CN-370000-CN331-T21CO3.pdf

PDF 500 KB Posted

Attached to
Master Agreement FL|CN331|fe7bede2f31aebfb9d3246ac73b5aa57
Contract number
CN331
Issued by
Florida

About this file

This is a Task Assignment Change Order No. 3 issued by the Florida Department of Environmental Protection (FDEP) under Agreement CN331 with Humiston & Moore Engineers, a coastal engineering firm based in Florida. The change order modifies Task Assignment No. 21 for the Interim Beach Nourishment project at Honeymoon Island State Park. The document was executed on June 2, 2025, with signatures from FDEP's Budget Representative (Tamika Bass), Project Manager (Terry McCullum Jr.), Contract Manager (Ralph Perkins), Contract Authority (Bryan Bradner), and the consultant representative (Brett D. Moore, P.E.).

The change order adds post-construction monitoring services and hurricane impact assessments for the 2025 beach nourishment project, with a total fixed price of $194,998.00. Services include four monitoring phases: 12-month post-construction survey and analysis (Subtasks 7a and 7b, $51,430.00); 24-month monitoring survey and analysis (Subtasks 8a and 8b, $61,404.00); 48-month monitoring survey and analysis (Subtasks 9a and 9b, $61,404.00); and post-hurricane impact assessments for Hurricanes Debby, Helene, and Milton (Subtasks 10a, 10b, and 10c, $20,760.00). All services are provided on a fixed-fee basis with no reimbursable expenses. Monitoring activities are scheduled to occur in August 2025, August 2026, and August 2028, with hurricane assessments to support Category G FEMA Funding Assistance applications. Payment is contingent upon FDEP approval of deliverables for each subtask. The task end date remains July 27, 2026, with zero net change in schedule from the previous change order.

View the file

Other files

File Type Posted
CN-370000-CN331-CMC5.pdf PDF
CN-370000-CN331-T13CO4.pdf PDF
CN-370000-CN331-T15CO1.pdf PDF
CN-370000-CN331-T16.pdf PDF
CN-370000-CN331-T17.pdf PDF
CN-370000-CN331-T17CO1.pdf PDF
CN-370000-CN331-T18CO4.pdf PDF
CN-370000-CN331-T19.pdf PDF
CN-370000-CN331-T1CO1.pdf PDF
CN-370000-CN331-T20.pdf PDF
CN-370000-CN331-T4CO2.pdf PDF
CN-370000-CN331-T4CO3.pdf PDF
CN-370000-CN331-T7.pdf PDF
CN-370000-CN331-CMC2.pdf PDF
CN-370000-CN331-R1.pdf PDF
CN-370000-CN331-T11.pdf PDF
CN-370000-CN331-T13CO2.pdf PDF
CN-370000-CN331-T16CO1.pdf PDF
CN-370000-CN331-T18CO1.pdf PDF
CN-370000-CN331-T18CO2.pdf PDF
CN-370000-CN331-T21.pdf PDF
CN-370000-CN331-T22CO1.pdf PDF
CN-370000-CN331-T22CO3.pdf PDF
CN-370000-CN331-T23.pdf PDF
CN-370000-CN331-T23CO1.pdf PDF
CN-370000-CN331-T24.pdf PDF
CN-370000-CN331-T3C01.pdf PDF
CN-370000-CN331-T4.pdf PDF
CN-370000-CN331-TA6.pdf PDF
CN-370000-CN331.pdf PDF
CN-370000-CN331-CMC3.pdf PDF
CN-370000-CN331-T13CO1.pdf PDF
CN-370000-CN331-T14.pdf PDF
CN-370000-CN331-T15.pdf PDF
CN-370000-CN331-T18.pdf PDF
CN-370000-CN331-T21CO2.pdf PDF
CN-370000-CN331-T22.pdf PDF
CN-370000-CN331-T22CO2.pdf PDF
CN-370000-CN331-T8.pdf PDF
CN-370000-CN331-CMC1.pdf PDF
CN-370000-CN331-CMC4.pdf PDF
CN-370000-CN331-T1.pdf PDF
CN-370000-CN331-T10.pdf PDF
CN-370000-CN331-T12.pdf PDF
CN-370000-CN331-T13.pdf PDF
CN-370000-CN331-T13CO3.pdf PDF
CN-370000-CN331-T16CO2.pdf PDF
CN-370000-CN331-T1CO2.pdf PDF
CN-370000-CN331-T1CO3.pdf PDF
CN-370000-CN331-T1CO4.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Florida Department of Environmental Protection

