This file is a Closeout Procedures specification (Section 017700) for the WC2608 SWOPE Stormwater Basin Retrofit Project at West Chester University of Pennsylvania, dated October 8, 2026. The document establishes procedures for substantial completion and final completion of the construction project, which involves the retrofit of an existing detention basin at the southeast corner of S High Street and E Campus Drive in West Chester, Pennsylvania. The specification requires contractors to complete 90 percent of work before substantial completion certification and outlines 16 prerequisite items including start-up and testing, user training, final cleaning, submission of manuals and warranties, and acquisition of necessary permits. Contractors must submit written requests for substantial completion inspections at least seven days in advance, and the University must respond within seven days to either proceed with inspection, schedule inspection, or advise of unmet requirements. Final completion requires all punchlist items and contract requirements to be satisfied before the Certificate of Final Completion is issued, which triggers processing of the Final Application for Payment.
The specification establishes comprehensive requirements for final cleaning and facility preparation, mandating that contractors employ experienced workers or professional cleaners to bring all surfaces, equipment, and grounds to commercial standards. Additional requirements include filter replacement, exterminator services for pest control, removal of temporary protection and construction debris, arrangement for disposition of excess materials, and videotaped recording of user training sessions. Each separate prime contractor is responsible for requesting inspections and coordinating with other contractors; the University designates a lead contractor when multiple contractors are involved in equipment or systems. The document references related specifications for Record Documents (Section 017836) and Operation and Maintenance Data (Section 017823) but contains no pricing information, set-asides, or incumbent vendor identification within the closeout procedures themselves.
View the file
Other files
Show 40 more
Latest 50 of 66 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
WCU Project No. WC2608 SWOPE Stormwater Basin Retrofit Project
October 8, 2026
General Requirements for 71-FA-8.1 Section 017700 – Closeout Procedures
SECTION 017700
CLOSEOUT PROCEDURES
PART 1 - GENERAL
1.01 SUBSTANTIAL COMPLETION INSPECTION
A. Substantial Completion is when the Work is sufficiently completed in accordance with the Contract and certified by the University, as modified by change orders, so that the project can be used, occupied, or operated for its intended use. In no event shall a project be certified as substantially complete until at least ninety percent (90%) of the Work on the project is complete.
The University reserves, at its sole discretion, the right to certify substantial completion for portions of the project.
B. Each Separate Prime Contractor is responsible for requesting and executing a Substantial Completion inspection. Maximum coordination between the various Separate Prime Contractors is strongly encouraged for the execution of Substantial Completion inspections.
C. Before a Substantial Completion inspection can be held, the following items shall have been completed by the Contactor and/or been submitted to the University.
1. completion of start-up, testing, and commissioning checks of equipment and systems
2. completion of user training
3. completion of Contract Work
4. completion of final cleaning
5. removal of temporary protection and facilities
6. removal of construction tools, mock-ups, and similar elements
7. removal of surplus materials, rubbish, and similar elements
8. change to permanent locks, and submission of keys
9. submission of testing, test and balance, and commissioning reports
10. submission of Operating and Maintenance Manuals and Instructions
11. submission of Record Documents
12. submission of warranty documents and warranty plan
13. submission of spare parts, tools, extra stock, and similar required items
14. submission of final meter readings, and measured record of stored fuel(s) (if any)
15. submission of or coordination for Occupancy permits (UCC)
16. submission of or coordination for other permits and approvals (boiler inspection, etc.)
D. The Contractor shall submit to the University a written request for a Substantial Completion inspection. The request shall certify that the items required for a Substantial Completion inspection (paragraph 1.01 C.) have been completed, or shall identify when they will be completed or explain reasons why items will not be complete. The request shall be submitted at least seven (7) days prior to the requested date for the inspection, unless otherwise specified or agreed upon.
E. Within seven (7) days of receipt of a request for a Substantial Completion inspection, unless otherwise specified or agreed upon, the University will either proceed with the inspection, schedule the inspection to take place within a reasonable period of time, or advise the Contractor of requirements that must be met before the Project can be considered ready for a Substantial Completion inspection.
October 8, 2026
General Requirements for 71-FA-8.1 Section 017700 – Closeout Procedures
F. Upon inspection, the University will either issue the Certificate of Substantial Completion, advise the Contractor of items that must be completed or corrected before the Certificate will be issued, or advise the Contractor that another Substantial Completion inspection must be requested and take place.
1.02 FINAL COMPLETION AND FINAL COMPLETION INSPECTION
A. Final Completion is that point in the Contract at which all Work on the Project is complete, and all other Contract requirements have been completed. Final Completion may or may not involve an inspection.
B. Each Separate Prime Contractor is responsible for requesting Final Completion. Coordination between the various Separate Prime Contractors is encouraged for the execution of any Final Completion inspections that may be required.
C. Before the Contractor can request Final Completion, the following items shall have been completed by the Contactor and/or been submitted to the University.
1. completion of punchlist items
2. completion of all items required for Substantial Completion (paragraph 1.01)
3. completion of any and all other Contract requirements
D. The Contractor shall submit to the University a written request for Final Completion. The request shall certify that the items required for Final Completion (paragraph 1.02 C.) have been completed. If an inspection is required, the request shall be submitted at least seven (7) days prior to the requested date for the inspection.
E. Upon receipt of a request for Final Completion, the University will either issue the Certificate of Final Completion or advise the Contractor of requirements that must be met before the Project can be considered ready for Final Completion.
