ATTACHMENT 2 - Volume 4 - WI ANG F-35 3-Bay CD Specs ADD 01 (1 of 2).pdf

PDF 44 MB Posted

Attached to
F-35 THREE BAY SPECIALIZED HANGAR
Solicitation number
W50S9F-22-B-0001
Issued by

About this file

This solicitation is for the construction of an F-35 three-bay specialized hangar at Dane County Regional Airport in Madison, Wisconsin. The project scope includes demolishing an existing 19,875 square foot building and constructing a new 31,000 square foot three-bay hangar with associated shop and administrative spaces to support F-35 fuel cell operations, indoor wash requirements, squadron-level surface coating operations, and weapons load training. The facility must also accommodate a future paint booth and composite make-up clean/dirty spaces. The contract is for a single firm fixed-price award with a base bid for construction and optional bids for a paint/mix addition and aircraft-rated pavement. The bid submission deadline is listed in the solicitation documents on SAM.gov. Interested contractors must register in SAM and attend the pre-bid conference and site visit to be eligible to respond. The contract duration is 550 days from notice to proceed.

View the file

Other files

File Type Posted
Bid Opening Attendance Sheet.pdf PDF
Abstract of Offers.pdf PDF
Questions and Answers 4.pdf PDF
39_ITEM 01.5-1_ADD 03_Bid Question Attachment_2022.06.14.pdf PDF
Question and Answer Set 4_Question 2_Custom Graphic.pdf PDF
W50S9F22B0001 Solicitation - Amend 0004.pdf PDF
22_ITEM 01.3-12_ADD 04_02700A-502.pdf PDF
19_ITEM 01.3-9_ADD 04_02700A-002.pdf PDF
00_FSB2020-270-00_WI-ANG_3-Bay_ADD NO. 04_2022.06.28_Narrative.pdf PDF
24_ITEM 01.3-14_ADD 04_02700A-702.pdf PDF
Questions and Answers 3.pdf PDF
25_ITEM 01.3-15_ADD 04_02700ES101.pdf PDF
10_ITEM 01.2-10_ADD 04_Section 32 13 14.13.pdf PDF
26_ITEM 01.3-16_ADD 04_02700EP102.pdf PDF
20_ITEM 01.3-10_ADD 04_02700A-140.pdf PDF
01_ITEM 01.2-1_ADD 04_PROJECT TOC.pdf PDF
15_ITEM 01.3-5_ADD 04_02700SF105.pdf PDF
23_ITEM 01.3-13_ADD 04_02700A-503.pdf PDF
03_ITEM 01.2-3_ADD 04_Section 07 21 13.pdf PDF
05_ITEM 01.2-5_ADD 04_Section 08 33 13.pdf PDF
07_ITEM 01.2-7_ADD 04_Section 09 90 00.pdf PDF
18_ITEM 01.3-8_ADD 04_02700SF504.pdf PDF
11_ITEM 01.3-1_ADD 04_02700C-301.pdf PDF
06_ITEM 01.2-6_ADD 04_Section 08 33 23.pdf PDF
09_ITEM 01.2-9_ADD 04_Section 11 94 00.01.pdf PDF
27_ITEM 01.3-17_ADD 04_02700EP701.pdf PDF
04_ITEM 01.2-4_ADD 04_Section 07 24 00.pdf PDF
16_ITEM 01.3-6_ADD 04_02700SF106.pdf PDF
28_ITEM 01.3-18_ADD 04_02700EP702.pdf PDF
14_ITEM 01.3-4_ADD 04_02700SF104.pdf PDF
17_ITEM 01.3-7_ADD 04_02700SF503.pdf PDF
02_ITEM 01.2-2_ADD 04_Section 04 20 00.pdf PDF
12_ITEM 01.3-2_ADD 04_02700C-401.pdf PDF
08_ITEM 01.2-8_ADD 04_Section 11 94 10.pdf PDF
21_ITEM 01.3-11_ADD 04_02700A-501.pdf PDF
13_ITEM 01.3-3_ADD 04_02700C-601.pdf PDF
FSB2020-270-00 - WI-ANG - 3-Bay Hangar - Addendum 004 COMBINED DRAWINGS.pdf PDF
W50S9F22B0001 Solicitation - Amend 0003.pdf PDF
28_ITEM 01.3-18_ADD 03_02700A-600.pdf PDF
24_ITEM 01.3-14_ADD 03_02700A-501.pdf PDF
01_ITEM 01.2-1_ADD 03_Section 02 65 00.pdf PDF
14_ITEM 01.3-4_ADD 03_02700C-402.pdf PDF
20_ITEM 01.3-10_ADD 03_02700A-002.pdf PDF
05_ITEM 01.2-5_ADD 03_Section 08 71 00.pdf PDF
Questions and Answers 2.pdf PDF
07_ITEM 01.2-7_ADD 03_Section 21 13 13.pdf PDF
FSB2020-270-00 - WI-ANG - 3-Bay Hangar - Addendum 003 Combined Drawings.pdf PDF
18_ITEM 01.3-8_ADD 03_02700SF103.pdf PDF
16_ITEM 01.3-6_ADD 03_02700C-601.pdf PDF
03_ITEM 01.2-3_ADD 03_Section 05 50 13.pdf PDF
Show 40 more

Latest 50 of 147 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Addendum No. 01

Volume 4 – CD Specifications (1 of 2)

F-35 3-Bay Specialized Hangar

Wisconsin Air National Guard 115th Fighter Wing Dane County Regional Airport

Truax Field Air National Guard Base

Madison, WI

NGB Contract: W9133L-16-D-0005

Task Order: W50S9F-20-F-0001

WI ANG PN: XGFG189002

April 22, 2022

ANG/WI – F-35: 3-Bay Specialized Hangar 20202700F353BAY

Addendum No. 01 22 April 2022

SEALS PAGE Page 1

SEALS PAGE

DESIGN PROFESSIONALS OF RECORD (DPOR)

A. Architect:

1. Jason Holuby, AIA, LEED AP BD+C

2. Responsible for Division 01 (Portion of Specification 01 57 19), U.N.O Herein; Divisions 06, 07, 08, 09, 10, 11, and 12; and

Specification 02 41 00

3. E-mail: jholuby@fsb-ae.com

4. Ph: 405.840.2931

B. Civil:

1. Lindsay Hausman, P.E.

2. Responsible for Divisions 31, 32, 33, and 46

3. E-mail: lhausman@hanson-inc.com

4. Ph: 217.747.9314

C. Structural:

1. Gene Brown, P.E., LEED AP

2. Responsible for Divisions 03, 04 and 05; and Specification 01 45 35

3. E-mail: gbrown@fsb-ae.com

D. Mechanical:

1. John Semtner, P.E.

2. Responsible for Divisions 22 and 23

3. E-mail: jsemtner@fsb-ae.com

W

IS C O NS IN

A R C H I T E C T

JASON T.