TASK ASSIGNMENT CHANGE ORDER FORM

( ) Page 1 of 1

Required Signatures: Adobe Signature

FDEP Contract No.: Task Assignment No.: Change Order No.: Project No.:

Project Location: Project Name:

Consultant Name:

Consultant Representative: Phone: Email:

FDEP Contract Manager: Phone: Email:

Description and Justification of Change:

Change in Task Amount:

Item Reimbursement Fixed Fee Total

Original Task Amount:

Task amount including all previous Change Orders:

Net increase/decrease in task amount for this Change Order:

Total Amounts with all Change Orders:

Change in Task Time:

Original Task Execution Date:

Original Task End Date:

Present Task End Date:

Net Change in Days:

New Task End Date:

Approval Signatures:

Budget Representative, FDEP Signature Date

Project Manager, FDEP Signature Date

Contract Manager, FDEP Signature Date

Consultant Signature Date

Contract Authority, FDEP Signature Date

Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount

29 Digit FLAIR Code: Total:

CN331 21 3 61457C

Beach Re-nourishment

Humiston & Moore Engineers

Brett D. Moore, P.E. (239) 566-0649 bdm@humistonandmoore.com

Ralph Perkins or successor (850) 245-2460 Ralph.Perkins@FloridaDEP.gov

Construction administration services for breakwater structure installation and post storm assessments at Honeymoon Island State Park, per attached proposal dated February 25, 2025.

$ 7,483.84 $ 458,007.75 $ 465,491.59 $ 14,967.68 $ 691,049.75 $ 706,017.43

$ 0.00 $ 194,998.00 $ 194,998.00 $ 14,967.68 $ 886,047.75 $ 901,015.43

06/16/2023

07/27/2026

07/27/2026

07/27/2026

Tamika Bass Tamika Bass Digitally signed by Tamika Bass Date: 2025.05.02 13:03:05 -04'00'

Terry McCullum, Jr. Terry McCullum Jr.

Digitally signed by Terry McCullum Jr.

Date: 2025.05.06 09:39:45 -04'00'

Ralph Perkins Ralph M Perkins Digitally signed by Ralph M Perkins Date: 2025.05.08 10:43:45 -04'00'

Brett D. Moore, P.E. Brett D. Moore Digitally signed by Brett D. Moore Date: 2025.05.08 10:52:44 -04'00'

Bryan Bradner Bryan Bradner Digitally signed by Bryan Bradner Date: 2025.06.02 14:41:07 -04'00'

61457C 37504008120 080041/23 423001 U3200 131500 QK $ 194,998.00

$ 194,998.00

Honeymoon Island State Park c:\users\mccullum_t\documents\projects\honeymoon island\arppi2-61457c\proposal\co3\2025-02-25 honeymoon island task 21-post-construction-monitoring co#3.docx

February 25, 2025

Terry McCullum, Jr., Design Project Manager Bureau of Design and Construction Florida Department of Environmental Protection 3900 Commonwealth Boulevard, MS 520 Tallahassee, FL 32399

RE: DEP Agreement CN331 - Humiston & Moore Engineers Honeymoon Island State Park Change Order #3 Interim Beach Nourishment Task Assignment Number – 21

Dear Mr. McCullum, Jr.

In reference to direction from DEP JCP staff relating to physical monitoring requirements for the 2024/5 interim beach restoration project under construction at this time, we are providing this Change Order #3 to include the required post construction monitoring beginning one year post construction which will be August 2025 to remain consistent with annual monitoring surveys for this project and to provide a post hurricanes Debby, Helene, and Milton impact assessment for filing for FEMA funding assistance.

The scope for the post construction monitoring and FEMA storm impact assessment is provided in the following breakdown of tasks and costs. These are the same rates and relative costs approved under the main contract for the 2021 project (Task 17).

As noted above, this Change Order includes evaluation of impacts from Hurricanes Debby, Helene, and Milton in 2024 utilizing pre-storm monitoring data and post storm pre-construction data. The evaluation will be conducted to determine eligibility for Category G FEMA Funding Assistance based on sand losses from an engineered beach.

Sincerely, HUMISTON & MOORE ENGINEERS

Brett D. Moore, P.E., BC.DE.

