Section 017839 Project Record Documents for WC2608 SWOPE Stormwater Basin Retrofit Project

This specification document outlines requirements for project record documents (as-built drawings and record specifications) for the WC2608 SWOPE Stormwater Basin Retrofit Project at West Chester University of Pennsylvania, with a project date of October 8, 2026. The document establishes mandatory procedures for maintaining, updating, and submitting record documentation throughout the construction phase. Each separate prime contractor must maintain clean, undamaged sets of contract drawings, shop drawings, and project specifications as record documents, with periodic updates during construction to capture concealed elements and actual installation variations. Record drawings must be marked in red erasable pencil to indicate deviations from original designs, with additional colors used to distinguish variations in separate work categories. All addenda and change orders must be cross-referenced on record drawings, and specifications must be organized into bound sets with clear identification on cover sheets. The contractor must submit one set of draft (red line) record drawings and record specifications to the University upon work completion, with provisions for University and professional review and mandatory corrections if information is missing.

The specification permits contractors to submit record documents in electronic format if agreeable to both the contractor and University. Upon review, if the University and professional determine submissions are satisfactory, the professional will incorporate red line changes into electronic format documents. This specification does not include product or execution requirements, functioning solely as a general requirements section for documentation procedures. No pricing, set-asides, or contract cost information is included in this specifications document; such information would be contained in other contract documents associated with the stormwater basin retrofit project.

View the file

Other files

File Type Posted
WC2608 Solicitation Cover Sheet. 10.29.26.pdf PDF
003-012600 CONTRACT MODIFIATION PROCEDURES 71-FA-8.1.pdf PDF
005-013100 PROJECT MANAGEMENT AND COORDINATION 71-FA-8.1.pdf PDF
008-013300 SUBMITTAL PROCEDURES 71-FA-8.1.pdf PDF
012-016000 PRODUCT REQUIREMENTS 71-FA-8.1.pdf PDF
015-017329 CUTTING AND PATCHING 71-FA-8.1.pdf PDF
315000 - Excavation Backfill and Compaction.pdf PDF
310519 - Geosynthetics.pdf PDF
B5 WC2608 Bid Bond Form, 71-FA-8.2_Dec_2023 10.24.26.pdf PDF
001-011000, SUMMARY 71-FA-8.1.pdf PDF
C4 WC2608 Insurance Rider_71-FA-8.2_Dec_2023 10.29.26.pdf PDF
004-012900 PAYMENT PROCEDURES 71-FA-8.1.pdf PDF
002-012200 UNIT PRICES 71-FA-8.1.pdf PDF
016-017700 CLOSEOUT PROCEDURES 71-FA-8.1.pdf PDF
312500 - Erosion & Sedimentation Control.pdf PDF
014-017123 FIELD ENGINEERING 71-FA-8.1.pdf PDF
329200 - TURF AND GRASSES.pdf PDF
C6 WC2608 Weekly Certified Payroll Form llc-25[1].pdf PDF
C5 WC2608 PW 26-07767.pdf PDF
B6 WC2608 SDB Instructions, 71-FA-8.2_Dec_2023 10.24.26.pdf PDF
006-013119 PROJECT MEETINGS 71-FA-8.1.pdf PDF
C2 WC2608 P and P Contract Bond Form 71-FA-8.2_Dec_2023 UPDATED 10.24.26.pdf PDF
017-017823 OPERATIONS AND MAINTENANCE DATA 71-FA-8.1.pdf PDF
B7 WC2608 SDB Form, 71-FA-8.2_Dec_2023 10.24.26.pdf PDF
B4 WC2608 Bid Form, 71-FA-8.2_Dec_2023 10.24.26.pdf PDF
013-016200 PRODUCT OPTIONS 71-FA-8.1.pdf PDF
010-014500 QUALITY CONTROL 71-FA-8.1.pdf PDF
Bid Set Oct 2026 SIGNED SEALED WC2608 1.pdf PDF
C3 WC2608 General_Conditions_71-FA-8.2_Dec_2023 10.24.26..pdf PDF
C1 WC2608 Standard Form of K_71-FA-8.2_Dec_2023.pdf PDF
334211 - Storm Drainage.pdf PDF
A WC2608.1_000000_TABLE OF CONTENTS_10-29-26.pdf PDF
C8 WC2608 PW EmploymentVerification FORM.pdf PDF
311000 - Site Clearing.pdf PDF
313700 - Riprap.pdf PDF
C7 WC2608 Public Works Employment Verification Notice 2.16.24 (1).pdf PDF
B2 WC2608 Spec Instr to Bidders 71-FA-8.2_Dec_2023 10.30.26.pdf PDF
007-013200B CONSTRUCTION PROGRES DOCUMENTATION 71-FA-8.1.pdf PDF
B8 WC2608 Contractor Qualification Statement updated 10.24.26.pdf PDF
018-017836 WARRANTIES 71-FA-8.1.pdf PDF
4-RFP WCU0508262274 - Appendix A - Technical Submittal Response.pdf PDF
1-RFP WCU05808262274 - Appendix C - Contract Exceptions.pdf PDF
2-RFP WCU0508262247 - Appendix B - Trade Secret Confidential Information Notice.pdf PDF
3-RFP WCU0508262274 - Full-Service Print, Mail, and Distribution Service Contractor.pdf PDF
1-IFB WCU0407261013 - (1) NEW 2025 Low Cab Forward (LCF) 16 Foot Box Truck .pdf PDF
2-IFB WCU0407261013 - Bid Specification - Attachment A.pdf PDF
1-WC2602 Contract Forms Conditions.zip ZIP file
4-WC2602 Drawings.zip ZIP file
2-WC2602 Specs 3.30.2026 updated.zip ZIP file
3-WC2602 Bid Form Requirements.zip ZIP file
Show 40 more

