This is a project meetings specification document (Section 013119) prepared by West Chester University of Pennsylvania for the WC2608 SWOPE Stormwater Basin Retrofit Project, dated October 8, 2026. The specification establishes requirements for three types of project meetings: a Pre-Construction Conference to be held prior to any work commencing at the project site; periodic Progress Meetings to be conducted normally every two weeks during the contract duration, with frequency and schedule determined by the University in coordination with the Contractor; and Pre-Completion Meetings to be held prior to project completion for larger, more complex projects. The Pre-Construction Conference agenda must address a minimum of 29 topics including contract basics, key representatives, lines of communication, construction schedule and sequencing, change order and payment procedures, prevailing wage requirements, permits, equipment deliveries, quality control, environmental protection, security, and warranty requirements. Progress Meeting agendas must include review of meeting minutes, outstanding submittals, open requests for information, change orders, schedule status, and planned work for the following two weeks, with particular focus on resolving schedule delays. Pre-Completion coordination should address final work plans, utility tie-ins, furniture and equipment delivery, final inspection procedures, record drawings and operations manuals, and warranty requirements. The University will designate a party, normally the Professional, to record and publish records of all meetings.

No specific pricing, contract cost ranges, set-asides, or incumbent contractor information is contained in this specification document. The document serves as contractual requirements for project administration and communication protocols rather than procurement terms. The Pre-Construction Conference must include attendance by the Contractor's project manager and superintendent at minimum, with the University's Professional typically in attendance. All meeting attendees are required to focus on resolution of open items and issues, with particular emphasis on schedule recovery discussions if the project falls behind schedule. The specification requires commitment from all parties involved to implement any agreed-upon solutions or schedule revisions necessary to ensure completion within the contract time.

View the file

Other files

File Type Posted
WC2608 Solicitation Cover Sheet. 10.29.26.pdf PDF
003-012600 CONTRACT MODIFIATION PROCEDURES 71-FA-8.1.pdf PDF
005-013100 PROJECT MANAGEMENT AND COORDINATION 71-FA-8.1.pdf PDF
008-013300 SUBMITTAL PROCEDURES 71-FA-8.1.pdf PDF
012-016000 PRODUCT REQUIREMENTS 71-FA-8.1.pdf PDF
015-017329 CUTTING AND PATCHING 71-FA-8.1.pdf PDF
315000 - Excavation Backfill and Compaction.pdf PDF
310519 - Geosynthetics.pdf PDF
B5 WC2608 Bid Bond Form, 71-FA-8.2_Dec_2023 10.24.26.pdf PDF
001-011000, SUMMARY 71-FA-8.1.pdf PDF
019-017839 PROJECT RECORD DOCUMENTS 71-FA-8.1.pdf PDF
C4 WC2608 Insurance Rider_71-FA-8.2_Dec_2023 10.29.26.pdf PDF
004-012900 PAYMENT PROCEDURES 71-FA-8.1.pdf PDF
002-012200 UNIT PRICES 71-FA-8.1.pdf PDF
016-017700 CLOSEOUT PROCEDURES 71-FA-8.1.pdf PDF
312500 - Erosion & Sedimentation Control.pdf PDF
014-017123 FIELD ENGINEERING 71-FA-8.1.pdf PDF
329200 - TURF AND GRASSES.pdf PDF
C6 WC2608 Weekly Certified Payroll Form llc-25[1].pdf PDF
C5 WC2608 PW 26-07767.pdf PDF
B6 WC2608 SDB Instructions, 71-FA-8.2_Dec_2023 10.24.26.pdf PDF
C2 WC2608 P and P Contract Bond Form 71-FA-8.2_Dec_2023 UPDATED 10.24.26.pdf PDF
017-017823 OPERATIONS AND MAINTENANCE DATA 71-FA-8.1.pdf PDF
B7 WC2608 SDB Form, 71-FA-8.2_Dec_2023 10.24.26.pdf PDF
B4 WC2608 Bid Form, 71-FA-8.2_Dec_2023 10.24.26.pdf PDF
013-016200 PRODUCT OPTIONS 71-FA-8.1.pdf PDF
010-014500 QUALITY CONTROL 71-FA-8.1.pdf PDF
Bid Set Oct 2026 SIGNED SEALED WC2608 1.pdf PDF
C3 WC2608 General_Conditions_71-FA-8.2_Dec_2023 10.24.26..pdf PDF
C1 WC2608 Standard Form of K_71-FA-8.2_Dec_2023.pdf PDF
334211 - Storm Drainage.pdf PDF
A WC2608.1_000000_TABLE OF CONTENTS_10-29-26.pdf PDF
C8 WC2608 PW EmploymentVerification FORM.pdf PDF
311000 - Site Clearing.pdf PDF
313700 - Riprap.pdf PDF
C7 WC2608 Public Works Employment Verification Notice 2.16.24 (1).pdf PDF
B2 WC2608 Spec Instr to Bidders 71-FA-8.2_Dec_2023 10.30.26.pdf PDF
007-013200B CONSTRUCTION PROGRES DOCUMENTATION 71-FA-8.1.pdf PDF
B8 WC2608 Contractor Qualification Statement updated 10.24.26.pdf PDF
018-017836 WARRANTIES 71-FA-8.1.pdf PDF
4-RFP WCU0508262274 - Appendix A - Technical Submittal Response.pdf PDF
1-RFP WCU05808262274 - Appendix C - Contract Exceptions.pdf PDF
2-RFP WCU0508262247 - Appendix B - Trade Secret Confidential Information Notice.pdf PDF
3-RFP WCU0508262274 - Full-Service Print, Mail, and Distribution Service Contractor.pdf PDF
1-IFB WCU0407261013 - (1) NEW 2025 Low Cab Forward (LCF) 16 Foot Box Truck .pdf PDF
2-IFB WCU0407261013 - Bid Specification - Attachment A.pdf PDF
1-WC2602 Contract Forms Conditions.zip ZIP file
4-WC2602 Drawings.zip ZIP file
2-WC2602 Specs 3.30.2026 updated.zip ZIP file
3-WC2602 Bid Form Requirements.zip ZIP file
Show 40 more

