013-016200 PRODUCT OPTIONS 71-FA-8.1.pdf

PDF 215 KB Posted

Attached to
WC2608 SWOPE Stormwater Basin Retrofit Project
Solicitation number
Not on record
Issued by
Chester County, Pennsylvania

About this file

This Product Options specification document, issued by West Chester University of Pennsylvania for the WC2608 SWOPE Stormwater Basin Retrofit Project, establishes the procedures and requirements for product substitutions during contract execution. The specification applies to the retrofit of an existing detention basin located at the southeast corner of the intersection of S High Street and E Campus Drive in West Chester, Pennsylvania. The project involves clearing and demolition, erosion and sediment controls, basin regrading, underdrain system installation, outlet structure replacement, drainage structures and piping, gabion basket forebay construction, and amended soil installation. The contract period runs from December 7, 2026, through July 3, 2027, comprising 208 calendar days. A pre-bid site visit is scheduled for November 6, 2026, at 11:00 AM. The specification does not establish firm response or bid due dates within its content but references Specification Section 013300 for submittal procedures. All requests for product substitution must follow formal submittal procedures and must include comprehensive supporting documentation, including product data, samples, detailed comparisons with specified products, coordination information, schedule impact analysis, cost proposals, and contractor certifications regarding equality, performance adequacy, and assumption of liability for performance failures.

The University will consider product substitutions only when specific conditions are met, including that extensive revisions to contract documents, price, or time are not required; proposed changes align with the general intent of contract documents; and the request is timely, fully documented, and properly submitted. Additionally, at least one of six enumerated conditions must be satisfied, such as the specified product creating schedule impacts, regulatory approval issues, compatibility problems, coordination difficulties, warranty concerns, or substantial advantage to the University in cost, time, or energy conservation. The contract cost range is $450,000 to $550,000 for general construction work, and this is a prevailing wage project under Prevailing Minimum Wage Determination serial number 26-07767, dated August 25, 2026. No liquidated damages clause applies to this project. The specification contains no information regarding set-asides, incumbent contractors, or specific funding sources beyond the general contract cost range established for the work.

