013-016200 PRODUCT OPTIONS 71-FA-8.1.pdf
PDF 215 KB Posted
- Attached to
- WC2608 SWOPE Stormwater Basin Retrofit Project
- Solicitation number
- Not on record
- Issued by
- Chester County, Pennsylvania
About this file
This Product Options specification document, issued by West Chester University of Pennsylvania for the WC2608 SWOPE Stormwater Basin Retrofit Project, establishes the procedures and requirements for product substitutions during contract execution. The specification applies to the retrofit of an existing detention basin located at the southeast corner of the intersection of S High Street and E Campus Drive in West Chester, Pennsylvania. The project involves clearing and demolition, erosion and sediment controls, basin regrading, underdrain system installation, outlet structure replacement, drainage structures and piping, gabion basket forebay construction, and amended soil installation. The contract period runs from December 7, 2026, through July 3, 2027, comprising 208 calendar days. A pre-bid site visit is scheduled for November 6, 2026, at 11:00 AM. The specification does not establish firm response or bid due dates within its content but references Specification Section 013300 for submittal procedures. All requests for product substitution must follow formal submittal procedures and must include comprehensive supporting documentation, including product data, samples, detailed comparisons with specified products, coordination information, schedule impact analysis, cost proposals, and contractor certifications regarding equality, performance adequacy, and assumption of liability for performance failures.
The University will consider product substitutions only when specific conditions are met, including that extensive revisions to contract documents, price, or time are not required; proposed changes align with the general intent of contract documents; and the request is timely, fully documented, and properly submitted. Additionally, at least one of six enumerated conditions must be satisfied, such as the specified product creating schedule impacts, regulatory approval issues, compatibility problems, coordination difficulties, warranty concerns, or substantial advantage to the University in cost, time, or energy conservation. The contract cost range is $450,000 to $550,000 for general construction work, and this is a prevailing wage project under Prevailing Minimum Wage Determination serial number 26-07767, dated August 25, 2026. No liquidated damages clause applies to this project. The specification contains no information regarding set-asides, incumbent contractors, or specific funding sources beyond the general contract cost range established for the work.
View the file
Other files
Show 40 more
Latest 50 of 66 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
WCU Project No. WC2608 SWOPE Stormwater Basin Retrofit Project
October 8, 2026
General Requirements for 71-FA-8.1 Section 016200 - Product Options
SECTION 016200
PRODUCT OPTIONS
PART 1 - GENERAL
1.01 DEFINITIONS
A. The Definitions used throughout this Section are not intended to change or modify the meaning of other terms used elsewhere throughout the Contract.
B. Products shall include products, materials, equipment, or methods of construction.
C. Request For Substitution is a proposal made by the Contractor after the award of the Contract for changes in Products required by Contract Documents.
D. The following are not considered to be Substitutions that are subject to this Section:
1. Substitutions requested by Bidders during the bidding period. If accepted, those substitutions will be published in an addendum to the solicitation and considered to be included in the Contract Documents. Those substitutions are not subject to the requirements of this Section.
2. Revisions to the Contract Documents requested by the University after award of the Contract.
3. Specified options of Products included as such in the Contract Documents.
4. The Contractor's determination of and compliance with governing regulations and orders issued by governing authorities.
1.02 REQUESTS FOR SUBSTITUTION
A. Requests For Substitution shall use the procedures for Submittals. Specification Section 013300, Submittal Procedures, specifies administrative and procedural requirements for submittals.
B. Requests for Substitution should be made in a timely manner. The Request should allow reasonable time for the University to review and make a decision on the Substitution without impacting the progress of the Work.
C. The Request for Substitution should identify the Product to be replaced, with the specific Technical Specification section and/or drawing numbers. Supporting documentation should be provided which shows compliance with the requirements for Substitutions and the following information, as appropriate:
1. Product Data, including drawings and descriptions of products, fabrication and installation procedures.
2. Samples, where applicable or requested.
3. Detailed comparison of significant qualities of the proposed Substitution with those of the Work specified. Significant qualities may include elements such as size, weight, durability, performance, and visual effect.
