This is a Statements of Submittal (SOMs) register that outlines all required submissions for the Operations and Maintenance Services contract for the Southbay Wastewater Treatment Plant (SBIWTP). The register details 21 distinct submittal requirements spanning planning documents, operational procedures, inspection records, reports, and compliance documentation. Key initial submissions due within 15-30 days of award include a Phase-In Plan, Preventative Maintenance Plan (PMP), personnel certifications and licenses, Site Safety Plan, Laboratory Quality Control & Management Plan, and Continuity of Operations Plan (COOP). Within 180 days of award, the contractor must verify and update Standard Operating Procedures (SOPs) transferred from the previous operator and conduct a physical inventory of real property. Additional one-time submissions include a Sequence of Operations (SOO) manual and SCADA documentation, and As-Builts as needed.
The register establishes ongoing monthly and annual reporting obligations requiring the contractor to maintain daily plant logs and records, submit monthly Operations & Maintenance reports by the 15th of each month documenting influent/effluent quality and quantity, sludge production, chemical storage and dosage, maintenance tasks, and network maintenance activities, and provide annual Condition & Risk Assessment Reports, 5-Year Capital Plans, and Deferred Maintenance & Repair Reports due by September 30 and January 15 respectively. Daily canyon collector inspections with monthly photo submissions and compliance with all NPDES permit requirements are also mandated. The contractor is responsible for maintaining all records for five years, with originals retained at the facility's Operations Office.
View the file
Other files
Show all 37
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOMS
| SUBMITTAL REGISTER (SOMs) | ||
| CONTRACT NO. | ||
| TITLE AND LOCATION | SPECIFICATION SECTION | |
| A C T I V I T Y |
N O
| TYPE OF SUBMITTAL | CLASSI- | |||
| FICATION | GOVT | CONTRACTOR | ||
| SCHEDULE DATES | GOVERNMENT |
ACTION
| SPECIFICATION/PWS PARAGRAPH NUMBER | DESCRIPTION OF ITEM SUBMITTED | Frequency | D A T A | ||||||||||
| D R A W I N G S | |||||||||||||
| I N S T R U C T I O N S | |||||||||||||
| S C H E D U L E S | |||||||||||||
| S T A T E M E N T S | |||||||||||||
| R E P O R T S | |||||||||||||
| C E R T I F I C A T E S | |||||||||||||
| S A M P L E | |||||||||||||
| R E C O R D S | |||||||||||||
| INFORMATION ONLY | GOVERNMENT APPROVAL NEEDED | REVIEWER | SUBMIT date | APPROVAL NEEDED BY | MATERIAL NEEDED BY | Date Rcvd | Date sent to KTR | REMARKS | |||||
| 2 | Solicitation, PWS 1.1.1 | Phase-In Plan | once | x | to be provided with Proposal | ||||||||
| 3 | PWS 1.3.13 | Preventative Maintenance Plan (PMP) | once, reviewed annually | x | NLT 30 SEP | ||||||||
| PWS 1.5.1 | Preventative Maintenance & Inspection Program (PMI) | ||||||||||||
| 4 | PWS1.1.1 | Certifications, Licenses of personnel | once, update as needed | x | to be provided 15 days after award | ||||||||
| 5 | PWS 3.2 | Physical Inventory of Real Property to be maintaned | initial | x | inventory to be conducted 90 days after award | ||||||||
| 6 | PWS 4.7 | Site Safety Plan | once, and update as needed | x | COR to Safety Office | to be provided 15 days after award | |||||||
| 7 | PWS 2.0 & 4.5 | Laboratory Quality Control & Management Plan | once and update as needed | x | COR to Env. Office | to be provided with proposal | |||||||
| 8 | PWS 1.1.1 & 4.6.3 | Continuity of Operations Plan (COOP) | once, and update as needed | x | COR | to be provided within 30 days after award | |||||||
| 10 | PWS 1.3.11 | SOPs Standard Operating Procedures | once, and update as needed | x | NLT 30 SEP | Transfer ownership from previous operator to new operator, Physical Location in Ops. Office at SBIWTP, new operator to verify SOPs and provide an update within 180 days of contract award | |||||||
| 11 | PWS 1.2.3 | Canyon collector daily inspections, with photos | monthly | x | NLT 15th of mo. | submit with Monthly Report | |||||||
| 12 | PWS 1.2.2 | Plant Log, Record keeping logs | daily | x | Contractor shall maintain records for 5 years and originals | ||||||||
| 13 | PWS 1.3.6 | Condition & Risk Assessment Report | annually | x | NLT 30 SEP | ||||||||
| 14 | PWS 1.3.7 | 5 Year Capital Plan | annually | x | NLT 30 SEP | ||||||||
| 15 | PWS 1.3.12 | Deferred Maintenance & Repair Report | annually | x | NLT 15 JAN | ||||||||
| 16 | PWS 1.3.3 | Monthly O&M Reports | monthly | x | to include influent effulent wwtp quality and qty., qty. of sludge produced, chemicals stored and dosage, repairs and maintenance tasks performed, pending modifications too, also include admin network maintenance performed | ||||||||
| 18 | PWS 1.2.4 & 4.2.1.1 &1.3.10 | Admin Network Cybersecurity Program | |||||||||||
| 19 | PWS 4.2.1.1 | Sequence of Operations (SOO) manual, SCADA | once and update as needed | x | |||||||||
| 20 | PWS 1.3.9 | As-Builts | as needed | x | |||||||||
| 21 | NPDES & PWS 1.3.2 | All reports required under NPDES Monitor & Program Requirements, Attachment E |