures:
Budget Representative, FDEP Signature Date
Project Manager, FDEP Signature Date
Contract Manager, FDEP Signature Date
Consultant Signature Date
Contract Authority, FDEP Signature Date
Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount
29 Digit FLAIR Code: Total:
CN331 TA13 CO4 61265C
Hillsborough River State Park Riverbank Stabilization
Humiston & Moore Engineers
Brett D. Moore, P.E. 239-825-6518 bdm@humistonandmoore.com
Ralph Perkins 850-245-2460 ralph.perkins@floridadep.gov
To reinstate the original Subtask 4 for processing of State and County environmental permits, with environmental support from ESA, per the attached dated 09/20/2024.
$ 0.00 $ 50,896.61 $ 50,896.61 $ 713.00 $ 130,564.60 $ 131,277.60 $ 0.00 $ 10,043.80 $ 10,043.80
$ 713.00 $ 140,608.40 $ 141,321.40
12/16/2019
03/10/2021
07/27/2026
07/27/2026
Tamika Bass Tamika Bass Digitally signed by Tamika Bass Date: 2024.10.22 13:23:18 -04'00'
Richard Marcil Richard Rene Marcil, III Digitally signed by Richard Rene Marcil, III Date: 2024.10.22 15:11:47 -04'00'
Ralph Perkins Ralph M Perkins Digitally signed by Ralph M Perkins Date: 2024.10.23 08:53:03 -04'00'
Brett D. Moore, P.E. Brett D. Moore Digitally signed by Brett D. Moore Date: 2024.10.23 12:00:34 -04'00'
Bryan Bradner Bryan Bradner Digitally signed by Bryan Bradner Date: 2024.11.06 15:31:46 -05'00'
61265C 37504015037 100718/00 675005 U1300 131500 X2 $ 10,043.80
$ 10,043.80