191BWC26R0009-0003.pdf

PDF 851 KB Posted

Attached to
Operations and Maintenance (O&M) Services for the SBIWTP
Solicitation number
191BWC26R0009
Issued by

About this file

This is Amendment 0003 to Solicitation 191BWC26R0009, issued by the International Boundary and Water Commission (USIBWC) on September 25, 2026, to procure Operations and Maintenance (O&M) services for the South Bay International Wastewater Treatment Plant (SBIWTP) in San Diego, California. The amendment incorporates Government responses to offeror questions and revises Sections L and M concerning joint venture, prime contractor, and major subcontractor experience and past performance evaluation criteria. Proposals must be submitted exclusively via secure Microsoft SharePoint portal, with access requests due by January 4, 2027 at 12:00 PM MDT and final submission deadline of January 6, 2027 at 2:00 PM MST. The solicitation requires two separate volumes: Volume I (Technical Proposal, maximum 20 double-sided pages excluding cover, table of contents, resumes, and certificates) and Volume II (Firm-Fixed-Price pricing proposal using the Government-provided O&M Services Price Workbook plus Business Proposal appendix including SF 33, acknowledgment of amendments, completed Section K, completed L.03, Section 508 compliance demonstration, and small business subcontracting plan if applicable).

The contract employs a Highest Technically Rated with Fair & Reasonable Price (HTR-FRP) evaluation methodology with no cost-technical tradeoffs. Technical evaluation is weighted as follows: Factor 1—Plant Operations and Permit Compliance (20%), Factor 2—Unique SBIWTP O&M Conditions (20%), Factor 3—Company Experience (15%), Factor 4—Staffing and Key Personnel (15%), Factor 5—SCADA Operations (10%), Factor 6—Plant Coordination (10%), and Factor 7—Past Performance (10%). Offerors must submit a minimum of five relevant past performance questionnaires for comparable U.S. wastewater treatment plants completed within the past five years. For joint ventures, the Government will collectively credit all JV members' experience to meet minimum requirements, with two options: either all members collectively provide five relevant contracts and five PPQs (with projects in the U.S.), or one entity fully meets the five-contract and five-PPQ minimum while the other demonstrates similar relevant experience without geographic restriction. Annual target price ranges are published for base year FY27 ($21,000,679–$23,211,276) through Option 4 FY31 ($22,731,810–$25,124,632), and offerors must explain any costs exceeding the high range. A pre-proposal site visit is mandatory at the USIBWC San Diego Field Office on October 14, 2026 at 9:00 AM PST; offeror names must be submitted by October 7, 2026, and written questions are due by November 19, 2026 at 1:00 PM PST.

View the file

Other files

File Type Posted
Offeror Questions_thru20261119.pdf PDF
Attch. 09 SBIWTP Capital Project List as of September 2026.pdf PDF
Attch. 33 O&M Services Price Workbook (blank template)_updatedNov2026.xlsx XLSX spreadsheet
191BWC26R0009 0004.pdf PDF
Attch. 01 PWS SBIWTP O&M Services 20261125.pdf PDF
Attch. 21 Wage Determination CA2015-5635 Rev32 20260908.pdf PDF
Attch. 32 0131 20260720 PCL Construction Security Plan.pdf PDF
191BWC26R0009 0002.pdf PDF
191BWC26R0009 0001.pdf PDF
Attch. 28 Temporary_Dewatering_Narrative.pdf PDF
Attch. 30.b. FSP ANNEX D MONTHLY SBIWTP (2026).pdf PDF
Attch. 34 SBIWTP O&M Site Visit oct14_26.pdf PDF
Attch. 30.a. FSP ANNEX A SBIWTP (2026).pdf PDF
Attch. 33 O&M Services Price Workbook (blank template).xls XLS spreadsheet
Attch. 29 Screw Press Map and Drawings.pdf PDF
FY27 SBIWTP OM PWS REV 1 10.19.26.pdf PDF
Attch. 27 SD.I.10031-M-2 Background Investigation Procedures for SBIWTP Contractor Personnel.pdf PDF
Attch. 30.c. FSP ANNEX D ANNUAL SBIWTP(2026).pdf PDF
Attch. 16 Plans Drawings Request Instructions.docx DOCX document
Attch. 01A SOM SUBMITTAL REGISTER SBIWTP O&M 2026.xlsx XLSX spreadsheet
Attch. 25 Client Authorization Letter.docx DOCX document
191BWC26R0009 OM SBIWTP Services.pdf PDF
Attch. 18 NIST.FIPS.199.pdf PDF
Attch. 11 Canyon Collector Daily Inspection template- MAR 2025.xlsx XLSX spreadsheet
Attch. 23 LAB SAMPLING QTY.xlsx XLSX spreadsheet
Attch. 04.a. GiantKelpVariance_09.11.26.pdf PDF
Attch. 21 Wage Determinations CA20240001 07.26.2024.pdf PDF
Attch. 04 Order No. R9-2021-0001 as amended R9-2026-0005.pdf PDF
Attch. 22 MX- Norma004_Semarnat_2002_english version.pdf PDF
Attch. 05 List-of-Permits.pdf PDF
Attch. 24 OEP-SBIWTP(2026).pdf PDF
Attch. 06 IBWC SBIWTP Asset Registry 2024.xlsx XLSX spreadsheet
Attch. 05 List-of-Permits.docx DOCX document
Attah. 01 PWS SBIWTP O&M Services.pdf PDF
Attch. 12 2025 NPDES ANNUAL BIOSOLIDS REPORT.pdf PDF
Attch. 02 FY26 SBIWTP O&M QASP.docx DOCX document
Attch. 15 NIST.SP.800-171r3.pdf PDF
Attch. 07 FY26 IBWC Condition Assessment Report.pdf PDF
Attch. 26 Past Performance Questionnaire.pdf PDF
Attch. 10 Monthly Chemical Dosage 2025 to 2026.pdf PDF
Attch. 02 FY26 SBIWTP O&M QASP.pdf PDF
Attch. 09 SBIWTP Capital Project List as of September 2025.pdf PDF
Attch. 20 SOUTH BAY SPILL PREVENTION AND RESPONSE PLAN October 2024.pdf PDF
Attch. 17 SBIWTP Map.pdf PDF
Attch. 19 SOO_V2_06192018.pdf PDF
Attch. 08 IBWC SBIWTP - Asset Maintenance Schedule.xlsx XLSX spreadsheet
Show all 46

