This is a Scope of Work document for the WC2608 SWOPE Stormwater Basin Retrofit Project, a construction project at West Chester University of Pennsylvania. Section 311000 addresses Site Clearing activities, which constitute the initial phase of work for the stormwater basin retrofit located at the southeast corner of the intersection of South High Street and East Campus Drive in West Chester, Pennsylvania. The site clearing work includes protecting existing trees and vegetation to remain, removing trees and other vegetation, clearing and grubbing, topsoil stripping, and removing above-grade and below-grade site features. The project timeline spans from December 7, 2026, to July 3, 2027, totaling 208 calendar days. A pre-bid site visit is scheduled for November 6, 2026, at 11:00 AM. The contract cost range is $450,000 to $550,000 for general construction work, and the project is classified as a Prevailing Wage project under Pennsylvania wage determination serial number 26-07767 dated August 25, 2026.
The specification document establishes that all cleared materials, except those designated for stockpiling or identified as Owner's property, become Contractor's property and must be removed from the site. Topsoil must be stripped carefully to prevent intermingling with subsoil, with stockpile heights limited to 72 inches and positioned away from the drip lines of remaining trees. The Contractor is responsible for providing erosion-control measures, protecting benchmarks and survey control points, and maintaining traffic flow on adjacent roads and walks without obstruction unless Owner permission is obtained. All debris, unsuitable topsoil, and waste materials must be legally disposed of off the Owner's property. The document contains no set-asides for disadvantaged enterprises, and no incumbent contractors are identified.
View the file
Other files
Show 40 more
Latest 50 of 66 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
WCU Project No. WC2608 SWOPE Stormwater Basin Retrofit Project
October 8, 2026
SITE CLEARING 311000-1
RETTEW Project No.: 0272903615
DIVISION 31 – EARTHWORK
SECTION 311000 - SITE CLEARING
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes the following:
1. Protecting existing trees and vegetation to remain.
2. Removing trees and other vegetation.
3. Clearing and grubbing.
4. Topsoil stripping.
5. Removing above-grade site features.
6. Removing below-grade site features.
1.2 DEFINITIONS
A. Topsoil: Natural or cultivated surface-soil layer containing organic matter and sand, silt, and clay particles; friable, pervious, and black or a darker shade of brown, gray, or red than underlying subsoil; reasonably free of subsoil, clay lumps, gravel, and other objects more than 2 inches in diameter; and free of weeds, roots, and other deleterious materials.
1.3 MATERIALS OWNERSHIP
A. Except for materials indicated to be stockpiled or to remain Owner's property, cleared materials shall become Contractor's property and shall be removed from the site.
1.4 SUBMITTALS
A. Photographs, sufficiently detailed, of existing conditions of trees and plantings, adjoining construction, and site improvements that might be misconstrued as damage caused by site clearing.
B. Record drawings according to Division 1 Section "Contract Closeout." Identify and accurately locate capped utilities and other subsurface structural, electrical, and mechanical conditions.
1.5 PROJECT CONDITIONS
A. Traffic: Minimize interference with adjoining roads, streets, walks, and other adjacent occupied or used facilities during site-clearing operations.
1. Do not close or obstruct streets, walks, or other adjacent occupied or used facilities without permission from Owner.
2. Provide alternate routes around closed or obstructed traffic ways if required by
Owner.Notify utility locator service for area where Project is located before site clearing.
October 8, 2026
SITE CLEARING 311000-2
RETTEW Project No.: 0272903615
PART 2 - PRODUCTS
2.1 SOIL MATERIALS
A. Satisfactory Soil Materials: Requirements for satisfactory soil materials are specified in Section 315000. Obtain approved borrow soil materials off-site when satisfactory soil materials are not available on-site.
PART 3 - EXECUTION
3.1 PREPARATION
A. Protect and maintain benchmarks and survey control points from disturbance during construction.
B. Provide erosion-control measures to prevent soil erosion and discharge of soil-bearing water runoff or airborne dust to adjacent properties and walkways.
C. Locate and clearly flag trees and vegetation to remain or to be relocated.
D. Protect existing site improvements to remain from damage during construction. Restore damaged improvements to their original condition, as acceptable to Owner.
3.2 CLEARING AND GRUBBING
A. Remove obstructions, trees, shrubs, grass, and other vegetation to permit installation of new construction. Removal includes digging out stumps and obstructions and grubbing roots.
1. Do not remove trees, shrubs, and other vegetation indicated to remain or to be relocated.
2. Cut minor roots and branches of trees indicated to remain in a clean and careful manner where such roots and branches obstruct installation of new construction.
3. Completely remove stumps, roots, obstructions, and debris extending to a depth of 18 inches below exposed subgrade.
4. Use only hand methods for grubbing within drip line of remaining trees.
B. Fill depressions caused by clearing and grubbing operations with satisfactory soil material, unless further excavation or earthwork is indicated.
1. Place fill material in horizontal layers not exceeding 8-inch loose depth and compact each layer to a density equal to adjacent original ground.
3.3 TOPSOIL STRIPPING
A. Remove sod and grass before stripping topsoil.
B. Strip topsoil to whatever depths are encountered in a manner to prevent intermingling with underlying subsoil or other waste materials.
