Summary: Prevailing Wage Rates Document for WC2608 SWOPE Stormwater Basin Retrofit Project
This is a Prevailing Wage Rates document issued by the Commonwealth of Pennsylvania Department of Labor & Industry for the WC2608 SWOPE Stormwater Basin Retrofit Project at West Chester University of Pennsylvania in Chester County, Pennsylvania. The project involves clearing and demolition, erosion and sediment controls, basin regrading, underdrain system installation, outlet structure replacement, drainage structures and piping, gabion basket forebay, amended soil installation, and associated work for the retrofit of an existing detention basin. The contract was awarded to West Chester University of PA on September 23, 2026, with a serial number of 26-07767. The project is classified as Highway work and was determined on August 25, 2026. The assigned field office is the Philadelphia Field Office, telephone (215)560-1858. The contract runs from December 7, 2026, through July 3, 2027, spanning 208 calendar days, with a pre-bid site visit scheduled for November 6, 2026, at 11:00 AM. The contract cost range is $450,000 to $550,000.
The prevailing wage rates document, dated October 29, 2026, establishes minimum hourly compensation requirements for various trade classifications under both Building and Heavy/Highway project categories. Rates vary by trade classification, effective date, and expiration date, with combined hourly rates (including base wages and fringe benefits) ranging from approximately $42.55 to $121.72 per hour across classifications such as carpenters, laborers, operators, electricians, plumbers, and numerous specialized trades. All rates are mandatory for contractors performing work on this prevailing wage project. No set-asides, incumbent contractors, or specific funding sources are identified in this wage determination document.
View the file
Other files
Show 40 more
Latest 50 of 66 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project Name: WC2608 SWOPE Stormwater Basin Retrofit Project
General Description: Work shall consist of clearing and demo, erosion and sediment controls, basin regrading, underdrain system, outlet structure replacement, drainage structures and piping, gabion basket forebay, amended soil installation, and other work as shown in the Contract Documents.
Project Locality West Chester University of PA
Awarding Agency: West Chester University of PA
Contract Award Date: 9/23/2026
Serial Number: 26-07767
Project Classification: Highway
Determination Date: 8/25/2026
Assigned Field Office: Philadelphia
Field Office Phone Number: (215)560-1858
Toll Free Phone Number:
Project County: Chester County
BUREAU OF LABOR LAW COMPLIANCE
PREVAILING WAGES PROJECT RATES
Commonwealth of Pennsylvania Department of Labor & Industry Report Date: 10/29/2026 Page 1 of 7
Project: 26-07767 - Building Effective Date
Expiration Date
Hourly Rate Fringe Benefits
Total
Asbestos & Insulation Workers 5/1/2025 $60.84 $48.71 $109.55
Asbestos & Insulation Workers 5/1/2026 $64.51 $50.26 $114.77
Boilermakers 3/1/2018 $45.89 $33.73 $79.62
Bricklayer 5/1/2025 $50.00 $32.57 $82.57
Bricklayer 5/1/2026 $51.15 $34.92 $86.07
Carpenter - Chief of Party (Surveying & Layout) 5/1/2025 $54.59 $29.02 $83.61