President c:\users\mccullum_t\documents\projects\honeymoon island\arppi2-61457c\proposal\co3\2025-02-25 honeymoon island task 21-post-

Interim Beach Nourishment at Honeymoon Island State Park

CN331 - TA #21 Change Order No. 3

Description: Post Construction Monitoring Phase The following services are related to the post-construction monitoring of the 2025 Beach Nourishment Project at North Beach on Honeymoon Island State park. The project involved the dredging of sand from the sand spit at the south end of Honeymoon Island and the offshore Borrow Area used in 2021 and placement of that sand within the authorized beach fill area along North Beach fronting the North and Oasis parking areas. Surveys will be conducted by approved hydrographic surveying subconsultants as part of the Humiston & Moore Engineers (H&M) team. H&M will work closely with the DEP Bureau of Design and Construction (BDC) staff and appointed representative for this project.

Subtask 7a: 12-Month Post Construction Survey: Conduct beach profile surveys and analysis in or near August 2025. Coordinate with surveyor on site, post and check data and initial plots. Changes from schedule will be coordinated with DEP and BDC staff in advance.

Deliverable 7a: Electronic copy containing August 2025 beach and T-groin profiles survey data in DEP format.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Fixed Price: 25,070.00

Subtask 7a August 2025 Monitoring Survey (Beach Profiles) Firm Name Position Classification Hourly

Rate Hours Total Fixed

Price Cost Sea Diversified 3-Person Hydro Survey Crew $165.00 38 $6,270.00 Sea Diversified 3-Person GPS Survey Crew $160.00 38 $6,080.00 Sea Diversified Computer/CADD $90.00 20 $1,800.00 Sea Diversified Survey Technician $90.00 16 $1,440.00 Sea Diversified Prof. Surveyor & Mapper $130.00 10 $1,300.00 Sea Diversified Project Manager $150.00 4 $600.00 Sea Diversified Hydrographic Survey System $680/Day 7 Days $4,760.00 Humiston & Moore Eng. Project Manager / P.E. $206.00 2 $412.00 Humiston & Moore Eng. Senior Engineer $172.00 1 $172.00 Humiston & Moore Eng. Engineer II $96.00 8 $768.00 Humiston & Moore Eng. Engineer I $94.00 12 $1,128.00 Humiston & Moore Eng. AutoCAD Technician II $85.00 4 $340.00 Subtotal $25,070.00

Total for Subtask 7a: $ 25,070.00

Subtask 7b: 12-Month Post Construction Monitoring Report: Obtain oblique site aerials and on-site aerials by a small, unmanned aircraft piloted by HM staff certified to operate an unmanned aircraft, merge for vertical aerial image, conduct engineering analysis of survey data, prepare technical report of shoreline change, volumetric change, and project performance evaluation.

Deliverable 7b: Electronic copy containing monitoring analysis of August 2025 survey data, report and aerial photographs in pdf.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

c:\users\mccullum_t\documents\projects\honeymoon island\arppi2-61457c\proposal\co3\2025-02-25 honeymoon island task 21-post-

Fixed Price: $26,360.00

Subtask 7b August 2025 Monitoring Report and Analysis Firm Name Position Classification Hourly

Rate Hours Total Fixed

Price Cost Humiston & Moore Eng. Project Manager / P.E. $206.00 24 $4,944.00 Humiston & Moore Eng. Senior Engineer $172.00 12 $2,064.00 Humiston & Moore Eng. Engineer III $123.00 24 $2,952.00 Humiston & Moore Eng. Engineer II $96.00 24 $2,304.00 Humiston & Moore Eng. Engineer I $94.00 100 $9,400.00 Humiston & Moore Eng. AutoCAD Technician II $85.00 40 $3,400.00 Humiston & Moore Eng. AutoCAD/Science Tech $81.00 16 $1,296.00 Subtotal $26,360.00

Total for Subtask 7b: $ 26,360.00

Subtask 8a: 24-Month Post Construction Survey: Conduct beach profile surveys and borrow area survey in or near August 2026. Coordinate with surveyor on site, post and check data and initial plots. Changes from schedule will be coordinated with DEP and BDC staff in advance.