View the file

Other files

File Type Posted
WC2608 Solicitation Cover Sheet. 10.29.26.pdf PDF
003-012600 CONTRACT MODIFIATION PROCEDURES 71-FA-8.1.pdf PDF
005-013100 PROJECT MANAGEMENT AND COORDINATION 71-FA-8.1.pdf PDF
008-013300 SUBMITTAL PROCEDURES 71-FA-8.1.pdf PDF
012-016000 PRODUCT REQUIREMENTS 71-FA-8.1.pdf PDF
015-017329 CUTTING AND PATCHING 71-FA-8.1.pdf PDF
315000 - Excavation Backfill and Compaction.pdf PDF
310519 - Geosynthetics.pdf PDF
B5 WC2608 Bid Bond Form, 71-FA-8.2_Dec_2023 10.24.26.pdf PDF
001-011000, SUMMARY 71-FA-8.1.pdf PDF
019-017839 PROJECT RECORD DOCUMENTS 71-FA-8.1.pdf PDF
C4 WC2608 Insurance Rider_71-FA-8.2_Dec_2023 10.29.26.pdf PDF
004-012900 PAYMENT PROCEDURES 71-FA-8.1.pdf PDF
002-012200 UNIT PRICES 71-FA-8.1.pdf PDF
016-017700 CLOSEOUT PROCEDURES 71-FA-8.1.pdf PDF
312500 - Erosion & Sedimentation Control.pdf PDF
014-017123 FIELD ENGINEERING 71-FA-8.1.pdf PDF
329200 - TURF AND GRASSES.pdf PDF
C6 WC2608 Weekly Certified Payroll Form llc-25[1].pdf PDF
C5 WC2608 PW 26-07767.pdf PDF
B6 WC2608 SDB Instructions, 71-FA-8.2_Dec_2023 10.24.26.pdf PDF
006-013119 PROJECT MEETINGS 71-FA-8.1.pdf PDF
C2 WC2608 P and P Contract Bond Form 71-FA-8.2_Dec_2023 UPDATED 10.24.26.pdf PDF
017-017823 OPERATIONS AND MAINTENANCE DATA 71-FA-8.1.pdf PDF
B7 WC2608 SDB Form, 71-FA-8.2_Dec_2023 10.24.26.pdf PDF
B4 WC2608 Bid Form, 71-FA-8.2_Dec_2023 10.24.26.pdf PDF
010-014500 QUALITY CONTROL 71-FA-8.1.pdf PDF
Bid Set Oct 2026 SIGNED SEALED WC2608 1.pdf PDF
C3 WC2608 General_Conditions_71-FA-8.2_Dec_2023 10.24.26..pdf PDF
C1 WC2608 Standard Form of K_71-FA-8.2_Dec_2023.pdf PDF
334211 - Storm Drainage.pdf PDF
A WC2608.1_000000_TABLE OF CONTENTS_10-29-26.pdf PDF
C8 WC2608 PW EmploymentVerification FORM.pdf PDF
311000 - Site Clearing.pdf PDF
313700 - Riprap.pdf PDF
C7 WC2608 Public Works Employment Verification Notice 2.16.24 (1).pdf PDF
B2 WC2608 Spec Instr to Bidders 71-FA-8.2_Dec_2023 10.30.26.pdf PDF
007-013200B CONSTRUCTION PROGRES DOCUMENTATION 71-FA-8.1.pdf PDF
B8 WC2608 Contractor Qualification Statement updated 10.24.26.pdf PDF
018-017836 WARRANTIES 71-FA-8.1.pdf PDF
4-RFP WCU0508262274 - Appendix A - Technical Submittal Response.pdf PDF
1-RFP WCU05808262274 - Appendix C - Contract Exceptions.pdf PDF
2-RFP WCU0508262247 - Appendix B - Trade Secret Confidential Information Notice.pdf PDF
3-RFP WCU0508262274 - Full-Service Print, Mail, and Distribution Service Contractor.pdf PDF
1-IFB WCU0407261013 - (1) NEW 2025 Low Cab Forward (LCF) 16 Foot Box Truck .pdf PDF
2-IFB WCU0407261013 - Bid Specification - Attachment A.pdf PDF
1-WC2602 Contract Forms Conditions.zip ZIP file
4-WC2602 Drawings.zip ZIP file
2-WC2602 Specs 3.30.2026 updated.zip ZIP file
3-WC2602 Bid Form Requirements.zip ZIP file
Show 40 more

Latest 50 of 66 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

WCU Project No. WC2608 SWOPE Stormwater Basin Retrofit Project

October 8, 2026

General Requirements for 71-FA-8.1 Section 016200 - Product Options

SECTION 016200

PRODUCT OPTIONS

PART 1 - GENERAL

1.01 DEFINITIONS

A. The Definitions used throughout this Section are not intended to change or modify the meaning of other terms used elsewhere throughout the Contract.

B. Products shall include products, materials, equipment, or methods of construction.

C. Request For Substitution is a proposal made by the Contractor after the award of the Contract for changes in Products required by Contract Documents.

D. The following are not considered to be Substitutions that are subject to this Section:

1. Substitutions requested by Bidders during the bidding period. If accepted, those substitutions will be published in an addendum to the solicitation and considered to be included in the Contract Documents. Those substitutions are not subject to the requirements of this Section.

2. Revisions to the Contract Documents requested by the University after award of the Contract.

3. Specified options of Products included as such in the Contract Documents.

4. The Contractor's determination of and compliance with governing regulations and orders issued by governing authorities.

1.02 REQUESTS FOR SUBSTITUTION

A. Requests For Substitution shall use the procedures for Submittals. Specification Section 013300, Submittal Procedures, specifies administrative and procedural requirements for submittals.

B. Requests for Substitution should be made in a timely manner. The Request should allow reasonable time for the University to review and make a decision on the Substitution without impacting the progress of the Work.

C. The Request for Substitution should identify the Product to be replaced, with the specific Technical Specification section and/or drawing numbers. Supporting documentation should be provided which shows compliance with the requirements for Substitutions and the following information, as appropriate:

1. Product Data, including drawings and descriptions of products, fabrication and installation procedures.

2. Samples, where applicable or requested.

3. Detailed comparison of significant qualities of the proposed Substitution with those of the Work specified. Significant qualities may include elements such as size, weight, durability, performance, and visual effect.

