This file is a Questions and Answers document for federal contract solicitation 191BWC26R0009, issued by the U.S. International Boundary and Water Commission (USIBWC) for Operation and Maintenance (O&M) services at the South Bay International Wastewater Treatment Plant (SBIWTP) in San Diego. The Q&A addresses 108 questions received through November 19, 2026, covering proposal format, technical requirements, contract scope, pricing, compliance, and operational details.

The contract involves a five-year firm-fixed-price (FFP) agreement with options to operate and maintain a 25 MGD wastewater treatment facility expanding to 50 MGD average capacity with 75 MGD peak capacity. Key proposal requirements include: Volume I technical proposal increased to 60 single-sided PDF pages (excluding cover, table of contents, resumes, and certifications); minimum five relevant past-performance contracts at up to two pages each; and detailed responses to seven evaluation factors covering company experience, technical approach, key personnel, cybersecurity, and operations plan. The contract incorporates Economic Price Adjustment clauses for diesel fuel and treatment chemicals to address market volatility. Proposals are due January 6, 2027 at 2:00 PM Mountain Time, with anticipated award by February 16, 2027 and a 60-day phase-in period beginning April 1, 2027 prior to full performance commencement June 1, 2027. The O&M Contractor bears responsibility for repairs under $200,000 per incident, with capital projects exceeding this threshold funded by USIBWC. Davis-Bacon wage determination 2015-5635 Rev. 32 (September 8, 2026) applies to all work. USIBWC retains responsibility for sludge hauling to Mexico, security personnel, NPDES permit certification, regional board notifications, and regulatory compliance liability. The contractor must provide 24/7 operations, maintain NIST 800-171 compliant cybersecurity systems with dedicated compliance enclaves for controlled unclassified information, complete 90-day vulnerability remediation cycles, and coordinate with concurrent Progressive Design-Build expansion construction through 2031.

View the file

Other files

File Type Posted
Attch. 09 SBIWTP Capital Project List as of September 2026.pdf PDF
Attch. 33 O&M Services Price Workbook (blank template)_updatedNov2026.xlsx XLSX spreadsheet
191BWC26R0009 0004.pdf PDF
Attch. 01 PWS SBIWTP O&M Services 20261125.pdf PDF
Attch. 21 Wage Determination CA2015-5635 Rev32 20260908.pdf PDF
Attch. 32 0131 20260720 PCL Construction Security Plan.pdf PDF
191BWC26R0009-0003.pdf PDF
191BWC26R0009 0002.pdf PDF
191BWC26R0009 0001.pdf PDF
Attch. 28 Temporary_Dewatering_Narrative.pdf PDF
Attch. 30.b. FSP ANNEX D MONTHLY SBIWTP (2026).pdf PDF
Attch. 34 SBIWTP O&M Site Visit oct14_26.pdf PDF
Attch. 30.a. FSP ANNEX A SBIWTP (2026).pdf PDF
Attch. 33 O&M Services Price Workbook (blank template).xls XLS spreadsheet
Attch. 29 Screw Press Map and Drawings.pdf PDF
FY27 SBIWTP OM PWS REV 1 10.19.26.pdf PDF
Attch. 27 SD.I.10031-M-2 Background Investigation Procedures for SBIWTP Contractor Personnel.pdf PDF
Attch. 30.c. FSP ANNEX D ANNUAL SBIWTP(2026).pdf PDF
Attch. 16 Plans Drawings Request Instructions.docx DOCX document
Attch. 01A SOM SUBMITTAL REGISTER SBIWTP O&M 2026.xlsx XLSX spreadsheet
Attch. 25 Client Authorization Letter.docx DOCX document
191BWC26R0009 OM SBIWTP Services.pdf PDF
Attch. 18 NIST.FIPS.199.pdf PDF
Attch. 11 Canyon Collector Daily Inspection template- MAR 2025.xlsx XLSX spreadsheet
Attch. 23 LAB SAMPLING QTY.xlsx XLSX spreadsheet
Attch. 04.a. GiantKelpVariance_09.11.26.pdf PDF
Attch. 21 Wage Determinations CA20240001 07.26.2024.pdf PDF
Attch. 04 Order No. R9-2021-0001 as amended R9-2026-0005.pdf PDF
Attch. 22 MX- Norma004_Semarnat_2002_english version.pdf PDF
Attch. 05 List-of-Permits.pdf PDF
Attch. 24 OEP-SBIWTP(2026).pdf PDF
Attch. 06 IBWC SBIWTP Asset Registry 2024.xlsx XLSX spreadsheet
Attch. 05 List-of-Permits.docx DOCX document
Attah. 01 PWS SBIWTP O&M Services.pdf PDF
Attch. 12 2025 NPDES ANNUAL BIOSOLIDS REPORT.pdf PDF
Attch. 02 FY26 SBIWTP O&M QASP.docx DOCX document
Attch. 15 NIST.SP.800-171r3.pdf PDF
Attch. 07 FY26 IBWC Condition Assessment Report.pdf PDF
Attch. 26 Past Performance Questionnaire.pdf PDF
Attch. 10 Monthly Chemical Dosage 2025 to 2026.pdf PDF
Attch. 02 FY26 SBIWTP O&M QASP.pdf PDF
Attch. 09 SBIWTP Capital Project List as of September 2025.pdf PDF
Attch. 20 SOUTH BAY SPILL PREVENTION AND RESPONSE PLAN October 2024.pdf PDF
Attch. 17 SBIWTP Map.pdf PDF
Attch. 19 SOO_V2_06192018.pdf PDF
Attch. 08 IBWC SBIWTP - Asset Maintenance Schedule.xlsx XLSX spreadsheet
Show all 46

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

11/25/2026 1:31 PM Page 1 of 29

191BWC26R0009

Questions & Answers - Received through 11/19/26

See Amendment 0003 for Q&A No. 1-2

3. Proposal format and page limit. Section L.05.A(c)(1)b limits the Technical Proposal to 40 single-sided pages and excludes the cover page, table of contents, indices, resumes, certificates, client authorization letters, and divider pages. Section M, Factor 3 (Company Experience), requires a minimum of five relevant contracts at two pages per contract. Do the five (or more) two-page contract write-ups required under Factor 3 count toward the 40-page limit? If they do not, please confirm that they may be provided as an attachment or appendix outside the page limit.