Latest 50 of 66 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

WCU Project No. WC2608 SWOPE Stormwater Basin Retrofit Project

October 8, 2026

General Requirements for 71-FA-8.1 Section 013119 - Project Meetings

SECTION 013119

PROJECT MEETINGS

PART 1 - GENERAL

1.01 PRE-CONSTRUCTION CONFERENCE

A. A Pre-Construction Conference shall be held prior to any work taking place on site. The purpose of the Pre-Construction Conference is to acquaint the Contractor(s) with University contract administration and policies and to introduce the entire project team to each other.

B. The University will conduct the Pre-Construction Conference at the project site or other convenient location. Representatives of the University and the Contractor shall attend.

Representatives should be familiar with and authorized to conclude matters relating to the Contract and the work. At a minimum, the Contractor’s project manager and superintendent shall attend. The Contractor may have his major subcontractors, manufacturers, and suppliers in attendance at the Conference, although their attendance is not normally necessary. The University’s Professional will normally be in attendance at the Conference.

C. The agenda should include at least the following topics:

1. contract basics (price, duration/dates, etc.)

2. key representatives and organization of all parties

3. lines of communication

4. contracting authorities and agents

5. distribution of contract documents

6. distribution of university procedures and forms

7. coordination of prime contractors’ work

8. tentative construction schedule and critical work sequencing

9. review of critical contract clauses and requirements

10. procedures for requests for information

11. procedures for change orders

12. procedures for applications for payment

13. procedures for submittals

14. preparation of record drawings/documents

15. use of the premises

16. office, work, and storage areas

October 8, 2026

General Requirements for 71-FA-8.1 Section 013119 - Project Meetings

17. utilities

18. university and facility policies and access

19. working hours

20. permits and intergovernmental requirements

21. UCC coordination with the Department of Labor & Industry

22. prevailing wage and labor standards

23. equipment deliveries and priorities

24. quality control

25. disputes

26. environmental protection

27. security

28. housekeeping and clean-up

29. substantial completion and contract completion

33. warranties

D. The University will designate a party to record and publish a record of the Conference.

Normally this will be the Professional.

1.02 PROGRESS MEETINGS

A. Periodic Progress Meetings will normally be held every two weeks during the Contract duration, but the frequency and schedule will be determined by the University in coordination with the Contractor. The purpose of Progress Meetings is to review status of work to date and plan for future work.

B. Representatives of the University and the Contractor shall attend the Meetings.

Representatives should be familiar with and authorized to conclude matters relating to the Contract and the work. At a minimum, the Contractor’s project manager and/or superintendent shall attend. The University’s Professional will normally be in attendance at the Meeting.

C. The agenda should include at least the following:

1. review and approval or correction of minutes of the previous meeting

2. review of any special coordination or other meetings held since the previous Periodic Progress Meeting

3. review of outstanding submittals and late submittals

October 8, 2026

General Requirements for 71-FA-8.1 Section 013119 - Project Meetings

4. review of open requests for information

5. review of open change orders and change order requests

6. review of any tests or inspections that were not successful

7. review of progress, in relation to the Project Schedule, since the last Periodic Progress Meeting

8. review of work, in relation to the Project Schedule, planned for the next two weeks

9. review of other items of significance that could impact the project or progress

10. review of present and future needs of each Contractor and party present

D. In all cases, the Meeting attendees shall focus on a plan for resolution of open items and issues.

If the project is behind schedule, discussion shall include a determination of how construction that is behind schedule will be returned to schedule, and securing of commitments from parties involved to do so; such discussion shall include whether schedule revisions are required to ensure that current and subsequent activities will be completed within the contract time

E. The University will designate a party to record and publish a record of the Meeting. Normally this will be the Professional.

1.04 PRE-COMPLETION MEETINGS

A. Prior to the completion of a project, and particularly for larger, more complex projects, specific pre-completion coordination should be accomplished. The purpose of pre-completion coordination is to conduct detailed planning and coordination for the completion of the project, with the goal of ensuring the facility is totally operational and functional and prepared for occupancy in a timely manner. Pre-completion coordination may involve parties, other than the Separate Prime Contractors, who have input or actions required to make the facility ready for occupancy. Pre-completion coordination may take place during or in conjunction with Progress Meetings, or a separate meeting may take place.

B. Pre-Completion coordination may include, at least, the following:

1. plan for the final work by each Separate Prime Contractor

2. tie-ins for permanent utilities

3. delivery and staging of furniture and equipment onsite

4. final inspection procedures

5. items due to the University at completion (record drawings, O&M manuals, etc.)

6. warranty requirements and plan

PART 2 – PRODUCTS

(Not Used)

October 8, 2026

General Requirements for 71-FA-8.1 Section 013119 - Project Meetings

PART 3 – EXECUTION

(Not Used)

END OF SECTION 013119

SECTION 013119
PROJECT MEETINGS
PART 1 - GENERAL
1.01 PRE-CONSTRUCTION CONFERENCE
D. The University will designate a party to record and publish a record of the Conference. Normally this will be the Professional.
1.02 PROGRESS MEETINGS
E. The University will designate a party to record and publish a record of the Meeting. Normally this will be the Professional.