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Document Number: 191BWC26R0009 PROCESSED Page 1 of 32

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE RATING

2. AMENDMENT/MODIFICATION NUMBER

3. EFFECTIVE DATE

09/25/2026

4. REQUISITION/PURCHASE REQ. NUMBER

FY27R3321007

5. PROJECT NUMBER (If applicable)

IBWC_CODE

International Boundary and Water Commission (IBWC)

USIBWC - ACQUISITIONS DIV

4191 NORTH MESA ST

EL PASO, TX 79902-1441

US

Philip Johnson

NAME

TEL.

johnsonpk@state.gov

EMAIL

6. ISSUED BY CODE7. ADMINISTERED BY (If other than Item 6)

9A. AMENDMENT OF SOLICITATION NUMBER

191BWC26R0009

CODE FACILITY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, country, state and ZIP Code) (X)

X 9B. DATED (SEE ITEM 11)

09/25/2026

10A. MODIFICATION OF CONTRACT/ORDER

NUMBER

10B. DATED (SEE ITEM 11)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X XThe above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended, is not extended, Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing items 8 and 15, and returning __1__copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

ORDER NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return _______ copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

This amendment is issued to: (1) provide the Government’s responses to offeror questions; (2) revise the proposal instructions in Section L concerning joint venture, prime contractor, and major subcontractor experience and past performance; (3) revise the corresponding evaluation criteria in Section M; and (4) ensure that proposals are evaluated solely in accordance with the factors and significant subfactors stated in the solicitation.

The attached Questions and Answers are incorporated into the solicitation. If a response conflicts with the solicitation, the solicitation as amended controls.

Section L and Section M are revised as stated below. Additions and replacement text in this amendment supersede inconsistent language in prior versions of the solicitation.

Except as expressly amended herein, all other terms and conditions remain unchanged.

Offerors shall acknowledge receipt of this and all other amendment in accordance with the solicitation instructions and FAR 52.215-1, Instructions to Offerors - Competitive Acquisition.

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

Philip Johnson

(Signature of person authorized to sign)

15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED

By (Signature of Contracting Officer)

16B. UNITED STATES OF AMERICA 16C. DATE SIGNED

11/18/2026

NSN 7540-01-152-8070

Previous edition unusable

STANDARD FORM 30 (REV.

11/2016) Prescribed by GSA FAR (48 CFR) 53.243

CGFS // CGFS

L.01 - Pre-Proposal Conference

(a) All potential Offerors are invited to attend a Pre-Proposal site visit to be held at the USIBWC San Diego Field Office, 2995 Clearwater Way, San Diego, CA 92154 at 09:00 AM PST (10:00 AM MST) on Wednesday, October 14th, 2026. The group will walk through the plant site.

Virtual site visits (video/live streaming) are not permitted. Visitors shall not take photographs or record videos of any infrastructure that is used for monitoring the border, such as security cameras or radio towers belonging to U.S. Customs and Border Protection or USIBWC.

(b) Names of individuals who plan to attend must be furnished on or before 09:00 AM PST (10:00 AM MDT), on October 7th, 2026, by email to the CO, Philip Johnson at Philip.Johnson@ibwc.gov.

(c) Due to time, distance, and cost associated with the Pre-Proposal site visit, prospective Offerors who fail to attend on the scheduled date will not be given a further opportunity to reschedule another site visit.

(d) The purpose of the site visit is to provide prospective Offerors, subcontractors and suppliers an opportunity to observe and evaluate project conditions; to present questions arising during preparation of offers; to discuss procedures and other matters anticipated to arise during operation and maintenance of the SBIWTP.

(e) Offerors are urged to submit questions in writing, before or after the site visit, to the email listed above, referencing the solicitation number 191BW26R0009. Answers will be prepared through the Request for Information log on sam.gov’s Solicitation Announcement. Questions shall be submitted to arrive at the aforementioned not later than 10:00 AM PDT (11:00 AM MDT) October 7th, 2026.

(f) While every effort will be made to provide meaningful responses or clarifications to all inquiries, no answer shall be binding by the Government and subsequently answered by means of a formal amendment to this solicitation.

L.02 - Questions

Written questions may be submitted to the CO, by email at Philip.Johnson@ibwc.gov until 1:00 PM PST (2:00 PM MST) on November 19th, 2026. Questions received after the cut-off deadline will NOT be responded to, unless deemed significant by the Contracting Officer or the question conveys a material mistake and/or error in the Solicitation.

L.03 - Contractor's Contract Administrator

Offeror is requested to delegate a person to be contacted for prompt contract administration.

Name: ___________________________________________

Address: ___________________________________________

Telephone: __________________ Mobile: _________________

Fax: __________________

E-mail: ___________________________________________

L.04 - Proposal Composition Requirements and Instructions

L.04.A. In order to assess the Offeror's Qualifications, the Offeror shall submit a proposal in accordance with the instructions contained in this provision. The Offeror is advised to carefully read the entire Solicitation.

To safeguard sensitive procurement data, the U.S. Section of the International Boundary and Water Commission (USIBWC) utilizes its secure FEDRAMP Microsoft SharePoint environment for the submission of bids and proposals. SharePoint is a cloud-based platform that integrates with Microsoft 365 and leverages enterprise-level security protocols, including data encryption at rest and in transit, multi-factor authentication (MFA), and role-based access controls. When folders are shared with external users for bid submission, access is limited to specific, authenticated email addresses. External users must verify their identity through a secure email link and authentication code prior to gaining access, ensuring that only authorized parties can view or upload content. Permissions can be tailored (view or edit), and access can be revoked or expire automatically. All activities on the platform are logged and monitored, providing traceability and accountability. These measures collectively ensure that procurement documents are handled with confidentiality, integrity, and compliance with federal IT security standards.