HOLUBY

A-13101

OKLAHOMA CITY

OK

W

IS C O NS IN

P R

O F

E

S S I O N A L

E N G

I N E

E R

GENE O.

BROWN

E-47748

OKLAHOMA CITY

OK

W

IS C O NS IN

P R

O F

E

S S I O N A L

E N G

I N E

E R

JOHN B.

SEMTNER

E-47742

OKLAHOMA CITY

OK

4/22/2022 mailto:jholuby@fsb-ae.com mailto:lhausman@hanson-inc.com mailto:gbrown@fsb-ae.com mailto:jsemtner@fsb-ae.com

SEALS PAGE Page 2

E. Electrical:

1. John T. Little, P.E.

2. Responsible for Divisions 25, 26, and 27

3. E-mail: jlittle@fsb-ae.com

F. Fire Protection:

1. Liane Ozmun, P.E.

2. Responsible for Divisions 21 and 28

3. E-mail: lozmun@fsb-ae.com

G. Environmental:

1. Ben Peotter, PE

2. Responsible for Portion of Specification 01 57 19; and

Specification 02 61 13, 02 65 00, 02 81 00, 02 82 00, 02 84 16, and 02 84 33

3. E-mail: peotterb@ayresassociates.com

4. Ph: 608.443.1200

P R

O F

E

S S I O N A L

E N G

I N E

E R

JOHN T

LITTLE

E-47833

EDMOND

OK

W

IS C O NS IN

P R

O F

E

S S I O N A L

E N G

I N E

E R

LIANE F

OZMUN

E-48073

OKLAHOMA CITY

OK

mailto:jlittle@fsb-ae.com mailto:lozmun@fsb-ae.com mailto:steinerj@ayresassociates.com

Type B-3 Submission 23 December 2021

SEALS PAGE Page 1

SEALS PAGE

DESIGN PROFESSIONALS OF RECORD (DPOR)

A. Architect:

1. Jason Holuby, AIA, LEED AP BD+C

2. Responsible for Division 01 (Portion of Specification 01 57 19), U.N.O Herein; Divisions 06, 07, 08, 09, 10, 11, and 12; and

Specification 02 41 00

3. E-mail: jholuby@fsb-ae.com

B. Civil:

1. Lindsay Hausman, P.E.

2. Responsible for Divisions 31, 32, 33, and 46

3. E-mail: lhausman@hanson-inc.com

4. Ph: 217.747.9314

C. Structural:

1. Gene Brown, P.E., LEED AP

2. Responsible for Divisions 03, 04 and 05; and Specification 01 45 35

3. E-mail: gbrown@fsb-ae.com

D. Mechanical:

1. John Semtner, P.E.

2. Responsible for Divisions 22 and 23

3. E-mail: jsemtner@fsb-ae.com

A R C H I T E C T

JASON T.

HOLUBY

A-13101

OKLAHOMA CITY

OK

W

IS C O NS IN

P R

O F

E

S S I O N A L

E N G

I N E

E R

GENE O.

BROWN

E-47748

OKLAHOMA CITY

OK

W

IS C O NS IN

P R

O F

E

S S I O N A L

E N G

I N E

E R

JOHN B.

SEMTNER

E-47742

OKLAHOMA CITY

OK

12/23/2021 mailto:jholuby@fsb-ae.com mailto:lhausman@hanson-inc.com mailto:gbrown@fsb-ae.com mailto:jsemtner@fsb-ae.com

SEALS PAGE Page 2

E. Electrical:

1. John T. Little, P.E.

2. Responsible for Divisions 25, 26, and 27

3. E-mail: jlittle@fsb-ae.com

4. Ph: 405.840.2931

F. Fire Protection:

1. Liane Ozmun, P.E.

2. Responsible for Divisions 21 and 28

3. E-mail: lozmun@fsb-ae.com

4. Ph: 405.840.2931

G. Environmental:

1. Ben Peotter, PE

2. Responsible for Portion of Specification 01 57 19; and

Specification 02 61 13, 02 65 00, 02 81 00, 02 82 00, 02 84 16, and 02 84 33

3. E-mail: peotterb@ayresassociates.com

4. Ph: 608.443.1200

12-21-21

W

IS C O NS IN

P R

O F

E

S S I O N A L

E N G

I N E

E R

LIANE F

OZMUN

E-48073

OKLAHOMA CITY

OK

W

IS C O NS IN

P R

O F

E

S S I O N A L

E N G

I N E

E R

JOHN T

LITTLE

E-47833

EDMOND

OK

mailto:jlittle@fsb-ae.com mailto:lozmun@fsb-ae.com mailto:steinerj@ayresassociates.com

ANG/WI - F-35: 3-Bay Specialized Hangar 20202700F353BAY

PROJECT TABLE OF CONTENTS

DI VI SI ON 01 - GENERAL REQUI REMENTS

01 11 00 SUMMARY OF WORK

01 14 00 WORK RESTRICTIONS

01 20 00 PRICE AND PAYMENT PROCEDURES

01 30 00 ADMINISTRATIVE REQUIREMENTS

01 32 01.00 10 PROJECT SCHEDULE

01 33 00 SUBMITTAL PROCEDURES

01 33 29 SUSTAINABILITY REPORTING

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00.00 10 QUALITY CONTROL

01 45 35 SPECIAL INSPECTIONS

01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS

01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS

01 58 00 PROJECT IDENTIFICATION

01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

01 78 00 CLOSEOUT SUBMITTALS

01 78 23 OPERATION AND MAINTENANCE DATA

01 91 00.15 10 TOTAL BUILDING COMMISSIONING

DI VI SI ON 02 - EXI STI NG CONDI TI ONS

02 41 00 DEMOLITION AND DECONSTRUCTION

02 61 13 EXCAVATION AND HANDLING OF CONTAMINATED MATERIAL

02 65 00 UNDERGROUND STORAGE TANK REMOVAL

02 81 00 TRANSPORTATION AND DISPOSAL OF HAZARDOUS MATERIALS

02 82 00 ASBESTOS REMEDIATION

02 84 16 HANDLING OF LIGHTING BALLASTS AND LAMPS CONTAINING PCBs

AND MERCURY

02 84 33 REMOVAL AND DISPOSAL OF POLYCHLORINATED BIPHENYLS (PCBs)

