Summary: Prevailing Wage Rates Document for WC2608 SWOPE Stormwater Basin Retrofit Project

This is a Prevailing Wage Rates document issued by the Commonwealth of Pennsylvania Department of Labor & Industry for the WC2608 SWOPE Stormwater Basin Retrofit Project at West Chester University of Pennsylvania in Chester County, Pennsylvania. The project involves clearing and demolition, erosion and sediment controls, basin regrading, underdrain system installation, outlet structure replacement, drainage structures and piping, gabion basket forebay, amended soil installation, and associated work for the retrofit of an existing detention basin. The contract was awarded to West Chester University of PA on September 23, 2026, with a serial number of 26-07767. The project is classified as Highway work and was determined on August 25, 2026. The assigned field office is the Philadelphia Field Office, telephone (215)560-1858. The contract runs from December 7, 2026, through July 3, 2027, spanning 208 calendar days, with a pre-bid site visit scheduled for November 6, 2026, at 11:00 AM. The contract cost range is $450,000 to $550,000.

The prevailing wage rates document, dated October 29, 2026, establishes minimum hourly compensation requirements for various trade classifications under both Building and Heavy/Highway project categories. Rates vary by trade classification, effective date, and expiration date, with combined hourly rates (including base wages and fringe benefits) ranging from approximately $42.55 to $121.72 per hour across classifications such as carpenters, laborers, operators, electricians, plumbers, and numerous specialized trades. All rates are mandatory for contractors performing work on this prevailing wage project. No set-asides, incumbent contractors, or specific funding sources are identified in this wage determination document.

View the file

Other files

File Type Posted
WC2608 Solicitation Cover Sheet. 10.29.26.pdf PDF
003-012600 CONTRACT MODIFIATION PROCEDURES 71-FA-8.1.pdf PDF
005-013100 PROJECT MANAGEMENT AND COORDINATION 71-FA-8.1.pdf PDF
008-013300 SUBMITTAL PROCEDURES 71-FA-8.1.pdf PDF
012-016000 PRODUCT REQUIREMENTS 71-FA-8.1.pdf PDF
015-017329 CUTTING AND PATCHING 71-FA-8.1.pdf PDF
315000 - Excavation Backfill and Compaction.pdf PDF
310519 - Geosynthetics.pdf PDF