L.04.B (a). Due to the schedule and security requirements associated with this solicitation, all proposals must be submitted exclusively via the USIBWC's secure Microsoft SharePoint portal.

This replaces prior instructions for submitting hard copy or physical media (DVD/CD) proposals.

Instructions for Access

1. Email Access Request:

Vendors must submit an email request to the Contracting Officer to gain access to their designated SharePoint upload folder.

Send request to: Philip.johnson@ibwc.gov Subject line: “Request for SharePoint Access – Solicitation 191BWC26R0009”

Include the following in your request:

• Company name

• Name of the authorized representative

• Email address (this must be the individual uploading the proposal)

• Contact phone number

2. Access Request Deadline:

All access requests must be submitted no later than 1/4/2027 at 12:00 PM MDT.

SharePoint Access Period: Vendors will be granted access to upload proposals starting October 8th, 2026.

Proposal Submission Deadline: All proposals must be uploaded by Monday, January 6th, 2027, at 2:00 PM MST. Late uploads will not be accepted, and expired links will not be reactivated.

3. Submission Restrictions:

• Only two access requests per vendor will be honored.

• The SharePoint link is non-transferable and must not be forwarded or shared.

• Access credentials must not be used by unauthorized personnel.

• Violations may be reported as breaches of FAR Subpart 3.1 and FAR 3.104 (Procurement Integrity Act).

4. Prohibited Submission Methods:

• Email, fax, mailed, or hand-delivered proposals will not be accepted under any circumstances.

L.04.B (b). Each file must be titled in the following format:

[OfferorName]_Vol_[I/II]_[ProposalType].pdf Example:ABCConstruction_Vol_II_TechnicalProposal.pdf

L.04.B (c). Technical Proposal (Volume I). Refer to the requirements contained in the Technical Proposal Instructions provision of this Solicitation.

L.04.B (d). Pricing and Business Proposal (Volume II). Refer to the requirements contained in the Pricing Proposal Instruction provision of this Solicitation.

L.04.C (a). Instructions concerning the content and organization of the proposal.

Each Offeror shall propose to satisfy the requirement as set forth in this solicitation. The proposals will be evaluated on the basis of content (what is written in the documents). No extraneous information will be used for evaluation purposes with the exception of past performance.

The Government will evaluate past performance using information obtained from the Contractor Performance Assessment Reporting System (CPARS), the Federal Awardee Performance and Integrity Information System (FAPIIS), and other sources of past performance information available to the Government (including SPRS when applicable). The Government reserves the right to use data from these systems as well as any other available past performance information when evaluating the offeror’s performance history.

L.04.C (b). Each Offeror is responsible for including sufficient details to permit a complete and accurate evaluation of the proposal from both a technical and management standpoint. Each Offeror shall identify technical uncertainties and assumptions within the requirement set forth in this solicitation and provide specific proposals for their resolution. The Government will not make assumptions concerning the Offeror's intent, capabilities, facilities and experiences. Clear identification is the sole responsibility of each Offeror. The Offeror shall be prepared to provide all services as described in their proposal. In the case of a conflict between the Offeror’s proposal and the Performance Work Statement (PWS), the PWS takes precedence.

L.04.C (c). Proposals shall be as brief as possible but sufficiently detailed to completely and adequately describe what is proposed.

L.04.C (d). Offerors shall comply with all requirements of the proposal submission instructions.

Deviations shall be fully explained; however, inclusion of cost/price information with the technical/management volume of the proposal is not considered an acceptable deviation.

Each Offeror is cautioned that "parroting" of the requirements with a statement of intent to perform does not reveal the Offeror’s understanding of the problem or his capability to solve it.

The inclusion of filler material from previous proposals or commercial applications shall be avoided unless there is a direct application to the objective of this solicitation.

L.04.C (e). Unless the Offeror inserts a longer period of time on the Standard Form (SF) 33, page 1, block 12, proposals will remain valid for a period of 120 calendar days from the date specified for receipt of proposals in Block 9.

L.05 - Proposal Volumes and Submission

L.05.A Volume I — Technical (No Price)

Offerors shall submit Volume I — Technical as a standalone, price‑free technical proposal.

Organize the Technical Volume exactly in the sequential order of the Section M evaluation factors and subfactors. Each section shall directly address the corresponding merit factor and include both quantitative and qualitative detail sufficient for a complete technical evaluation.

L.05.A (a). The Technical Volume shall incorporate the following required elements:

Factor 1 — Plant Operations and Permit Compliance

Factor 2 — Unique SBIWTP O&M Conditions

Factor 3 — Company Experience

Factor 4 — Staffing and Key Personnel

Factor 5 — Supervisory Control and Data Acquisition (SCADA) Operations

Factor 6 — Plant Coordination

Factor 7 — Past Performance

L.05.A (b). Section M provides the detailed requirements for evaluation factors and Section M criteria govern the evaluation. Offerors are reminded that The Technical Volume must clearly demonstrate how the proposal satisfies each factor without referencing cost or price.

L.05.A (c). Submittal Compliance and Instruction for Volume I

(1) Formatting. Proposals shall be legible, clear, and easy to read. To assist in the uniform evaluation of proposals, the following format shall be utilized in preparing the technical proposal:

(1).a. Table of Contents. The Table of Contents shall list all sections of the Technical Proposal including a list of any tables, drawings, charts, and all other enclosures which summarize data or information.

(1).b. The Technical Proposal shall not exceed 20 double-sided 8.5 inch x 11 inch pages in length (40 single-sided), excluding cover page, table of contents, indices, resumes, certificates, client authorization letters, and divider pages.

(1)c. Proposals shall be uncomplicated, legible, with text no smaller than 10 point font (this does not include graphics, captions, tables, and charts) printed in black on white, uncolored background. Offerors shall use their best judgment in selecting the appropriate font size and color for graphics, caption, tables, and charts to ensure that they are legible.

(1)d. Pages shall be consistently formatted with the same font type and size, number of columns, paragraph settings, etc.

