Attch. 28 Temporary_Dewatering_Narrative.pdf
PDF 25 KB Posted
- Solicitation number
- 191BWC26R0009
About this file
This document is an informational specification regarding temporary sludge dewatering equipment and operations at the Santa Barbara Integrated Wastewater Treatment Plant (SBIWTP) during planned facility rehabilitation.
The SBIWTP currently operates a screw press and auxiliary mobile conveyor supplementing the belt filter press for sludge dewatering, located at the south end of the existing Sludge Dewatering Building. The existing Sludge Dewatering Facility, Lime Stabilization Facility, and Truck Loading Facility are scheduled for major rehabilitation beginning in the second half of 2027, with an anticipated 30-month construction duration. Prior to rehabilitation commencement, the Construction Contractor must install a second temporary screw press and auxiliary mobile conveyor and provide a comprehensive service and maintenance agreement for this equipment throughout the rehabilitation period. During rehabilitation, sludge dewatering will operate exclusively with polymer totes configured for the screw press units, with no bulk polymer provisions available. Upon final completion and commissioning of the rehabilitation work, the temporary screw press units will be removed from service and replaced with the new permanent bulk dewatering polymer facility. Additional location maps and detailed drawings of the temporary equipment configuration are available in the referenced attachment, Screw Press Map and Drawings.pdf.
View the file
Other files
Show all 37
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sludge Dewatering During Construction
Temporary Dewatering Equipment
Currently, the SBIWTP has a screw press and auxiliary mobile conveyor that is supplementing the belt filter press process for sludge dewatering. The screw press is located at the south end of the existing Sludge Dewatering Building. Refer to the attachment, Screw Press Map and Drawings.pdf, for a location map and drawings of the temporary screw press and auxiliary mobile conveyor.
The existing Sludge Dewatering Facility, Lime Stabilization Facility, and Truck Loading
Facility are planned to undergo major rehabilitation as part of Phase 1 construction, anticipated to begin during the second half of 2027. The duration of the rehabilitation work is expected to be approximately a 30-month period. Permanent sludge dewatering equipment becomes available upon final completion and commissioning of said work.
Prior to the commencement of rehabilitation activities, the Construction Contractor will install a second temporary screw press and auxiliary mobile conveyor. The Construction
Contractor will provide a service and maintenance agreement for the second temporary screw press throughout the rehabilitation period.
During the rehabilitation period, there will be no provisions for use of bulk polymer for sludge dewatering. The screw press units are configured to use polymer totes.
When the sludge dewatering facility rehabilitation is complete, the screw press units will be removed from service and the new bulk dewatering polymer facility placed in service.