Response 3. Yes. The contract descriptions submitted under Factor 3, Company Experience, count toward the page limitation for Volume I. In order to allow for more information, the page limit in Solicitation Section L.05.A(c)(1)b. has been increased to a maximum of 60 single-sided or PDF pages. Factor 3 requires a minimum of five relevant contracts and allows up to two pages for each contract. These pages are part of the Technical Proposal and may not be submitted outside the page limitation as a separate attachment or appendix. The cover page, table of contents, indices, resumes, certificates, client authorization letters, and divider pages remain excluded items from the page limit. Amendment 0002 also clarified that all relevant experience submitted for Factor 3 must comply with the maximum page limitation. Also see Responses 5 and 66.

4. Proposal format and page limit. Because proposals are uploaded as PDF files, please confirm that the 40 single-sided page limit means 40 PDF pages as uploaded.

Response 4. Yes, PDF pages. Also see revised page limit in Solicitation Section L.05.A(c)(1)b.

5. Proposal format and page limit. Please confirm whether the following are excluded from the page count: (a) letters of commitment and availability for key personnel and critical operators (Factor 6, Subfactor 2); (b) surety reference letters and insurance evidence (Factor 3); (c) the signed security controls self-attestation (Factor 5); (d) the detailed information on enforcement actions related to effluent discharge requirements (Factor 3).

Response 5. The following items are excluded from the page count and may be provided as an appendix: Letters for personnel commitments; references from sureties, insurance, banks, etc.; security controls self-attestation; and disclosure documents from other entities as applicable. The Offeror’s proposal narrative which is part of the page limit shall retain the substantive details disclosing enforcement actions, failures, litigation, and actions related to effluent discharge requirements.

11/25/2026 1:31 PM Page 2 of 29

6. Small Business Subcontracting Plan. Small Business Subcontracting Plan. Section L.05.B(b)(6) requires a plan consistent with Contract Clause 52.219-9 Alt II. Section I lists 52.219-9 and 52.219-9 Alt I (DEVIATION FEB 2026) by title only; Alt II is not listed and the clause text is not in the solicitation. Please clarify: (a) whether Alternate I or Alternate II applies, and if Alternate II, whether Section I will be amended to include it;

(b) which version of the clause text controls, the standard FAR or the February 2026 deviation, with the text or a link; (c) whether a specific format or template is required;

and (d) that the plan is submitted with the proposal in Volume II and negotiated within 30 calendar days of the Contracting Officer's notice of intent to negotiate.

Response 6.

a. FAR 52.219-9, Alternate II, February 2026 deviation, applies. Section L.05.B(b)(6) correctly identifies Alternate II. Section I will be amended to replace the existing reference to Alternate I with the applicable Alternate II reference.

b. The February 2026 deviation version identified in the solicitation and amendment controls. The amendment will incorporate the applicable clause by reference and provide the clause title and date.

c. The Government does not require a separate agency-specific template. An Offeror may use its customary format, provided the plan includes all information required by the applicable version of FAR 52.219-9, Alternate II.

d. An offeror classified as other than small shall include its proposed Small Business Subcontracting Plan in the Business Proposal appendix of Volume II.

Following the Contracting Officer's notice of intent to negotiate the plan, the offeror must complete negotiations within 30 calendar days. An acceptable subcontracting plan is required before award. The requirement does not apply to an Offeror that qualifies as a small business concern for this procurement

7. Reference Documents. Can USIBWC provide a copy of the following:

1. The Treatment Optimization Report due to the San Diego Water Board by December 1, 2026 (Attachment E, Section 6.4).

2. The engineer’s technical report required by CDO R9-2025-0139, Paragraph 5 (due March 1, 2026), assessing post-expansion performance.

3. The CEPT design and the SOPs certified under CDO Table 2, Items 4 and 8 (headworks, CEPT, skimming, solids handling, bypass and blending).

4. The USIBWC predictive model results for 35 MGD blended effluent that support the R9-2026-0005 limits.

5. The last 12 complete calendar months of WIMS database data for the facility.

6. If the December 1 report won’t be released before proposals are due, will the Government provide the daily flow, ferric chloride and polymer dosing data from September 1, 2025 to September 30, 2026 that the report is required to include?

Response 7.

11/25/2026 1:31 PM Page 3 of 29

Item #1. Referenced document will be provided after 12/1/2026 by a separate amendment.

Item #2. Referenced document provided as Attachment 37.

Item #3. Referenced documents provided as Attachment 38.

Item #4. Referenced document provided as Attachment 39.

Item #5. SBIWTP does not use WIMS (assuming Water Information Management System). The available public data for the past 12 months can be found at California Integrated Water Quality System. If this is not what was requested, please clarify specifically what data is being requested, i.e. process control parameters or other data.

Item #6. The dataset requested is provided in Attachment 40.

8. Reference Documents. Factor 5, IT attestation - Does a dedicated, separately accredited enclave for contract data satisfy the Factor 5 attestation for corporate business systems?

Response 8. As long as the enclave is NIST 800-171 compliant, then yes. The Government will need evidence of an established cyber security program.

9. Repairs, maintenance responsibility and equipment data. Is there an annual limit on repairs under $200,000?

Response 9. No. All repairs and replacements under the amount are intended to be completed either routinely or as needed and not wait for the condition to worsen which would elevate the repair to a major repair under a capital project. If work is being done as needed, it would not reach a disrepair condition. The Offeror should come up with an estimate based on the condition and risk assessment provided and note all assumptions in the price proposal narrative.

10. Repairs, maintenance responsibility and equipment data. Please clarify how a “single repair” is defined when applying the $200,000 threshold: by individual asset, by asset system (parent/child asset hierarchy), or by work order or failure event? For example, if a pump, its motor, VFD, and PLC are replaced together as one pump system, and each component is under $200,000 but the combined cost exceeds $200,000, is the threshold applied to each component or to the system as a whole?

