334211 - Storm Drainage.pdf

PDF 188 KB Posted

Attached to
WC2608 SWOPE Stormwater Basin Retrofit Project
Solicitation number
Not on record
Issued by
Chester County, Pennsylvania

About this file

Summary

This is a Storm Drainage specification document for the WC2608 SWOPE Stormwater Basin Retrofit Project issued by West Chester University of Pennsylvania with RETTEW as the project manager. The work encompasses the furnishing of all equipment, labor, and materials necessary to construct pipe culverts, combination storm sewer and underdrains, endwalls, inlets, pipes, pavement base drains, and end sections in accordance with Pennsylvania Department of Transportation (PennDOT) Publication 408 specifications and applicable contract drawings. The project is located at the southeast corner of the intersection of South High Street and East Campus Drive in West Chester, Pennsylvania. The contract period runs from December 7, 2026, through July 3, 2027, spanning 208 calendar days. A pre-bid and site visit is scheduled for November 6, 2026, at 11:00 AM. Material specifications reference PennDOT Publication 408 for pipes (Sections 601 and 610), manholes, inlets and endwalls (Section 605), gabions (Section 626), and outlet structures (Section 875). Contractors must submit three copies of manufacturer certifications and PennDOT form CS-4171, along with detailed shop drawings for precast concrete catch basins, inlet grates, frames, and poured-in-place concrete construction.

The contract is classified as a prevailing wage project with Prevailing Minimum Wage Determination serial number 26-07767, dated August 25, 2026, applicable to highway classifications. The contract cost range is $450,000 to $550,000. No liquidated damages provision is included. The project involves the retrofit of an existing detention basin, including clearing and grubbing, installation of amended soils and underdrain systems, outlet structure replacement, drainage structures and piping, gabion basket forebay construction, and connection to the existing storm sewer within East Campus Drive. No incumbent vendors or set-aside designations are identified in this specification section.