DI VI SI ON 03 - CONCRETE

03 30 00 CAST-IN-PLACE CONCRETE

DI VI SI ON 04 - MASONRY

04 20 00 UNIT MASONRY

04 72 00 CAST STONE MASONRY

DI VI SI ON 05 - METALS

05 12 00 STRUCTURAL STEEL

05 30 00 STEEL DECKS

05 40 00 COLD-FORMED METAL FRAMING

05 50 13 MISCELLANEOUS METAL FABRICATIONS

05 51 33 METAL LADDERS

05 52 00 METAL RAILINGS

DI VI SI ON 06 - WOOD, PLASTI CS, AND COMPOSI TES

06 10 00 ROUGH CARPENTRY

06 20 00 FINISH CARPENTRY

06 41 16.00 10 PLASTIC-LAMINATE-CLAD ARCHITECTURAL CABINETS

06 61 16 SOLID SURFACING FABRICATIONS

06 73 01 FIBERGLASS REINFORCED PLASTIC (FRP) GRATING

PROJECT TABLE OF CONTENTS Page 1

DI VI SI ON 07 - THERMAL AND MOI STURE PROTECTI ON

07 05 23 PRESSURE TESTING AN AIR BARRIER SYSTEM FOR AIR TIGHTNESS

07 22 00 ROOF AND DECK INSULATION

07 24 00 EXTERIOR INSULATION AND FINISH SYSTEMS

07 27 10.00 10 BUILDING AIR BARRIER SYSTEM

07 27 26 FLUID-APPLIED MEMBRANE AIR BARRIERS

07 27 36 SPRAY FOAM AIR BARRIERS

07 42 13 METAL WALL PANELS

07 42 63 FABRICATED WALL PANEL ASSEMBLIES

07 54 19 POLYVINYL-CHLORIDE ROOFING

07 60 00 FLASHING AND SHEET METAL

07 61 14.00 20 STEEL STANDING SEAM ROOFING

07 84 00 FIRESTOPPING

07 92 00 JOINT SEALANTS

07 95 00 ARCHITECTURAL EXPANSION JOINTS

DI VI SI ON 08 - OPENI NGS

08 11 13 STEEL DOORS AND FRAMES

08 11 16 ALUMINUM DOORS AND FRAMES

08 14 00 WOOD DOORS

08 31 00 ACCESS DOORS AND PANELS

08 33 23 OVERHEAD COILING DOORS

08 34 16.20 VERTICAL LIFT FABRIC DOORS

08 44 00 CURTAIN WALL AND GLAZED ASSEMBLIES

08 44 26 ALL-GLASS PARTITIONS

08 60 45 SKYLIGHTS AND TRANSLUCENT PANELS

08 71 00 DOOR HARDWARE

08 81 00 GLAZING

08 87 35 ARCHITECTURAL WINDOW FILM

08 91 00 METAL WALL LOUVERS

DI VI SI ON 09 - FI NI SHES

09 06 00 SCHEDULES FOR FINISHES

09 29 00 GYPSUM BOARD

09 30 10 CERAMIC, AND GLASS TILING

09 51 00 ACOUSTICAL CEILINGS

09 62 38 STATIC-CONTROL FLOORING

09 65 00 RESILIENT FLOORING

09 67 23.13 STANDARD RESINOUS FLOORING

09 67 23.16 FUEL RESISTIVE RESINOUS FLOORING, 5-COAT SYSTEM

09 68 00 CARPETING

09 77 20 FIBERGLASS REINFORCED WALL PANELS

09 90 00 PAINTS AND COATINGS

09 97 13.27 HIGH PERFORMANCE COATING FOR STEEL STRUCTURES

DI VI SI ON 10 - SPECI ALTI ES

10 14 00.10 EXTERIOR SIGNAGE

10 14 00.20 INTERIOR SIGNAGE

10 21 13 TOILET COMPARTMENTS

10 26 00 WALL AND DOOR PROTECTION

10 28 13 TOILET ACCESSORIES

10 44 16 FIRE EXTINGUISHERS

10 51 13 METAL LOCKERS

10 53 00 MANUFACTURED CANOPY

PROJECT TABLE OF CONTENTS Page 2

DI VI SI ON 11 - EQUI PMENT

11 94 10 ROOFTOP FALL PROTECTION ANCHORS

DI VI SI ON 12 - FURNI SHI NGS

12 24 13 ROLLER WINDOW SHADES

DI VI SI ON 21 - FI RE SUPPRESSI ON

21 13 13 WET PIPE SPRINKLER SYSTEMS, FIRE PROTECTION

21 13 18 PREACTION SPRINKLER SYSTEMS, FIRE PROTECTION

DI VI SI ON 22 - PLUMBI NG

22 00 00 PLUMBING, GENERAL PURPOSE

22 31 00 WATER SOFTENERS, CATION-EXCHANGE (SODIUM CYCLE)

DI VI SI ON 23 - HEATI NG, VENTI LATI NG, AND AI R CONDI TI ONI NG ( HVAC)

