Attachment 1 -014010 Quality Juba Electrical Upgrades Final.pdf

PDF 173 KB Posted

Attached to
USAID/South Sudan Juba Compound Electrical Upgrade Federal contract opportunity
Solicitation number
72066821R00014
Issued by
US Agency for International Development South Sudan

About this file

This document contains the quality control plan requirements for a federal contract to upgrade the electrical system at a compound in Juba, South Sudan. The contractor must establish and implement an effective quality control plan that meets the minimum requirements outlined, including processes for all contractor, subcontractor, supplier and purchasing agent work. Key quality control roles and responsibilities are defined for the quality control manager and inspection personnel. The plan must incorporate ISO 9001:2015 standards and address preparatory meetings, initial and follow-up inspections, daily reporting, record keeping, and corrective action procedures. The contractor must submit the required quality control plan and personnel qualifications within 30 days of award for government review and acceptance.

View the file

Other files for this federal contract opportunity

Other files attached to USAID/South Sudan Juba Compound Electrical Upgrade, newest first.
File Type Posted
J.3.8_E1-704_Residential Compound Single Line Diagram_AMD003.pdf PDF
J.3.8_E1-701_Existing Office Single Diagram. AMD003.pdf PDF
J.3.7_E1-102_Existing Residential Site Plan_AMD003.pdf PDF
J.3.7_E1-101_Existing Office Compound Site Plan_AMD003.pdf PDF
Amendment 03 RFP 72066821R00014 Juba Elec. Upgrade..pdf PDF
J.3.8_E1-703_Office Compound Single Line Diagram_AMD003.pdf PDF
J.3.8_E1-701_Existing Office Compound Single Line Diagram_AMD003.pdf PDF
J.3.7_G001_Compound Electrical Upgrade_Cover Page_AMD003.pdf PDF
J.3.3.2_Design Intent Report Cover_AMD003.pdf PDF
RFP 72066821R00014 Juba Compound Electrical Upgrade Amendment 0002.pdf PDF
Attachment 1 -013550 ConSec Juba Electrical Upgrade Project Final.pdf PDF
Attachment 1 - 011005 Exec and Coord Juba Electrical Upgrades Final.pdf PDF
Attachment 3 - 230905 INSTRUMENTATION AND CONTROLS FOR HVAC OBO.pdf PDF
Attachment 3 - 260508 COMMON WORK ELEC-COMM.pdf PDF
Attachment 3 - 260518 LOW-VOLT POWER CONDUCTORS JAN19.pdf PDF
Attachment 3 - 261214 MEDIUM-VOLTAGE TRANSFORMERS.pdf PDF
Attachment 3 - 262725 WIRING DEVICES JAN19.pdf PDF
Attachment 3 - 262417 PANELBOARDS JAN19.pdf PDF
Attachment 3 - 262913 ENCLOSED CONTROLLERS JAN12.pdf PDF
Attachment 4 - E1-102 EXISTING RESIDENTIAL COMPOUND SITE PLAN.pdf PDF
Attachment 4 - E1-101 EXISTING OFFICE COMPOUND SITE PLAN.pdf PDF
Attachment 4 - M1-705 GENERATOR DIESEL FUEL SYSTEM PIPING SCHEMATIC.pdf PDF
Attachment 4 - M1-104 RESIDENTIAL COMPOUND ENLARGED SITE PLAN.pdf PDF
Attachment 4 - E1-701 EXISTING OFFICE COMPOUND SINGLE LINE DIAGRAM.pdf PDF
Attachment 6 - Design Intent Report.pdf PDF
Attachment 8-Past Performance Information Sheet.xlsx XLSX spreadsheet
SF1442-14b Juba Compound Electrical Upgrade.pdf PDF
Attachment 3 - 262500 ENCLOSED BUS ASSEMBLIES.pdf PDF
Attachment 1 -017825A CMMS Template v2-00-02.xlsx XLSX spreadsheet
Attachment 1 -017705 Closeout Juba Electrical Upgrades Final.pdf PDF
Attachment 1 -015005 TempFa Juba Electrical Upgrades Final.pdf PDF
Attachment 1 -013525 Safety Juba Electrical Upgrades Final.pdf PDF
Attachment 1 -013205 Scheduling Juba Electrical Upgrades Final.pdf PDF
Attachment 3 - 000000 TABLE OF CONTENTS.pdf PDF
Attachment 3 - 262313 PARALLELING SWITCHGEAR JAN20.pdf PDF
Attachment 3 - 262315 DOUBLE-ENDED SWITCHGEAR JAN17RR.pdf PDF
Attachment 3 - 262813 FUSES FL.pdf PDF
Attachment 3 - 263552 LOW-VOLTAGE AVR JAN17.pdf PDF
Attachment 4 - M1-001 GENERAL NOTES LEGEND AND ABBREVIATIONS.pdf PDF
Attachment 3 - 264315 SURGE PROTECTIVE DEVICE JAN17.pdf PDF
Attachment 4 - M1-702 EXISTING GENERATOR DIESEL FUEL SYSTEM PIPING SCHEMATIC.pdf PDF
Attachment 4 - M1-704 GENERATOR DIESEL FUEL SYSTEM PIPING SCHEMATIC.pdf PDF
Attachment 4 - M1-103 OFFICE COMPOUND ENLARGED SITE PLAN.pdf PDF
Attachment 4 - E1-702 EXISTING RESIDENTIAL COMPOUND SINGLE LINE DIAGRAM.pdf PDF
Attachment 4 - E1-703 OFFICE COMPOUND SINGLE LINE DIAGRAM.pdf PDF
Attachment 1 -017905 DemonstrationTraining Juba Electrical Upgrades Final.pdf PDF
Attachment 1 -019115 Commissioning Juba Electrical Upgrades Final.pdf PDF
Attachment 1 -017825 O and M Juba Electrical Upgrades Final.pdf PDF
Attachment 3 - 260573 OVERCURRENT PROTECTIVE DEVICE STUDY JAN17R.pdf PDF
Attachment 3 - 260915 ELECTRICAL POWER MONITOR JAN20.pdf PDF
Show all 50