Latest 50 of 66 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

WCU Project No. WC2608 SWOPE Stormwater Basin Retrofit Project

October 8, 2026

General Requirements for 71-FA-8.1 Section 017839 – Project Record Documents

SECTION 017839

PROJECT RECORD DOCUMENTS

PART 1 - GENERAL

1.01 RECORD DOCUMENTS

A. Record Documents consist of Record Drawings (As-Built Drawings) and Record Specifications.

B. Record Documents shall not be used for construction purposes. During the Work they shall be protected from deterioration and loss in a secure, fire-resistive location.

C. Record Documents shall have been updated and checked periodically during the Work.

D. The Contractor shall provide reasonable periodic access to Record Documents by the University during normal working hours.

1.02 RECORD DRAWINGS (AS-BUILT DRAWINGS)

A. Each Separate Prime Contractor shall maintain a clean and undamaged set of Contract Drawings and Shop Drawings as the Record Drawings. Periodic updating shall pay particular attention to concealed elements that would be difficult to measure and record at a later date.

B. Record Drawings shall be marked to show where the actual installation varies from the drawings as originally shown. Markings shall be in red erasable pencil. Other colors shall be used to distinguish between variations in separate categories of the Work.

C. Where Shop Drawings are used, cross references shall be noted at the corresponding locations on the Contract Drawings.

D. Related Addenda and Change Orders shall be noted where applicable.

E. Record Drawings shall be organized into manageable sets of sheets, bound with durable paper cover sheets, and printed with suitable titles, dates, and other identification on the cover of each set.

F. At the completion of the Work, the Contractor shall submit one (1) set of draft (Red Line) Record Drawings to the University.

G. The University and/or the Professional will review the submitted Record Drawings. If the Drawings are missing changes or other information, they will be returned to the Contractor for correction and proper completion. If the Drawings are satisfactory, the University will have the Professional incorporate the Red Line changes into the electronic format drawings.

H. If agreeable to the Contractor and the University, the Contractor may maintain and submit his Record Drawings in electronic format.

1.03 RECORD SPECIFICATIONS

A. Each Separate Prime Contractor shall maintain a clean and undamaged copy of the Project Manual (Technical Specifications), including Addenda and Change Orders, as the Record Specifications.

WCU Project No. WC2608 SWOPE Stormwater Basin Retrofit Project

October 8, 2026

General Requirements for 71-FA-8.1 Section 017839 – Project Record Documents

B. During the Work, periodic updating of the Record Specifications shall be done, with particular attention paid to substitutions, selection of options, and similar information on elements that are concealed or cannot otherwise be readily discerned later by direct observation.

C. Record Specifications shall be marked to show where the actual Work varies from the original Specifications. Markings shall be in red erasable pencil. Other colors shall be used to distinguish between variations in separate categories of the Work.

D. Related Addenda and Change Orders shall be noted where applicable.

E. At the completion of the Work, the Contractor shall submit one (1) set of draft Record Specifications to the University.

F. The University and/or the Professional will review the submitted Record Specifications. If the Specifications are missing changes or other information, they will be returned to the Contractor for correction and proper completion. If the Specifications are satisfactory, the University will have the Professional incorporate the Red Line changes into the electronic format specifications.

G. If agreeable to the Contractor and the University, the Contractor may maintain and submit his Record Specifications in electronic format.

PART 2 – PRODUCTS

(Not Used)

PART 3 – EXECUTION

(Not Used)

END OF SECTION 017839

SECTION 017839
PROJECT RECORD DOCUMENTS
PART 1 - GENERAL

File details come from the government source that posted it. Updated .