October 8, 2026

General Requirements for 71-FA-8.1 Section 016200 - Product Options

4. Coordination information, including a list of changes or modifications needed to other parts of the Work and to construction performed, including by other Separate Prime Contractors, that will become necessary to accommodate the proposed Substitution.

5. A statement indicating the Substitution’s effect on the Construction Schedule compared to the schedule without approval of the Substitution, including the effect, if any, of the Substitution on overall Contract Time.

6. Cost information, including a proposal of the net change, if any, in the Contract Price.

7. Certification by the Contractor, including the following:

a. certification and evidence that the proposed Substitution is equal to or better than, in every significant respect, the item required by the Contract Documents,

b. certification and evidence that the proposed Substitution will perform adequately in the application indicated, and

c. waiver of rights to additional payment or time that may subsequently become necessary if the Substitution fails to perform adequately.

D. In all cases, the Contractor must provide a Substitution that meets any stated salient features or performance criteria listed in the Technical Specifications.

1.03 ACTIONS ON REQUESTS FOR SUBSTITUTION

A. A Request For Substitution which is incomplete or does not comply with the requirements in paragraph 1.02 above will be returned to the Contractor without action, except to record noncompliance with these requirements.

B. If a decision on the use of a proposed Substitution cannot be made in a timely manner, the Contractor shall use the specified Product.

1.04 FACTORS FOR CONSIDERATION OF A SUBSTITUTION

A. The Contractor's Request For Substitution will be reviewed by the University and may be considered favorably if all of the following conditions are satisfied, as determined by the University.

1. Extensive revisions to Contract Documents, the Contract Price, or the Contract Time are not required.

2. Proposed changes are in keeping with the general intent of Contract Documents.

3. The Request is timely, fully documented, and properly submitted.

B. In addition to the conditions in paragraph 1.04 A. above, at least one of the following conditions must also be satisfied, as determined by the University.

1. The specified Product cannot be provided without impact to the Contract Time. The proposed Substitution will not be considered if the Product cannot be provided as a result of failure to pursue the Work promptly or coordinate activities properly.

October 8, 2026

General Requirements for 71-FA-8.1 Section 016200 - Product Options

2. The specified Product cannot receive necessary approval by a governing authority, and the proposed Substitution can be approved.

3. The specified Product cannot be provided in a manner that is compatible with the rest of the Work and its materials, and where the Contractor certifies that the proposed Substitution will overcome the incompatibility.

4. The specified Product cannot be coordinated with the rest of the Work and its materials, and where the Contractor certifies that the proposed Substitution can be coordinated.

5. The specified Product cannot be warranted as required by the Contract Documents, or the specified Product adversely affects a warranty or another Product or system, and the Contractor certifies that the proposed Substitution can fulfill the required warranty requirements.

6. The Substitution results in a substantial advantage to the University, in terms of cost, time, energy conservation, or other considerations of merit, after deducting offsetting responsibilities that the University may be required to bear. Additional responsibilities for the University may include additional compensation to the Professional for redesign and evaluation services, increased cost of other construction by the University or other Separate Prime Contractors, and similar considerations.

C. The University will make a determination if the Substitution can be coordinated with all other Separate Prime Contractors. Where a proposed Substitution involves more than one Separate Prime Contractor, the Contractor proposing the Substitution shall coordinate the Work with the other Separate Prime Contractors involved, to provide uniformity and consistency, and to assure compatibility of products.

PART 2 – PRODUCTS

(Not Used)

PART 3 – EXECUTION

(Not Used)

END OF SECTION 016200

SECTION 016200
PRODUCT OPTIONS
1.01 DEFINITIONS
1.02 REQUESTS FOR SUBSTITUTION
A. Requests For Substitution shall use the procedures for Submittals. Specification Section 013300, Submittal Procedures, specifies administrative and procedural requirements for submittals.
1.03 ACTIONS ON REQUESTS FOR SUBSTITUTION