Attachment 0009 - Pre-TRR Checklist.pdf
PDF 174 KB Posted
- Solicitation number
- W56HZV21R0185
About this file
This document contains a pre-test readiness review (Pre-TRR) checklist and details of a related federal contract opportunity for a Cold Weather All-Terrain Vehicle (CATV).
The Pre-TRR checklist assesses the contractor's readiness to conduct formal vehicle testing, including verification of vehicle configuration, completion of required documentation, correction of failures from preliminary testing, certification of vehicles and materials, identification of required test support, acceptance of safety assessments, and confirmation that the delivery schedule is on track. It will be considered complete when all items are satisfactorily addressed and there are no unresolved issues.
The federal contract opportunity is a solicitation from the Department of the Army Materiel Command TACOM Life Cycle Management Command for a follow-on FAR-based production contract for the CATV. It seeks a single-award, firm-fixed-price requirements contract with a potential total term of seven years, consisting of production units, spare parts, and contractor logistics support.
View the file
Other files
Show all 43
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
UNCLASSIFIED
Attachment 0009
Pre-TRR Checklist
Distribution Statement A – Approved for Public Release; distribution unlimited
1 PURPOSE
The TRR process for the Cold Weather All-Terrain Vehicle (CATV) Product Lead (PL) will assess the readiness of the CATV to enter the formal testing event. The Contractor Performed Pre-Test Readiness Review (Pre-TRR) and the TRR will assesses the status of planning for and capability to conduct a given test event, to include available resources and other requirements. This process allows key CATV leadership and stakeholders to assess whether CATV test vehicles, personnel, ranges, and test resources are ready to be committed to Government Vehicle Testing with safe and manageable risks. The process begins with a meeting with the Contractor and concludes with a formal Government TRR meeting and a recommendation which is provided to the CATV Product Lead to proceed (or not) into Government testing.
1.1 COMPLETION OF CHECKLIST
The Pre-TRR Checklist will be considered completed when the items in the Checklist have been satisfactorily completed, key issues addressed, and there are no unresolved items.
UNCLASSIFIED Page 3 of 4
Pre-Test Readiness Review (PreTRR) Checklist Criteria Responsibility Status Comment/Mitigation 1 Introductions/Purpose
1.1 Test purpose Government
2 Vehicle Configuration
2.1 Configuration of the system is consistent with the defined product baseline. Contractor 3 CDRLs Status
3.1 All CDRL submissions and updates required have been delivered. Contractor 4 System-Level Verification Test Results/Corrective Actions
4.1 Break In tests are complete Contractor
4.2 All known residual catastrophic failures and safety issues identified during break in testing have been corrected. Contractor
5 Government Inspection Results/Certifications
5.1 Vehicles have been prepared for shipment. Contractor
5.2 Vehicle, certifications, and analyses have been completed and submitted Contractor
5.3 Unapproved Hazardous Materials are not present in the CATV, IAW the materials detailed section of the contract addressing Hazardous Materials Management.
Contractor
6 Test Support
6.1 FSRs /SMEs are identified and ready to support testing at designated locations (which will be identified at the TRR) Contractor
6.2 Logistics limitations and risks associated with them have been identified and mitigated. Contractor
6.3 All BII items are complete and ready for shipment with the vehicle. Contractor
6.4 Tester Training packages/plans have been reviewed, approved, and made available. Contractor
6.5 Operators’ Manuals are complete, delivered, and adequate to support tests. Contractor
6.6 Foreign visitor visit requests approved Contractor
6.7 COVID related Restrictions to Movement (ROM) Exception to Policy (ETP) approved, or ROM plan in place if required Contract
6.8 Vendor VDLS access request (or other plan for how contractor will access TIRs)
7 Safety Assessment Reports/Concerns
7.1 Contractors Safety Assessment has been completed and accepted by the
Program Office Contractor
UNCLASSIFIED Page 4 of 4
Pre-Test Readiness Review (PreTRR) Checklist
8 System Delivery Schedule
8.1 Delivery schedule has been provided and is on track with contract requirements. Contractor
8.2 Vehicles: arrival dates and offload support requirements coordinated with test site Contractor
8.3 BII: all required BII on site in time to support start of test Contractor
8.4 SSP: sufficient spares on site in time to support start of test, delivery plan for additional spares as required in place Contractor
8.5 Any required special tools identified and available Contractor
8.6 Vendor supplied POLs and consumables available Contractor
9 Facilities
9.1 Vendor Admin spaces coordinated/ confirmed with test sites Contractor
Test Readiness Review (TRR) Checklist
10 TRR Entrance Criteria
10.1 Action Items from prior technical reviews have been closed. Government
10.2 Program Manager's and T&E WIPT's determination that preliminary, functional, and pre-qualification test evaluation results form a satisfactory basis to initiate formal, system-level testing
Government
10.3 Cybersecurity assessment (RMF step 4) is underway with final test plans in place Government
| 1 Purpose |
| 1.1 Completion of Checklist |