Response 10. See Response no. 9. Also, “One-time repair” under Section 1.7 of the PWS refers to Major Repair or Capital Project. This does not apply to the repairs to maintain operations and compliance. For a major repair or capital project (over $200,000), the scope would be comprehensive to include all components and systems associated.

The repair under $200,000 typically applies to an individual asset, not an asset as a system. The O&M Contractor shall not defer or delay any repair, refurbishment, replacement, or upgrade until the cost exceeds $200,000 in order to transform the work into an out-of-scope task.

https://ciwqs.waterboards.ca.gov/ciwqs/index.jsp

11/25/2026 1:31 PM Page 4 of 29

For example, if the 1 component of a pump fails, it should be repaired or replaced immediately to restore its operating condition. An Operator should not wait to replace it with the VFD, PLC, or the valves, or wait until a second pump fail to replace two at the same time. However, if an upset took out the pump along with other components of the system, then the $200,000 would apply to the entire system to be replaced.

11. Repairs, maintenance responsibility and equipment data. Who is responsible for the cost to restore pre-existing equipment failures already classified as out of service or requiring major repairs at contract start-up?

Response 11. Some of the equipment is to be replaced with the expansion of the plant. The pre-existing equipment failures should have been listed on the capital plan.

IBWC will be responsible for the replacement. Repairs to maintain operation will be O&M contractor’s responsibility.

12. Repairs, maintenance responsibility and equipment data. Who is responsible for the cost of repairs to an asset when its CIP replacement is delayed?

Response 12. The O&M Contractor is responsible for maintaining an asset in working order through any means necessary as long as the item is still repairable. Once an asset can truly no longer be repaired or maintained in working condition, the USIBWC will assess how to proceed with each case.

13. Repairs, maintenance responsibility and equipment data. Who is responsible for the cost of maintaining temporary equipment installed during construction?

Response 13. The maintenance of temporary equipment under rental during construction may have separate maintenance agreements through the expansion PDB Contractor. Otherwise, the maintenance would be the responsibility of the O&M Contractor. Maintenance of new equipment installed during the course of the O&M Contract that was not previously identified would be added by a modification.

Equipment that was purchased and installed for the additional 10MGD capacity in a temporary location (screw press/RDTs/CEPT) are the responsibility of the O&M Contractor. Reference the PWS Section A. 1.0. and 1.1.

14. Repairs, maintenance responsibility and equipment data. At what point does maintenance responsibility transfer to the O&M contractor for newly commissioned equipment?

Response 14. Maintenance of the equipment will be the responsibility of the O&M Contractor once satisfactory function has been demonstrated and beneficial use (processing wastewater) is occurring. For equipment and assets throughout the plant being replaced or rehabilitated in areas currently under operation, this will occur once the equipment has been concurrently inspected with the O&M Contractor and the item is placed into service. For an entire process area or new tanks, this would occur during the Guaranteed Performance Testing phase of commissioning.

11/25/2026 1:31 PM Page 5 of 29

15. Repairs, maintenance responsibility and equipment data. Can USIBWC provide an updated Out-of-Service Equipment/Asset list?

Response 15. Please see Attachment 07 FY26 IBWC Condition Assessment Report.

16. Repairs, maintenance responsibility and equipment data. Can USIBWC provide an updated CIP schedule, and an updated schedule showing awarded, ongoing and planned equipment replacements?

Response 16. A new headworks facility, primary treatment expansion (2 PSTs), solids processing expansion (install RDTs, centrifuges, lime addition), new odor control, and new electrical building (complete replacement) is ongoing under the PDB Contract as Phase 1 and is scheduled for completion in April 2031. The construction of the Phase 2 secondary treatment expansion (7 ASTs & 10 SSTs) is anticipated to be awarded in FY27. A CUI Attachment 35 has been provided to show the project construction phasing. Once an O&M Contract award is made, the final design for expansion will be shared with the O&M Operator. An early work package (referenced as EWP-1C) under the expansion includes replacement of equipment assets throughout the plant and all remaining existing poor condition roofs to be reroofed. Reference Attachment 36 for a list of the assets to be replaced.

Other ongoing rehabilitation projects by others include the following, descriptions updated in Attachment 09:

-Rehab Belt Filter Presses #1-4 -Rehab Hollister & Goats Pump Station -Headworks Upgrades All are ongoing and scheduled for completion in March 2027

17. Repairs, maintenance responsibility and equipment data. Can USIBWC provide an updated list of vehicles and heavy equipment available to the contractor?

Response 17. Vactor Truck (International 2115 Combination Catch Basin) and Forklift (Bobcat 11 Ton). Both are in working condition.

18. Repairs, maintenance responsibility and equipment data. Can USIBWC provide historical repair expenditure summaries?

Response 18. No. The O&M Services are a FFP, performance-based contract, so this information is not available. Reference updated Attachment 09, SBIWTP Capital Project list for the capital projects from the last 5 years.

19. Repairs, maintenance responsibility and equipment data. How many wet weather/post-storm cleaning events were recognized/actioned in each of the last 3 years (2023 through YTD 2026)?

Response 19. During the wet weather months of November through March, the Canyon Collector structures shall be fully cleaned of all debris and put back into service within ninety-six (96) hours following a storm event of 0.1 inches or greater (i.e., 11/25/2026 1:31 PM Page 6 of 29

24 hours after wet weather, as defined in the NPDES Permit). Post-storm cleaning is required after each rain before returning the canyon collectors back to service. The O&M Contractor determines when and how much cleaning is necessary to protect the pump stations and the plant operations. Offerors may review historical weather records to identify the number of rain events that occurred. Public information for daily reports may also be found at California Integrated Water Quality System.

20. Repairs, maintenance responsibility and equipment data. If total annual debris removed from the canyons is <7000 yards, will IBWC wish to see those unexpended funds credited to IBWC, or shifted at IBWC’s direction to future years’ balances?

Response 20. This is a FFP. The 7,000CY are provided as an estimated quantity per year.

Whether the amount per year is less or more, the Government doesn’t expect to make an adjustment to the cost.

21. PWS § 1.2.4 refers to a "SCADA Systems Maintenance and Improvements PWS for SBIWTP." Please confirm that this reference explicitly refers to PWS § 1.2.4 of Attachment 01. If a separate document exists, please provide it in Section J.