B5 WC2608 Bid Bond Form, 71-FA-8.2_Dec_2023 10.24.26.pdf PDF
001-011000, SUMMARY 71-FA-8.1.pdf PDF
019-017839 PROJECT RECORD DOCUMENTS 71-FA-8.1.pdf PDF
C4 WC2608 Insurance Rider_71-FA-8.2_Dec_2023 10.29.26.pdf PDF
004-012900 PAYMENT PROCEDURES 71-FA-8.1.pdf PDF
002-012200 UNIT PRICES 71-FA-8.1.pdf PDF
016-017700 CLOSEOUT PROCEDURES 71-FA-8.1.pdf PDF
312500 - Erosion & Sedimentation Control.pdf PDF
014-017123 FIELD ENGINEERING 71-FA-8.1.pdf PDF
329200 - TURF AND GRASSES.pdf PDF
C6 WC2608 Weekly Certified Payroll Form llc-25[1].pdf PDF
B6 WC2608 SDB Instructions, 71-FA-8.2_Dec_2023 10.24.26.pdf PDF
006-013119 PROJECT MEETINGS 71-FA-8.1.pdf PDF
C2 WC2608 P and P Contract Bond Form 71-FA-8.2_Dec_2023 UPDATED 10.24.26.pdf PDF
017-017823 OPERATIONS AND MAINTENANCE DATA 71-FA-8.1.pdf PDF
B7 WC2608 SDB Form, 71-FA-8.2_Dec_2023 10.24.26.pdf PDF
B4 WC2608 Bid Form, 71-FA-8.2_Dec_2023 10.24.26.pdf PDF
013-016200 PRODUCT OPTIONS 71-FA-8.1.pdf PDF
010-014500 QUALITY CONTROL 71-FA-8.1.pdf PDF
Bid Set Oct 2026 SIGNED SEALED WC2608 1.pdf PDF
C3 WC2608 General_Conditions_71-FA-8.2_Dec_2023 10.24.26..pdf PDF
C1 WC2608 Standard Form of K_71-FA-8.2_Dec_2023.pdf PDF
334211 - Storm Drainage.pdf PDF
A WC2608.1_000000_TABLE OF CONTENTS_10-29-26.pdf PDF
C8 WC2608 PW EmploymentVerification FORM.pdf PDF
311000 - Site Clearing.pdf PDF
313700 - Riprap.pdf PDF
C7 WC2608 Public Works Employment Verification Notice 2.16.24 (1).pdf PDF
B2 WC2608 Spec Instr to Bidders 71-FA-8.2_Dec_2023 10.30.26.pdf PDF
007-013200B CONSTRUCTION PROGRES DOCUMENTATION 71-FA-8.1.pdf PDF
B8 WC2608 Contractor Qualification Statement updated 10.24.26.pdf PDF
018-017836 WARRANTIES 71-FA-8.1.pdf PDF
4-RFP WCU0508262274 - Appendix A - Technical Submittal Response.pdf PDF
1-RFP WCU05808262274 - Appendix C - Contract Exceptions.pdf PDF
2-RFP WCU0508262247 - Appendix B - Trade Secret Confidential Information Notice.pdf PDF
3-RFP WCU0508262274 - Full-Service Print, Mail, and Distribution Service Contractor.pdf PDF
1-IFB WCU0407261013 - (1) NEW 2025 Low Cab Forward (LCF) 16 Foot Box Truck .pdf PDF
2-IFB WCU0407261013 - Bid Specification - Attachment A.pdf PDF
1-WC2602 Contract Forms Conditions.zip ZIP file
4-WC2602 Drawings.zip ZIP file
2-WC2602 Specs 3.30.2026 updated.zip ZIP file
3-WC2602 Bid Form Requirements.zip ZIP file
Show 40 more