Deliverable 8a: Electronic copy containing August 2026 borrow area, beach and T-groin profiles survey data in DEP format.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Fixed Price: $31,070.00

Subtask 8a August 2026 Monitoring Survey (Beach Profiles and Borrow Area) Firm Name Position Classification Hourly

Rate Hours Total Fixed

Price Cost Sea Diversified 3-Person Hydro Survey Crew $165.00 50 $8,250.00 Sea Diversified 3-Person GPS Survey Crew $160.00 56 $8,960.00 Sea Diversified Computer/CADD $90.00 24 $2,160.00 Sea Diversified Survey Technician $90.00 16 $1,440.00 Sea Diversified Prof. Surveyor & Mapper $130.00 16 $2,080.00 Sea Diversified Project Manager $150.00 4 $600.00 Sea Diversified Hydrographic Survey System $680/Day 7 Days $4,760.00 Humiston & Moore Eng. Project Manager / P.E. $206.00 2 $412.00 Humiston & Moore Eng. Senior Engineer $172.00 1 $172.00 Humiston & Moore Eng. Engineer II $96.00 8 $768.00 Humiston & Moore Eng. Engineer I $94.00 12 $1,128.00 Humiston & Moore Eng. AutoCAD Technician II $85.00 4 $340.00 Subtotal $31,070.00

Total for Subtask 8a: $ 31,070.00

Subtask 8b: 24-Month Post Construction Monitoring Report: Obtain oblique site aerials and on-site aerials by a small, unmanned aircraft piloted by HM staff certified to operate an unmanned aircraft, merge for vertical aerial image, conduct engineering analysis of survey data, prepare technical report of shoreline change, volumetric change, and project performance evaluation.

c:\users\mccullum_t\documents\projects\honeymoon island\arppi2-61457c\proposal\co3\2025-02-25 honeymoon island task 21-post-

Deliverable 8b: Electronic copy containing monitoring analysis of August 2026 survey data, report and aerial photographs in pdf.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Fixed price: $30,334.00

Subtask 8b August 2026 Monitoring Report and Analysis Firm Name Position Classification Hourly

Rate Hours Total Fixed

Price Cost Humiston & Moore Eng. Project Manager / P.E. $206.00 24 $4,944.00 Humiston & Moore Eng. Senior Engineer $172.00 12 $2,064.00 Humiston & Moore Eng. Engineer III $123.00 30 $3,690.00 Humiston & Moore Eng. Engineer II $96.00 40 $3,840.00 Humiston & Moore Eng. Engineer I $94.00 100 $9,400.00 Humiston & Moore Eng. AutoCAD Technician II $85.00 60 $5,100.00 Humiston & Moore Eng. AutoCAD/Science Tech $81.00 16 $1,296.00 Subtotal $30,334.00

Total for Subtask 8b: $ 30,334.00

Subtask 9a: 48-Month Post Construction Survey: Conduct beach profile surveys and borrow area survey in or near August 2028. Coordinate with surveyor on site, post and check data and initial plots. Changes from schedule will be coordinated with DEP and BDC staff in advance.

Deliverable 6c: Electronic copy containing August 2028 borrow area, beach and T-groin profiles survey data in DEP format.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Fixed Price: $ 31,070.00

Subtask 9a August 2028 Monitoring Survey (Beach Profiles and Borrow Area) Firm Name Position Classification Hourly

Rate Hours Total Fixed

Price Cost Sea Diversified 3-Person Hydro Survey Crew $165.00 50 $8,250.00 Sea Diversified 3-Person GPS Survey Crew $160.00 56 $8,960.00 Sea Diversified Computer/CADD $90.00 24 $2,160.00 Sea Diversified Survey Technician $90.00 16 $1,440.00 Sea Diversified Prof. Surveyor & Mapper $130.00 16 $2,080.00 Sea Diversified Project Manager $150.00 4 $600.00 Sea Diversified Hydrographic Survey System $680/Day 7 Days $4,760.00 Humiston & Moore Eng. Project Manager / P.E. $206.00 2 $412.00 Humiston & Moore Eng. Senior Engineer $172.00 1 $172.00 Humiston & Moore Eng. Engineer II $96.00 8 $768.00 Humiston & Moore Eng. Engineer I $94.00 12 $1,128.00 Humiston & Moore Eng. AutoCAD Technician II $85.00 4 $340.00 Subtotal $31,070.00

Total for Subtask 9a: $ 31,070.00 Subtask 9b: 48-Month Post Construction Monitoring Report: Obtain oblique site aerials and on-site aerials by a small, unmanned aircraft piloted by HM staff certified to operate an unmanned aircraft, merge for vertical c:\users\mccullum_t\documents\projects\honeymoon island\arppi2-61457c\proposal\co3\2025-02-25 honeymoon island task 21-post-aerial image, conduct engineering analysis of survey data, prepare technical report of shoreline change, volumetric change, and project performance evaluation.