USAID/South Sudan Juba Compound Electrical Upgrade has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

JUBA COMPOUND ELECTRICAL UPGRADE JUBA, SOUTH SUDAN

SECTION 014010

CONTRACTOR QUALITY CONTROL

Part 1 General

1.01 Quality Control

A. The Quality Control system used during the project construction phase must ensure that the facility meets the contract design, quality and functional standards. To this end the Contractor is required to establish, implement and maintain an effective Construction Quality Control (QC) Plan. The QC Plan must cover all construction operations both onsite and offsite, and must be keyed to the proposed construction sequence (definable features of work).

B. The Construction Quality Control Plan must include, as a minimum, all quality processes performed by the contractor, subcontractors, fabricators, suppliers, and purchasing agents. ISO 9001:2015 must be used as a base line for developing the control processes identified in Part 3 (Execution) of this specification.

C. The Contractor is responsible for quality control and must establish and maintain an effective quality control system. The quality control system must be defined by the QC Plan, which defines the Contractor’s quality policy, lines of authority and responsibility, QC personnel qualifications, and the procedures and organization necessary to produce a finished product that complies with the contract requirements.

D. The project manager and superintendents will be held accountable for the quality of work and are subject to removal at the direction of the COR for failure to comply with quality requirements specified in the contract. The Contractor’s project manager and superintendents in this context must mean the individuals with responsibility for the overall supervision of field activities for the project.

E. The Government will schedule performance audits during the construction phase to assess the Contractor’s performance against contract requirements and QC Plan implementation. The COR must use the audit results to evaluate the completed work and progress made against the contract documents and project schedule when reviewing Contractor requests for progress payments.