Carpenter - Instrument Person (Surveying & Layout) 5/1/2025 $47.47 $29.02 $76.49
Carpenter - Rodman (Surveying & Layout) 5/1/2025 $23.74 $20.62 $44.36
Carpenters 5/1/2026 $48.55 $30.39 $78.94
Carpenters 5/1/2027 $50.46 $30.74 $81.20
Carpenters 5/1/2028 $52.43 $31.09 $83.52
Carpenters 5/1/2029 $54.46 $31.44 $85.90
Carpenters 5/1/2030 $56.55 $31.79 $88.34
Cement Finishers & Plasterers 5/1/2022 $38.57 $32.39 $70.96
Cement Masons 5/1/2024 $46.70 $32.46 $79.16
Cement Masons 5/1/2025 $48.70 $32.46 $81.16
Dockbuilder, Pile Drivers 5/1/2026 $56.98 $37.99 $94.97
Dockbuilder/Pile Driver Diver 5/1/2026 $66.54 $41.74 $108.28
Dockbuilder/pile driver tender 5/1/2026 $56.98 $37.99 $94.97
Drywall Finisher 5/1/2025 $40.14 $32.35 $72.49
Drywall Finisher 5/1/2026 $41.10 $32.99 $74.09
Electricians 6/1/2026 $55.25 $41.28 $96.53
Electricians 5/31/2027 $57.33 $42.80 $100.13
Electricians 5/29/2028 $59.49 $44.14 $103.63
Electricians 5/28/2029 $61.64 $45.49 $107.13
Elevator Constructor 1/1/2025 $71.85 $45.77 $117.62
Elevator Constructor 1/1/2026 $74.86 $46.86 $121.72
Floor Coverer 5/1/2025 $51.67 $31.69 $83.36
Floor Coverer 5/1/2026 $52.84 $32.86 $85.70
Glazier 5/1/2025 $49.96 $38.34 $88.30
Glazier 5/1/2026 $51.30 $39.37 $90.67
Interior Finish 5/1/2023 $34.60 $25.80 $60.40
Iron Workers (Bridge, Structural, Ornamental, Precast) 7/1/2024 $53.20 $45.01 $98.21
Iron Workers (Riggers) 7/1/2025 $44.77 $36.27 $81.04
Iron Workers (Riggers) 7/1/2026 $48.84 $36.52 $85.36
Iron Workers (Rodman/Reinforcing) 7/1/2024 $47.70 $34.77 $82.47
Iron Workers (Rodman/Reinforcing) 7/1/2025 $47.80 $36.65 $84.45
Iron Workers (Rodman/Reinforcing) 7/1/2026 $52.39 $36.90 $89.29
Laborers (Class 01 - See notes) 5/1/2025 $37.25 $26.10 $63.35
Laborers (Class 02 - See notes) 5/1/2025 $41.00 $27.70 $68.70
Laborers (Class 03 - See notes) 5/1/2025 $37.67 $26.28 $63.95
Laborers (Class 04 - See notes) 5/1/2025 $37.67 $26.28 $63.95
Laborers (Class 05 - See notes) 5/1/2025 $37.25 $26.10 $63.35
Landscape Laborer 5/1/2025 $32.15 $24.30 $56.45
BUREAU OF LABOR LAW COMPLIANCE
PREVAILING WAGES PROJECT RATES
Report Date: 10/29/2026 Page 2 of 7
Expiration Date
Hourly Rate Fringe Benefits
Total
Marble Finisher 5/1/2025 $41.17 $30.75 $71.92
Marble Finisher 5/1/2026 $42.07 $31.85 $73.92
Marble Mason 5/1/2023 $47.20 $31.95 $79.15
Marble Setter 5/1/2026 $51.50 $33.80 $85.30
Mason Tender, Cement 5/1/2023 $35.02 $25.98 $61.00
Millwright 5/1/2025 $57.39 $35.81 $93.20
Millwright 5/1/2026 $60.20 $35.81 $96.01
Operators (Building, Class 01 - See Notes) 5/1/2025 $54.52 $34.49 $89.01
Operators (Building, Class 01 - See Notes) 5/1/2026 $55.67 $35.34 $91.01
Operators (Building, Class 01A - See Notes) 5/1/2025 $57.52 $35.38 $92.90
Operators (Building, Class 01A - See Notes) 5/1/2026 $58.68 $36.22 $94.90
Operators (Building, Class 02 - See Notes) 5/1/2025 $54.27 $34.42 $88.69
Operators (Building, Class 02 - See Notes) 5/1/2026 $55.43 $35.26 $90.69
Operators (Building, Class 02A - See Notes) 5/1/2025 $57.29 $35.29 $92.58
Operators (Building, Class 02A - See Notes) 5/1/2026 $58.44 $36.14 $94.58
Operators (Building, Class 03 - See Notes) 5/1/2025 $50.18 $33.22 $83.40
Operators (Building, Class 03 - See Notes) 5/1/2026 $51.34 $34.06 $85.40
