Attch. 09 SBIWTP Capital Project List as of September 2026.pdf
PDF 96 KB Posted
- Solicitation number
- 191BWC26R0009
About this file
This document is a capital improvements budget summary for urgent repairs at the Santa Barbara Integrated Wastewater Treatment Plant (SBIWTP) designed to restore performance and add process redundancy.
The project encompasses 15 separate repair and rehabilitation actions totaling $67,149,482. Major actions include: Emergency Generator Controls upgrade ($1,092,543, completed 09/2022); Repair Influent Flow Meter ($1,791,532, completed 8/17/2021); Repair Junction Box #1 ($6,991,399, completed 8/10/2023); Rehab PSTs #1-5 ($3,368,414, completed 8/14/2023); USST Valves and Piping Replacement ($4,441,271, completed 9/29/2023); Backup Pumps & Motors for redundancy following Tropical Storm Hilary ($4,190,233, completed 9/29/2023); 4 Backup Influent Pumps ($1,908,000, completed 3/25/2024); Rehab Belt Filter Presses #1-4 ($13,250,587, scheduled complete by March 2027); Rehab Grit Facility ($7,560,323, completed 3/29/2025); Replacement of Silva Drain and Del Sol Line ($1,287,012, completed 4/21/2025); Rehab Hollister and Goats Pump Station ($12,041,188, scheduled complete 09/2025); and Headworks Upgrades ($6,844,441, scheduled complete 9/25/2026). Most actions have been completed, with three projects scheduled for completion by March 2027. Work addresses emergency maintenance needs caused by excess inflows, sediment accumulation, equipment deterioration, and system redundancy requirements.
View the file
Other files
Show all 46
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Urgent repairs at SBIWTP to restore performance and add redundancy in process:
ACTION DESCRIPTION COST
DATE
AWARDED
NOTES
Emergency Generator Controls
Upgrade of the controls of Standby Generators #1 & #2.
$ 1,092,543 09/2022 Completed
Repair Influent flow meter and associated piping and valves
Replace deteriorated Cement-Lined Ductile Iron (CLDI) piping and flow meter
$1,791,532 8/17/2021 Completed
Clean PSTs #1-4 Emergency Maintenance due to excess trash and sediment from excess inflows from MX. Dewater and clean tanks.
$1,782,473 7/28/2023 Completed
Repair Junction Box #1 Design and construction of new Junction Box 1.1.
$6,991,399 8/10/2023 Completed
Rehab PSTs #1-5 Emergency Maintenance due to trash and sediment from excess inflows from MX. Replace all moving mechanical components to include sprockets, bearings, flights, chains, hubs, skimmers, and all required hardware, spacers, and fittings.
$3,368,414 8/14/2023 Completed
USST Valves and Piping Replacement
Rehab USST #1&2 including pumps, piping, valves and installation of new soft starters (Variable Frequency Drives - VFDs).
$4,441,271 9/29/2023 Completed
Backup Pumps & Motors
For redundancy after TS Storm Hilary.
Replace WAS pumps, AST pumps, grinders, NPW pumps & motors.
Hollister Pump Station - install new submersible pumps & VFDs
$4,190,233 9/29/2023 Completed
Clean Grit Chambers Emergency Maintenance due to trash and sediment from excess inflows from MX. Dewater and clean grit chamber.
$439,066 2/16/2024 Completed
4 Backup Influent Pumps
For redundancy after TS Storm Hilary.
Replace failing pumps to keep plant operable.
$1,908,000 3/25/2024 Completed
Rehab Belt Filter Presses #1-4
Rapid deterioration caused by sand in sludge. Rehab presses 1-4, including VFDs & PLCs.
$13,250,587 5/10/2024 Complete by March 2027
Hollister Street Pump Station Repairs
Clean out surge tanks filled with sediment and perform electrical repairs
$161,000 8/2/2024 Completed
Rehab Grit Facility
(PDB EWP-1A)
Replaced grit classifiers, pumps, blowers, piping/valves, and other components
$7,560,323
3/29/2025
Completed
Replacement of Silva Drain & Replacement of Del Sol Line
Replace collector structure and conveyance line to JB2, install 4 manholes
$1,287,012
4/21/2025
Completed
Rehab Hollister and Goats Pump Station
Replace Surge Arrestor system, Pumps, Odor Control, and electrical systems
$12,041,188 09/2025 Complete by March 2027
Headworks Upgrades Replace critical equipment to maintain operations during expansion including influent pumps, VFDs, and plug & check valves.
$6,844,441 9/25/2026 Complete by March 2027
Total $67,149,482
File details come from the government source that posted it. Updated .