CN-370000-CN331-T17CO1.pdf
PDF 600 KB Posted
- Contract number
- CN331
- Issued by
- Florida
About this file
This is a Task Assignment Change Order Form (Change Order No. 1) issued by the Florida Department of Environmental Protection (FDEP) for Contract CN331, a beach renourishment project located at Honeymoon Island State Park. The consultant is Humiston & Moore Engineers, with Brett Moore, P.E. serving as the consultant representative, and Ralph Perkins as the FDEP Contract Manager. The change order was approved by FDEP personnel including Budget Representative Tamika Bass, Project Manager Terry McCullum Jr., Contract Manager Ralph Perkins, and Contract Authority Bryan Bradner, with all parties executing digital signatures on February 13, 2025.
The change order modifies Task Assignment 17 for post-construction monitoring services by updating the scope and timing of the 48-month post-construction survey to be conducted in August 2024 instead of August 2025 and eliminating the borrow area from the survey scope. This modification results in a net cost reduction of $9,974.00, reducing the total fixed fee from $174,238.00 to $164,264.00. The change removes two subtasks (3a and 3b) originally scheduled for August 2025, crediting $31,070.00 and $30,334.00 respectively, and replaces them with two new subtasks (3c and 3d) for August 2024 monitoring survey ($25,070.00) and monitoring report and analysis ($26,360.00). The new subtasks involve beach profile surveys conducted by Sea Diversified and engineering analysis by Humiston & Moore Engineers, with deliverables including electronic survey data in DEP format and a monitoring report with aerial photographs. The task end date remains December 31, 2025, with no change in the overall task timeline.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT CHANGE ORDER FORM
( ) Page 1 of 1
Required Signatures: Adobe Signature
FDEP Contract No.: Task Assignment No.: Change Order No.: Project No.:
Project Location: Project Name:
Consultant Name:
Consultant Representative: Phone: Email:
FDEP Contract Manager: Phone: Email:
Description and Justification of Change:
Change in Task Amount:
Item Reimbursement Fixed Fee Total
Original Task Amount:
Task amount including all previous Change Orders:
Net increase/decrease in task amount for this Change Order:
Total Amounts with all Change Orders:
Change in Task Time:
Original Task Execution Date:
Original Task End Date:
Present Task End Date:
Net Change in Days:
New Task End Date:
Approval Signatures:
Budget Representative, FDEP Signature Date
Project Manager, FDEP Signature Date
Contract Manager, FDEP Signature Date
Consultant Signature Date
Contract Authority, FDEP Signature Date
Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount
29 Digit FLAIR Code: Total:
CN331 17 1 6H401
Beach Renourishment
Humiston & Moore Engineers
Brett Moore, P.E. (239) 594-2021 bdm@humistonandmoore.com
Ralph Perkins or successor (850) 245-2460 Ralph.Perkins@FloridaDEP.gov
Modification to original task assignment: updated scope and timing of the 48-month post construction survey to be conducted in 2024 instead of 2025 and cost reduction due to the survey not including the borrow area, per attached proposal dated February 6, 2025.
$ 0.00 $ 174,238.00 $ 174,238.00 $ 0.00 $ 174,238.00 $ 174,238.00 $ 0.00 -$ 9,974.00 -$ 9,974.00 $ 0.00 $ 164,264.00 $ 164,264.00
10/05/2021
12/31/2025
12/31/2025
12/31/2025
Tamika Bass
Terry McCullum, Jr.
Ralph Perkins
Brett Moore, P.E.
Bryan Bradner
6H401 37504008120 080039/22 423001 U3200 131500 QK -$ 9,974.00
-$ 9,974.00
February 6, 2025
Terry McCullum, Jr., Design Project Manager Bureau of Design and Construction Florida Department of Environmental Protection 3900 Commonwealth Boulevard, MS 520 Tallahassee, FL 32399
RE: Contract CN331
North Beach Renourishment Task Assignment 17, Post-Construction Monitoring Change Order #1 / 48-month survey and scope
Dear Terry, For your review, Humiston & Moore Engineers has updated the scope and timing of the 48-month post construction survey to be conducted in 2024 instead of 2025 and for the survey to not include the borrow area. The results are a reduction in costs and are updated in the following scope of work and related costs.
This change was verified with the staff of the Florida DEP Joint Coastal Permitting staff and related emails indicating this change are also attached for compliance with the state approved Physical Monitoring Plan.
Please let me know if you have any questions.
Sincerely, HUMISTON & MOORE ENGINEERS
Brett D. Moore, P.E., BC.CE.