23 05 48.00 40 VIBRATION AND SEISMIC CONTROLS FOR HVAC PIPING AND

EQUIPMENT

23 05 48.19 BRACING FOR HVAC

23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC

23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS

23 09 00 INSTRUMENTATION AND CONTROL FOR HVAC

23 09 13 INSTRUMENTATION AND CONTROL DEVICES FOR HVAC

23 09 23.02 BACNET DIRECT DIGITAL CONTROL FOR HVAC AND OTHER BUILDING

CONTROL SYSTEMS

23 11 20 FACILITY GAS PIPING

23 21 23 HYDRONIC PUMPS

23 23 00 REFRIGERANT PIPING

23 30 00 HVAC AIR DISTRIBUTION

23 31 13.00 40 METAL DUCTS

23 34 23.00 40 HVAC POWER VENTILATORS

23 35 19.00 20 INDUSTRIAL VENTILATION AND EXHAUST

23 36 00.00 40 AIR TERMINAL UNITS

23 37 13.00 40 DIFFUSERS, REGISTERS, AND GRILLES

23 52 00 HEATING BOILERS

23 74 33.00 40 PACKAGED, OUTDOOR, HEATING AND COOLING MAKEUP

AIR-CONDITIONERS

23 75 15 CUSTOM-PACKAGED, AIRCRAFT PRE-CONDITIONED AIR UNITS

23 80 20.00 10 GAS-FIRED HEATING EQUIPMENT

23 82 19.00 40 FAN COIL UNITS

DI VI SI ON 25 - I NTEGRATED AUTOMATI ON

25 05 11.01 CYBERSECURITY FOR LOW IMPACT HVAC CONTROL SYSTEMS

25 05 11.02 CYBERSECURITY FOR LOW IMPACT PORTABLE GENERATOR LOAD BANK

CONNECTION CABINET CONTROL SYSTEMS

25 05 11.03 CYBERSECURITY FOR LOW IMPACT SWITCH GEAR AUTOMATION

CONTROL SYSTEMS

25 05 11.04 CYBERSECURITY FOR LOW IMPACT FIRE PROTECTION/MASS

NOTIFICATION SYSTEM FACILITY-RELATEDCONTROL SYSTEMS

25 05 11.05 CYBERSECURITY FOR LOW IMPACT ACCESS CONTROL SYSTEM AND

INTRUSION DETECTION SYSTEM FACILITY-RELATED CONTROL

SYSTEMS

25 05 11.06 CYBERSECURITY FOR LOW IMPACT CCTV SYSTEM FACILITY-RELATED

PROJECT TABLE OF CONTENTS Page 3

CONTROL SYSTEMS

25 05 11.07 CYBERSECURITY FOR LOW IMPACT ELECTRICAL METERING AND

NETWORK LIGHTING CONTROLS FACILITY-RELATED CONTROL SYSTEMS

25 10 10 UTILITY MONITORING AND CONTROL SYSTEM (UMCS) FRONT END

AND INTEGRATION

DI VI SI ON 26 - ELECTRI CAL

26 05 19.10 10 INSULATED WIRE AND CABLE

26 05 26.00 40 GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS

26 08 00 APPARATUS INSPECTION AND TESTING

26 09 43 NETWORK LIGHTING CONTROLS (WIRED)

26 20 00 INTERIOR DISTRIBUTION SYSTEM

26 24 13 SWITCHBOARDS

26 27 13.10 30 ELECTRIC METERS

26 28 00.00 10 MOTOR CONTROL CENTERS, SWITCHBOARDS AND PANELBOARDS

26 28 01.00 10 COORDINATED POWER SYSTEM PROTECTION

26 35 44 270 VDC SOLID STATE CONVERTER

26 36 20 PORTABLE GENERATOR AND LOAD BANK CONNECTION CABINETS

(PGLBCC)

26 41 00 LIGHTNING PROTECTION SYSTEM

26 51 00 INTERIOR LIGHTING

26 56 00 EXTERIOR LIGHTING

DI VI SI ON 27 - COMMUNI CATI ONS

27 05 14.00 10 CABLE TELEVISION PREMISES DISTRIBUTION SYSTEM

27 05 28.36 40 CABLE TRAYS FOR COMMUNICATIONS SYSTEMS

27 10 00 BUILDING TELECOMMUNICATIONS CABLING SYSTEM

27 51 16 RADIO AND PUBLIC ADDRESS SYSTEMS

DI VI SI ON 28 - ELECTRONI C SAFETY AND SECURI TY

28 31 76 INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM,

ADDRESSABLE

DI VI SI ON 31 - EARTHWORK

31 00 00 EARTHWORK

DI VI SI ON 32 - EXTERI OR I MPROVEMENTS

32 01 19.61 SEALING OF JOINTS IN RIGID PAVEMENT

32 11 20 BASE COURSE FOR RIGID PAVING AND SIDEWALK AND SUBBASES

FOR FLEXIBLE PAVING

32 12 13 BITUMINOUS TACK AND PRIME COATS

32 12 15.13 ASPHALT PAVING FOR AIRFIELDS

32 12 16.16 ROAD-MIX ASPHALT PAVING

32 13 14.13 CONCRETE PAVING FOR AIRFIELDS AND OTHER HEAVY DUTY

PAVEMENTS

32 16 19 CONCRETE CURBS, GUTTERS AND SIDEWALKS

32 17 23 PAVEMENT MARKINGS

32 92 19 SEEDING

DI VI SI ON 33 - UTI LI TI ES

33 40 00 STORM DRAINAGE UTILITIES

DI VI SI ON 46 - WATER AND WASTEWATER EQUI PMENT

PROJECT TABLE OF CONTENTS Page 4

46 25 14 COALESCING OIL-WATER SEPARATORS

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 5

THIS PAGE INTENTIONALLY LEFT BLANK

PROJECT TABLE OF CONTENTS Page 6

SECTION 01 11 00

SUMMARY OF WORK

08/15

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor Quality Control approval. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance with Section 01 33 29 SUSTAINABILITY REPORTING.

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-01 Preconstruction Submittals Salvage Plan ; G

1.2 WORK COVERED BY CONTRACT DOCUMENTS

1.2.1 Project Description

The work includes demolition of the existing Fuel Cell Maintenance Hangar (Building 414) at Truax Field and the construction of a new 3-Bay Specialized Hangar in its place compatible with the F-35 mission. The new 3-Bay Specialized Hangar will support fuel cell operations, indoor wash requirements, F-35 surface coating operations, and Weapons Load Trainer (WLT) operations. The new hangar will include attached administration, office, and shop spaces. Site work will include removal of existing underground elements and utilities, and the installation and construction of new elements and utilities required for, and in support of, the new 3-Bay Specialized Hangar. Construction of the 3-Bay Specialized Hangar will not be phased and will occur immediately following demolition of the existing Fuel Cell Maintenance Hangar (Building 414), and its associated underground elements and utilities; and incidental related work.

1.2.2 Location

The work is located at the Truax Field Air National Guard Base, Madison, Wisconsin , approximately as indicated. The exact location will be shown by the Contracting Officer.

1.2.3 Contract Documents

These contract documents (specifications and drawings) have been created to illustrate the project's scope and to describe the design intent.

These contract documents are not intended to be complete, shop drawing level documents, which will be prepared by the Contractor based upon the final materials, products and equipment selected by the contractor. The Contractor is required to provide the expertise to successfully coordinate and execute the work, including as follows:

a. Means and methods of construction are the sole domain and exclusive responsibility of the Contractor. Materials, products and equipment are indicated as generically as practical when/where sole-sourcing such items is not permitted by the Contracting Officer. Contractor coordination is required based upon the final materials, products and

SECTION 01 11 00 Page 1 equipment selected by the contractor, even when the basis of design material, product or equipment is selected for use. Contractor shall fully coordinate and modify, as required and at no additional cost or time to the Government or Architect/Engineer of Record, all dimensions, clearances, arrangements, assemblies, programming/controls, etc. which may vary based upon the final materials, products or equipment selected by the Contractor.

b. Building systems, components and functionality indicated in these contract documents are included where specific project requirements shall be adhered to in the construction of this project. Not all components, wiring, conduit, mountings, bracing, peripheral items, programming, controls, etc. are shown or indicated. In cases where no specific project requirements are indicated in the contract documents or where variations exist in the materials, products or equipment selected by the Contractor, these are delegated designs and the Contractor is responsible for providing a complete and usable building system, component and/or functionality.