F. Additional requirements for Design/Build Contracts

1. The design quality control program is specified elsewhere in the contract. The Contractor’s QC Plan must include a Design Quality Control process that will ensure that the design is continually up to date with respect to field changes.

Changes to the construction documents must be reviewed and approved by the Architect/Engineer of record.

2. The construction phase design control process must be implemented and coordinated by the contractor’s field engineering staff or the QC Manager. The design control coordinator must be a registered professional engineer. The Contractor must notify the Government who will be responsible for design control coordination and name an alternate as well.

1.02 Referenced/Related Documents: The publications listed below are incorporated into the specification by reference:

A. American Society for Testing and Materials (ASTM) ASTM D 3740 (Latest edition as of contract award date) Minimum requirements for agencies engaged in the testing and/or inspection of soils and rock as used in engineering design and construction.

B. ASTM E 329 (Latest edition as of contract award date) Agencies engaged in the testing and/or inspection of materials used in construction.

C. ISO 9001:2008 Quality Management Systems requirements is a quality program document that the contractor must use to develop quality control processes for the QC Plan.

1.03 Submittals: The Contractor must submit, in accordance with Section 013305, (Construction Submittals) the following:

A. Contractor’s Quality Control Plan (QC Plan): The QC Plan must be submitted within thirty (30) calendar days after Contract Award. No work must be undertaken before QC Plan acceptance.

B. The name, qualifications (in resume format), duties, responsibilities and authorities of each person assigned to a Quality Control (QC) function must be submitted to the Government for review. The Government will reject personnel who are not qualified for the positions for which they have been proposed. Changes to QC organization staffing must only be made after acceptance by the Government of the proposed changes.

C. The Contractor must submit a Quality Control Report to the Government daily.

Reporting must begin on the first day the contractor’s forces arrive on site and must continue until the contractor’s forces have completely demobilized. Daily reports must be submitted by 8:00 the following morning and must include, at a minimum, the information discussed in this section. The report format must be accepted by the Government prior to use.

D. The Contractor must submit copies of audits and surveys of testing agency qualifications, which should include both personnel and equipment certifications.

E. Other contract provisions and attachments, including those provided by reference and amendment, apply to the requirements of this section. This Section in turn applies to the Contract Drawings and to Specification Divisions 2 through 48.

1.04 Qualifications of Quality Control Personnel

A. The Contractor Quality Control (QC) Manager must have experience implementing construction quality control programs for similar projects. The QC Manager must be on site at all times during construction and must be an employee of the prime contractor. In the event the QC Manager must be away from the site, the contractor must provide a suitable substitute, acceptable to the Government, who is familiar with the project and the QC program. The QC Manager must report to the Contractor’s home office management team and not to the Project Manager on site. His autonomy in managing and enforcing the quality control program is critical and must be reviewed and tested periodically by the Government.

B. QC Inspection and Testing personnel must be qualified in accordance with the following:

1. Current certifications as determined by the individual’s employment specialties from National or International standards organizations (AWS, ICBO, ASME, IEEE, ISO, ACI, AWWA, etc.) and,

a. College degree in engineering or architecture that is relevant to the individuals’ employment specialty. In addition, experience must include a minimum of 8 years implementing construction quality control programs for similar projects, or;

b. Completed High School education with 15 years of construction experience and successful completion of a company or union sponsored training program in the discipline to be inspected. In addition, experience must include a minimum of 10 years as a tradesman including 5 years in the performance of QC inspection activities.

1.05 Incidental Services

A. The contractor must provide incidental services by engaged QC agencies, laboratories, and consultants, and must accommodate services performed by the Government directly or by vendors engaged by the Government. Incidental services include, but are not limited to:

1. Material testing;

2. Assistance in gaining access to the works, in obtaining test samples, and in the subsequent repair of work and substrates where requested by the QC agency;

3. Temporary facilities to be utilized for testing services;

4. Handling, curing, storing and protecting test samples at the Project site.

Part 2 Products (not used)

Part 3 Execution

3.01 Content of the Construction Quality Control Plan.

A. The QC Plan must include, at a minimum, all work processes performed by the contractor, subcontractors, fabricators, suppliers, and purchasing agents.

