About this file

This is a Section 017123 Field Engineering specification document for the WC2608 SWOPE Stormwater Basin Retrofit Project at West Chester University of Pennsylvania, dated October 8, 2026. The specification establishes requirements for field engineering services, including land surveying and professional engineering oversight throughout the project. The General Construction Contractor or Lead Prime Contractor must engage a Professional Land Surveyor registered in Pennsylvania to perform all required land surveying and engineering land surveys. Additional field engineering services must be provided by a Professional Engineer registered in Pennsylvania with competency in the specific discipline required. The contractor must establish and maintain a minimum of two permanent reference points on site, verify all layout information against property surveys and existing reference points, and preserve existing control data. Working from established lines and levels, the contractor shall locate and lay out site improvements including pavements, grading, utilities, and building elements such as foundations, column grids, and floor levels. The surveyor must maintain a comprehensive log of all control and field survey work, check every major element for line, level, and plumb as construction proceeds, and document any deviations that exceed specified tolerances. Upon project completion, the contractor must submit a certificate signed by the Land Surveyor or Professional Engineer certifying compliance with Contract Documents, along with a record of work performed and record survey data.

The contractor must investigate and verify the existence and location of all underground utilities and other construction before beginning sitework, and furnish all information necessary to adjust, move, or relocate existing structures, utility poles, lines, services, or other appurtenances affected by the work. The contractor shall coordinate with local authorities having jurisdiction and advise the University and all Separate Prime Contractors of reference points and marked lines and levels provided. The specification does not identify specific cost provisions, set-asides, or pricing information, as it functions as a technical requirements document within the broader project specification. The SWOPE Stormwater Basin Retrofit Project involves the retrofit of an existing detention basin with clearing, amended soils installation, underdrain systems, outlet structures, and piping work, located at the southeast corner of South High Street and East Campus Drive in West Chester, Pennsylvania, with a contract timeline of 208 calendar days from December 7, 2026, to July 3, 2027, and a cost range of $450,000 to $550,000 under prevailing wage requirements.

View the file

Other files

File Type Posted
WC2608 Solicitation Cover Sheet. 10.29.26.pdf PDF
003-012600 CONTRACT MODIFIATION PROCEDURES 71-FA-8.1.pdf PDF
005-013100 PROJECT MANAGEMENT AND COORDINATION 71-FA-8.1.pdf PDF
008-013300 SUBMITTAL PROCEDURES 71-FA-8.1.pdf PDF
012-016000 PRODUCT REQUIREMENTS 71-FA-8.1.pdf PDF
015-017329 CUTTING AND PATCHING 71-FA-8.1.pdf PDF
315000 - Excavation Backfill and Compaction.pdf PDF
310519 - Geosynthetics.pdf PDF
B5 WC2608 Bid Bond Form, 71-FA-8.2_Dec_2023 10.24.26.pdf PDF
001-011000, SUMMARY 71-FA-8.1.pdf PDF
019-017839 PROJECT RECORD DOCUMENTS 71-FA-8.1.pdf PDF
C4 WC2608 Insurance Rider_71-FA-8.2_Dec_2023 10.29.26.pdf PDF
004-012900 PAYMENT PROCEDURES 71-FA-8.1.pdf PDF
002-012200 UNIT PRICES 71-FA-8.1.pdf PDF
016-017700 CLOSEOUT PROCEDURES 71-FA-8.1.pdf PDF
312500 - Erosion & Sedimentation Control.pdf PDF
329200 - TURF AND GRASSES.pdf PDF
C6 WC2608 Weekly Certified Payroll Form llc-25[1].pdf PDF
C5 WC2608 PW 26-07767.pdf PDF
B6 WC2608 SDB Instructions, 71-FA-8.2_Dec_2023 10.24.26.pdf PDF
006-013119 PROJECT MEETINGS 71-FA-8.1.pdf PDF
C2 WC2608 P and P Contract Bond Form 71-FA-8.2_Dec_2023 UPDATED 10.24.26.pdf PDF
017-017823 OPERATIONS AND MAINTENANCE DATA 71-FA-8.1.pdf PDF
B7 WC2608 SDB Form, 71-FA-8.2_Dec_2023 10.24.26.pdf PDF
B4 WC2608 Bid Form, 71-FA-8.2_Dec_2023 10.24.26.pdf PDF
013-016200 PRODUCT OPTIONS 71-FA-8.1.pdf PDF
010-014500 QUALITY CONTROL 71-FA-8.1.pdf PDF
Bid Set Oct 2026 SIGNED SEALED WC2608 1.pdf PDF
C3 WC2608 General_Conditions_71-FA-8.2_Dec_2023 10.24.26..pdf PDF
C1 WC2608 Standard Form of K_71-FA-8.2_Dec_2023.pdf PDF
334211 - Storm Drainage.pdf PDF
A WC2608.1_000000_TABLE OF CONTENTS_10-29-26.pdf PDF
C8 WC2608 PW EmploymentVerification FORM.pdf PDF
311000 - Site Clearing.pdf PDF
313700 - Riprap.pdf PDF
C7 WC2608 Public Works Employment Verification Notice 2.16.24 (1).pdf PDF
B2 WC2608 Spec Instr to Bidders 71-FA-8.2_Dec_2023 10.30.26.pdf PDF
007-013200B CONSTRUCTION PROGRES DOCUMENTATION 71-FA-8.1.pdf PDF
B8 WC2608 Contractor Qualification Statement updated 10.24.26.pdf PDF
018-017836 WARRANTIES 71-FA-8.1.pdf PDF
4-RFP WCU0508262274 - Appendix A - Technical Submittal Response.pdf PDF
1-RFP WCU05808262274 - Appendix C - Contract Exceptions.pdf PDF
2-RFP WCU0508262247 - Appendix B - Trade Secret Confidential Information Notice.pdf PDF
3-RFP WCU0508262274 - Full-Service Print, Mail, and Distribution Service Contractor.pdf PDF
1-IFB WCU0407261013 - (1) NEW 2025 Low Cab Forward (LCF) 16 Foot Box Truck .pdf PDF
2-IFB WCU0407261013 - Bid Specification - Attachment A.pdf PDF
1-WC2602 Contract Forms Conditions.zip ZIP file
4-WC2602 Drawings.zip ZIP file
2-WC2602 Specs 3.30.2026 updated.zip ZIP file
3-WC2602 Bid Form Requirements.zip ZIP file
Show 40 more

