Attch. 09 SBIWTP Capital Project List as of September 2026.pdf

PDF 96 KB Posted

Attached to
Operations and Maintenance (O&M) Services for the SBIWTP
Solicitation number
191BWC26R0009
Issued by

About this file

This document is a capital improvements budget summary for urgent repairs at the Santa Barbara Integrated Wastewater Treatment Plant (SBIWTP) designed to restore performance and add process redundancy.

The project encompasses 15 separate repair and rehabilitation actions totaling $67,149,482. Major actions include: Emergency Generator Controls upgrade ($1,092,543, completed 09/2022); Repair Influent Flow Meter ($1,791,532, completed 8/17/2021); Repair Junction Box #1 ($6,991,399, completed 8/10/2023); Rehab PSTs #1-5 ($3,368,414, completed 8/14/2023); USST Valves and Piping Replacement ($4,441,271, completed 9/29/2023); Backup Pumps & Motors for redundancy following Tropical Storm Hilary ($4,190,233, completed 9/29/2023); 4 Backup Influent Pumps ($1,908,000, completed 3/25/2024); Rehab Belt Filter Presses #1-4 ($13,250,587, scheduled complete by March 2027); Rehab Grit Facility ($7,560,323, completed 3/29/2025); Replacement of Silva Drain and Del Sol Line ($1,287,012, completed 4/21/2025); Rehab Hollister and Goats Pump Station ($12,041,188, scheduled complete 09/2025); and Headworks Upgrades ($6,844,441, scheduled complete 9/25/2026). Most actions have been completed, with three projects scheduled for completion by March 2027. Work addresses emergency maintenance needs caused by excess inflows, sediment accumulation, equipment deterioration, and system redundancy requirements.

View the file

Other files

File Type Posted
Offeror Questions_thru20261119.pdf PDF
Attch. 33 O&M Services Price Workbook (blank template)_updatedNov2026.xlsx XLSX spreadsheet
191BWC26R0009 0004.pdf PDF
Attch. 01 PWS SBIWTP O&M Services 20261125.pdf PDF
Attch. 21 Wage Determination CA2015-5635 Rev32 20260908.pdf PDF
Attch. 32 0131 20260720 PCL Construction Security Plan.pdf PDF
191BWC26R0009-0003.pdf PDF
191BWC26R0009 0002.pdf PDF
191BWC26R0009 0001.pdf PDF
Attch. 28 Temporary_Dewatering_Narrative.pdf PDF
Attch. 30.b. FSP ANNEX D MONTHLY SBIWTP (2026).pdf PDF
Attch. 34 SBIWTP O&M Site Visit oct14_26.pdf PDF
Attch. 30.a. FSP ANNEX A SBIWTP (2026).pdf PDF
Attch. 33 O&M Services Price Workbook (blank template).xls XLS spreadsheet
Attch. 29 Screw Press Map and Drawings.pdf PDF
FY27 SBIWTP OM PWS REV 1 10.19.26.pdf PDF
Attch. 27 SD.I.10031-M-2 Background Investigation Procedures for SBIWTP Contractor Personnel.pdf PDF
Attch. 30.c. FSP ANNEX D ANNUAL SBIWTP(2026).pdf PDF
Attch. 16 Plans Drawings Request Instructions.docx DOCX document
Attch. 01A SOM SUBMITTAL REGISTER SBIWTP O&M 2026.xlsx XLSX spreadsheet
Attch. 25 Client Authorization Letter.docx DOCX document
191BWC26R0009 OM SBIWTP Services.pdf PDF
Attch. 18 NIST.FIPS.199.pdf PDF
Attch. 11 Canyon Collector Daily Inspection template- MAR 2025.xlsx XLSX spreadsheet
Attch. 23 LAB SAMPLING QTY.xlsx XLSX spreadsheet
Attch. 04.a. GiantKelpVariance_09.11.26.pdf PDF
Attch. 21 Wage Determinations CA20240001 07.26.2024.pdf PDF
Attch. 04 Order No. R9-2021-0001 as amended R9-2026-0005.pdf PDF
Attch. 22 MX- Norma004_Semarnat_2002_english version.pdf PDF
Attch. 05 List-of-Permits.pdf PDF
Attch. 24 OEP-SBIWTP(2026).pdf PDF
Attch. 06 IBWC SBIWTP Asset Registry 2024.xlsx XLSX spreadsheet
Attch. 05 List-of-Permits.docx DOCX document
Attah. 01 PWS SBIWTP O&M Services.pdf PDF
Attch. 12 2025 NPDES ANNUAL BIOSOLIDS REPORT.pdf PDF
Attch. 02 FY26 SBIWTP O&M QASP.docx DOCX document
Attch. 15 NIST.SP.800-171r3.pdf PDF
Attch. 07 FY26 IBWC Condition Assessment Report.pdf PDF
Attch. 26 Past Performance Questionnaire.pdf PDF
Attch. 10 Monthly Chemical Dosage 2025 to 2026.pdf PDF
Attch. 02 FY26 SBIWTP O&M QASP.pdf PDF
Attch. 09 SBIWTP Capital Project List as of September 2025.pdf PDF
Attch. 20 SOUTH BAY SPILL PREVENTION AND RESPONSE PLAN October 2024.pdf PDF
Attch. 17 SBIWTP Map.pdf PDF
Attch. 19 SOO_V2_06192018.pdf PDF
Attch. 08 IBWC SBIWTP - Asset Maintenance Schedule.xlsx XLSX spreadsheet
Show all 46