1. A description of the quality control organization, including a chart showing lines of authority and acknowledgement that the QC staff will implement the three phase approach to construction quality control as described within.

2. The name, qualifications (in resume format), duties, responsibilities and authority of each person assigned a QC function.

3. A copy of a letter, signed by the same official of the firm who signed the contract, which describes the responsibilities of the QC Manager and delegates sufficient authorities to him to ensure he can implement the QC plan effectively.

The QC Manager must have the authority to stop the installation of work that does not comply with the contract and construction documents.

4. Procedures for scheduling, reviewing, certifying and managing submittals, including those of subcontractors, offsite fabricators, suppliers and purchasing agents. The QC Manager must be responsible for certifying that all submittals are in compliance with the contract requirements.

5. Procedures to control, verify, accept, and document each specific test required to be performed in the specification. The Contractor must provide a written report of each QC Plan inspection and test performed. The report must include the following as a minimum:

a. Project title and project number.

b. Inspection/test title, contract reference, and sequence number.

c. Dates and locations of inspections, dates of inspections/tests, and the related contract specification section number.

d. Recognized industry test methods and specifications. List all testing equipment used with serial numbers.

e. Name of testing laboratory and the individual conducting the inspection or test.

f. Ambient conditions at the time of sample-taking and inspection or test.

g. Inspection and test data, results, interpretations, and analysis of information developed.

h. Agency or individual comments and professional opinions concerning test compliance, whether work complies with requirements, and whether retesting or other testing is recommended. These comments and opinions must bear the responsible individual's signature.

i. Other data as required or implied by the nature of a particular inspection or test or by provisions in related technical sections of the contract specifications or drawing notes.

j. Where applicable, the Contractor must include a statement (Certificate of Compliance) of the agency or individual conducting the inspection or test, certifying that the materials, equipment, or services comply with the requirements of the Contract. This statement must include any observed or determined reservations in certifying such materials, equipment, or services.

6. Procedure for tracking preparatory, initial, and follow-up control phases of each definable feature of work.

7. A procedure for inspection of work and materials, including receiving inspections and control of materials staged for construction on site.

8. A corrective action procedure for identifying and controlling construction deficiencies from identification through corrective action and acceptance.

9. Document control and reporting procedures, including format.

10. A list of the definable features of work. A definable feature of work is a task which is separate and distinct from other tasks, has separate control requirements, and may be performed by different trades or disciplines.

Although each specification section may generally be considered a definable feature of work, there are frequently more than one definable feature under a particular section. This list must be included and submitted as the index to the QC Plan.

11. Procedures to control and document design changes must be included in the QC Plan. All design changes must be submitted to and accepted by the Government. A complete set of drawings used in the As-Built (red line) process will be controlled on site by the QC Manager. All red line changes to the design must be accepted by the Government. Red line changes must be initialed by the QC Manager and the COR or his designated representative.

12. Logs of test equipment calibrations.

3.02 Quality Control Meetings

A. Prior to starting site work, the Contractor must schedule a coordination meeting with the Government (COR and CO) and discuss the QC Plan. During the meeting, a mutual understanding of the plan details must be developed, including the forms for recording the QC inspections, control activities, testing, administration of the system for both onsite and offsite work, and the interrelationship of the Contractor's management and control with the Government. Meeting minutes must be prepared by the Contractor and signed by both the Contractor and the Government and the minutes must become a part of the contract record. There may be occasions when subsequent conferences will be called by either party to reconfirm mutual understandings and/or address deficiencies in the QC system or procedures that may require corrective action by the Contractor.

B. All timeframes identified in the QC Plan, for onsite and offsite activities, including interrelationships between QC Plan actions and the Government’s related actions, will be reviewed for acceptance by the Government.