Latest 50 of 66 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project Name: WC2608 SWOPE Stormwater Basin Retrofit Project

General Description: Work shall consist of clearing and demo, erosion and sediment controls, basin regrading, underdrain system, outlet structure replacement, drainage structures and piping, gabion basket forebay, amended soil installation, and other work as shown in the Contract Documents.

Project Locality West Chester University of PA

Awarding Agency: West Chester University of PA

Contract Award Date: 9/23/2026

Serial Number: 26-07767

Project Classification: Highway

Determination Date: 8/25/2026

Assigned Field Office: Philadelphia

Field Office Phone Number: (215)560-1858

Toll Free Phone Number:

Project County: Chester County

BUREAU OF LABOR LAW COMPLIANCE

PREVAILING WAGES PROJECT RATES

Commonwealth of Pennsylvania Department of Labor & Industry Report Date: 10/29/2026 Page 1 of 7

Project: 26-07767 - Building Effective Date

Expiration Date

Hourly Rate Fringe Benefits

Total

Asbestos & Insulation Workers 5/1/2025 $60.84 $48.71 $109.55

Asbestos & Insulation Workers 5/1/2026 $64.51 $50.26 $114.77

Boilermakers 3/1/2018 $45.89 $33.73 $79.62

Bricklayer 5/1/2025 $50.00 $32.57 $82.57

Bricklayer 5/1/2026 $51.15 $34.92 $86.07

Carpenter - Chief of Party (Surveying & Layout) 5/1/2025 $54.59 $29.02 $83.61

Carpenter - Instrument Person (Surveying & Layout) 5/1/2025 $47.47 $29.02 $76.49

Carpenter - Rodman (Surveying & Layout) 5/1/2025 $23.74 $20.62 $44.36

Carpenters 5/1/2026 $48.55 $30.39 $78.94

Carpenters 5/1/2027 $50.46 $30.74 $81.20

Carpenters 5/1/2028 $52.43 $31.09 $83.52

Carpenters 5/1/2029 $54.46 $31.44 $85.90

Carpenters 5/1/2030 $56.55 $31.79 $88.34

Cement Finishers & Plasterers 5/1/2022 $38.57 $32.39 $70.96

Cement Masons 5/1/2024 $46.70 $32.46 $79.16

Cement Masons 5/1/2025 $48.70 $32.46 $81.16

Dockbuilder, Pile Drivers 5/1/2026 $56.98 $37.99 $94.97

Dockbuilder/Pile Driver Diver 5/1/2026 $66.54 $41.74 $108.28

Dockbuilder/pile driver tender 5/1/2026 $56.98 $37.99 $94.97

Drywall Finisher 5/1/2025 $40.14 $32.35 $72.49

Drywall Finisher 5/1/2026 $41.10 $32.99 $74.09

Electricians 6/1/2026 $55.25 $41.28 $96.53

Electricians 5/31/2027 $57.33 $42.80 $100.13

Electricians 5/29/2028 $59.49 $44.14 $103.63

Electricians 5/28/2029 $61.64 $45.49 $107.13

Elevator Constructor 1/1/2025 $71.85 $45.77 $117.62

Elevator Constructor 1/1/2026 $74.86 $46.86 $121.72

Floor Coverer 5/1/2025 $51.67 $31.69 $83.36

Floor Coverer 5/1/2026 $52.84 $32.86 $85.70

Glazier 5/1/2025 $49.96 $38.34 $88.30

Glazier 5/1/2026 $51.30 $39.37 $90.67

Interior Finish 5/1/2023 $34.60 $25.80 $60.40

Iron Workers (Bridge, Structural, Ornamental, Precast) 7/1/2024 $53.20 $45.01 $98.21