Response 21. This question is unclear (perhaps correct reference is PWS 4.6.6). The only SCADA Systems Maintenance and Improvements PWS is in reference to PWS 1.2.4.

22. PWS § 1.2.4 & § 4 requires SCADA maintenance, risk assessments, and EOL network switch/hardware replacement. Please clarify: (a) whether replacement of EOL network/server/storage/virtualization assets with repair costs ≤ $200,000 is included in the Firm-Fixed-Price (FFP) O&M CLIN, while capital replacements > $200,000 are funded under separate Over & Above (O&A) task orders; (b) whether the $200,000 repair threshold applies per discrete asset/incident or cumulatively; and (c) the target Period of Performance for replacement of legacy/EOL network equipment.

Response 22. (a) For single items that require repair, USIBWC will rely on the O&M Contractor for repair. The O&M contractor will develop plans and submit to the Agency items that are above the $200K threshold for inclusion into future capitals projects. Also see Response 9. (b) See Response 10. (c) There is no target POP for replacement of legacy/EOL network equipment.

23. PWS § 1.2.4 SCADA/OT: Does USIBWC have VLAN architecture and Layer 3 routing guidelines for distribution switch upgrades between treatment areas and remote pumping stations?

Response 23. We have a topology, and USIBWC is currently responsible for the connection. USIBWC can share any details the Agency has after award. USIBWC will rely on the O&M Contractor to develop these guidelines.

https://ciwqs.waterboards.ca.gov/ciwqs/index.jsp

11/25/2026 1:31 PM Page 7 of 29

24. PWS § 1.2.4 SCADA/OT: Will USIBWC provide a Network Design Plan or is the Contractor required to submit one for approval? If the PDB expansion project requires modification of the plan, who will be responsible for integration and revision of the new Plan?

Response 24. The O&M Contractor will be provided the existing Network Design Plans available along with all documentation from the incumbent Contractor turned over during the transition period. The PDB Expansion Contractor will provide network design submittals for the expansion. The O&M Contractor will continue to develop their own through discovery and/or modify what is provided as needed.

The PDB Expansion Contractor is responsible for the expansion project modifications and integration. A Network Design Plan for the expansion project will be provided by the PDB Contractor. And integration will be responsibility of the PDB Team. New SCADA screens will require coordination and input from the O&M Contractor (for new areas - Headworks, New CEPT, New Solids Handling). Existing PSTs, ASTs, SST would be a replica of existing screens. The O&M Contractor should anticipate participating in the development of trends, alarm tables, and any integration/SCADA testing that requires the actual processing of wastewater.

25. PWS § 1.2.4 SCADA/OT: What is the current communication method/media for the Pump Stations? Is there a plan or project to migrate to a different method, and if so what is the planned new method and timeline for implementation? Who would be performing any ancillary integration work to ensure no functionality or operations are interrupted or lost?

Response 25. At this time, there is no project planned for pump station communications. Pump station communication (via Fiber/Copper/SAT) will be the Government's responsibility until a time that the connections can be upgraded. End Devices (e.g. PLCs, HMIs, etc.) will be the responsibility of the O&M Contractor.

26. PWS § 1.2.4 SCADA/OT: Please clarify whether optical module replacements and fiber-optic link maintenance connecting main facilities and offsite pumping stations fall under the contractor's base operational scope? What is the Contractor’s responsibility for communications infrastructure, including telephone lines, at the Pumping Station facilities (e.g. Goat/Hollister)? Will those areas receive new infrastructure or security network equipment, such as telephone lines or card readers?

Response 26. From an IT perspective there are no upgrades to infrastructure planned at this time. See Response 25 for more details. Fiber optic links for the main facilities will be the responsibility of the O&M Contractor.

27. PWS § 1.2.4.b.2 requires the Contractor to maintain and support radio/telephone infrastructure on the main campus, but excludes long haul circuits off campus. Will the

11/25/2026 1:31 PM Page 8 of 29 telephone infrastructure remain as is or will it be converted to Voice-Over-Internet- Protocol (VOIP)?

Response 27. The O&M Contractor will use the existing communications in place. If the O&M Contractor wishes to convert to VoIP for their convenience, that should be provided at no cost to the Government but is not required.

28. PWS § 1.2.4 requires the Contractor to maintain and support radio/telephone infrastructure on the main campus. Will the PDB expansion project include replacement of telephone infrastructure (e.g. analog phone lines and hardware and software)?

Response 28. The PDB Expansion project does not include replacement of telephone infrastructure or provision of phone system hardware/software.

29. PWS § 1.2.4: Are hardware, re-wiring, and SCADA programming costs for migrating legacy and End-of-Life (EOL) equipment/hardware included in the base O&M scope, or will these be executed under separate Over-and-Above (O&A) task orders? Please confirm whether hardware replacement and migration of End of Life network/control equipment at Hollister and Goat Canyon Pumping Stations falls under baseline FFP O&M or future PDB capital upgrades Response 29. The PDB expansion project does not include any hardware or infrastructure replacement for offsite facilities including the pump stations.

Current/Existing O&M Contractor is on contract to update PLC’s at the lift stations.

Hardware, rewiring, and SCADA Programming will be part of the basic scope and will complete prior to start of the new O&M contract.

30. PWS § 1.2.2 & § 1.4: Please confirm that the Government will authorize planned SCADA/network outage windows for system cutovers under 24/7 operating requirements, and that COR-approved cutover outages will be excluded from performance evaluation (H.01 / QASP) and non-compliance liabilities under PWS § 1.4 Response 30. Outages will be coordinated with the San Diego Field Office and Information Management Division (IMD) with appropriate back-up plans in-place.

31. § 1.2.4 SCADA/OT: Will the Government require redundant PLC processor configurations for critical treatment processes and switchgear to eliminate single-point control failures during contract performance? Are there additional notable PLC design requirements such as network rings or Device Level Rings (DLR)?

Response 31. Redundant PLC processor configurations and DLRs will be incorporated into the control system architecture as part of the PDB Expansion project.

If a critical vulnerability is identified by the O&M Contractor, it should be provided to USIBWC to be captured as a future capital project.