(1)e. Page Numbering. All pages in the proposal that count towards the maximum number of pages (A.(c)(1)b.) shall be consecutively numbered (including pages with tables and exhibits).

The Offeror shall clearly identify/label all exhibits and supporting information.

(1)f. Proposal shall be organized by factor and subfactor providing the material in each section that directly pertains to the required information.

(1)g. All information shall be submitted in electronic format (pdf). Pdfs shall be high quality scan or shall be a document produced directly to pdf.

(2) Instructions. Proposals shall be provided per the instructions included within this Solicitation.

(2)a. IMPORTANT! Offerors shall adhere to the required page limitations. If the Offeror exceeds the maximum allowable pages, any information provided beyond the page limit will not be reviewed for evaluation. This may result in the Offeror receiving an unacceptable rating for factors and subfactors provided on pages beyond the page limit.

(2)b. Offerors shall only submit material that is directly pertinent to the requirements of this Solicitation.

(2)c. Information shall be consistent and logically presented. Only duplicate information if absolutely required.

(2)d. Illustrations shall be used wherever practical to depict organizations, systems and layout, implementation schedules, plans, etc.

(2)e. Extraneous narrative, elaborate brochures, uninformative promotional material, unnecessary resumes, and so forth, shall not be submitted.

(2)f. Information submitted beyond that noted herein will be counted as part of the maximum allowable pages.

L.05.A (d). Electronic Submission

Submit proposals electronically in accordance with the secure upload instructions provided in the solicitation. Volume I (Technical) and Volume II (Price) shall be uploaded as separate files.

L.05.B. Volume II: Price & Business Proposal (HTR‑FRP)

L.05.B (a). Volume II — Price (Firm‑Fixed‑Price)

Offerors shall submit Firm‑Fixed‑Price (FFP) for all required Contract Line Item Numbers (CLIN) and performance periods. The price shall also be submitted using the Government-provided “O&M Services Price Workbook” format. Populate all Government‑provided price worksheets and mapped cost‑element tables exactly as instructed. Any deviation from the required structure or instructions may render the price proposal nonresponsive. Propose the necessary labor, materials, equipment, and services to meet the PWS objectives. Include pricing assumptions for each task in the PWS.

The following minimum items shall be included for the Price Proposal and narrative in Volume

II:

(1) Detailed breakdown for each applicable CLIN, including: Labor; Fringe Benefits; Travel;

Vehicle Expense; Office Supplies/Equipment; Delivery/Postage; Professional Fees;

Dues/Subscriptions; Business Insurance; Telephone Expense; Subcontractors; Laboratory/Safety Supplies; Chemical Costs; Scrap/Sludge; Repair & Maintenance; Utilities; Taxes;

Depreciation/Amortization; Other Expenses; Indirect Rates (Overhead and G&A); Profit; and Escalation for option years.

(2) Provide a separate breakdown of labor by category and by contract period, including basis of estimates for technical, management, administrative, QA, and other personnel. Labor costs must be realistic, reasonable, and consistent with industry conditions and the proposed work.

(3) Provide a separate breakdown of direct material indicating quantity and unit price.

(4) Provide rationale for indirect rate structures (e.g., overhead, G&A).

(5) Show phase‑in costs separately and align with the Offeror’s phase‑in plan.

(6) Provide narratives for each cost category describing the estimation method and basis. Include a narrative of all assumptions and explanations with the pricing.

(7) For chemical costs, provide breakdown by chemicals consistent with PWS requirements.

Provide a copy of quote or invoice from supplier for the cost of each chemical.

(8) Provide the “O&M Services Price Workbook” in native excel format and a pdf of the entire workbook shall be provided within the price proposal.

(9) The CLIN structure is provided in Section B, Supplies or Services and Price/Costs. Offerors shall submit the unit price and total price for each CLIN and the total proposed price consisting of all CLINs.

(10) Rounding of Costs. All price or cost amounts proposed for the CLINs shall be expressed to the nearest whole dollar.

(11) Offerors are hereby notified that the Contracting Officer reserves the right to request additional data necessary to support proposed prices.

L.05.B (b). Volume II — Business Proposal

The following items shall be included for the Business Proposal under an Appendix of the Volume II:

(1) SF 33. Provide a completed SF 33 as part of the Price and Business Proposal.

(2) Amendments. Acknowledge ALL amendments issued against the solicitation in the Price and Business Proposal.

(3) Section K. Provide a completed Section K for ALL provisions. Note: If FAR 52.204‑7 is included, paragraph (d) of FAR 52.204‑8 applies. Check the appropriate box for FAR 52.209‑7.

(4) Section L. Provide a completed L.03.

(5) Section 508 Compliance. Demonstrate how the solution meets applicable Section 508 standards identified in the accessibility determination template (Attachment 15) or provide equivalent information. This deliverable is required and will be evaluated prior to award.

(6) Small Business Subcontracting Plan: If an Offeror is classified as "Other than Small" the Offeror shall submit a Small Business Subcontracting Plan consistent with Contract Clause 52.219-9 Alt II. Consistent with Alt II the plan shall be negotiated within thirty (30) calendar days of the CO's notice of intent to negotiate the Subcontracting Plan. Failure to submit and negotiate a Subcontracting Plan shall make the Offeror ineligible for award of a contract. NOTE:

The Subcontracting Plan will be made available to the Small Business Administration (SBA) and will be subject to their review and approval.

(7) Disclosure of Conflict(s) of Interest and action(s) taken to mitigate conflict. See L.08.

L.05.B (c). Electronic Submission

Submit proposals via the secure upload portal identified in the solicitation. Volume II (Price) following all file‑naming conventions and encryption/password requirements.

L.06 - Price Responsiveness and Evaluation Sequence

L.06.A. Price Responsiveness.

Price proposals must be complete and compliant with all pricing instructions (worksheets, CLIN structure, narratives, assumptions). Failure to submit a compliant price proposal may render the Offeror ineligible for award.

L.06.B. Highest Technically Rated — Fair & Reasonable Price (HTR‑FRP) Evaluation Sequence.