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Urgent repairs at SBIWTP to restore performance and add redundancy in process:

ACTION DESCRIPTION COST

DATE

AWARDED

NOTES

Emergency Generator Controls

Upgrade of the controls of Standby Generators #1 & #2.

$ 1,092,543 09/2022 Completed

Repair Influent flow meter and associated piping and valves

Replace deteriorated Cement-Lined Ductile Iron (CLDI) piping and flow meter

$1,791,532 8/17/2021 Completed

Clean PSTs #1-4 Emergency Maintenance due to excess trash and sediment from excess inflows from MX. Dewater and clean tanks.

$1,782,473 7/28/2023 Completed

Repair Junction Box #1 Design and construction of new Junction Box 1.1.

$6,991,399 8/10/2023 Completed

Rehab PSTs #1-5 Emergency Maintenance due to trash and sediment from excess inflows from MX. Replace all moving mechanical components to include sprockets, bearings, flights, chains, hubs, skimmers, and all required hardware, spacers, and fittings.

$3,368,414 8/14/2023 Completed

USST Valves and Piping Replacement

Rehab USST #1&2 including pumps, piping, valves and installation of new soft starters (Variable Frequency Drives - VFDs).

$4,441,271 9/29/2023 Completed

Backup Pumps & Motors

For redundancy after TS Storm Hilary.

Replace WAS pumps, AST pumps, grinders, NPW pumps & motors.

Hollister Pump Station - install new submersible pumps & VFDs

$4,190,233 9/29/2023 Completed

Clean Grit Chambers Emergency Maintenance due to trash and sediment from excess inflows from MX. Dewater and clean grit chamber.

$439,066 2/16/2024 Completed

4 Backup Influent Pumps

For redundancy after TS Storm Hilary.

Replace failing pumps to keep plant operable.

$1,908,000 3/25/2024 Completed

Rehab Belt Filter Presses #1-4

Rapid deterioration caused by sand in sludge. Rehab presses 1-4, including VFDs & PLCs.

$13,250,587 5/10/2024 Complete by March 2027

Hollister Street Pump Station Repairs

Clean out surge tanks filled with sediment and perform electrical repairs

$161,000 8/2/2024 Completed

Rehab Grit Facility

(PDB EWP-1A)

Replaced grit classifiers, pumps, blowers, piping/valves, and other components

$7,560,323

3/29/2025

Completed

Replacement of Silva Drain & Replacement of Del Sol Line

Replace collector structure and conveyance line to JB2, install 4 manholes

$1,287,012

4/21/2025

Completed

Rehab Hollister and Goats Pump Station

Replace Surge Arrestor system, Pumps, Odor Control, and electrical systems

$12,041,188 09/2025 Complete by March 2027

Headworks Upgrades Replace critical equipment to maintain operations during expansion including influent pumps, VFDs, and plug & check valves.

$6,844,441 9/25/2026 Complete by March 2027

Total $67,149,482