1.3 OCCUPANCY OF PREMISES

Adjacent building(s) will be occupied during performance of work under this Contract.

Before work is started, arrange with the Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways which does not restrict use of adjacent buildings.

1.4 EXISTING WORK

In addition to FAR 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements:

a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remains.

b. Repair or replace portions of existing work whch have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to, or better than, that which existed before new work started.

1.5 LOCATION OF UNDERGROUND UTILITIES

Obtain digging permits prior to start of excavation, and comply with Installation requirements for locating and marking underground utilities.

Contact the Installation and local utility locating service a minimum of 7 calendar days prior to excavating, to mark utilities, and within sufficient time required if work occurs on a Monday or after a Holiday.

Provide a mininum of 7 calendar days for Installation personnel to mark private utility and communication lines. Verify existing utility locations indicated on contract drawings, within area of work.

1.5.1 Notification Prior to Excavation

Notify the Contracting Officer at least 15 days prior to starting excavation work.

SECTION 01 11 00 Page 2

1.6 SALVAGE MATERIAL AND EQUIPMENT

Items designated by the Contracting Officer to be salvaged remain the property of the Government. Segregate, itemize, and store the salvaged property at the construction site until disposition by the Contracting Officer.

Provide a salvage plan , listing material and equipment to be salvaged, and their storage location. Maintain property control records for material or equipment designated as salvage. Use a system of property control that is approved by the Contracting Officer. Store and protect salvaged materials and equipment until disposition by the Contracting Officer.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

-- End of Section --

SECTION 01 11 00 Page 3

SECTION 01 11 00 Page 4

SECTION 01 14 00

WORK RESTRICTIONS

11/11

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor Quality Control approval. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance with Section 01 33 29 SUSTAINABILITY REPORTING.

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-01 Preconstruction Submittals

List of Contact Personnel

1.2 CONTRACTOR ACCESS AND USE OF PREMISES

1.2.1 Activity Regulations

Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Wear appropriate personal protective equipment (PPE) in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. Mark Contractor equipment for identification.

1.2.1.1 Subcontractors and Personnel Contacts

Provide a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.

1.2.1.2 No Smoking Policy

Smoking is prohibited within and outside of all buildings on installation, except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. The Contracting Officer will identify designated smoking areas.

1.2.2 Working Hours

Regular working hours will consist of a 10 hour period established by the Contracting Officer, sometime between approximately 0600 and 1700, Monday through Friday , excluding Government holidays.

1.2.3 Work Outside Regular Hours

Work outside regular working hours requires Contracting Officer approval.

Make application 5 calendar days prior to such work to allow arrangements

SECTION 01 14 00 Page 1 to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours. During periods of darkness, the different parts of the work must be lighted in a manner approved by the Contracting Officer.

1.2.4 Utility Cutovers and Interruptions

a. Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and Government holidays. Conform to procedures required in paragraph WORK OUTSIDE REGULAR HOURS.

b. Ensure that new utility lines are complete, except for the connection, before interrupting existing service.

c. Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, air conditioning, heating, fire alarm, compressed air, and are considered utility cutovers pursuant to the paragraph

WORK OUTSIDE REGULAR HOURS.PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

SECTION 01 14 00 Page 2

SECTION 01 20 00

PRICE AND PAYMENT PROCEDURES

11/20

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor Quality Control approval. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance with Section 01 33 29 SUSTAINABILITY REPORTING.

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

1.2 CONTRACTOR'S INVOICE AND CONTRACT PERFORMANCE STATEMENT

1.2.1 Final Invoice

a. A final invoice must be accompanied by the certification required by DFARS 252.247.7023 Transportation of Supplies by Sea, and the Contractor's Final Release. If the Contractor is incorporated, the Final Release must contain the corporate seal. An officer of the corporation must sign and the corporate secretary must certify the Final Release.

b. For final invoices being submitted via WAWF, the original Contractor's Final Release Form and required certification of Transportation of Supplies by Sea must be provided directly to the respective Contracting Officer prior to submission of the final invoice. Once receipt of the original Final Release Form and required certification of Transportation of Supplies by Sea has been confirmed by the Contracting Officer, the Contractor must then submit final invoice and attach a copy of the Final Release Form and required certification of Transportation of Supplies by Sea in WAWF.

c. Final invoices not accompanied by the Contractor's Final Release and required certification of Transportation of Supplies by Sea will be considered incomplete and will be returned to the Contractor.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

SECTION 01 20 00 Page 1

SECTION 01 20 00 Page 2

SECTION 01 30 00

ADMINISTRATIVE REQUIREMENTS

11/20

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2014) Safety and Health Requirements Manual

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor Quality Control approval. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance with Section 01 33 29 SUSTAINABILITY REPORTING.

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-01 Preconstruction Submittals

View Location Map

Progress and Completion Pictures

SD-04 Samples

Color Boards ; G

1.3 COLOR BOARDS FOR AIR FORCE PROJECTS

Submit five sets of color boards within 90 calendar days after Contract Award. Each set of boards must include samples of colors and finishes of interior surfaces, such as walls, floors, and ceilings. Present the samples on 8 by 10-1/2 inches boards (modules) with a maximum spread of 24 by 31-1/2 inches for foldouts. Design modules to fit in a standard loose-leaf, three-ring binder. Where special finishes such as architectural concrete, carpet, or prefinished textured metal panels are required, submit samples not less than 12 inches square with the board.

If more space is needed, more than one board per set may be submitted.

Certify that the color samples have been reviewed in detail, and that the color samples are in strict accordance with contract drawings and specifications, except as may be otherwise explicitly stated. Submittal of color samples does not relieve the Contractor of the responsibility to submit samples required elsewhere herein.

SECTION 01 30 00 Page 1

1.4 VIEW LOCATION MAP

Submit, prior to or with the first digital photograph submittals, a sketch or drawing indicating the required photographic locations. Update as required if the locations are moved.

1.5 PROGRESS AND COMPLETION PICTURES

Photographically document site conditions prior to start of construction operations. Include aerial photographs. Provide monthly, and within one month of the completion of work, digital photographs, 1600x1200x24 bit true color minimum resolution in JPEG file format showing the sequence and progress of work. Take a minimum of 20 digital photographs each week throughout the entire project from a minimum of ten different viewpoints selected by the Contractor unless otherwise directed by the Contracting Officer. Submit with the monthly invoice two sets of digital photographs, each set on a separate compact disc (CD) or data versatile disc (DVD), cumulative of all photos to date. Indicate photographs demonstrating environmental procedures. Provide photographs for each month in a separate monthly directory and name each file to indicate its location on the view location sketch. Also provide the view location sketch on the CD or DVD as a digital file. Include a date designator in file names.