(1) Evaluate and rank all Technical proposals from highest to lowest based solely on the disclosed non‑price factors and subfactors.

(2) Evaluate the price of the Highest Technically Rated (HTR) Offeror first for a fair and reasonable determination in accordance with FAR 15.404‑1.

(3) If the HTR’s price is unavailable, withdrawn, non‑responsive, non‑compliant, not fair and reasonable, unaffordable, or otherwise unawardable, proceed to the next HTR Offeror and repeat the analysis until award is made to the highest technically rated, responsible Offeror whose price is fair and reasonable.

(4) No cost‑technical tradeoffs will be performed. Price will not be used as a comparative discriminator among Offerors; it will be assessed only for fairness and reasonableness (and affordability, if disclosed).

L.06.C. Exchanges with Offerors (Clarifications, Communications, Discussions).

The Government may establish a competitive range of one and conduct targeted, time‑boxed clarifications or discussions with the HTR Offeror limited to price compliance, reasonableness, and affordability alignment. Exchanges will be conducted in accordance with FAR 15.306. If the proposal remains unawardable after discussions, the Government will proceed per L.06(b)(3).

L.06.D. No Cost‑Technical Tradeoffs.

When combined, non‑price factors are significantly more important than price. The Government will not make comparative tradeoffs between price and non‑price factors under this solicitation.

L.06.E. Price Realism (Informational Only).

The Government may review internal consistency of the proposed price to gain insight into performance risk; no adjustments will be made to Firm‑Fixed‑Price values.

L.06.F. Procurement Integrity & Organizational Conflicts of Interest (OCI).

Offerors shall submit all required representations and any OCI mitigation plans. Inadequate mitigation may render an Offeror ineligible for award.

L.07 - Affordability — Published Planning Target Bands

L.07.A. The Government publishes the following planning‑only Target Price Ranges. These ranges do not constitute a cap; offers outside the ranges remain eligible. Offerors shall explain why their cost exceeds the high range, if applicable. Price will be evaluated for fairness and reasonableness after technical ranking; affordability is assessed against appropriated funding.

Annual Target Ranges

Period Target Range Low ($) Target Range High ($)

Base FY27 21,000,679.06 23,211,276.86 Option 1 FY28 21,420,692.63 23,675,502.39 Option 2 FY29 21,849,106.48 24,149,012.42 Option 3 FY30 22,286,088.64 24,631,992.70 Option 4 FY31 22,731,810.43 25,124,632.59

L.08 - Conflict of Interest

L.08.A. The Offeror’s attention is directed to 23 CFR 636 Subpart A and in particular to §636.116 regarding organizational conflicts of interests. Section 636.103 defines “organizational conflict of interest” as follows:

L.08.A. (a). “Organizational conflict of interest means that because of other activities or relationships with other persons, a person is unable or potentially unable to render impartial assistance or advice to the owner, or the person’s objectivity in performing the Contract work is or might be otherwise impaired, or a person has an unfair competitive advantage.”

L.08.B. Offeror shall provide information concerning potential organizational conflicts of interest and disclose all relevant facts concerning any past, present, or currently planned interests which may present an organizational conflict of interest. Offeror shall state how its interests or those of its chief executives, directors, key individuals for this project, or any proposed consultant, contractor or subcontractor may result, or could be viewed as, an organizational conflict of interest.

L.08.C. The Offeror is prohibited from receiving any advice or discussing any aspect relating to the contract or the procurement of the project with any person or entity with an organizational conflict of interest. Such persons and entities are prohibited from participating in a Offeror’s organization relating to the contract.

L.08.D. The Offeror agrees that, if an organizational conflict of interest is discovered, the Offeror must make an immediate and full disclosure to USIBWC that includes a description of the action that the Offeror has taken or proposes to take to avoid or mitigate such conflict. If after award of the Contract an organizational conflict of interest is determined to exist, USIBWC may, at its discretion, cancel the Contract for the project. If the Offeror was aware of an organizational conflict of interest prior to the award of the Contract and did not disclose the conflict to USIBWC, then USIBWC may terminate the Contract for default.

L.08.E. If applicable, this information shall be included in the Business Proposal section of Volume II.

Appendix — Section M: Method of Award (HTR‑FRP)

Method of Award: The Government intends to award a single contract to the highest technically rated, responsible Offeror whose price is determined fair and reasonable under FAR 15.404‑1.

No cost‑technical tradeoffs will be made. Price will not be used as a comparative discriminator among Offerors. If the apparent HTR Offeror’s price is not fair and reasonable or otherwise unawardable, the Government will evaluate the price of the next highest technically rated Offeror and repeat this process until award is made.

Technical Tie‑Breakers: If multiple proposals receive the same top adjectival rating, the Government will resolve ties using documented factor‑level discriminators, considering (i) Density and significance of strengths, (ii) Evaluated performance risk, (iii) Past performance confidence, and (iv) Soundness of key personnel and staffing approach. Only if proposals are indistinguishable on non‑price factors will the Government apply the lower fair‑and‑reasonable price as a secondary tie‑break without conducting a tradeoff. Price will not be used in as a tie breaker.

M.01 - Method of Award — Highest Technically Rated with a Fair & Reasonable Price

(HTR-FRP)

M.01.A. Basis. The Government will make award to the Offeror whose proposal is determined to be the Highest Technically Rated (HTR), provided that the Offeror’s proposed price is determined fair and reasonable under FAR 15.404-1 and awardable. No cost-technical tradeoffs will be made.

M.01.B. Relative Importance. Non-price factors, when combined, are significantly more important than price. Price will not be scored; it will be evaluated solely for fair and reasonable determination.