View the file

Other files

File Type Posted
WC2608 Solicitation Cover Sheet. 10.29.26.pdf PDF
003-012600 CONTRACT MODIFIATION PROCEDURES 71-FA-8.1.pdf PDF
005-013100 PROJECT MANAGEMENT AND COORDINATION 71-FA-8.1.pdf PDF
008-013300 SUBMITTAL PROCEDURES 71-FA-8.1.pdf PDF
012-016000 PRODUCT REQUIREMENTS 71-FA-8.1.pdf PDF
015-017329 CUTTING AND PATCHING 71-FA-8.1.pdf PDF
315000 - Excavation Backfill and Compaction.pdf PDF
310519 - Geosynthetics.pdf PDF
B5 WC2608 Bid Bond Form, 71-FA-8.2_Dec_2023 10.24.26.pdf PDF
001-011000, SUMMARY 71-FA-8.1.pdf PDF
019-017839 PROJECT RECORD DOCUMENTS 71-FA-8.1.pdf PDF
C4 WC2608 Insurance Rider_71-FA-8.2_Dec_2023 10.29.26.pdf PDF
004-012900 PAYMENT PROCEDURES 71-FA-8.1.pdf PDF
002-012200 UNIT PRICES 71-FA-8.1.pdf PDF
016-017700 CLOSEOUT PROCEDURES 71-FA-8.1.pdf PDF
312500 - Erosion & Sedimentation Control.pdf PDF
014-017123 FIELD ENGINEERING 71-FA-8.1.pdf PDF
329200 - TURF AND GRASSES.pdf PDF
C6 WC2608 Weekly Certified Payroll Form llc-25[1].pdf PDF
C5 WC2608 PW 26-07767.pdf PDF
B6 WC2608 SDB Instructions, 71-FA-8.2_Dec_2023 10.24.26.pdf PDF
006-013119 PROJECT MEETINGS 71-FA-8.1.pdf PDF
C2 WC2608 P and P Contract Bond Form 71-FA-8.2_Dec_2023 UPDATED 10.24.26.pdf PDF
017-017823 OPERATIONS AND MAINTENANCE DATA 71-FA-8.1.pdf PDF
B7 WC2608 SDB Form, 71-FA-8.2_Dec_2023 10.24.26.pdf PDF
B4 WC2608 Bid Form, 71-FA-8.2_Dec_2023 10.24.26.pdf PDF
013-016200 PRODUCT OPTIONS 71-FA-8.1.pdf PDF
010-014500 QUALITY CONTROL 71-FA-8.1.pdf PDF
Bid Set Oct 2026 SIGNED SEALED WC2608 1.pdf PDF
C3 WC2608 General_Conditions_71-FA-8.2_Dec_2023 10.24.26..pdf PDF
C1 WC2608 Standard Form of K_71-FA-8.2_Dec_2023.pdf PDF
A WC2608.1_000000_TABLE OF CONTENTS_10-29-26.pdf PDF
C8 WC2608 PW EmploymentVerification FORM.pdf PDF
311000 - Site Clearing.pdf PDF
313700 - Riprap.pdf PDF
C7 WC2608 Public Works Employment Verification Notice 2.16.24 (1).pdf PDF
B2 WC2608 Spec Instr to Bidders 71-FA-8.2_Dec_2023 10.30.26.pdf PDF
007-013200B CONSTRUCTION PROGRES DOCUMENTATION 71-FA-8.1.pdf PDF
B8 WC2608 Contractor Qualification Statement updated 10.24.26.pdf PDF
018-017836 WARRANTIES 71-FA-8.1.pdf PDF
4-RFP WCU0508262274 - Appendix A - Technical Submittal Response.pdf PDF
1-RFP WCU05808262274 - Appendix C - Contract Exceptions.pdf PDF
2-RFP WCU0508262247 - Appendix B - Trade Secret Confidential Information Notice.pdf PDF
3-RFP WCU0508262274 - Full-Service Print, Mail, and Distribution Service Contractor.pdf PDF
1-IFB WCU0407261013 - (1) NEW 2025 Low Cab Forward (LCF) 16 Foot Box Truck .pdf PDF
2-IFB WCU0407261013 - Bid Specification - Attachment A.pdf PDF
1-WC2602 Contract Forms Conditions.zip ZIP file
4-WC2602 Drawings.zip ZIP file
2-WC2602 Specs 3.30.2026 updated.zip ZIP file
3-WC2602 Bid Form Requirements.zip ZIP file
Show 40 more

Latest 50 of 66 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

WCU Project No. WC2608 SWOPE Stormwater Basin Retrofit Project

October 8, 2026

STORM DRAINAGE 334211 - 1

RETTEW Project No.: 0272903615

DIVISION 33 – UTILITIES

SECTION 334211 - STORM DRAINAGE

PART 1 - GENERAL

1.1 RELATED REFERENCES

A. Drawings and general provisions of this Contract, including General and Supplementary Conditions and Division 1 specification sections, apply to this section.

1.2 DESCRIPTION OF WORK

A. The Work within this section includes, but is not limited to, the furnishing of all equipment, labor and materials, and performing all operations necessary to construct pipe culverts, combination storm sewer and underdrain, endwalls, inlets, pipes underdrain, pavement base drain, and end sections in accordance with the specifications, applicable drawings, and Contract Documents.

1.3 QUALITY ASSURANCE

A. Referenced standards shall be the current Pennsylvania Department of Transportation (PennDOT) Publication 408, specifications and its revisions.

1.4 SUBMITTALS

A. Certificates: CONTRACTOR shall submit three (3) copies of each manufacturer's certification and PennDOT form CS-4171 certifying that the materials meet or exceed specification requirements.

B. Shop Drawings: Submit detailed shop drawings for precast concrete catch basins, inlet grates and frames, and poured in place concrete construction. Submit manufacturer's descriptive and technical product data for storm sewer pipes.