11/25/2026 1:31 PM Page 9 of 29

32. § 1.2.4 SCADA/OT: Is the Contractor responsible for procuring, licensing, and installing new virtual host clusters and storage hardware under Volume II pricing, or will USIBWC provide host server and storage infrastructure as Government-Furnished Equipment (GFE)? If so, can the Government provide any examples of licenses/software/hardware that may be required?

Response 32. It is the O&M Contractor's responsibility to obtain the licenses, but the O&M Contractor will use the host servers and storage that are in place. Software Examples: VM Ware, Ignition, Windows.

33. § 1.2.4 SCADA/OT: Does the Government have a plan or guiding document to establish Recovery Time Objectives (RTO), Recovery Point Objectives (RPO), or other outage event requirements, or will the Contractor be required to develop these products?

Response 33. The O&M Contractor will develop these in coordination with SDFO and

IMD.

34. Given the air-gapped SCADA architecture requirement (PWS § 1.2.4.a.3), please identify the approved backup repository and offsite storage methods. Will USIBWC provide authorized FedRAMP cloud storage endpoints for backup repositories, or is the contractor required to independently license and maintain an appropriately certified cloud backup environment? Will the Government provide documentation and guidance for proper classification of documents?

Response 34. USIBWC can provide small elements of back-ups and some strategies. USIBWC will not provide FedRamp cloud storage endpoints. The Government will provide guidance for proper classification.

35. Section M, Factor 5, Subfactor 3 and PWS § 1.2.4.b.5 limit the 90-day vulnerability remediation requirement to findings "within Contractor control." Please confirm that findings requiring Government-funded hardware replacement or formal Government administrative approval are deemed outside Contractor control and automatically toll the 90-day remediation period.

Response 35. These findings will be captured in a Plan of Action & Milestones (POAMs) and Risk Registers provided by the O&M Contractor with approval from USIBWC’s Authorizing Official (IMD). The Government needs shortfalls identified, the solution, and the timeline. As long as the plan of action is being followed, the O&M Contractor is not liable or penalized if the work extends beyond 90 days.

36. § 1.2.4 SCADA/OT: Please clarify the operational boundary for Controlled Unclassified Information (CUI) and other documents with classification requirements. Is CUI compliance restricted to local plant network drives and designated government portals, or must the contractor construct and maintain a dedicated compliance enclave for

11/25/2026 1:31 PM Page 10 of 29 external corporate data processing? Is Government approval required for external corporate enclaves? Are there any reporting requirements and if so what are they?

Response 36. The O&M Contractor must construct and maintain a dedicated compliance enclave for daily business. Any documents, data, information that pertain to the SCADA environment and federal interaction will be protected via NIST Standards as outlined in PWS. Any data/information related to the company (employee records, timecards, etc.) can be managed however the O&M Contractor sees fit.

37. PWS § 1.2.4 requires corporate systems processing Controlled Unclassified Information (CUI) to comply with NIST SP 800-171 Rev 3 and other applicable regulations/Executive Orders. Please confirm if CUI compliance is limited to corporate endpoints accessing USIBWC SharePoint portals, or if the Contractor must build an independently audited, dedicated cloud compliance enclave.

Response 37. The O&M Contractor must build an independently audited compliance enclave. The Government must have access to the cybersecurity plan for the network and to the enclave.

38. PWS § 1.2.4.b.4: Does the Government mandate specific vulnerability scanning and continuous monitoring software tools for the SCADA/OT network, and will these licenses be provided as GFP or must they be procured and licensed by the Contractor?

Response 38. The licenses must be procured by the O&M Contractor but will belong to the Government. USIBWC will provide recommendations for tools after award.

39. PWS § 1.2.4.b.3 & § 4.2.4: Please define Contractor responsibility for control hardware, PLC/HMI programming, loop tuning, graphics, and commissioning for assets installed under the progressive design-build (PDB) expansion. Confirm that PDB design reviews and integration support (PWS pp. 4–5) are included in baseline FFP, and state what turnover documentation, spare parts, and warranties will be provided by the PDB team upon handover.

Response 39. The PDB Contractor and their system integrator are responsible for all work to expand the plant. The O&M Contractor will provide reviews, coordination, and input to the PDB Contractor/Integrator. This support shall be included in the baseline FFP for O&M Services. Warranties, O&M Manuals, Training, and Manufacturer Inspections &Certifications for completion will be provided for turnover. The O&M Contractor should anticipate participating in the loop tuning process as well as collecting/providing performance data to optimize loops.

40. PWS § 1.2.4 SCADA/OT: Will expansion contractors (e.g., via PDB Team) deliver pre-programmed, fully integrated control hardware to the edge of the network, or will the O&M contractor be required to program and integrate new field I/O into the primary SCADA framework?

11/25/2026 1:31 PM Page 11 of 29

Response 40. Yes, this is the PDB Contractor's responsibility for a full and operable system.

41. PWS § 1.2.2.q: PWS § 1.2.2.q assigns O&M responsibility for temporary equipment installed by the PDB team. Please clarify: (a) equipment ownership status (GFP vs. PDB-owned vs. vendor-leased) and inclusion on the § 3.2 joint inventory; (b) whether major overhauls or component replacements (> $200,000) are covered by the Government;

and (c) vendor warranty coverage and expected operational duration.

Response 41.

(a) GFP and PDB-owned equipment will be included in joint inventory.

(b) Major replacement over $200,000 will require a capital project by the Government.

All other preventive maintenance and requirements included in the O&M manuals regardless of cost are the O&M Contractor’s responsibility.

(c) Vendor warranty coverage will be maintained for at least 2 years from date of beneficial use unless an extended warranty is provided. The operational duration is expected to last through the entire construction period of 4-5 years.

42. PWS § 1.3.9: PWS § 1.3.9 requires the Contractor to update as-built drawings within 30 days of modification. Please state how the Contractor will be formally notified of Owner/PDB facility modifications to initiate the 30-day compliance window.

Response 42. These as-built drawings are for capital projects or plant changes completed by the O&M Contractor. The 30-day window starts once the capital project or field modification/repair is completed. The PDB Contractor is responsible for the record drawings of their own construction project.