Photographs provided are for unrestricted use by the Government.

1.6 MINIMUM INSURANCE REQUIREMENTS

Provide the minimum insurance coverage required by FAR 28.307-2 Liability, during the entire period of performance under this contract. Provide other insurance coverage as required by Wisconsin law.

1.7 SUPERVISION

1.7.1 Superintendent Qualifications

Provide project superintendent with a minimum of 5 years experience in construction with at least 5 of those years as a superintendent on projects similar in size and complexity. The individual must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification and safety compliance. The individual must be capable of interpreting a critical path schedule and construction drawings. The qualification requirements for the alternate superintendent are the same as for the project superintendent. The Contracting Officer may request proof of the superintendent's qualifications at any point in the project if the performance of the superintendent is in question.

1.7.2 Minimum Communication Requirements

Have at least one qualified superintendent, or competent alternate, capable of reading, writing, and conversing fluently in the English language, on the job-site at all times during the performance of Contract work.In addition, if a Quality Control (QC) representative is required on the Contract, then that individual must also have fluent English communication skills.

1.7.3 Duties

The project superintendent is primarily responsible for managing subcontractors and coordinating day-to-day production and schedule adherence on the project. The superintendent is required to attend Red

SECTION 01 30 00 Page 2

Zone meetings, partnering meetings, and quality control meetings. The superintendent or qualified alternative must be on-site at all times during the performance of this contract until the work is completed and accepted.

1.7.4 Non-Compliance Actions

The Project Superintendent is subject to removal by the Contracting Officer for non-compliance with requirements specified in the contract and for failure to manage the project to ensure timely completion.

Furthermore, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders is acceptable as the subject of claim for extension of time for excess costs or damages by the Contractor.

1.8 PRECONSTRUCTION

Immediately after award , prior to commencing any work at the site, coordinate with the Contracting Officer a time and place to meet for the Preconstruction . The must take place within 35 calendar days after award of the contract, but prior to commencement of any work at the site.

The purpose of this is to discuss and develop a mutual understanding of the administrative requirements of the Contract including but not limited to: daily reporting, invoicing, value engineering, safety, base-access, outage requests, hot work permits, schedule requirements, quality control, schedule of prices or earned value report, shop drawings, submittals, cybersecurity, prosecution of the work, government acceptance, final inspections and contract close-out. Contractor must present and discuss their basic approach to scheduling the construction work and any required phasing.

1.8.1 Attendees

Contractor attendees must include the Project Manager, Superintendent, Site Safety and Health Officer (SSHO), Quality Control Manager and major subcontractors.

1.9 FACILITY TURNOVER PLANNING MEETINGS (Red Zone Meetings)

Meet with the Government to identify strategies to ensure the project is carried to expeditious closure and turnover to the Client. Start planning the turnover process at the Pre-Construction Conference meeting with a discussion of the Red Zone process and convene at regularly scheduled NRZ Meetings beginning at approximately 75 percent of project completion.

Include the following in the facility Turnover effort:

1.9.1 Red Zone Checklist

a. Contracting Officer's Technical Representative (COTR) will provide the Contractor a copy of the Red Zone Checklist template.

b. Prior to 75 percent completion, modify the Red Zone Checklist template by adding or deleting critical activities applicable to the project and assign planned completion dates for each activity. Submit the modified Red Zone Checklist to the Contracting Officer. The Contracting Officer may request additional activities be added to the Red Zone Checklist at any time as necessary.

SECTION 01 30 00 Page 3

1.9.2 Meetings

a. Conduct regular Red Zone Meetings beginning at approximately 75 percent project completion, or three to six months prior to Beneficial Occupancy Date (BOD), whichever comes first.

b. The Contracting Officer will establish the frequency of the meetings, which is expected to increase as the project completion draws nearer.

At the beginning, Red Zone meetings may be every two weeks then increase to weekly towards the final month of the project.

c. Using the Red Zone Checklist as a Plan of Action and Milestones (POAM) and basis for discussion, review upcoming critical activities and strategies to ensure work is completed on time.

d. During the Red Zone Meetings discuss with the COTR any upcoming activities that require Government involvement.

e. Maintain the Red Zone Checklist by documenting the actual completion dates as work is completed and update the Red Zone Checklist with revised planned completion dates as necessary to match progress.

Distribute copies of the current Red Zone Checklist to attendees at each Red Zone Meeting.

1.10 PARTNERING

Contractor shall host the partnering session within 45 calendar days of contract award. To most effectively accomplish this Contract, the Contractor and Government must form a cohesive partnership with the common goal of drawing on the strength of each organization in an effort to achieve a successful project without safety mishaps, conforming to the Contract, within budget and on schedule. The partnering team must consist of personnel from both the Government and Contractor including project level and corporate level leadership positions. Key Personnel from the supported command, end user, Base personnel , Contractor, key subcontractors and the Designer of Record are required to participate in the Partnering process.

1.11 MOBILIZATION

Contractor shall mobilize to the jobsite within 60 calendar days of contract award. Mobilize is defined as having equipment AND having a physical presence of at least one person from the contractor's team on the jobsite.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

SECTION 01 30 00 Page 4

SECTION 01 32 01.00 10

PROJECT SCHEDULE

02/15

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AACE INTERNATIONAL (AACE)

AACE 29R-03 (2011) Forensic Schedule Analysis

AACE 52R-06 (2006) Time Impact Analysis - As Applied in Construction

U.S. ARMY CORPS OF ENGINEERS (USACE)

ER 1-1-11 (1995) Administration -- Progress, Schedules, and Network Analysis Systems

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor Quality Control approval. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance to Section 01 33 29 SUSTAINABILITY REPORTING.

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-01 Preconstruction Submittals

Project Scheduler Qualifications ; G

Preliminary Project Schedule ; G

Initial Project Schedule ; G

Periodic Schedule Update ; G

1.3 PROJECT SCHEDULER QUALIFICATIONS

Designate an authorized representative to be responsible for the preparation of the schedule and all required updating and production of reports. The authorized representative must have a minimum of 2-years experience scheduling construction projects similar in size and nature to this project with scheduling software that meets the requirements of this specification. Representative must have a comprehensive knowledge of CPM scheduling principles and application.

SECTION 01 32 01.00 10 Page 1

PART 2 PRODUCTS

2.1 SOFTWARE

The scheduling software utilized to produce and update the schedules required herein must be capable of meeting all requirements of this specification.

2.1.1 Government Default Software

The Government intends to use Primavera P6.

2.1.2 Contractor Software

Scheduling software used by the contractor must be commercially available from the software vendor for purchase with vendor software support agreements available. The software routine used to create the required sdef file must be created and supported by the software manufacturer.

