This is a Task Assignment Change Order Form (Change Order #2) issued by the Florida Department of Environmental Protection (FDEP) for a consulting services contract with Humiston & Moore Engineers regarding the Interim Beach Nourishment project at Gasparilla Island State Park in Lee County, Florida. The contract is administered by FDEP's Bureau of Design and Construction, with Ralph Perkins serving as the FDEP Contract Manager and Brett Moore, P.E., representing the consultant. All required approvals have been obtained as evidenced by digital signatures from Budget Representative Tamika Bass, Project Manager Garland Sandel, Contract Manager Ralph Perkins, Consultant Brett Moore, and Contract Authority Bryan Bradner, with signatures dated between July 26 and August 13, 2024.
This change order authorizes consulting services for the construction phase and post-construction certification of the beach nourishment project, including construction observation and project management over an estimated 120-day construction period, substantial completion walkthrough, post-construction report preparation, certifications for state and federal permits, and post-construction monitoring surveys and analysis. The net increase in task amount for this change order is $144,335.52, comprised of $137,820.00 in fixed fees and $6,515.52 in reimbursable costs for travel and mileage. The total cumulative contract value including all previous change orders is $290,703.52. The task execution period runs from August 3, 2023, through July 27, 2026, with no change to the original end date. Subtasks span sixteen weeks of construction observation support with weekly site meetings, followed by post-construction phases including monitoring surveys and technical reporting, with costs allocated through specific deliverables such as weekly meeting summaries, certifications, and monitoring analysis reports.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT CHANGE ORDER FORM
( ) Page 1 of 1
Required Signatures: Adobe Signature
FDEP Contract No.: Task Assignment No.: Change Order No.: Project No.:
Project Location: Project Name:
Consultant Name:
Consultant Representative: Phone: Email:
FDEP Contract Manager: Phone: Email:
Description and Justification of Change:
Change in Task Amount:
Item Reimbursement Fixed Fee Total
Original Task Amount:
Task amount including all previous Change Orders:
Net increase/decrease in task amount for this Change Order:
Total Amounts with all Change Orders:
Change in Task Time:
Original Task Execution Date:
Original Task End Date:
Present Task End Date:
Net Change in Days:
New Task End Date:
Approval Signatures:
Budget Representative, FDEP Signature Date
Project Manager, FDEP Signature Date
Contract Manager, FDEP Signature Date
Consultant Signature Date
Contract Authority, FDEP Signature Date
Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount
29 Digit FLAIR Code: Total:
CN331 TA22 CO2 ARPLE1
Gasparilla Island State Park Beach Re-Nourishment
Humiston & Moore Engineers
Brett Moore, P.E. 239-566-0649 bdm@humistonandmoore.com
Ralph Perkins 850-245-2560 Ralph.Perkins@FloridaDEP.gov
Change Order is to address the necessary tasks needed for the construction phase, and post construction certification for the project. Per Propasal date 7-23-24
$ 0.00 $ 112,550.00 $ 112,550.00 $ 0.00 $ 146,368.00 $ 146,368.00
$ 6,515.52 $ 137,820.00 $ 144,335.52 $ 6,515.52 $ 284,188.00 $ 290,703.52
08/03/2023
07/27/2026
07/27/2026
07/27/2026
Tamika Bass Tamika Bass Digitally signed by Tamika Bass Date: 2024.07.26 10:25:14 -04'00'
Garland Sandel Garland Sandel Digitally signed by Garland Sandel Date: 2024.07.26 13:26:54 -04'00'
Ralph Perkins Ralph M Perkins Digitally signed by Ralph M Perkins Date: 2024.07.29 10:03:13 -04'00'
Brett Moore, P.E. Brett D. Moore Digitally signed by Brett D. Moore Date: 2024.07.29 12:24:39 -04'00'
Bryan Bradner Bryan Bradner Digitally signed by Bryan Bradner Date: 2024.08.13 10:31:52 -04'00'
ARPLE1 37536050000 140126/22 423001 U1671 241000 QY $ 144,335.52