43. § 1.2.4 SCADA/OT: What security protocols, change-control approvals, and monitoring mechanisms including remote access will govern third-party contractor personnel requiring physical or logical access to the control network during expansion construction and commissioning? Will remote or cloud access capabilities be fully controlled by the Government only, or will the Contractor have joint control and administrative responsibility?

Response 43. There is no remote or cloud access capability for SCADA. The Government will give admin rights or access rights to any third party contractor working on the SCADA/OT as part of the PDB expansion or other capital projects. The O&M Contractor will allow physical access as needed to the integrators. In order to keep the plant in operation, there will be joint access to allow the expansion integration to take place. The administrative responsibility remains with the O&M Contractor, but the PDB Contractor is responsible for their work and any damages/disruptions they cause.

44. PWS § 1.2.4 requires the Contractor to operate and maintain the air-gapped SCADA system. Will the procurement, licensing, and installation of replacement EOL

11/25/2026 1:31 PM Page 12 of 29 equipment/hardware be funded via Government O&A task orders, or is hardware procurement expected within the baseline O&M FFP?

Response 44. EOL equipment/hardware is a capital project. See Response 22.

45. § 1.2.4 / § 1.3 - Cybersecurity & Reporting Requirements: Will the Government provide a comprehensive list of periodic cybersecurity reporting requirements the Contractor must perform (quarterly or annually security control assessments, monthly patching reports, etc.) and if so what are they?

Response 45. This will be developed between the O&M Contractor and IMD.

46. § 1.2.2 Operation & Maintenance of SBIWTP: Please identify the existing facilities, equipment, and resources that will be available to the Contractor to perform on site lime stabilization of biosolids, including sufficient holding capacity to accommodate the full 24 hour stabilization period. Please also clarify which equipment and materials will be provided by the Government and which the Contractor will be responsible for supplying.

Response 46. The SBIWTP disposes of biosolids in Mexico per agreements between the United States and Mexico. This is recognized in the current NPDES permit and U.S.

regulations do not apply unless biosolids are disposed in the U.S. In Mexico, their official standard is similar to U.S. regulations for biosolids and specifically for lime stabilized biosolids, pH >12 for 2 hrs, pH > 11.5 for 22 hrs is practiced to meet vector attraction reductions. The goal of the SBIWTP is to dose lime to meet the >12 pH for 2 hrs for vector reduction. The facility was designed to dose with lime then load onto trucks for disposal in Mexico, and not for beneficial uses. The second step of verifying the pH of 11.5 would be the responsibility of Mexico once it reaches the disposal site.

The U.S. Contractor is responsible for dosing biosolids with lime to raise the pH up to

12. The lime system is currently offline but will be replaced under the PDB Expansion project. The existing lime stabilization equipment will be replaced in its entirety with exception of the two existing lime silos, which will be rehabilitated. A third lime stabilization train will be added, inclusive of a new third lime silo. Rehab/replacement of the lime stabilization equipment is anticipated to start late 2028.

The Contractor will not implement lime stabilization until the new system is in place. At that time, the additional O&M services related to lime stabilization will be added to the contract by modification. Note that the existing sludge /lime mixers (Pug mills) will be replaced December 2026.

47. PWS § 1.2.2 & Attachment 10: PWS § 1.2.2 notes that lime stabilization parameters under NOM-004-SEMARNAT-2002 are temporarily waived until silos are rehabilitated.

For inactive or uninstalled processes (e.g., lime stabilization, centrifuges) lacking historical dosage data in Attachment 10, should Offerors exclude these chemical costs

11/25/2026 1:31 PM Page 13 of 29 from the baseline FFP proposal and address chemical costs for reactivated processes via formal contract modifications upon return to service?

Response 47. Yes.

48. § 1.2.2 Operation & Maintenance of SBIWTP: Given the requirement to base chemical pricing on the highest monthly dosage identified in Attachment 10, please clarify how Offerors should account for chemical costs associated with processes that are not currently installed, for which the chemicals and required dosages have not been defined, and for which no historical usage data are available (i.e. dewatering centrifuge).

Response 48. Using Attachment 10 for highest dose and consumption for dewatering with centrifuges is comparable. Published estimated cationic polymer dosages for belt filter and centrifuge technologies are available from vendors that can provide additional information to base chemical costs to that listed in Attachment 10.

49. PWS § 1.0 and § 1.2.2 assign O&M responsibility for temporary 10 MGD equipment (Rotary Drum Thickeners, trailer-mounted screw press). Will major overhaul/replacement costs for these temporary rental skids be covered by the equipment vendors/USIBWC, or does the O&M Contractor bear full asset replacement risk?

Response 49. The O&M Contractor is responsible for the routine and preventive maintenance of the skids. The skids should last the construction duration during which they will be in use, hence an overhaul or replacement should not be necessary. In the event an overhaul or replacement is needed, USIBWC will evaluate the need and address it accordingly.

50. PWS § 1.0: PWS § 1.0 references an anticipated new NPDES permit during the contract term. Please confirm that any expanded testing parameters, altered sampling frequencies, or operational/facility modifications required under a new NPDES permit will be implemented through priced contract modifications pursuant to FAR 52.243-1 prior to execution.

Response 50. Yes. Reference PWS A. 1.0 which states, "It is anticipated that a new NPDES Permit will be issued during the contract period that may have additional requirements outside the current scope. When needed, a modification to this Contract will be prepared to address additional permitting requirements."

51. § 1.6 Over & Above (O&A) Maintenance/Repairs: Please clarify whether O&A capacity will be established via a separate contract CLIN or task order structure, or if offerors are expected to fold major repair contingencies into the FFP CLINs.

Response 51. The term "O&A capacity" is unclear. It is assumed the question is asking about work that qualifies above the $200,000 threshold. The O&M Contractor

11/25/2026 1:31 PM Page 14 of 29 should account for the initial $200,000 for an emergency response. Costs beyond $200,000 will be reviewed and approved accordingly. If approved, the cost will be issued by modification either to an applicable existing CLIN or by a separate CLIN.

52. Evaluation Factors for Award: Section M lists weightings for Factors 1 through 7.

However, Factor 1 and Factor 2 each contain detailed subfactors. Please clarify whether all subfactors within a given Factor are weighted equally during numerical scoring calculations.