Deliverable 9b: Electronic copy containing monitoring analysis of August 2028 survey data, report and aerial photographs in pdf.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Fixed Price: $30,334.00

Subtask 9b August 2028 Monitoring Report and Analysis Firm Name Position Classification Hourly

Rate Hours Total Fixed

Price Cost Humiston & Moore Eng. Project Manager / P.E. $206.00 24 $4,944.00 Humiston & Moore Eng. Senior Engineer $172.00 12 $2,064.00 Humiston & Moore Eng. Engineer III $123.00 30 $3,690.00 Humiston & Moore Eng. Engineer II $96.00 40 $3,840.00 Humiston & Moore Eng. Engineer I $94.00 100 $9,400.00 Humiston & Moore Eng. AutoCAD Technician II $85.00 60 $5,100.00 Humiston & Moore Eng. AutoCAD/Science Tech $81.00 16 $1,296.00 Subtotal $30,334.00

Total for Subtask 9b: $ 30,334.00

The 2024 hurricane season included impacts from Hurricanes Debby (August 3, 2024), Helene (September 26, 2024) and Milton (October 10, 2024). Survey data is available pre and post Debby using monitoring data, and post Milton using pre-construction data. Estimated percentage of impacts from Helene and Milton will be based on site observations and surge data since survey data is only available pre Helene and post Milton per discussion with FEMA staff.

Subtask 10a: Post Hurricane Impact Assessment for Hurricane Debby, Coordination with FEMA, and preparation of FEMA report to support Category G funding from FEMA: Plot pre and post hurricane monitoring surveys and evaluate volumetric changes to determine eligible storm losses and vulnerability comparing latest pre-storm and post Debby survey data, data analysis, and coordination with FEMA on project losses for engineered beach limits (Category G). Provide related technical support and exhibits in accordance with FEMA standards and requirements to support background erosion and depth of closure for volume computations. The technical report will be filed for Hurricane Debby per FEMA guidelines.

Deliverable 10a: Electronic copy containing monitoring FEMA report for Hurricane Debby Category G Funding Assistance in pdf.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Fixed Price: $6,920.00

Subtask 10a Post Hurricane Debby Impact Assessment Analysis and Report c:\users\mccullum_t\documents\projects\honeymoon island\arppi2-61457c\proposal\co3\2025-02-25 honeymoon island task 21-post-

Firm Name Position Classification Hourly Rate

Hours Total Fixed Price Cost

Humiston & Moore Eng. Project Manager / P.E. $206.00 14 $2,884.00 Humiston & Moore Eng. Senior Engineer $172.00 1 $172.00 Humiston & Moore Eng. Engineer III $123.00 6 $738.00 Humiston & Moore Eng. Engineer II $96.00 6 $576.00 Humiston & Moore Eng. Engineer I $94.00 0 $0.00 Humiston & Moore Eng. AutoCAD Technician II $85.00 30 $2,550.00 Humiston & Moore Eng. AutoCAD/Science Tech $81.00 0 $0.00 Subtotal $6,920.00

Total for Subtask 10a: $ 6,920.00

Subtask 10b: Post Hurricane Impact Assessment for Hurricane Helene, Coordination with FEMA, and preparation of FEMA report to support Category G funding from FEMA: Plot pre and post hurricane surveys and evaluate volumetric changes to determine eligible storm losses and vulnerability comparing latest pre-storm survey and post Milton survey data, data analysis, and coordination with FEMA on project losses for engineered beach limits (Category G). Provide related technical support and exhibits in accordance with FEMA standards and requirements to support background erosion and depth of closure for volume computations. The technical report will be filed for Hurricane Helene per FEMA guidelines.

Deliverable 10b: Electronic copy containing monitoring FEMA report for Hurricane Helene Category G Funding Assistance in pdf.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Fixed Price: $6,920.00

Subtask 10b Post Hurricane Helene Impact Assessment Analysis and Report Firm Name Position Classification Hourly

Rate Hours Total Fixed

Price Cost Humiston & Moore Eng. Project Manager / P.E. $206.00 14 $2,884.00 Humiston & Moore Eng. Senior Engineer $172.00 1 $172.00 Humiston & Moore Eng. Engineer III $123.00 6 $738.00 Humiston & Moore Eng. Engineer II $96.00 6 $576.00 Humiston & Moore Eng. Engineer I $94.00 0 $0.00 Humiston & Moore Eng. AutoCAD Technician II $85.00 30 $2,550.00 Humiston & Moore Eng. AutoCAD/Science Tech $81.00 0 $0.00