Latest 50 of 66 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

WCU Project No. WC2608 SWOPE Stormwater Basin Retrofit Project

October 8, 2026

General Requirements for 71-FA-8.1 Section 017123 - Field Engineering

SECTION 017123

FIELD ENGINEERING

PART 1 - GENERAL

1.01 RESPONSIBILITIES

A. To perform any Land Surveying required for the Project, the General Construction Contractor shall engage a Professional Land Surveyor registered in the Commonwealth of Pennsylvania.

If there is no General Construction Contractor, the Lead Prime Contractor shall have the responsibility.

B. To perform any Engineering Land Surveys required for the Project, the General Construction Contractor shall engage either a Professional Land Surveyor registered in the Commonwealth of Pennsylvania, or a Professional Engineer registered in the Commonwealth of Pennsylvania.

If a Professional Engineer is to be used, he shall be competent in Engineering Land Surveys, and the Contractor shall provide to the University evidence of that competence. If there is no General Construction Contractor, the Lead Prime Contractor shall have the responsibility.

C. To perform other field engineering services as required or specified, each Separate Prime Contractor shall engage a Professional Engineer registered in the Commonwealth of Pennsylvania. The Professional Engineer shall be of the discipline required or specified, and shall be competent in the services required or specified. The Contractor shall provide to the University evidence of the Professional Engineer’s competence.

1.02 SURVEY CONTROL DATA

A. The Contract Documents will identify existing reference points, such as benchmarks, control points, and property line corner stakes. If it is missing, the University will provide this data.

B. Before proceeding to layout the work, the Contractor shall verify layout information shown on the drawings in relation to the property survey and existing reference points. The Contractor shall locate and protect existing reference points.

C. Permanent reference points shall be preserved during construction. If necessary in the prosecution of the work, relocations and replacements shall be executed in accordance with the following requirements.

1. Permanent reference points shall not be changed or relocated without prior written approval from the University.

2. Requests to relocate reference points because of necessary changes in grades or locations shall be made in a timely manner so as not to impact the Work.

3. Lost or destroyed permanent reference points shall be promptly reported. Replacements shall be based on the original survey reference points.

D. The Contractor shall establish and maintain a minimum of two permanent reference points on the site, referenced to data established by original survey reference points. Record of the reference points shall be established and recorded on project record documents with horizontal and vertical data.

October 8, 2026

General Requirements for 71-FA-8.1 Section 017123 - Field Engineering

1.03 SURVEY PROCEDURES

A. Working from lines and levels established by the property survey, the Contractor shall establish benchmarks and markers to set lines and levels at each story of construction and elsewhere as needed to properly locate each element of the Project.

1. For site improvements, including pavements, stakes for grading, fill, and topsoil placement, and utility slopes and invert elevations, the Contractor shall locate and lay out the Work by instrumentation and similar appropriate means.

2. For building work, the Contractor shall locate and lay out, by instrumentation and similar appropriate means, building foundations, column grids and locations, floor levels, control lines, and any reference points required for mechanical, plumbing, and electrical work.

3. Required dimensions shall be calculated and measured within indicated or recognized tolerances. Scaled drawings should not be measured to determine dimensions.

4. As construction proceeds, every major element shall be checked for line, level, and plumb.

5. Other Separate Prime Contractors and entities engaged in the Work shall be advised of reference points and marked lines and levels provided.

B. The Contractor shall maintain a surveyor's log of control and other field survey work. The log shall be made available for reference to the University and other Separate Prime Contractors and appropriate entities.

C. The University shall be advised when deviations that exceed indicated or recognized tolerances are detected. The surveyor’s log shall record deviations from required lines and levels. Project record drawings shall indicate record deviations that are accepted and not corrected.

1.04 CERTIFICATION OF SURVEY

At the completion of the Project, the Contractor shall submit to the University the following items:

A. A certificate signed by the Land Surveyor or Professional Engineer certifying that the location and elevation of the Work complies with the Contract Documents

B. A record of work performed and record survey data

1.05 UTILITIES

A. The existence and location of underground and other utilities and construction indicated on the Contract Documents as existing are not guaranteed. Before beginning sitework, the Contractor shall investigate and verify the existence and location of underground utilities and other construction, and the locations and invert elevations at points of connection of sanitary sewer, storm sewer, and water service piping.

B. The Contractor shall furnish all information necessary to adjust, move, or relocate existing structures, utility poles, lines, services, or other appurtenances located in or affected by the Work. The Contractor shall coordinate with local authorities having jurisdiction.

October 8, 2026

General Requirements for 71-FA-8.1 Section 017123 - Field Engineering

PART 2 – PRODUCTS

(Not Used)

PART 3 – EXECUTION

(Not Used)

END OF SECTION 017123

SECTION 017123
FIELD ENGINEERING
PART 1 - GENERAL
1.02 SURVEY CONTROL DATA
1.03 SURVEY PROCEDURES
1.05 UTILITIES