October 8, 2026
General Requirements for 71-FA-8.1 Section 016200 - Product Options
4. Coordination information, including a list of changes or modifications needed to other parts of the Work and to construction performed, including by other Separate Prime Contractors, that will become necessary to accommodate the proposed Substitution.
5. A statement indicating the Substitution’s effect on the Construction Schedule compared to the schedule without approval of the Substitution, including the effect, if any, of the Substitution on overall Contract Time.
6. Cost information, including a proposal of the net change, if any, in the Contract Price.
7. Certification by the Contractor, including the following:
a. certification and evidence that the proposed Substitution is equal to or better than, in every significant respect, the item required by the Contract Documents,
b. certification and evidence that the proposed Substitution will perform adequately in the application indicated, and
c. waiver of rights to additional payment or time that may subsequently become necessary if the Substitution fails to perform adequately.
D. In all cases, the Contractor must provide a Substitution that meets any stated salient features or performance criteria listed in the Technical Specifications.
1.03 ACTIONS ON REQUESTS FOR SUBSTITUTION
A. A Request For Substitution which is incomplete or does not comply with the requirements in paragraph 1.02 above will be returned to the Contractor without action, except to record noncompliance with these requirements.
B. If a decision on the use of a proposed Substitution cannot be made in a timely manner, the Contractor shall use the specified Product.
1.04 FACTORS FOR CONSIDERATION OF A SUBSTITUTION
A. The Contractor's Request For Substitution will be reviewed by the University and may be considered favorably if all of the following conditions are satisfied, as determined by the University.
1. Extensive revisions to Contract Documents, the Contract Price, or the Contract Time are not required.
2. Proposed changes are in keeping with the general intent of Contract Documents.
3. The Request is timely, fully documented, and properly submitted.
B. In addition to the conditions in paragraph 1.04 A. above, at least one of the following conditions must also be satisfied, as determined by the University.
1. The specified Product cannot be provided without impact to the Contract Time. The proposed Substitution will not be considered if the Product cannot be provided as a result of failure to pursue the Work promptly or coordinate activities properly.
October 8, 2026
General Requirements for 71-FA-8.1 Section 016200 - Product Options
2. The specified Product cannot receive necessary approval by a governing authority, and the proposed Substitution can be approved.
3. The specified Product cannot be provided in a manner that is compatible with the rest of the Work and its materials, and where the Contractor certifies that the proposed Substitution will overcome the incompatibility.
4. The specified Product cannot be coordinated with the rest of the Work and its materials, and where the Contractor certifies that the proposed Substitution can be coordinated.
5. The specified Product cannot be warranted as required by the Contract Documents, or the specified Product adversely affects a warranty or another Product or system, and the Contractor certifies that the proposed Substitution can fulfill the required warranty requirements.
6. The Substitution results in a substantial advantage to the University, in terms of cost, time, energy conservation, or other considerations of merit, after deducting offsetting responsibilities that the University may be required to bear. Additional responsibilities for the University may include additional compensation to the Professional for redesign and evaluation services, increased cost of other construction by the University or other Separate Prime Contractors, and similar considerations.
C. The University will make a determination if the Substitution can be coordinated with all other Separate Prime Contractors. Where a proposed Substitution involves more than one Separate Prime Contractor, the Contractor proposing the Substitution shall coordinate the Work with the other Separate Prime Contractors involved, to provide uniformity and consistency, and to assure compatibility of products.
PART 2 – PRODUCTS
(Not Used)
PART 3 – EXECUTION
(Not Used)
END OF SECTION 016200
| SECTION 016200 |
| PRODUCT OPTIONS |
| 1.01 DEFINITIONS |
| 1.02 REQUESTS FOR SUBSTITUTION |
| A. Requests For Substitution shall use the procedures for Submittals. Specification Section 013300, Submittal Procedures, specifies administrative and procedural requirements for submittals. |
| 1.03 ACTIONS ON REQUESTS FOR SUBSTITUTION |
File details come from the government source that posted it. Updated .