Operators (Building, Class 04 - See Notes) 5/1/2025 $49.88 $33.13 $83.01
Operators (Building, Class 04 - See Notes) 5/1/2026 $51.04 $33.97 $85.01
Operators (Building, Class 05 - See Notes) 5/1/2025 $48.16 $32.62 $80.78
Operators (Building, Class 05 - See Notes) 5/1/2026 $49.32 $33.46 $82.78
Operators (Building, Class 06 - See Notes) 5/1/2025 $47.17 $32.33 $79.50
Operators (Building, Class 06 - See Notes) 5/1/2026 $48.34 $33.16 $81.50
Operators (Building, Class 07A- See Notes) 5/1/2025 $66.26 $39.55 $105.81
Operators (Building, Class 07A- See Notes) 5/1/2026 $67.73 $40.48 $108.21
Operators (Building, Class 07B- See Notes) 5/1/2025 $65.97 $39.46 $105.43
Operators (Building, Class 07B- See Notes) 5/1/2026 $67.44 $40.39 $107.83
Painters Class 1 (see notes) 5/1/2025 $44.38 $34.55 $78.93
Painters Class 1 (see notes) 5/1/2026 $45.71 $35.22 $80.93
Painters - Line Stripping 12/1/2024 $44.12 $27.91 $72.03
Painters - Line Stripping 12/1/2025 $45.12 $29.41 $74.53
Painters Class 4 (see notes) 5/1/2025 $46.47 $34.55 $81.02
Painters Class 4 (see notes) 5/1/2026 $48.45 $35.22 $83.67
Plasterers 5/1/2024 $39.88 $33.08 $72.96 plumber 5/1/2025 $70.53 $39.46 $109.99 plumber 5/1/2026 $73.73 $40.36 $114.09
Pointers, Caulkers, Cleaners 5/1/2025 $51.35 $31.80 $83.15
Pointers, Caulkers, Cleaners 5/1/2026 $53.35 $32.30 $85.65
Roofers (Composition) 5/1/2025 $46.03 $34.77 $80.80
Roofers (Composition) 5/1/2026 $47.53 $35.22 $82.75
Roofers (Shingle) 5/1/2024 $34.35 $22.20 $56.55
Roofers (Slate & Tile) 5/1/2024 $37.35 $22.20 $59.55
Sheet Metal Workers 5/1/2025 $62.62 $52.17 $114.79
Sheet Metal Workers 5/1/2026 $65.06 $54.48 $119.54
BUREAU OF LABOR LAW COMPLIANCE
PREVAILING WAGES PROJECT RATES
Report Date: 10/29/2026 Page 3 of 7
Expiration Date
Hourly Rate Fringe Benefits
Total
Sign Makers and Hangars 7/15/2025 $33.48 $26.41 $59.89
Sign Makers and Hangars 7/15/2026 $36.38 $25.01 $61.39
Sprinklerfitters 1/1/2023 $62.23 $31.99 $94.22
Sprinklerfitters 5/1/2025 $70.37 $34.85 $105.22
Steamfitters 5/1/2024 $70.32 $43.09 $113.41
Steamfitters 5/1/2025 $72.52 $44.89 $117.41
Stone Masons 5/1/2025 $50.00 $32.80 $82.80
Stone Masons 5/1/2026 $51.50 $33.80 $85.30
Terrazzo Finisher 5/1/2025 $45.61 $29.41 $75.02
Terrazzo Finisher 5/1/2026 $47.78 $29.61 $77.39
Terrazzo Grinder 5/1/2025 $45.88 $29.41 $75.29
Terrazzo Grinder 5/1/2026 $47.78 $29.61 $77.39
Terrazzo Mechanics 5/1/2025 $52.21 $31.26 $83.47
Terrazzo Mechanics 5/1/2026 $53.36 $32.61 $85.97
Tile Finisher 5/1/2025 $41.17 $30.75 $71.92
Tile Finisher 5/1/2026 $42.07 $31.85 $73.92
Tile Setter 5/1/2025 $52.21 $31.26 $83.47
Tile Setter 5/1/2026 $53.36 $32.61 $85.97
Truckdriver class 1(see notes) 5/1/2024 $36.79 $22.54 $59.33
Truckdriver class 1(see notes) 5/1/2026 $38.57 $23.87 $62.44
Truckdriver class 2 (see notes) 5/1/2024 $36.89 $22.54 $59.43
Truckdriver class 2 (see notes) 5/1/2026 $38.67 $23.87 $62.54
Truckdriver class 3 (see notes) 5/1/2026 $38.92 $23.87 $62.79
Window Film / Tint Installer 6/1/2025 $27.42 $15.13 $42.55
BUREAU OF LABOR LAW COMPLIANCE
PREVAILING WAGES PROJECT RATES
Report Date: 10/29/2026 Page 4 of 7
Project: 26-07767 - Heavy/Highway Effective
Expiration Date
Hourly Rate Fringe Benefits
Total