F. When the University issues the Certificate of Final Completion, the Final Application for Payment can be processed.
1.03 FINAL CLEANING AND PREPARATION OF THE FACILITY
A. The following paragraphs address final cleaning and preparation generally applicable to most Contracts. Additional or specific requirements applicable to this Contract may be included in Specification Section 011000, Summary, in specific Technical Specification sections, or in a dedicated Section on Final Cleaning and Preparation.
B. Cleaning.
1. The Contractor shall employ experienced workers or professional cleaners for final cleaning. Workers shall be supervised.
2. Each surface, equipment, or unit shall be cleaned to the condition expected in a normal, commercial building cleaning and maintenance program.
3. Transparent materials, including mirrors and glass in doors and windows, shall be cleaned.
Glazing compound and other substances that are noticeable vision-obscuring materials shall be removed. Chipped or broken glass and other damaged transparent materials shall be replaced. Windows and two-sided glass shall be cleaned on both sides.
October 8, 2026
General Requirements for 71-FA-8.1 Section 017700 – Closeout Procedures
4. Exposed exterior and interior hard-surfaced finishes shall be cleaned to a dust-free condition, free of stains, films, and similar foreign substances. Reflective surfaces shall be restored to their original reflective condition. Concrete floors shall be broom clean.
Finished floors shall be clean wet-mopped. Carpeted surfaces shall be vacuumed.
5. Surfaces of mechanical and electrical equipment shall be wiped to remove excess lubrication and other substances. Plumbing fixtures shall be cleaned to a sanitary condition.
Light fixtures, lamps, switches, and outlet plates shall be cleaned. Construction bulbs shall be replaced with new bulbs.
6. The site, including landscape development areas, shall be cleaned of rubbish, litter, and other foreign substances. Paved areas shall be broom clean, and all stains, spills, and other foreign deposits shall be removed. Grounds that are neither paved nor planted shall be raked to a smooth even-textured surface.
7. Debris shall be removed from roofs, drainage systems, gutters, and downspouts.
8. The inside of cabinets and other concealed areas shall be cleaned.
9. Labels that are not permanent labels shall be removed.
10. In all cases the Contractor shall comply with manufacturer's instructions for cleaning and preparation, and with regulations of authorities having jurisdiction and safety standards for cleaning.
C. Other Preparation.
1. Filters of operating equipment shall be replaced. Strainers of operating equipment and/or systems shall be cleaned. Ducts, blowers, coils, and similar components shall be cleaned if the system was operated during construction without filters.
2. The Contractor shall engage an experienced exterminator to make a final inspection, and rid the Project of rodents, insects, and other pests.
3. The Contractor shall remove temporary protection and facilities installed for protection of the Work, workers, and the general public during construction.
4. Waste or excess materials and debris shall be removed from the site and disposed of in a lawful manner. Such materials shall not be burned, and shall not be buried on University property. Volatile, harmful, or dangerous materials shall not be discharged into drainage systems or onto or into the ground.
5. The Contractor shall arrange with the University for disposition of excess materials of value that remain after completion of Work and become University property.
1.04 RECORD DOCUMENTS
See Specification Section 017836, Project Record Documents.
1.05 OPERATION AND MAINTENANCE MANUALS
See Specification Section 017823, Operation and Maintenance Data.
1.06 USER TRAINING
October 8, 2026
General Requirements for 71-FA-8.1 Section 017700 – Closeout Procedures
A. The following subparagraphs address general User Training requirements. The requirements for User Training, and any additional or specific requirements related to that User Training, is identified and included in specific Technical Specification sections.
B. Each Separate Prime Contractor shall arrange for and perform User Training for any equipment or system installed by that Contractor. Where equipment and systems involve more than one Separate Prime Contractor, the University will designate one Contractor as the lead for the Training. The Lead shall coordinate with the other Separate Prime Contractors involved, and all Contractors shall participate in the Training.
C. User Training shall provide to the University’s operating and maintenance personnel instruction in proper operation and maintenance or that equipment or system.
D. User Training shall be held at mutually agreed upon times and locations. Unless impossible or impractical, Training should be held at the location of the equipment or the system.
E. For equipment or systems that require seasonal operation, separate Training sessions may be required at appropriate times.
F. The Contractor shall engage for the Training instructors who are thoroughly trained and experienced in the operation and maintenance of the equipment or system involved. The instructors should come from the installers or from the manufacturer.
G. Draft Operating and Maintenance Manuals shall be available for User Training, and shall be used as the basis of the Training.
H. The Contractor shall videotape or digitally record the User Training, in a format suitable to the University. One (1) copy shall be provided with the Operating and Maintenance Manual.
PART 2 – PRODUCTS
(Not Used)
PART 3 – EXECUTION
(Not Used)
END OF SECTION 017700
| SECTION 017700 |
| CLOSEOUT PROCEDURES |
| PART 1 - GENERAL |
| 1.01 SUBSTANTIAL COMPLETION INSPECTION |
| 1.02 FINAL COMPLETION AND FINAL COMPLETION INSPECTION |
| 1.03 FINAL CLEANING AND PREPARATION OF THE FACILITY |
| 1.04 RECORD DOCUMENTS |
| See Specification Section 017836, Project Record Documents. |
| H. The Contractor shall videotape or digitally record the User Training, in a format suitable to the University. One (1) copy shall be provided with the Operating and Maintenance Manual. |