Response 52. The Government will evaluate the subfactors under Factors 1 through 7 in accordance with the relative importance and evaluation methodology stated in Section M. Unless Section M expressly assigns different weights to individual subfactors, the subfactors within each applicable factor are of equal importance. The solicitation does not establish a separate undisclosed weighting for any subfactor.

53. Please clarify whether the requirements of Section 1.3, including as-built markups/redlines, AutoCAD and PDF updates, and any required Professional Engineer review and support, apply only to Plant modifications performed by the Contractor or also extend to modifications performed by the Owner or other contractors. If these responsibilities extend to modifications performed by others, please clarify who is responsible for providing the necessary modification details and supporting documentation, how the Contractor will be notified to meet the 30-day deadline, and whether the associated drafting and engineering costs must be included in the bid proposal price.

Response 53. These apply only to the plant modifications performed by the O&M Contractor. Separate construction projects have their own separate requirements for record drawings. For separate capital projects by the O&M Contractor, the costs for drafting and engineering to prepare as-builts drawings should be included in the cost proposal prepared during that RFP process, not in the cost of this contract. This contract should include a measure of associated as-built preparation for miscellaneous modifications that the O&M Contractor may perform during maintenance repairs or field changes.

54. PWS § 1.2.2 requires the Contractor to manage, transport, and dispose of debris. Given the multi-year period of performance and significant volatility in commercial diesel markets, would the Government consider incorporating a FAR 16.203 Economic Price Adjustment (EPA) clause indexed to the EIA On-Highway Diesel Fuel Price Index?

Response 54. Yes. The Offeror should include inflation/escalation in their price. The EPA clause will be added to reduce risk of unusual events.

55. PWS § 1.2.2.p & § 4.6: PWS § 1.2.2.p requires "dedicated gate entry security," and PWS §

4.6 requires "posted security or equivalent." Please specify whether physically posted

11/25/2026 1:31 PM Page 15 of 29 security personnel are required at: (a) main plant gates (Gates 3 & 4); (b) Hollister and Goat Canyon pump stations; and (c) canyon collectors; and state required operational hours and armed/unarmed status.

Response 55. The O&M Contractor will not be providing any security guards.

USIBWC is responsible for providing officers. Reference the revised PWS for clarifications.

56. § 1.1 Scope of Work: The scope requires the Contractor to protect the SBIWTP’s biological treatment system during zero influent flow conditions that may extend over several days and references the established contract modification request process for associated impacts and compensation. Because biological preservation can be costly and greatly depends on the duration of low flow/ zero flow conditions, please clarify the following:

a. The anticipated number of zero flow events per contract year.

b. The expected duration of zero flow shutdowns.

c. Where immediate action is necessary to protect the biological treatment system before a formal contract modification can be approved, what notification and authorization procedures must the Contractor follow?

Please clarify how costs incurred under those procedures before formal approval will be evaluated for compensation.

Response 56.

a. Expect at least 1 per contract year.

b. It could vary from few hours to few days. The O&M Contractor determines ways to protect the plant.

c. The O&M Contractor must notify the CO, COR, and SDFO AOM immediately of the emergency and proposed response. Reference PWS Section 1.6, O&A procedure for contractual requirement and procedures. Also, reference NPDES Permit Attachment D for 24-hours Reporting, permit compliance requirements.

57. PWS § 1.3.13 & SCADA SOW: Please specify the existing fire alarm and suppression systems across facilities, state whether they integrate with SCADA (PWS § 1.2.4), clarify if the PDB project will modify or duplicate these systems, and confirm maintenance responsibility under PWS § 1.3.13.

Response 57. See the list below for the existing fire suppression system locations.

The system is not integrated with SCADA. The only fire alarm and suppression system to be modified during the PDB Expansion project is for the expansion/renovation of the O&M admin building. All other systems remain as is. The O&M Contractor is responsible for maintenance of all fire alarm and suppression systems currently in use at the plant and all administrative/personnel buildings, including annual inspection and any required service. Note that USIBWC is planning a future capital project to rehabilitate or

11/25/2026 1:31 PM Page 16 of 29 replace all remaining fire suppression systems after the PDB expansion project is complete. Also, please note that the current systems were never tied to the local Fire Marshal to respond.

1. Operations Building FACP and Sprinklers

2. Maintenance Building FACP and Sprinklers

3. Blower Building FACP

4. SST LCC (Electric) FACP

5. DAF Control Building FACP

6. Personnel Building/Maintenance Garage FACP and Sprinklers

7. Headworks FACP and Sprinklers

8. Main SWGR Building FACP

9. NaOCl-LCC (Electric) Building FACP

10. Sludge Dewatering Building FACP

11. Truck Loading Building FACP

12. PST-LCC (Electric) Building FACP

13. Hollister Pump Station FACP

14. Goat Canyon Pump Station FACP

FACP=Fire Alarm Control Panel

58. PWS § 3.2 & Section C.3.2.c(2): PWS § C.3.2.c(2) requires maintaining a critical spare parts inventory on site based on historical repairs. Will the Government provide initial spare parts seed stock as Government Furnished Property (GFP) during phase-in, or is the Contractor required to procure the complete initial inventory under the Base Year

FFP?

Response 58. Any existing spare parts remaining will be transferred to the O&M Contractor as GFP during the transition period. There is no set spare part requirement established. The O&M Contractor must determine what is required to be on hand the first year as the subject matter expert.

59. PWS § 4.0 & Section M Factor 4: PWS § 4.0 defines Key Personnel as Plant Manager, Superintendent, SSHO, SSP, and Plant Asset Manager. However, Section M Factor 4 evaluates Plant Superintendent, Operations Supervisor, Maintenance Supervisor, SCADA System Analyst, Shift Supervisor, and Safety Lead. Please confirm which position list governs Section H.11 Key Personnel requirements and proposal evaluation.

Response 59. The PWS specifies the required minimum key personnel. Section M Factor 4 requires Offerors to provide the key personnel and plant staffing plan proposed to meet the contract requirements for evaluation. Reference the revised Section M Factor 4 for clarifications.