Bricklayer 5/1/2025 $50.00 $32.57 $82.57
Bricklayer 5/1/2026 $51.15 $34.92 $86.07
Carpenter - Chief of Party (Surveying & Layout) 5/1/2025 $65.96 $30.09 $96.05
Carpenter - Chief of Party (Surveying & Layout) 5/1/2026 $67.52 $30.44 $97.96
Carpenter - Instrument Person (Surveying & Layout) 5/1/2025 $58.39 $29.06 $87.45
Carpenter - Instrument Person (Surveying & Layout) 5/1/2026 $60.09 $29.06 $89.15
Carpenter - Rodman (Surveying & Layout) 5/1/2025 $45.88 $23.19 $69.07
Carpenter - Rodman (Surveying & Layout) 5/1/2026 $46.97 $23.54 $70.51
Carpenter 5/1/2025 $57.36 $30.09 $87.45
Carpenter 5/1/2026 $58.71 $30.44 $89.15
Cement Masons 5/1/2023 $43.20 $32.91 $76.11
Cement Masons 5/1/2025 $46.55 $32.66 $79.21
Dockbuilder, Pile Drivers 5/1/2026 $56.98 $37.99 $94.97
Dockbuilder/Pile Driver Diver 5/1/2026 $61.88 $45.47 $107.35
Dockbuilder/pile driver tender 5/1/2026 $56.98 $37.99 $94.97
Electric Lineman 6/3/2024 $62.07 $33.96 $96.03
Electric Lineman 6/2/2025 $65.10 $34.45 $99.55
Iron Workers (Bridge, Structural, Ornamental, Precast) 7/1/2024 $53.20 $45.01 $98.21
Iron Workers (Riggers) 7/1/2023 $42.53 $34.14 $76.67
Iron Workers (Rodman/Reinforcing) 7/1/2023 $45.70 $34.77 $80.47
Laborers (Class 01 - See notes) 5/1/2025 $40.20 $27.80 $68.00
Laborers (Class 01 - See notes) 5/1/2026 $41.65 $27.90 $69.55
Laborers (Class 02 - See notes) 5/1/2025 $40.40 $27.80 $68.20
Laborers (Class 02 - See notes) 5/1/2026 $41.85 $27.90 $69.75
Laborers (Class 03 - See notes) 5/1/2025 $40.40 $27.80 $68.20
Laborers (Class 03 - See notes) 5/1/2026 $41.85 $27.90 $69.75
Laborers (Class 04 - See notes) 5/1/2025 $35.00 $27.80 $62.80
Laborers (Class 04 - See notes) 5/1/2026 $36.45 $27.90 $64.35
Laborers (Class 05 - See notes) 5/1/2025 $41.05 $27.80 $68.85
Laborers (Class 05 - See notes) 5/1/2026 $42.50 $27.90 $70.40
Laborers (Class 06 - See notes) 5/1/2025 $41.10 $27.80 $68.90
Laborers (Class 06 - See notes) 5/1/2026 $42.55 $27.90 $70.45
Laborers (Class 07 - See notes) 5/1/2025 $40.95 $27.80 $68.75
Laborers (Class 07 - See notes) 5/1/2026 $42.40 $27.90 $70.30
Laborers (Class 08 - See notes) 5/1/2025 $40.70 $27.80 $68.50
Laborers (Class 08 - See notes) 5/1/2026 $42.15 $27.90 $70.05
Laborers (Class 09 - See notes) 5/1/2025 $40.55 $27.80 $68.35
Laborers (Class 09 - See notes) 5/1/2026 $42.00 $27.90 $69.90
Laborers (Class 10- See notes) 5/1/2025 $40.70 $27.80 $68.50
Laborers (Class 10- See notes) 5/1/2026 $42.15 $27.90 $70.05
Laborers (Class 11 -See Notes) 5/1/2025 $40.60 $27.80 $68.40
Laborers (Class 11 -See Notes) 5/1/2026 $42.05 $27.90 $69.95
Laborers (Class 12 -See Notes) 5/1/2025 $42.30 $27.80 $70.10
Laborers (Class 12 -See Notes) 5/1/2026 $42.85 $27.90 $70.75
BUREAU OF LABOR LAW COMPLIANCE
PREVAILING WAGES PROJECT RATES
Report Date: 10/29/2026 Page 5 of 7
Expiration Date
Hourly Rate Fringe Benefits
Total
Laborers (Class 13 -See Notes) 5/1/2025 $44.33 $27.80 $72.13
Laborers (Class 13 -See Notes) 5/1/2026 $45.78 $27.90 $73.68
Laborers (Class 14 -See Notes) 5/1/2025 $40.90 $27.80 $68.70
Laborers (Class 14 -See Notes) 5/1/2026 $41.90 $27.90 $69.80
Laborers Utility (PGW ONLY) (Flagperson) 5/1/2025 $34.07 $19.73 $53.80
Laborers Utility (PGW ONLY) (Flagperson) 5/1/2026 $35.52 $19.83 $55.35