Non-price (technical) factors have the following weighting:

Factor 1 — Plant Operations and Permit Compliance: 20% Factor 2 — Unique SBIWTP O&M Conditions: 20% Factor 3 — Company Experience: 15% Factor 4 — Staffing and Key Personnel: 15% Factor 5 — Supervisory Control and Data Acquisition (SCADA) Operations: 10% Factor 6 — Plant Coordination: 10% Factor 7 — Past Performance: 10%

M.01.C. Technical Evaluation & Ranking. The Government will evaluate proposals against the disclosed non-price factors and subfactors and assign adjectival ratings with narrative discriminators. For purposes of applying the factor weighting listed above, adjectival ratings will be assigned a value (based on their description) and multiplied by the weight listed above and summed up to determine the total numerical rating score of each offer. Proposals will be ranked from highest to lowest based on their total score. Offers that receive higher factor ratings will receive higher scores, therefore, the proposals are ranked based on technical merit.

Factor 1 — Plant Operations and Permit Compliance Provide a detailed plan for operation and maintenance of SBIWTP to comply with the permit requirements and keep the plant treatment and equipment in good working condition. Include:

(1) Proposed operations for the 35MGD advanced primary treatment and the 25MGD secondary treatment, including the temporary equipment in place for solids processing of the temporary 10MGD capacity increase.

(2) Proposed maintenance plan to ensure continuity of 24/7 plant operation. Provide preventive maintenance (PM) tracking, asset management, spare parts strategy and work-order processes.

(3) Proposed Asset Management, Computerized Maintenance Management System (CMMS), and data management systems to be used. Describe proposed plant monitoring for process control/optimization/reporting; evidence of successful process efficiency; and regulatory compliance with all permits.

(4) Provide the proposed wastewater treatment plant safety plan. The program will be evaluated for completeness, validity, and conformance to OSHA/Cal/OSHA standards. Includes all required baseline elements (e.g., safety training, roles/responsibilities, inspections, accident investigation/reporting, emergency response, PPE, respiratory protection, hazard communication, electrical safety, lockout/tagout, permit-required confined space, hot work, machine guarding, fall protection, job hazard analysis, material handling, compressed gas/air, powered industrial trucks, medical/first aid, bloodborne pathogens, hazardous material storage/disposal, laboratory chemical exposure controls, and site visitor safety).

(a) Subfactor 1: Submission Completeness (Go/No Go + Adjectival) The Government will verify that a complete plan was provided addressing operation, maintenance, and permit compliance. Missing significant required elements for evaluation will result in a No Go for this factor resulting in an overall unacceptable rating. Missing minor items required will result in a weakness or deficiency.

(b) Subfactor 2: Risk Mitigation (Adjectival) The Government will assess how the proposed plans address the plant operation and compliance.

(c) Subfactor 3: Contract Records and Reporting (Adjectival) The Government will evaluate procedures for maintaining accurate records, immediate reporting of serious issues to the COR, and compliance with submission of records consistent with PWS expectations.

(d) Subfactor 4: Permit Compliance, Monitoring & Reporting (Adjectival) The Government will assess how the plan sustains NPDES CA0108928 requirements: composite sampling points (influent, primary effluent, secondary effluent, final effluent), QA/QC, timely submittals, and a Regulatory Support Log that documents inspections, sampling, spill events, and agency coordination.

(e) Subfactor 5: Schedule Adherence and Continuity of Operations (Adjectival) The Government will assess if the plan demonstrates timeliness of services, prompt restoration of service levels, and continuity of 24/7 operations.

(f) Subfactor 6: Asset Management and CMMS Discipline (Adjectival) The Government will assess maintenance execution and data discipline, including preventative maintenance, spares strategy, and anticipated work-order quality.

(g) Subfactor 7: Emergency Response (Adjectival). The Government will evaluate emergency response plans (e.g., fire, earthquake) and alignment with SBIWTP spill and transboundary flow event prevention/response requirements and operational restoration expectations.

(h) Subfactor 8: Data Integrity and Reporting Timeliness (Adjectival). The Government will assess accuracy, completeness, and timeliness of providing operational data, sampling and regulatory reporting, and QA/QC procedures.

(i) Subfactor 9: OSHA/Cal-OSHA Conformance & Program Validity (Adjectival). The Government will assess completeness and validity of the safety program and its conformance to Cal-OSHA General Industry/Construction Safety Orders and federal OSHA 29 CFR Parts 1910/1926, as required for SBIWTP operations.

(j) Subfactor 10: Confined Space, Lockout/Tagout (LOTO) & Hot Work Programs (Adjectival). The Government will evaluate the adequacy of written procedures and training for permit-required confined spaces, lockout/tagout of hazardous energy, and hot work permitting, consistent with Wastewater Treatment Plant (WWTP) hazards and Cal-OSHA/OSHA requirements.

(k) Subfactor 11: PPE, Respiratory Protection & Exposure Controls (Adjectival). The Government will assess the Offeror’s PPE program (selection/fit/inspection), respiratory protection (including medical clearance and fit testing where applicable), and controls for laboratory and process chemical exposure, aligned to the PWS baseline.

(l) Subfactor 12: Safety Inspections, Records, Audits, & Rapid Correction Protocols (Adjectival). The Government will assess planned safety inspections/audits, documentation quality, corrective-action tracking, and adherence to required correction windows (e.g., ≤7 days after notification), including clear stop-work authority and restart criteria.

Factor 2 — Unique SBIWTP O&M Conditions Provide a detailed plan to address SBIWTP’s unique operational scenarios: heavy sediment at influent; excessive flow due to upstream shutdowns; sludge/solids contingency when hauling is unavailable; zero-flow periods; and heavy sediment/debris accumulation in canyon collectors post-storm, including timely restoration. Address operational adjustments, additional maintenance/coordination, prevention/response to transboundary flows, permit compliance, and staffing adequacy. The Government will focus on recovery speed, operational stability, and prevention measures.

(a) Subfactor 1: Plan Completeness (Go/No Go + Adjectival) The Government will verify the plan addresses all five scenarios: heavy sediment at influent; excessive flow from upstream shutdowns; sludge/solids hauling contingency; zero-flow periods; canyon collectors post-storm restoration. Omission of any scenario is a No Go. Missing significant required elements for evaluation will result in a No Go for this factor resulting in an overall unacceptable rating.

Missing minor items required will result in a weakness or deficiency.