2.1.2.1 Primavera

If Primavera P6 is selected for use, provide the "xer" export file in a version of P6 importable by the Government system.

PART 3 EXECUTION

3.1 GENERAL REQUIREMENTS

Prepare for approval a Project Schedule, as specified herein, pursuant to FAR Clause 52.236-15 Schedules for Construction Contracts. Show in the schedule the proposed sequence to perform the work and dates contemplated for starting and completing all schedule activities. The scheduling of the entire project is required. The scheduling of construction is the responsibility of the Contractor. Contractor management personnel must actively participate in its development. Subcontractors and suppliers working on the project must also contribute in developing and maintaining an accurate Project Schedule. Provide a schedule that is a forward planning as well as a project monitoring tool. Use the Critical Path Method (CPM) of network calculation to generate all Project Schedules.

Prepare each Project Schedule using the Precedence Diagram Method (PDM).

3.2 BASIS FOR PAYMENT AND COST LOADING

The schedule is the basis for determining contract earnings during each update period and therefore the amount of each progress payment. The aggregate value of all activities coded to a contract CLIN must equal the value of the CLIN.

3.2.1 Activity Cost Loading

Activity cost loading must be reasonable and without front-end loading.

Provide additional documentation to demonstrate reasonableness if requested by the Contracting Officer.

3.2.2 Withholdings / Payment Rejection

Failure to meet the requirements of this specification may result in the disapproval of the preliminary, initial or periodic schedule updates and subsequent rejection of payment requests until compliance is met.

SECTION 01 32 01.00 10 Page 2

In the event that the Contracting Officer directs schedule revisions and those revisions have not been included in subsequent Project Schedule revisions or updates, the Contracting Officer may withhold 10 percent of pay request amount from each payment period until such revisions to the project schedule have been made.

3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS

3.3.1 Level of Detail Required

Develop the Project Schedule to the appropriate level of detail to address major milestones and to allow for satisfactory project planning and execution. Failure to develop the Project Schedule to an appropriate level of detail will result in its disapproval. The Contracting Officer will consider, but is not limited to, the following characteristics and requirements to determine appropriate level of detail:

3.3.2 Activity Durations

Reasonable activity durations are those that allow the progress of ongoing activities to be accurately determined between update periods.

Less than 2 percent of all non-procurement activities may have Original Durations (OD) greater than 20 work days or 30 calendar days.

3.3.3 Procurement Activities

Include activities associated with the critical submittals and their approvals, procurement, fabrication, and delivery of long lead materials, equipment, fabricated assemblies, and supplies. Long lead procurement activities are those with an anticipated procurement sequence of over 90 calendar days.

3.3.4 Mandatory Tasks

Include the following activities/tasks in the initial project schedule and all updates.

a. Submission, review and acceptance of SD-01 Preconstruction Submittals (individual activity for each).

b. Submission, review and acceptance of features require design completion

c. Submission of mechanical/electrical/information systems layout drawings.

d. Long procurement activities

e. Submission and approval of O & M manuals.

f. Submission and approval of as-built drawings.

g. Submission and approval of DD1354 data and installed equipment lists.

h. Submission and approval of testing and air balance (TAB).

i. Submission of TAB specialist design review report.

SECTION 01 32 01.00 10 Page 3

j. Submission and approval of fire protection specialist.

k. Submission and approval of Building Commissioning Plan, test data, and reports: Develop the schedule logic associated with testing and commissioning of mechanical systems to a level of detail consistent with the contract commissioning requirements. All tasks associated with all building testing and commissioning will be completed prior to submission of building commissioning report and subsequent contract completion.

l. Air and water balancing.

m. Building commissioning - Functional Performance Testing.

n. Controls testing plan submission.

o. Controls testing.

p. Performance Verification testing.

q. Other systems testing, if required.

r. Contractor's pre-final inspection.

s. Correction of punch list from Contractor's pre-final inspection.

t. Government's pre-final inspection.

u. Correction of punch list from Government's pre-final inspection.

v. Final inspection.

3.3.5 Government Activities

Show Government and other agency activities that could impact progress.

These activities include, but are not limited to: approvals, environmental permit approvals by State regulators, inspections, utility tie-in, Government Furnished Equipment (GFE) and Notice to Proceed (NTP) for phasing requirements.

3.3.6 Standard Activity Coding Dictionary

Use the activity coding structure defined in the Standard Data Exchange Format (SDEF) in ER 1-1-11 . This exact structure is mandatory. Develop and assign all Activity Codes to activities as detailed herein. A template SDEF compatible schedule backup file is available on the QCS web site: http://rms.usace.army.mil .

The SDEF format is as follows:

Field Activity Code Length Description

1 WRKP 3 Workers per day

2 RESP 4 Responsible party

SECTION 01 32 01.00 10 Page 4

Field Activity Code Length Description

3 AREA 4 Area of work

4 MODF 6 Modification Number

5 BIDI 6 Bid Item (CLIN)

6 PHAS 2 Phase of work

7 CATW 1 Category of work

8 FOW 20 Feature of work*

*Some systems require that FEATURE OF WORK values be placed in several activity code fields. The notation shown is for Primavera P6. Refer to the specific software guidelines with respect to the FEATURE OF WORK field requirements.

3.3.6.1 Workers Per Day (WRKP)

Assign Workers per Day for all field construction or direct work activities, if directed by the Contracting Officer. Workers per day is based on the average number of workers expected each day to perform a task for the duration of that activity.

3.3.6.2 Responsible Party Coding (RESP)

Assign responsibility code for all activities to the Prime Contractor, Subcontractor(s) or Government agency(ies) responsible for performing the activity.

a. Activities coded with a Government Responsibility code include, but are not limited to: Government approvals, Government design reviews, environmental permit approvals by State regulators, Government Furnished Property/Equipment (GFP) and Notice to Proceed (NTP) for phasing requirements.

b. Activities cannot have more than one Responsibility Code. Examples of acceptable activity code values are: DOR (for the designer of record);

ELEC (for the electrical subcontractor); MECH (for the mechanical subcontractor); and GOVT (for USACE).

3.3.6.3 Area of Work Coding (AREA)

Assign Work Area code to activities based upon the work area in which the activity occurs. Define work areas based on resource constraints or space constraints that would preclude a resource, such as a particular trade or craft work crew from working in more than one work area at a time due to restraints on resources or space. Examples of Work Area Coding include different areas within a floor of a building, different floors within a building, and different buildings within a complex of buildings.

Activities cannot have more than one Work Area Code.

Not all activities are required to be Work Area coded. A lack of Work

SECTION 01 32 01.00 10 Page 5

Area coding indicates the activity is not resource or space constrained.