C. After start of construction, the Contractor’s QC Manager must conduct weekly QC meetings at the Project Site with key Contractor staff, including the Project Manager, superintendents, and other QC staff.

D. The Contractor must notify the Government, who may elect to attend or send representatives, at least 48 hours in advance of weekly QC meetings.

E. At a minimum, the following topics must be discussed and documented at QC meetings:

1. Status of all on-going quality-related matters.

2. Deficiencies identified or rectified since previous meetings.

3. Work planned for the following two weeks and supporting QC actions.

4. Construction methods and approaches for quality construction on upcoming work items.

5. The Contractor must prepare and distribute detailed minutes of all QC meetings for signature by the Contractor's Project Manager and the COR.

3.03 Three Phase Approach to Quality Control

A. The three phases of control must be conducted by the QC Manager for each definable feature of work as follows:

1. Preparatory Phase: This phase must be performed prior to beginning work on each definable feature of work; after all required plans, documents, materials are accepted. A preparatory meeting must be called by the QC Manager to demonstrate that the Contractor has all the necessary materials, equipment and personnel to start a definable feature of work. Agenda items must include:

a. Review of the applicable specifications.

b. Review of the contract drawings.

c. Confirmation that all materials and/or equipment have been tested and submittals have been received and accepted.

d. Review of provisions that have been made to provide required control inspection and testing.

e. Examination of the work area to ensure that all required preliminary work has been completed and is in compliance with the contract.

f. Physical examination of required materials, equipment, and sample work to ensure that they are on hand, conform to accepted shop drawings or submitted data, and are properly stored.

g. Review of the applicable safety requirements to ensure they are met.

h. Discussion of procedures for controlling quality of the work, including repetitive deficiencies.

i. Discussion and scheduling for the initial control phase.

j. The Contractor will provide to the COR the agenda 48 hours in advance of the preparatory control meeting. This meeting must be conducted by the QC Manager and attended by the superintendent and foremen responsible for the definable feature of work and other QC personnel as applicable. The results of the preparatory phase activities must be documented by separate minutes prepared by the QC Manager and attached to the daily QC report. The responsible superintendent and foremen must instruct applicable craftsmen as to the acceptable level of workmanship required by the contract specifications.

2. Initial Phase: This phase must be accomplished at the beginning of field construction of a definable feature of work. This phase must be held at the work site with a demonstration of how the work is to be performed in order to meet the contract requirements. If mock-ups are required for a definable feature of work, they must have been completed far enough in advance of the Initial Phase that all materials must have hardened or dried and must be in such condition as the finished product will achieve at completion. Agenda items must include:

a. Review the work to ensure that it is in full compliance with contract requirements as discussed in the Preparatory Phase meeting. The minutes of the preparatory meeting must be reviewed as necessary.

b. Verify the adequacy of controls to ensure full contract compliance.

Verify required control inspections and testing.

c. Establish the level of workmanship and verify that it meets minimum acceptable workmanship standards. Compare with required samples and mock-ups as appropriate.

d. Resolve all differences.

e. Review safety requirements to include compliance with and possible revision of the safety plan and activity hazard analysis. Review the activity hazard analysis with all workers. Ensure that the safety control barriers and/or signs have been correctly installed.

f. The initial phase should be repeated anytime a new crew begins work on a definable feature of work or any time acceptable quality standards are not being met.

g. The Contractor will provide the agenda to the COR at least 48 hours in advance of beginning the initial phase. Separate minutes for this phase must be prepared by the QC Manager and attached to the daily QC report. The exact location of the initial phase must be indicated for future reference and comparison with follow-up phases.

3. Follow-up Phase:

Daily checks must be performed to ensure that control activities, including control testing, are providing continued compliance with contract requirements until completion of the particular feature of work. The checks must be made a matter of record in the QC documentation. Final follow-up checks must be conducted and all deficiencies corrected prior to starting additional features of work which may be affected by the deficient work. The Contractor must not build upon nor conceal deficient work.