Iron Workers (Riggers) 7/1/2025 $44.77 $36.27 $81.04

Iron Workers (Riggers) 7/1/2026 $48.84 $36.52 $85.36

Iron Workers (Rodman/Reinforcing) 7/1/2024 $47.70 $34.77 $82.47

Iron Workers (Rodman/Reinforcing) 7/1/2025 $47.80 $36.65 $84.45

Iron Workers (Rodman/Reinforcing) 7/1/2026 $52.39 $36.90 $89.29

Laborers (Class 01 - See notes) 5/1/2025 $37.25 $26.10 $63.35

Laborers (Class 02 - See notes) 5/1/2025 $41.00 $27.70 $68.70

Laborers (Class 03 - See notes) 5/1/2025 $37.67 $26.28 $63.95

Laborers (Class 04 - See notes) 5/1/2025 $37.67 $26.28 $63.95

Laborers (Class 05 - See notes) 5/1/2025 $37.25 $26.10 $63.35

Landscape Laborer 5/1/2025 $32.15 $24.30 $56.45

BUREAU OF LABOR LAW COMPLIANCE

PREVAILING WAGES PROJECT RATES

Report Date: 10/29/2026 Page 2 of 7

Expiration Date

Hourly Rate Fringe Benefits

Total

Marble Finisher 5/1/2025 $41.17 $30.75 $71.92

Marble Finisher 5/1/2026 $42.07 $31.85 $73.92

Marble Mason 5/1/2023 $47.20 $31.95 $79.15

Marble Setter 5/1/2026 $51.50 $33.80 $85.30

Mason Tender, Cement 5/1/2023 $35.02 $25.98 $61.00

Millwright 5/1/2025 $57.39 $35.81 $93.20

Millwright 5/1/2026 $60.20 $35.81 $96.01

Operators (Building, Class 01 - See Notes) 5/1/2025 $54.52 $34.49 $89.01

Operators (Building, Class 01 - See Notes) 5/1/2026 $55.67 $35.34 $91.01

Operators (Building, Class 01A - See Notes) 5/1/2025 $57.52 $35.38 $92.90

Operators (Building, Class 01A - See Notes) 5/1/2026 $58.68 $36.22 $94.90

Operators (Building, Class 02 - See Notes) 5/1/2025 $54.27 $34.42 $88.69

Operators (Building, Class 02 - See Notes) 5/1/2026 $55.43 $35.26 $90.69

Operators (Building, Class 02A - See Notes) 5/1/2025 $57.29 $35.29 $92.58

Operators (Building, Class 02A - See Notes) 5/1/2026 $58.44 $36.14 $94.58

Operators (Building, Class 03 - See Notes) 5/1/2025 $50.18 $33.22 $83.40

Operators (Building, Class 03 - See Notes) 5/1/2026 $51.34 $34.06 $85.40

Operators (Building, Class 04 - See Notes) 5/1/2025 $49.88 $33.13 $83.01

Operators (Building, Class 04 - See Notes) 5/1/2026 $51.04 $33.97 $85.01

Operators (Building, Class 05 - See Notes) 5/1/2025 $48.16 $32.62 $80.78

Operators (Building, Class 05 - See Notes) 5/1/2026 $49.32 $33.46 $82.78

Operators (Building, Class 06 - See Notes) 5/1/2025 $47.17 $32.33 $79.50

Operators (Building, Class 06 - See Notes) 5/1/2026 $48.34 $33.16 $81.50

Operators (Building, Class 07A- See Notes) 5/1/2025 $66.26 $39.55 $105.81

Operators (Building, Class 07A- See Notes) 5/1/2026 $67.73 $40.48 $108.21

Operators (Building, Class 07B- See Notes) 5/1/2025 $65.97 $39.46 $105.43

Operators (Building, Class 07B- See Notes) 5/1/2026 $67.44 $40.39 $107.83

Painters Class 1 (see notes) 5/1/2025 $44.38 $34.55 $78.93

Painters Class 1 (see notes) 5/1/2026 $45.71 $35.22 $80.93

Painters - Line Stripping 12/1/2024 $44.12 $27.91 $72.03

Painters - Line Stripping 12/1/2025 $45.12 $29.41 $74.53

Painters Class 4 (see notes) 5/1/2025 $46.47 $34.55 $81.02

Painters Class 4 (see notes) 5/1/2026 $48.45 $35.22 $83.67

Plasterers 5/1/2024 $39.88 $33.08 $72.96 plumber 5/1/2025 $70.53 $39.46 $109.99 plumber 5/1/2026 $73.73 $40.36 $114.09