Laborers Utility (PGW ONLY) 5/1/2024 $39.70 $19.63 $59.33
Laborers Utility (PGW ONLY) 5/1/2025 $41.10 $19.73 $60.83
Laborers Utility (PGW ONLY) 5/1/2026 $42.55 $19.83 $62.38
Landscape Laborer 5/1/2024 $30.28 $24.05 $54.33
Landscape Laborer 5/1/2025 $31.73 $24.15 $55.88
Millwright 5/1/2025 $57.39 $35.81 $93.20
Millwright 5/1/2026 $60.20 $35.81 $96.01
Operators Class 01 - See Notes (Building, Heavy, Highway)
5/1/2025 $54.52 $34.49 $89.01
Operators Class 01 - See Notes (Building, Heavy, Highway)
5/1/2026 $55.67 $35.34 $91.01
Operators Class 01a - See Notes (Building, Heavy, Highway)
5/1/2025 $57.52 $35.38 $92.90
Operators Class 01a - See Notes (Building, Heavy, Highway)
5/1/2026 $58.68 $36.22 $94.90
Operators Class 02 - See Notes (Building, Heavy, Highway)
5/1/2025 $54.27 $34.42 $88.69
Operators Class 02 - See Notes (Building, Heavy, Highway)
5/1/2026 $55.43 $35.26 $90.69
Operators Class 02a - See Notes (Building, Heavy, Highway)
5/1/2025 $57.29 $35.29 $92.58
Operators Class 02a - See Notes (Building, Heavy, Highway)
5/1/2026 $58.44 $36.14 $94.58
Operators Class 03 - See Notes (Building, Heavy, Highway)
5/1/2025 $50.18 $33.22 $83.40
Operators Class 03 - See Notes (Building, Heavy, Highway)
5/1/2026 $51.34 $34.06 $85.40
Operators Class 04 - See Notes (Building, Heavy, Highway)
5/1/2025 $49.88 $33.13 $83.01
Operators Class 04 - See Notes (Building, Heavy, Highway)
5/1/2026 $51.04 $33.97 $85.01
Operators Class 05 - See Notes (Building, Heavy, Highway)
5/1/2025 $48.16 $32.62 $80.78
Operators Class 05 - See Notes (Building, Heavy, Highway)
5/1/2026 $49.32 $33.46 $82.78
Operators Class 06 - See Notes (Building, Heavy, Highway)
5/1/2025 $47.17 $32.33 $79.50
Operators Class 06 - See Notes (Building, Heavy, Highway)
5/1/2026 $48.34 $33.16 $81.50
Operators Class 07 (A) - See Notes (Building, Heavy, Highway)
5/1/2025 $66.26 $39.55 $105.81
Operators Class 07 (A) - See Notes (Building, Heavy, Highway)
5/1/2026 $67.73 $40.48 $108.21
Operators Class 07 (B) - See Notes (Building, Heavy, Highway)
5/1/2025 $65.97 $39.46 $105.43
BUREAU OF LABOR LAW COMPLIANCE
PREVAILING WAGES PROJECT RATES
Report Date: 10/29/2026 Page 6 of 7
Expiration Date
Hourly Rate Fringe Benefits
Total
Operators Class 07 (B) - See Notes (Building, Heavy, Highway)
5/1/2026 $67.44 $40.39 $107.83
Painters - Line Stripping 12/1/2024 $44.12 $27.91 $72.03
Painters - Line Stripping 12/1/2025 $45.12 $29.41 $74.53
Painters Class 2 (see notes) 2/1/2025 $50.85 $33.91 $84.76
Painters Class 2 (see notes) 2/1/2026 $51.61 $35.00 $86.61
Painters Class 3 (see notes) 2/1/2025 $61.81 $33.95 $95.76
Painters Class 3 (see notes) 2/1/2026 $62.57 $35.04 $97.61
Pointers, Caulkers, Cleaners 5/1/2025 $51.35 $31.80 $83.15
Steamfitters (Heavy and Highway - Gas Distribution) 5/1/2025 $68.89 $44.73 $113.62
Steamfitters 5/1/2018 $56.37 $34.39 $90.76
Truckdriver class 1(see notes) 5/1/2024 $36.64 $22.54 $59.18
Truckdriver class 1(see notes) 5/1/2026 $38.42 $23.87 $62.29
Truckdriver class 2 (see notes) 5/1/2024 $36.74 $22.54 $59.28
Truckdriver class 2 (see notes) 5/1/2026 $38.52 $23.87 $62.39
Truckdriver class 3 (see notes) 5/1/2026 $38.77 $23.87 $62.64
BUREAU OF LABOR LAW COMPLIANCE
PREVAILING WAGES PROJECT RATES
Report Date: 10/29/2026 Page 7 of 7