Total for Subtask 10b: $ 6,920.00

Subtask 10c: Post Hurricane Impact Assessment for Hurricane Milton, Coordination with FEMA, and preparation of FEMA report to support Category G funding from FEMA: Plot pre and post hurricane surveys and evaluate volumetric changes to determine eligible storm losses and vulnerability comparing latest pre-storm survey and post Milton survey data, data analysis, and coordination with FEMA on project losses for engineered beach limits (Category G). Provide related technical support and exhibits in accordance with FEMA standards and requirements to support background erosion and depth of closure for volume computations. The technical report will be filed for Hurricane Helene per FEMA guidelines.

c:\users\mccullum_t\documents\projects\honeymoon island\arppi2-61457c\proposal\co3\2025-02-25 honeymoon island task 21-post-

Deliverable 10c: Electronic copy containing monitoring FEMA report for Hurricane Milton Category G Funding Assistance in pdf.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Fixed Price: $6,920.00

Subtask 10c Post Hurricane Milton Impact Assessment Analysis and Report Firm Name Position Classification Hourly

Rate Hours Total Fixed

Price Cost Humiston & Moore Eng. Project Manager / P.E. $206.00 14 $2,884.00 Humiston & Moore Eng. Senior Engineer $172.00 1 $172.00 Humiston & Moore Eng. Engineer III $123.00 6 $738.00 Humiston & Moore Eng. Engineer II $96.00 6 $576.00 Humiston & Moore Eng. Engineer I $94.00 0 $0.00 Humiston & Moore Eng. AutoCAD Technician II $85.00 30 $2,550.00 Humiston & Moore Eng. AutoCAD/Science Tech $81.00 0 $0.00

Total for Subtask 10c: $ 6,920.00

The following services are related to the post-construction monitoring of the 2025 Beach Nourishment Project at North Beach on Honeymoon Island State park and seeking FEMA funding assistance for impacts from 2024 hurricanes. The project involved the dredging of sand from the sand spit at the south end of Honeymoon Island and the offshore Borrow Area used in 2021 and placement of that sand within the authorized beach fill area along North Beach fronting the North and Oasis parking areas. Surveys will be conducted by approved hydrographic surveying subconsultants as part of the Humiston & Moore Engineers (H&M) team. H&M will work closely with the DEP Bureau of Design and Construction (BDC) staff and appointed representative for this project.

Project Schedule:

Activity Duration (Calendar Days) Subtask 7a: 12-Month Post Construction Monitoring Survey (August 2025) 10 Subtask 7b: Monitoring Report & Analysis August 2025 data 120 Subtask 8a: 24-Month Monitoring Survey (August 2026) 10 Subtask 8b: Monitoring Report & Analysis August 2026 data 120 Subtask 9a: 48-Month Monitoring Survey (August 2028) 10 Subtask 9b: Monitoring Report & Analysis August 2028 data 120 Subtask 10a: Post Debby Storm Assessment and FEMA Funding Report 90 Subtask 10b: Post Helene Storm Assessment and FEMA Funding Report 90 Subtask 10c: Post Milton Storm Assessment and FEMA Funding Report 90 c:\users\mccullum_t\documents\projects\honeymoon island\arppi2-61457c\proposal\co3\2025-02-25 honeymoon island task 21-post-

Summary of Fees:

Activity – Monitoring and FEMA Funding Subtask Fixed Price Cost

Subtask 7a: 12-Month Post Construction Monitoring Survey (August 2025) $25,070.00

Subtask 7b: Monitoring Report & Analysis August 2025 data $26,360.00

Subtask 8a: 24-Month Monitoring Survey (August 2026) $31,070.00

Subtask 8b: Monitoring Report & Analysis August 2026 data $30,334.00 Subtask 9a: 48-Month Monitoring Survey (August 2028) $31,070.00

Subtask 9b: Monitoring Report & Analysis August 2028 data $30,334.00 Subtask 10a: Post Debby Storm Assessment and FEMA Funding Report $6,920.00 Subtask 10b: Post Helene Storm Assessment and FEMA Funding Report $6,920.00 Subtask 10c: Post Milton Storm Assessment and FEMA Funding Report $6,920.00 Subtotal Fixed Price Cost Monitoring Services $194,998.00 Reimbursable Price $0.00 Total Contract, or Task Assignment Price: (Subtask 7a through 10c) $194,998.00

Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified.

File details come from the government source that posted it. Updated .