B. Completion Inspection (also known as Schedule of Defects):

1. Punch-List Inspection:

At completion of all work or any increment thereof, the contractor must conduct joint inspections of the work with the government. The contractor must record all deficiencies and work identified as not conforming to the plans and specifications, and a list of the findings, by location, must be submitted to the Government within two days after each joint inspection. The list of these findings must constitute the punch-list. At completion of all punch-list work or any increment thereof, the contractor must conduct a joint re-inspection with the Government to verify completion of the punch-list work. Both the contractor and the Government must confirm mutual agreement of completion by signing the punch-list and indicating that each item on the punch-list is complete. The contractor must submit two hardcopies of the signed punch-list and an electronic copy of the signed list in xxx.pdf format.

2. Final Acceptance Inspection:

No later than six (6) weeks after substantial completion the contractor must conduct the joint, final acceptance inspection with the Government. The contractor must provide a minimum of 14-days advance written notice to the Government and certify the work must be complete prior to commencing the final acceptance inspection.

During the joint, final acceptance inspection the contractor must record all deficiencies and all work identified as not conforming to the plans and specifications. A list of the findings, by location, must be submitted to the Government within two days after the inspection. The list of these findings must constitute the list of final acceptance defects. The contractor must immediately complete all work on the list of final acceptance defects. At completion of all items on the list of final acceptance defects, the contractor must conduct a joint re-inspection with the Government to verify completion. Both the contractor and the Government must confirm mutual agreement of completion by signing the list of final acceptance defects and indicating that each item is complete. The contractor must submit two hardcopies of the signed list of final acceptance defects and an electronic copy of the signed list in xxx.pdf format.

3.04 Daily Reporting

A. The Contractor must provide QC Daily Reports that provide factual evidence that required quality control activities and/or tests have been performed. These records must include the work of subcontractors and suppliers and must be on an acceptable form that includes, as a minimum, the following information:

1. Contractor/subcontractor and their area of responsibility.

2. Work performed each day, giving location, description, and by whom performed. Work conducted on building structures must be located by column line.

3. Test and/or control activities performed with results and references to specifications and drawings requirements. The control phase should be identified Preparatory, Initial, or Follow-up.

4. List deficiencies noted along with corrective action.

5. Quantity of materials received at the site with statement as to acceptability, storage, and reference to contract specifications and drawings. Documents used to certify materials and equipment should be traceable to the material or equipment by a unique identification number i.e. heat number, serial number, etc.

6. Submittals reviewed, with contract reference, by whom reviewed, and action taken.

7. Off-site surveillance activities, including actions taken.

8. Job safety evaluations stating what was checked, results, and instructions or corrective actions taken.

9. Instructions given/received and conflicts in plans and/or Specifications.

10. The QC Daily Report must indicate a description of trades working on the project and where; the number of personnel working; weather conditions encountered; and any delays encountered. These records must cover both conforming and deficient features and must include a statement that equipment and materials incorporated in the work and workmanship comply with the contract. The original and one copy of these records in report form must be furnished to the Government daily by 8:00am the following day.

Reports must be submitted for days on which no work was performed.

Attached to the daily reports must be copies of test reports, inspection reports, and reports prepared by subordinate quality control personnel.

3.05 RESTORATION AND PROTECTION

A. Restoration: Upon completion of inspections, sampling, testing, and correction of defects, the Contractor must repair damaged work and substrates and restore finishes to eliminate deficiencies in visual and performance qualities. This restoration must be in compliance with the Contract Documents.

B. Continued Protection: Continued protection of completed work must be provided throughout the construction period and protective measures must be monitored in relation to construction activity.

3.06 Records

A. The Contractor must maintain a complete record of QC Plan actions, ready for Governments examination at any time. Defects, deficiencies, and non-compliance must be highlighted along with corrective actions and any reconstruction completed, to be completed, or recommended for acceptance by the Government.

END OF SECTION