(b) Subfactor 2: Heavy Sediment & Debris Management at Influent (Adjectival) The Government will evaluate how the Offeror will prevent coarse screen blinding, protect grit systems and PSTs, and keep solids out of secondary. Strengths apply for approaches that integrate CEPT optimization with measurable targets (e.g., ≥75% TSS removal in PSTs when CEPT is active), proactive cleaning cycles, spare parts, and debris logistics.

(c) Subfactor 3: Excessive Flow Contingency for Upstream Shutdowns (Adjectival) The Government will assess hydraulic tactics that maintain process stability when Mexico’s infrastructure causes flow spikes: headworks load management, clarifier flow splitting, temporary equalization strategies, prioritized maintenance sequencing in non-redundant areas, and pre-approved tie-in/shutdown playbooks.

(d) Subfactor 4: Sludge/Solids Hauling Unavailable — Storage & Dewatering Contingency (Adjectival) The Government will evaluate the onsite storage, thickening, and dewatering plan (capacity, equipment, crew), vendor mobilization timelines, and alternate disposal routes consistent with permit and binational constraints. Strength for planned use or readiness of temporary units (e.g., RDT packages, rental screw press) and safe staging that prevents process failure.

(e) Subfactor 5: Zero-Flow Biological Protection Plan (Adjectival) The Government will assess how the Offeror will protect the activated sludge biomass during extended zero-influent periods: recirculation schemes, controlled wasting, seed preservation, and SOPs to avoid nitrification collapse or filament outbreaks when loads resume.

(f) Subfactor 6: Canyon Collectors Post-Storm Restoration SLA Compliance (Go/No Go + Adjectival): Go/No Go Application: The Government will verify the plan meets the daily inspections requirement and restores each collector within the specified post-storm window (e.g., ≤96 hours), including conveyance clearance.

Adjectival Application: The Government will evaluate debris removal logistics, staffed heavy-equipment operations, and off-site disposal within 7 calendar days per environmental rules.

(g) Subfactor 7: Transboundary Flow Prevention & Response Integration (Adjectival) The Government will assess alignment to the Spill & Transboundary Flow Event Prevention and Response Plan and readiness to execute inspections, documentation, notifications, and coordination. Apply strengths for clear triggers, checklists, and regulatory communication flows.

(h) Subfactor 8: Binational Coordination & Bilingual Coverage (Adjectival):

The Government will evaluate real-time protocols with Mexico’s Pumping Station No. 1 for flow management, storm response, and canyon system restoration.

(i) Subfactor 9: Permit Compliance, Monitoring & Reporting (Adjectival) The Government will assess how the plan sustains NPDES CA0108928 requirements: composite sampling points (event based), reporting, QA/QC, timely submittals, and a Regulatory Support Log that documents inspections, sampling, spill events, and agency coordination.

(j) Subfactor 10: Surge Staffing & Equipment Readiness (Adjectival) The Government will evaluate surge rosters, cross-training, vendor MOUs, temporary equipment mobilization (screens, pumps, thickening/dewatering skids), and spare part strategies sized to South Bay’s storm/sediment profile and the added 10 MGD operational condition.

(k) Subfactor 11: Risk Triggers, Metrics & Restoration Timelines (Adjectival) The Government will assess the plan’s leading indicators and thresholds (e.g., headworks differential pressure rises; PST solids loading; canyon debris depth) and time-bound actions: post-storm ≤96-hour restoration, ≤7-day debris disposal, and CEPT performance targets tied to sampling trends.

(l) Subfactor 12: O&A (Over-and-Above) Integration for Unusual Volumes (Adjectival) The Government will apply strengths for clear procedures to document extraordinary sediment loads (e.g., ≥2× projected sediment within 1–2 weeks, persistent), submit scope/price for Government approval, and maintain operations while O&A actions proceed.

Factor 3 — Company Experience Provide corporate structure and relevant company experience (within last five years) operating secondary activated sludge plants with aeration tanks; relate previous contracts to the requirement; describe education/experience/capabilities of support team; lines of authority;

management commitment. Provide evidence of experience in process instrumentation/control;

capability to implement Computerized Maintenance Management System (CMMS) and data management systems; plant monitoring for process control/optimization/reporting; evidence of successful process efficiency; and regulatory compliance knowledge with EPA/State audit reports and responses.

Submit a minimum of five relevant contracts, two pages per contract. Include contract number/type/value and point of contact. Furnish complete and detailed information regarding service contracts which show your company's experience for services on wastewater treatment plants of similar size, complexity, and scope to the requirements of this Solicitation.

Provide the company’s safety record, number of accidents within the last three years and corrective measures.

Provide current insurance coverages (e.g., general liability, pollution liability, workers’ compensation) and bonding capacity by reference letters from sureties. Disclose failures to complete work; litigation where named as a defendant (O&M context); enforcement actions related to labor, health/safety, loss of life/welfare; and actions related to effluent discharge requirements.

(a) Subfactor 1: Submission Completeness (Go/No Go + Adjectival). The Government will verify inclusion of (i) an organizational chart covering engineering, O&M, administrative, and scientific functions; (ii) defined lines of authority, responsibility, and communication; (iii) a management commitment statement; (iv) a summary of support team education/experience/capabilities; (v) a minimum of five relevant contracts; (vi) three-year accident/incident summary and documented corrective actions; (vii) insurance and bonding capacity references; and (viii) disclosures of any failures to complete awarded work with responsible contacts/phone numbers, disclosure of cases (style, court, docket) in which the Offeror is a defendant related to O&M services, disclosure of labor or health/safety fines or enforcement actions, and disclosure of fines or enforcement actions tied to effluent discharge requirements. Omission of any required element results in a No Go for this subfactor. Missing significant required elements for evaluation will result in a No Go for this factor resulting in an overall unacceptable rating. Missing minor items required will result in a weakness or deficiency.

(b) Subfactor 2: Relevance & Comparability of Experience (Adjectival). The Government will assess the Offeror’s last five (5) years of operating secondary activated sludge plants with aeration tanks for similarity in size/complexity, clarity of roles performed, and explicit linkage of prior work to the SBIWTP requirements. Higher ratings are supported by greater size/complexity, clear process comparability, and persuasive relevance mapping.