60. Section L.05.B & Factor 3: Section L.05.B sets a proposal limit of 20 double-sided pages. Factor 3 requires detailed write-ups for at least five past performance references

11/25/2026 1:31 PM Page 17 of 29

(up to two pages each). Please confirm whether past performance reference write-ups count against the 20-page limit.

Response 60. See Response no. 3. Past performance client letters for Factor 7 are not part of the page limit.

61. Please confirm: (a) the official proposal due date; (b) anticipated award date; and (c) the official start date for the 60-day Phase-In period prior to full PoP commencement on June 1, 2027.

Response 61.

(a) Proposals are due 1/6/2027 by 2:00 PM Mountain per the SF-33 Item 9 and Solicitation Section L.04.B(a).2.

(b) The goal is to award by February 16, 2027.

(c) The official start date of the 60-day Phase-In period is anticipated to be April 1, 2027.

62. Section H.06 cites Wage Determination WD 2015-5635 Rev. 31 (dated 08/22/2026), whereas Attachment 21 includes CA20240001 (dated 07/26/2024). Please confirm which wage determination governs contract execution and whether a Collective Bargaining Agreement (CBA) applies to current incumbent personnel.

Response 62. WD 2015-5635 governs, however, refer to the updated WD 2015-5635 Rev.32 09/08/2026 in the Solicitation to replace Attachment 21. See revised H.06 and revised Attachment 21 for WD 2015-5635 Rev.32 09/07/2026. Refer to Solicitation Section H.05 for CBA.

63. Standard Form 33. Proposal submission due date. As of November 17, 2026, we have not received complete solicitation attachments from the government, specifically CUI files. Will the government extend the current submission deadline to February 10, 2027 to account for this delay?

Response 63. No.

64. Solicitation Doc 191BWC26R0009, Sec. L.02, Questions. Questions submission deadline. As of November 17, 2026, we have not received complete solicitation attachments from the government, specifically CUI files. Will the government extend the current questions submission deadline by two weeks from date of receipt of CUI files?

Response 64. No.

65. RFP Sec. L.04.C(2), L.05.A(a) Factor 3 (Company Experience). Proposal Format & Page Limits Section L.04 establishes a strict page limitation of 20 double-sided (40 single-sided) pages for Volume I. Under Factor 3, offerors are instructed to submit a minimum of 5 project descriptions at up to 2 pages each (totaling up to 10 pages). Will the Government confirm whether the 5 contract experience descriptions under Factor 3 are

11/25/2026 1:31 PM Page 18 of 29 included in the 40-page limit for Volume I, or may they be submitted as an Appendix excluded from the page count, similar to resumes and certifications?

Response 65. See Response no. 3.

66. RFP Sec. L.04.C(2), L.05.A(a) Volume I Appendices. Proposal Format & Supplemental Technical Data. Section L.04 explicitly excludes cover pages, tables of contents, indices, divider sheets, resumes, certifications, and Client Authorization Letters from the page count. May offerors include supplemental non-pricing technical documentation—such as staffing matrices, 24/7 shift rosters, sample CMMS maintenance schedules, and SOP flowcharts—as an excluded Appendix to Volume I?

Response 66. Staffing matrices, 24/7 shift rosters, and sample CMMS maintenance schedules may be provided as appendices as long as the material is directly pertinent to the requirements of this Solicitation and for use in the evaluation. SOP flowcharts should be provided within the proposal (included in the page limit) for the corresponding factor/subfactor narrative to provide a complete, substantive technical plan for evaluation. In the proposal submission, ensure to annotate which Factor/Subfactor the appendix supplements. Do not include any samples, elaborate/uninformative material, and unnecessary information that does not clearly tie to a subfactor.

67. RFP Sec. B (CLIN Schedule) PWS Sec. 1.1. CLIN 002 (10 MGD Expansion) Activation.

Section B lists annual CLINs for 25 MGD base treatment (e.g., CLIN 001) and separate CLINs for the additional 10 MGD treatment increment (e.g., CLIN 002). PWS 1.1 notes the contractor must operate temporary facilities installed by the Progressive Design- Build (PDB) contractor. Given that the PDB expansion and temporary 10 MGD commissioning schedule is ongoing, should offerors price CLIN 002 assuming a full 12 months of operation in the Base Year, or will CLIN 002 be exercised on an as-needed / partial-year basis via contract modification upon physical handover?

Response 67. Yes, assume a full 12 months of operation; the additional 10MGD is active at this time (reference PWS 1.1). Separation of CLIN 001 and CLIN 002 are required for administrative purposes only to track funding source. Please note that the equipment may be referenced as temporary due to its interim location, but the operation of the 10 MGD is not temporary.

68. RFP Sec. L.05.B(a)(7) FAR 52.216-4. Chemical Escalation & Economic Price Adjustment. The solicitation requires vendor quotes/invoices for bulk chemicals based on historical dosages in Attachment 10 under a 5-year Firm-Fixed-Price (FFP) contract structure. Given market volatility for bulk treatment chemicals (Sodium Hypochlorite, Ferric Chloride, Polymer), will the Government incorporate an Economic Price Adjustment (EPA) clause for chemical commodities, or must offerors absorb 5-year market escalation risk entirely within fixed CLIN pricing?

11/25/2026 1:31 PM Page 19 of 29

Response 68. Yes, the Government will consider an Economic Price Adjustment for chemicals. The Offeror should include a reasonable escalation/inflation cost for probable market increases.

69. Attachment 07 (Condition Assessment) PWS Sec. 1.6 & 4.2. Pre-Existing Asset Deficiencies & Maintenance Scope. Attachment 07 documents numerous legacy assets "Approaching end of life," "In need of rehabilitation," or operating with severe thermal anomalies (e.g., MCC bucket breakers operating at 156°F). If a legacy plant asset identified in Attachment 07 as degraded or in need of rehabilitation suffers a mechanical, electrical, or structural failure during the 60-day phase-in or early contract performance, will repairs/replacements be funded under Capital Projects / Over-and- Above (O&A), or is the contractor expected to repair preexisting legacy defects under routine FFP maintenance?

Response 69. Replacement/rehabilitation for pre-existing conditions will be funded as Capital Projects.