3.3.6.4 Modification Number (MODF)

Assign a Modification Number Code to any activity or sequence of activities added to the schedule as a result of a Contract Modification, when approved by Contracting Officer. Key all Code values to the Government's modification numbering system. An activity can have only one Modification Number Code.

3.3.6.5 Bid Item Coding (BIDI)

Assign a Bid Item Code to all activities using the Contract Line Item Schedule (CLIN) to which the activity belongs, even when an activity is not cost loaded. An activity can have only one BIDI Code.

3.3.6.6 Phase of Work Coding (PHAS)

Assign Phase of Work Code to all activities. Examples of phase of work are procurement phase and construction phase. Each activity can have only one Phase of Work code.

a. Code proposed fast track design and construction phases proposed to allow filtering and organizing the schedule by fast track design and construction packages.

b. If the contract specifies phasing with separately defined performance periods, identify a Phase Code to allow filtering and organizing the schedule accordingly.

3.3.6.7 Category of Work Coding (CATW)

Assign a Category of Work Code to all activities. Category of Work Codes include, but are not limited to construction submittal, procurement, fabrication, weather sensitive installation, non-weather sensitive installation, start-up, and testing activities. Each activity can have no more than one Category of Work Code.

3.3.6.8 Feature of Work Coding (FOW)

Assign a Feature of Work Code to appropriate activities based on the Definable Feature of Work to which the activity belongs based on the approved QC plan.

Definable Feature of Work is defined in Section 01 45 00.00 10 QUALITY CONTROL. An activity can have only one Feature of Work Code.

3.3.7 Contract Milestones and Constraints

Milestone activities are to be used for significant project events including, but not limited to, project phasing, project start and end activities, or interim completion dates. The use of artificial float constraints such as "zero free float" or "zero total float" are prohibited.

Mandatory constraints that ignore or effect network logic are prohibited.

No constrained dates are allowed in the schedule other than those specified herein. Submit additional constraints to the Contracting Officer for approval on a case by case basis.

SECTION 01 32 01.00 10 Page 6

3.3.7.1 Project Start Date Milestone and Constraint

The first activity in the project schedule must be a start milestone titled "NTP Acknowledged," which must have a "Start On" constraint date equal to the date that the NTP is acknowledged.

3.3.7.2 End Project Finish Milestone and Constraint

The last activity in the schedule must be a finish milestone titled "End Project."

Constrain the project schedule to the Contract Completion Date in such a way that if the schedule calculates an early finish, then the float calculation for "End Project" milestone reflects positive float on the longest path. If the project schedule calculates a late finish, then the "End Project" milestone float calculation reflects negative float on the longest path. The Government is under no obligation to accelerate Government activities to support a Contractor's early completion.

3.3.7.3 Interim Completion Dates and Constraints

Constrain contractually specified interim completion dates to show negative float when the calculated late finish date of the last activity in that phase is later than the specified interim completion date.

3.3.7.3.1 Start Phase

Use a start milestone as the first activity for a project phase. Call the start milestone "Start Phase X" where "X" refers to the phase of work.

3.3.7.3.2 End Phase

Use a finish milestone as the last activity for a project phase. Call the finish milestone "End Phase X" where "X" refers to the phase of work.

3.3.8 Calendars

Schedule activities on a Calendar to which the activity logically belongs. Develop calendars to accommodate any contract defined work period such as a 7-day calendar for Government Acceptance activities, concrete cure times, etc. Develop the default Calendar to match the physical work plan with non-work periods identified including weekends and holidays. Develop sSeasonal Calendar(s) and assign to seasonally affected activities as applicable.

If an activity is weather sensitive it should be assigned to a calendar showing non-work days on a monthly basis, with the non-work days selected at random across the weeks of the calendar, using the anticipated adverse weather delay work days provided in the Special Contract . Assign non-work days over a seven-day week as weather records are compiled on seven-day weeks, which may cause some of the weather related non-work days to fall on weekends .

3.3.9 Open Ended Logic

Only two open ended activities are allowed: the first activity "NTP Acknowledged" may have no predecessor logic, and the last activity -"End Project" may have no successor logic.

SECTION 01 32 01.00 10 Page 7

Predecessor open ended logic may be allowed in a time impact analyses upon the Contracting Officer's approval.

3.3.10 Default Progress Data Disallowed

Actual Start and Finish dates must not automatically update with default mechanisms included in the scheduling software. Updating of the percent complete and the remaining duration of any activity must be independent functions. Disable program features that calculate one of these parameters from the other. Activity Actual Start (AS) and Actual Finish (AF) dates assigned during the updating process must match those dates provided in the Contractor Quality Control Reports. Failure to document the AS and AF dates in the Daily Quality Control report will result in disapproval of the Contractor's schedule.

3.3.11 Out-of-Sequence Progress

Activities that have progressed before all preceding logic has been satisfied (Out-of-Sequence Progress) will be allowed only on a case-by-case basis subject to approval by the Contracting Officer.

Propose logic corrections to eliminate out of sequence progress or justify not changing the sequencing for approval prior to submitting an updated project schedule. Address out of sequence progress or logic changes in the Narrative Report and in the periodic schedule update meetings.

3.3.12 Added and Deleted Activities

Do not delete activities from the project schedule or add new activities to the schedule without approval from the Contracting Officer. Activity ID and description changes are considered new activities and cannot be changed without Contracting Officer approval.

3.3.13 Original Durations

Activity Original Durations (OD) must be reasonable to perform the work item. OD changes are prohibited unless justification is provided and approved by the Contracting Officer.

3.3.14 Leads, Lags, and Start to Finish Relationships

Lags must be reasonable as determined by the Government and not used in place of realistic original durations, must not be in place to artificially absorb float, or to replace proper schedule logic.

a. Leads (negative lags) are prohibited.

b. Start to Finish (SF) relationships are prohibited.

3.3.15 Retained Logic

Schedule calculations must retain the logic between predecessors and successors ("retained logic" mode) even when the successor activity(s) starts and the predecessor activity(s) has not finished (out-of-sequence progress). Software features that in effect sever the tie between predecessor and successor activities when the successor has started and the predecessor logic is not satisfied ("progress override") are not be allowed.

SECTION 01 32 01.00 10 Page 8

3.3.16 Percent Complete

Update the percent complete for each activity started, based on the realistic assessment of earned value. Activities which are complete but for remaining minor punch list work and which do not restrain the initiation of successor activities may be declared 100 percent complete to allow for proper schedule management.

3.3.17 Remaining Duration

Update the remaining duration for each activity based on the number of estimated work days it…

This is the start of the file's text. The full file is on GovTribe.