Pointers, Caulkers, Cleaners 5/1/2025 $51.35 $31.80 $83.15

Pointers, Caulkers, Cleaners 5/1/2026 $53.35 $32.30 $85.65

Roofers (Composition) 5/1/2025 $46.03 $34.77 $80.80

Roofers (Composition) 5/1/2026 $47.53 $35.22 $82.75

Roofers (Shingle) 5/1/2024 $34.35 $22.20 $56.55

Roofers (Slate & Tile) 5/1/2024 $37.35 $22.20 $59.55

Sheet Metal Workers 5/1/2025 $62.62 $52.17 $114.79

Sheet Metal Workers 5/1/2026 $65.06 $54.48 $119.54

BUREAU OF LABOR LAW COMPLIANCE

PREVAILING WAGES PROJECT RATES

Report Date: 10/29/2026 Page 3 of 7

Expiration Date

Hourly Rate Fringe Benefits

Total

Sign Makers and Hangars 7/15/2025 $33.48 $26.41 $59.89

Sign Makers and Hangars 7/15/2026 $36.38 $25.01 $61.39

Sprinklerfitters 1/1/2023 $62.23 $31.99 $94.22

Sprinklerfitters 5/1/2025 $70.37 $34.85 $105.22

Steamfitters 5/1/2024 $70.32 $43.09 $113.41

Steamfitters 5/1/2025 $72.52 $44.89 $117.41

Stone Masons 5/1/2025 $50.00 $32.80 $82.80

Stone Masons 5/1/2026 $51.50 $33.80 $85.30

Terrazzo Finisher 5/1/2025 $45.61 $29.41 $75.02

Terrazzo Finisher 5/1/2026 $47.78 $29.61 $77.39

Terrazzo Grinder 5/1/2025 $45.88 $29.41 $75.29

Terrazzo Grinder 5/1/2026 $47.78 $29.61 $77.39

Terrazzo Mechanics 5/1/2025 $52.21 $31.26 $83.47

Terrazzo Mechanics 5/1/2026 $53.36 $32.61 $85.97

Tile Finisher 5/1/2025 $41.17 $30.75 $71.92

Tile Finisher 5/1/2026 $42.07 $31.85 $73.92

Tile Setter 5/1/2025 $52.21 $31.26 $83.47

Tile Setter 5/1/2026 $53.36 $32.61 $85.97

Truckdriver class 1(see notes) 5/1/2024 $36.79 $22.54 $59.33

Truckdriver class 1(see notes) 5/1/2026 $38.57 $23.87 $62.44

Truckdriver class 2 (see notes) 5/1/2024 $36.89 $22.54 $59.43

Truckdriver class 2 (see notes) 5/1/2026 $38.67 $23.87 $62.54

Truckdriver class 3 (see notes) 5/1/2026 $38.92 $23.87 $62.79

Window Film / Tint Installer 6/1/2025 $27.42 $15.13 $42.55

BUREAU OF LABOR LAW COMPLIANCE

PREVAILING WAGES PROJECT RATES

Report Date: 10/29/2026 Page 4 of 7

Project: 26-07767 - Heavy/Highway Effective

Expiration Date

Hourly Rate Fringe Benefits

Total

Bricklayer 5/1/2025 $50.00 $32.57 $82.57

Bricklayer 5/1/2026 $51.15 $34.92 $86.07

Carpenter - Chief of Party (Surveying & Layout) 5/1/2025 $65.96 $30.09 $96.05

Carpenter - Chief of Party (Surveying & Layout) 5/1/2026 $67.52 $30.44 $97.96

Carpenter - Instrument Person (Surveying & Layout) 5/1/2025 $58.39 $29.06 $87.45

Carpenter - Instrument Person (Surveying & Layout) 5/1/2026 $60.09 $29.06 $89.15

Carpenter - Rodman (Surveying & Layout) 5/1/2025 $45.88 $23.19 $69.07

Carpenter - Rodman (Surveying & Layout) 5/1/2026 $46.97 $23.54 $70.51

Carpenter 5/1/2025 $57.36 $30.09 $87.45

Carpenter 5/1/2026 $58.71 $30.44 $89.15

Cement Masons 5/1/2023 $43.20 $32.91 $76.11

Cement Masons 5/1/2025 $46.55 $32.66 $79.21

Dockbuilder, Pile Drivers 5/1/2026 $56.98 $37.99 $94.97

Dockbuilder/Pile Driver Diver 5/1/2026 $61.88 $45.47 $107.35

Dockbuilder/pile driver tender 5/1/2026 $56.98 $37.99 $94.97

Electric Lineman 6/3/2024 $62.07 $33.96 $96.03

Electric Lineman 6/2/2025 $65.10 $34.45 $99.55

Iron Workers (Bridge, Structural, Ornamental, Precast) 7/1/2024 $53.20 $45.01 $98.21