PART 2 - MATERIALS

2.1 PIPES

A. As specified in PennDOT Publication 408, Sections 601 and Section 610 and as shown on the drawings.

2.2 MANHOLES, INLETS & ENDWALLS

A. As specified in PennDOT Publication 408, Section 605.

October 8, 2026

STORM DRAINAGE 334211 - 2

RETTEW Project No.: 0272903615

2.3 AMENDED SOILS

A. As specified on the drawings.

2.4 CLEANOUT

A. As specified on the drawings.

2.5 GATE VALVE

A. As specified on the drawings.

2.6 GABIONS

A. As specified in PennDOT Publication 408, Section 626 and as shown on the drawings

2.7 OUTLET STRUCTURE

A. As specified in PennDOT Publication 408, Section 875 and as shown on the drawings

PART 3 - CONSTRUCTION

3.1 PIPES

A. As specified in PennDOT Publication 408, Sections 601 and 610, and as shown on the drawings.

3.2 MANHOLES, INLETS & ENDWALLS

A. As specified in PennDOT Publication 408, Section 605.

3.3 AMENDED SOILS

A. As specified on the drawings.

3.4 CLEANOUT

A. As specified on the drawings.

3.5 GATE VALVE

A. As specified on the drawings.

October 8, 2026

STORM DRAINAGE 334211 - 3

RETTEW Project No.: 0272903615

3.6 GABIONS

A. As specified in PennDOT Publication 408, Section 626 and as shown on the drawings

3.7 OUTLET STRUCTURE

A. As specified in PennDOT Publication 408, Section 875 and as shown on the drawings

END OF SECTION 334211

PART 1 - GENERAL
1.1 RELATED REFERENCES
A. Drawings and general provisions of this Contract, including General and Supplementary Conditions and Division 1 specification sections, apply to this section.
1.2 DESCRIPTION OF WORK
A. The Work within this section includes, but is not limited to, the furnishing of all equipment, labor and materials, and performing all operations necessary to construct pipe culverts, combination storm sewer and underdrain, endwalls, inlets, pipes ...
1.3 QUALITY ASSURANCE
A. Referenced standards shall be the current Pennsylvania Department of Transportation (PennDOT) Publication 408, specifications and its revisions.
1.4 SUBMITTALS
A. Certificates: CONTRACTOR shall submit three (3) copies of each manufacturer's certification and PennDOT form CS-4171 certifying that the materials meet or exceed specification requirements.
B. Shop Drawings: Submit detailed shop drawings for precast concrete catch basins, inlet grates and frames, and poured in place concrete construction. Submit manufacturer's descriptive and technical product data for storm sewer pipes.
PART 2 - MATERIALS
2.1 PIPES
A. As specified in PennDOT Publication 408, Sections 601 and Section 610 and as shown on the drawings.
2.2 MANHOLES, INLETS & ENDWALLS
A. As specified in PennDOT Publication 408, Section 605.
2.3 AMENDED SOILS
A. As specified on the drawings.
2.4 CLEANOUT
A. As specified on the drawings.
2.5 GATE VALVE
A. As specified on the drawings.
2.6 GABIONS
A. As specified in PennDOT Publication 408, Section 626 and as shown on the drawings
2.7 OUTLET STRUCTURE
A. As specified in PennDOT Publication 408, Section 875 and as shown on the drawings
PART 3 - CONSTRUCTION
3.1 PIPES
A. As specified in PennDOT Publication 408, Sections 601 and 610, and as shown on the drawings.
3.2 MANHOLES, INLETS & ENDWALLS
A. As specified in PennDOT Publication 408, Section 605.
3.3 AMENDED SOILS
A. As specified on the drawings.
3.4 CLEANOUT
A. As specified on the drawings.
3.5 GATE VALVE
A. As specified on the drawings.
3.6 GABIONS
A. As specified in PennDOT Publication 408, Section 626 and as shown on the drawings
3.7 OUTLET STRUCTURE
A. As specified in PennDOT Publication 408, Section 875 and as shown on the drawings