1. Strip surface soil of unsuitable topsoil, including trash, debris, weeds, roots, and other waste materials.
October 8, 2026
SITE CLEARING 311000-3
RETTEW Project No.: 0272903615
C. Stockpile topsoil materials away from edge of excavations without intermixing with subsoil.
Grade and shape stockpiles to drain surface water. Cover to prevent windblown dust.
1. Limit height of topsoil stockpiles to 72 inches.
2. Do not stockpile topsoil within drip line of remaining trees.
3. Dispose of excess topsoil as specified for waste material disposal.
4. Stockpile surplus topsoil and allow for respreading deeper topsoil.
3.4 DISPOSAL
A. Disposal: Remove surplus soil material, unsuitable topsoil, obstructions, demolished materials, and waste materials, including trash and debris, and legally dispose of them off Owner's property.
END OF SECTION 311000
| PART 1 - GENERAL |
| 1.1 SUMMARY |
| A. This Section includes the following: |
| 1. Protecting existing trees and vegetation to remain. |
| 2. Removing trees and other vegetation. |
| 3. Clearing and grubbing. |
| 4. Topsoil stripping. |
| 5. Removing above-grade site features. |
| 6. Removing below-grade site features. |
| 1.2 DEFINITIONS |
| A. Topsoil: Natural or cultivated surface-soil layer containing organic matter and sand, silt, and clay particles; friable, pervious, and black or a darker shade of brown, gray, or red than underlying subsoil; reasonably free of subsoil, clay lumps, g... |
| 1.3 MATERIALS OWNERSHIP |
| A. Except for materials indicated to be stockpiled or to remain Owner's property, cleared materials shall become Contractor's property and shall be removed from the site. |
| 1.4 SUBMITTALS |
| A. Photographs, sufficiently detailed, of existing conditions of trees and plantings, adjoining construction, and site improvements that might be misconstrued as damage caused by site clearing. |
| B. Record drawings according to Division 1 Section "Contract Closeout." Identify and accurately locate capped utilities and other subsurface structural, electrical, and mechanical conditions. |
| 1.5 PROJECT CONDITIONS |
| A. Traffic: Minimize interference with adjoining roads, streets, walks, and other adjacent occupied or used facilities during site-clearing operations. |
| 1. Do not close or obstruct streets, walks, or other adjacent occupied or used facilities without permission from Owner. |
| 2. Provide alternate routes around closed or obstructed traffic ways if required by Owner.Notify utility locator service for area where Project is located before site clearing. |
| PART 2 - PRODUCTS |
| 2.1 SOIL MATERIALS |
| A. Satisfactory Soil Materials: Requirements for satisfactory soil materials are specified in Section 315000. Obtain approved borrow soil materials off-site when satisfactory soil materials are not available on-site. |
| PART 3 - EXECUTION |
| 3.1 PREPARATION |
| A. Protect and maintain benchmarks and survey control points from disturbance during construction. |
| B. Provide erosion-control measures to prevent soil erosion and discharge of soil-bearing water runoff or airborne dust to adjacent properties and walkways. |
| C. Locate and clearly flag trees and vegetation to remain or to be relocated. |
| D. Protect existing site improvements to remain from damage during construction. Restore damaged improvements to their original condition, as acceptable to Owner. |
| 3.2 CLEARING AND GRUBBING |
| A. Remove obstructions, trees, shrubs, grass, and other vegetation to permit installation of new construction. Removal includes digging out stumps and obstructions and grubbing roots. |
| 1. Do not remove trees, shrubs, and other vegetation indicated to remain or to be relocated. |
| 2. Cut minor roots and branches of trees indicated to remain in a clean and careful manner where such roots and branches obstruct installation of new construction. |
| 3. Completely remove stumps, roots, obstructions, and debris extending to a depth of 18 inches below exposed subgrade. |
| 4. Use only hand methods for grubbing within drip line of remaining trees. |
| B. Fill depressions caused by clearing and grubbing operations with satisfactory soil material, unless further excavation or earthwork is indicated. |
| 1. Place fill material in horizontal layers not exceeding 8-inch loose depth and compact each layer to a density equal to adjacent original ground. |
| 3.3 TOPSOIL STRIPPING |
| A. Remove sod and grass before stripping topsoil. |
| B. Strip topsoil to whatever depths are encountered in a manner to prevent intermingling with underlying subsoil or other waste materials. |
| 1. Strip surface soil of unsuitable topsoil, including trash, debris, weeds, roots, and other waste materials. |
| C. Stockpile topsoil materials away from edge of excavations without intermixing with subsoil. Grade and shape stockpiles to drain surface water. Cover to prevent windblown dust. |
| 1. Limit height of topsoil stockpiles to 72 inches. |
| 2. Do not stockpile topsoil within drip line of remaining trees. |
| 3. Dispose of excess topsoil as specified for waste material disposal. |
| 4. Stockpile surplus topsoil and allow for respreading deeper topsoil. |
| 3.4 DISPOSAL |
| A. Disposal: Remove surplus soil material, unsuitable topsoil, obstructions, demolished materials, and waste materials, including trash and debris, and legally dispose of them off Owner's property. |