Iron Workers (Riggers) 7/1/2023 $42.53 $34.14 $76.67

Iron Workers (Rodman/Reinforcing) 7/1/2023 $45.70 $34.77 $80.47

Laborers (Class 01 - See notes) 5/1/2025 $40.20 $27.80 $68.00

Laborers (Class 01 - See notes) 5/1/2026 $41.65 $27.90 $69.55

Laborers (Class 02 - See notes) 5/1/2025 $40.40 $27.80 $68.20

Laborers (Class 02 - See notes) 5/1/2026 $41.85 $27.90 $69.75

Laborers (Class 03 - See notes) 5/1/2025 $40.40 $27.80 $68.20

Laborers (Class 03 - See notes) 5/1/2026 $41.85 $27.90 $69.75

Laborers (Class 04 - See notes) 5/1/2025 $35.00 $27.80 $62.80

Laborers (Class 04 - See notes) 5/1/2026 $36.45 $27.90 $64.35

Laborers (Class 05 - See notes) 5/1/2025 $41.05 $27.80 $68.85

Laborers (Class 05 - See notes) 5/1/2026 $42.50 $27.90 $70.40

Laborers (Class 06 - See notes) 5/1/2025 $41.10 $27.80 $68.90

Laborers (Class 06 - See notes) 5/1/2026 $42.55 $27.90 $70.45

Laborers (Class 07 - See notes) 5/1/2025 $40.95 $27.80 $68.75

Laborers (Class 07 - See notes) 5/1/2026 $42.40 $27.90 $70.30

Laborers (Class 08 - See notes) 5/1/2025 $40.70 $27.80 $68.50

Laborers (Class 08 - See notes) 5/1/2026 $42.15 $27.90 $70.05

Laborers (Class 09 - See notes) 5/1/2025 $40.55 $27.80 $68.35

Laborers (Class 09 - See notes) 5/1/2026 $42.00 $27.90 $69.90

Laborers (Class 10- See notes) 5/1/2025 $40.70 $27.80 $68.50

Laborers (Class 10- See notes) 5/1/2026 $42.15 $27.90 $70.05

Laborers (Class 11 -See Notes) 5/1/2025 $40.60 $27.80 $68.40

Laborers (Class 11 -See Notes) 5/1/2026 $42.05 $27.90 $69.95

Laborers (Class 12 -See Notes) 5/1/2025 $42.30 $27.80 $70.10

Laborers (Class 12 -See Notes) 5/1/2026 $42.85 $27.90 $70.75

BUREAU OF LABOR LAW COMPLIANCE

PREVAILING WAGES PROJECT RATES

Report Date: 10/29/2026 Page 5 of 7

Expiration Date

Hourly Rate Fringe Benefits

Total

Laborers (Class 13 -See Notes) 5/1/2025 $44.33 $27.80 $72.13

Laborers (Class 13 -See Notes) 5/1/2026 $45.78 $27.90 $73.68

Laborers (Class 14 -See Notes) 5/1/2025 $40.90 $27.80 $68.70

Laborers (Class 14 -See Notes) 5/1/2026 $41.90 $27.90 $69.80

Laborers Utility (PGW ONLY) (Flagperson) 5/1/2025 $34.07 $19.73 $53.80

Laborers Utility (PGW ONLY) (Flagperson) 5/1/2026 $35.52 $19.83 $55.35

Laborers Utility (PGW ONLY) 5/1/2024 $39.70 $19.63 $59.33

Laborers Utility (PGW ONLY) 5/1/2025 $41.10 $19.73 $60.83

Laborers Utility (PGW ONLY) 5/1/2026 $42.55 $19.83 $62.38

Landscape Laborer 5/1/2024 $30.28 $24.05 $54.33

Landscape Laborer 5/1/2025 $31.73 $24.15 $55.88

Millwright 5/1/2025 $57.39 $35.81 $93.20

Millwright 5/1/2026 $60.20 $35.81 $96.01

Operators Class 01 - See Notes (Building, Heavy, Highway)

5/1/2025 $54.52 $34.49 $89.01

Operators Class 01 - See Notes (Building, Heavy, Highway)

5/1/2026 $55.67 $35.34 $91.01

Operators Class 01a - See Notes (Building, Heavy, Highway)

5/1/2025 $57.52 $35.38 $92.90

Operators Class 01a - See Notes (Building, Heavy, Highway)

5/1/2026 $58.68 $36.22 $94.90

Operators Class 02 - See Notes (Building, Heavy, Highway)

5/1/2025 $54.27 $34.42 $88.69

Operators Class 02 - See Notes (Building, Heavy, Highway)

5/1/2026 $55.43 $35.26 $90.69

Operators Class 02a - See Notes (Building, Heavy, Highway)

5/1/2025 $57.29 $35.29 $92.58

Operators Class 02a - See Notes (Building, Heavy, Highway)

5/1/2026 $58.44 $36.14 $94.58

Operators Class 03 - See Notes (Building, Heavy, Highway)

5/1/2025 $50.18 $33.22 $83.40

Operators Class 03 - See Notes (Building, Heavy, Highway)

5/1/2026 $51.34 $34.06 $85.40

Operators Class 04 - See Notes (Building, Heavy, Highway)

5/1/2025 $49.88 $33.13 $83.01

Operators Class 04 - See Notes (Building, Heavy, Highway)

5/1/2026 $51.04 $33.97 $85.01

Operators Class 05 - See Notes (Building, Heavy, Highway)

5/1/2025 $48.16 $32.62 $80.78

Operators Class 05 - See Notes (Building, Heavy, Highway)

5/1/2026 $49.32 $33.46 $82.78

Operators Class 06 - See Notes (Building, Heavy, Highway)

5/1/2025 $47.17 $32.33 $79.50

Operators Class 06 - See Notes (Building, Heavy, Highway)

5/1/2026 $48.34 $33.16 $81.50

Operators Class 07 (A) - See Notes (Building, Heavy, Highway)

5/1/2025 $66.26 $39.55 $105.81

Operators Class 07 (A) - See Notes (Building, Heavy, Highway)

5/1/2026 $67.73 $40.48 $108.21

Operators Class 07 (B) - See Notes (Building, Heavy, Highway)

5/1/2025 $65.97 $39.46 $105.43

BUREAU OF LABOR LAW COMPLIANCE

PREVAILING WAGES PROJECT RATES

Report Date: 10/29/2026 Page 6 of 7

Expiration Date

Hourly Rate Fringe Benefits

Total

Operators Class 07 (B) - See Notes (Building, Heavy, Highway)

5/1/2026 $67.44 $40.39 $107.83

Painters - Line Stripping 12/1/2024 $44.12 $27.91 $72.03

Painters - Line Stripping 12/1/2025 $45.12 $29.41 $74.53

Painters Class 2 (see notes) 2/1/2025 $50.85 $33.91 $84.76

Painters Class 2 (see notes) 2/1/2026 $51.61 $35.00 $86.61

Painters Class 3 (see notes) 2/1/2025 $61.81 $33.95 $95.76

Painters Class 3 (see notes) 2/1/2026 $62.57 $35.04 $97.61

Pointers, Caulkers, Cleaners 5/1/2025 $51.35 $31.80 $83.15

Steamfitters (Heavy and Highway - Gas Distribution) 5/1/2025 $68.89 $44.73 $113.62

Steamfitters 5/1/2018 $56.37 $34.39 $90.76

Truckdriver class 1(see notes) 5/1/2024 $36.64 $22.54 $59.18

Truckdriver class 1(see notes) 5/1/2026 $38.42 $23.87 $62.29

Truckdriver class 2 (see notes) 5/1/2024 $36.74 $22.54 $59.28

Truckdriver class 2 (see notes) 5/1/2026 $38.52 $23.87 $62.39

Truckdriver class 3 (see notes) 5/1/2026 $38.77 $23.87 $62.64

BUREAU OF LABOR LAW COMPLIANCE

PREVAILING WAGES PROJECT RATES

Report Date: 10/29/2026 Page 7 of 7