(c) Subfactor 3: Process Instrumentation & Control Proficiency (Adjectival). The Government will evaluate demonstrated experience implementing and maintaining I&C necessary for secondary treatment, including DO control, blower/valve logic, analyzer programs, alarm management, and loop tuning practices integrated with plant SCADA. Strength is credited for mature, repeatable methods and outcomes at comparable plants.

(d) Subfactor 4: CMMS/EAM & Data Management Capability (Adjectival). The Government will assess capability to implement and operate a CMMS/EAM for work orders, asset histories, spares, and backlog control, together with a data management system that preserves complete operational records and supports regulatory reporting. Evidence of disciplined preventive maintenance completion and traceable records earns higher confidence.

(e) Subfactor 5: Plant Monitoring for Process Control, Optimization & Reporting (Adjectival). The Government will evaluate the Offeror’s monitoring programs and Key Performance Indicators (e.g., SRT, F:M, MLSS, clarifier performance indicators) used to maintain biological stability and optimize secondary processes, and how these programs feed accurate, timely reporting. Documented optimization case results support stronger ratings.

(f) Subfactor 6: Demonstrated Process Efficiency Outcomes (Adjectival). The Government will review evidence of efficiency improvements achieved in similar secondary systems (e.g., reduced energy per lb-BOD removed, improved clarifier solids capture, reduced aeration demand, sludge handling gains) with quantified outcomes and methods. Credible measurements and sustained improvements earn higher ratings.

(g) Subfactor 7: Regulatory Compliance Knowledge & Audit Responses (Adjectival). The Government will assess the quality and timeliness of corrective actions and preventive measures documented in those responses. Thorough, timely remediation and durable preventive actions support higher confidence.

(h) Subfactor 8: Support Team Qualifications & Integration (Adjectival). The Government will evaluate the education, certifications, and experience of the engineering, laboratory, data, and reliability/maintenance specialists supporting plant operations, and how they integrate with operators and maintenance staff.

(i) Subfactor 9: Management Commitment & Escalation (Adjectival). The Government will assess the Offeror’s documented executive support, decision rights, and escalation paths that ensure resourcing and rapid resolution of operational issues. Evidence of active management oversight on comparable O&M contracts earns stronger ratings.

(j) Subfactor 10: Secondary System Technical Mastery (Adjectival). The Government will evaluate demonstrated mastery of activated sludge process control (e.g., wasting strategies, SRT/F:M control, filament management, clarifier optimization and solids inventory control) proven at comparable facilities. Clear procedures and outcomes indicating stable compliance improve ratings.

(k) Subfactor 11: Safety WWTP Experience and Accident/Incident Record (Adjectival).

The Government will evaluate depth of relevant WWTP safety experience, certifications, and demonstrated capability to lead investigations and corrective actions. Evaluate the timeliness of corrective measures and evidence of prevention of recurrence (including immediate reporting protocols for serious incidents as required).

(l) Subfactor 12: Insurance & Bonding Capacity (Adjectival). The Government will evaluate evidence of current insurance coverages (e.g., general liability, pollution liability, workers’ compensation) and bonding capacity/letters from sureties commensurate with contract risk.

(m) Subfactor 13: Failures to Complete Work — Disclosures and Resolution History (Adjectival). The Government will evaluate context, recurrence, and corrective actions taken for failures to complete work. Evaluate the nature, frequency, outcomes, and settlement terms of litigation, and improvements implemented to prevent recurrence.

(n) Subfactor 14: Labor Law and Health/Safety, Loss of Life/Welfare Enforcement Actions (Adjectival). The Government will evaluate any actions, fines, or orders relating to labor violations, health/safety or loss of life/welfare, with emphasis on root-cause analyses and demonstrated, audited corrective measures.

(o) Subfactor 15: Effluent Discharge Enforcement Actions (Adjectival). The Government will assess recurrence, regulatory posture, and completeness/timeliness of remedial steps, including process improvements and compliance monitoring.

Factor 4 — Staffing and Key Personnel Provide a staffing plan and position descriptions demonstrating coverage for normal and peak workloads, simultaneous tasks, and leave coverage; identify working hours/shifts; address turnover, recruitment, compensation, and training. Provide qualifications/resumes for key team members (e.g., Plant Superintendent, Operations Supervisor, Maintenance Supervisor, SCADA System Analyst, Shift Supervisor, Safety Lead), including education, certifications, directly related experience, credentials, professional development, and performance record. Provide an organizational chart for the proposed plant staff/key personnel.

Identify any proposed major subcontractors contributing to WWTP O&M.

(a) Subfactor 1: Staffing Plan Submission Completeness (Go/No Go + Adjectival). The Government will verify inclusion of all required elements: number and types of positions;

working hours/shift; brief position descriptions; coverage for normal/peak workloads;

overlapping/simultaneous task management; leave coverage; and discussion of turnover, recruitment, compensation, and training; qualifications for key personnel demonstrating experience on wastewater treatment plants of similar size/complexity and scope;

and organizational chart. Omission of any required element for evaluation will result in a No Go for this factor resulting in an overall unacceptable rating. Missing minor items required will result in a weakness or deficiency.

(b) Subfactor 2: 24/7 Coverage & Shift Redundancy (Adjectival). The Government will assess the realism and sufficiency of continuous coverage (24/7/365), including redundancy at critical posts and cross-trained operators to avoid single-point dependencies. Stronger ratings are supported by clear rotation schedules, surge backfill, and resilience at non-redundant systems.

(c) Subfactor 3: Operator Certification Compliance (Adjectival). The Government will verify that proposed operators meet applicable California certification requirements and that key operating roles satisfy the minimum grade level for a 25–35 MGD facility (e.g., Grade V).

Failure to demonstrate certifications as required results in an unacceptable rating.

(d) Subfactor 4: Key Personnel Qualifications & Resumes (Adjectival). The Government will evaluate education, registrations/certifications, directly related WWTP O&M…

This is the start of the file's text. The full file is on GovTribe.