President
Construction Administration Services Honeymoon Island Sand Placement Monitoring Contract Number CN331, Task Assignment Number 17
Change Order #1
Description: Post-Construction Monitoring
The following services are related to the post-construction monitoring of the Beach Nourishment Project at North Beach on Honeymoon Island State park. The project involved the dredging of sand from the sand spit at the south end of Honeymoon Island and the 2015 Borrow Area and placement of that sand within the authorized beach fill area along North Beach fronting the North and Oasis parking areas. Surveys will be conducted by approved hydrographic surveying subconsultants as part of the Humiston & Moore Engineers (H&M) team. H&M will work closely with the DEP Bureau of Design and Construction (BDC) staff and appointed representative for this project.
Subtask 3a: 48-Month Post Construction Survey (August 2025): Subtask should be removed from the task assignment and credited.
Deliverable 3a: Subtask to be removed.
Performance Measure: Subtask to be removed.
Total Credit for Subtask 3a: ($31,070.00)
Subtask 3b: 48-Month Post Construction Monitoring Report (August 2025): Subtask should be removed from the task assignment and credited.
Deliverable 3b: Subtask to be removed.
Performance Measure: Subtask to be removed.
Total Credit for Subtask 3b: ($30,334.00)
Subtask 3c: 48-Month Post Construction Survey (August 2024): Conduct beach profile surveys in or near August 2024. Coordinate with surveyor on site, post and check data and initial plots. Changes from schedule will be coordinated with DEP and BDC staff in advance.
Deliverable 3c: Electronic copy containing August 2024 beach and T-groin profiles survey data in DEP format.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price: $25,070.00 Subtask 3c August 2024 Monitoring Survey (Beach Profiles)
Firm Name Position Classification Hourly Rate
Hours Total Fixed Price Cost
Sea Diversified 3-Person Hydro Survey Crew $165.00 38 $6,270.00 Sea Diversified 3-Person GPS Survey Crew $160.00 38 $6,080.00 Sea Diversified Computer/CADD $90.00 20 $1,800.00
Sea Diversified Survey Technician $90.00 16 $1,440.00 Sea Diversified Prof. Surveyor & Mapper $130.00 10 $1,300.00 Sea Diversified Project Manager $150.00 4 $600.00 Sea Diversified Hydrographic Survey System $680/Day 7 Days $4,760.00 Humiston & Moore Eng. Project Manager / P.E. $206.00 2 $412.00 Humiston & Moore Eng. Senior Engineer $172.00 1 $172.00 Humiston & Moore Eng. Engineer II $96.00 8 $768.00 Humiston & Moore Eng. Engineer I $94.00 12 $1,128.00 Humiston & Moore Eng. AutoCAD Technician II $85.00 4 $340.00
Subtotal $25,070.00 Total for Subtask 3c: $ 25,070.00
Subtask 3d: 48-Month Post Construction Monitoring Report: Obtain oblique site aerials and on-site aerials by a small, unmanned aircraft piloted by H&M staff certified to operate an unmanned aircraft, merge for vertical aerial image, conduct engineering analysis of survey data, prepare technical report of shoreline change, volumetric change, and project performance evaluation.
Deliverable 3d: Electronic copy containing monitoring analysis of August 2024 survey data, report and aerial photographs in pdf.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price: $26,360.00 Subtask 3d August 2024 Monitoring Report and Analysis Firm Name Position Classification Hourly
Rate Hours Total Fixed
Price Cost Humiston & Moore Eng. Project Manager / P.E. $206.00 24 $4,944.00 Humiston & Moore Eng. Senior Engineer $172.00 12 $2,064.00 Humiston & Moore Eng. Engineer III $123.00 24 $2,952.00 Humiston & Moore Eng. Engineer II $96.00 24 $2,304.00 Humiston & Moore Eng. Engineer I $94.00 100 $9,400.00 Humiston & Moore Eng. AutoCAD Technician II $85.00 40 $3,400.00 Humiston & Moore Eng. AutoCAD/Science Tech $81.00 16 $1,296.00
Subtotal $26,360.00 Total for Subtask 3d: $ 26,360.00
Project Schedule:
Activity Duration (Calendar Days)
Subtask 3c: 48-Month Monitoring Survey (August 2024) 10 Subtask 3d: Monitoring Report & Analysis August 2024 data 240
Summary of Fees:
Activity - Monitoring Subtask Fixed Price Cost
Subtask 3a: 48-Month Monitoring Survey (August 2025) ($3 ,070.00)
Subtask 3b: Monitoring Report & Analysis August 2025 data ($30,334.00) Subtask 3c: 48-Month Monitoring Survey (August 2024) $25,070.00 Subtask 3d: Monitoring Report & Analysis August 2024 data $26,360.00 Subtotal Fixed Price Cost Monitoring Services ($9,974.00) Reimbursable Price $0.00 Total Contract, or Task Assignment Price: (Subtask 3a through 3d) ($9,974.00)
Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified.