Attachment 0002 - Integrated Master Schedule.pdf

PDF 196 KB Posted

Attached to
Cold Weather All-Terrain Vehicle (CATV) - Solicitation
Solicitation number
W56HZV21R0185
Issued by

About this file

This document contains an integrated master schedule (IMS) template for a federal contract and details of a related solicitation opportunity. The IMS template requires submission in PDF format with a 13-column table in landscape orientation including columns for line item, task name, duration, start, finish, actual start, actual finish, baseline start, baseline finish, predecessors, successors and total slack. The header must identify the contract data requirements list and data date.

The solicitation is for a follow-on production contract of an articulated tracked Cold Weather All-Terrain Vehicle capable of amphibious operations in extreme cold down to -50 degrees Fahrenheit and transportable by sling load. The Department of the Army Materiel Command TACOM Life Cycle Management Command seeks a single-award firm fixed price commercial requirements contract with potential total term of seven years, consisting of production units, spare parts and contractor logistics support.

View the file

Other files

File Type Posted
W56HZV21R0185_Conformed Copy 24 MAR 2022.pdf PDF
W56HZV21R0185-0004.pdf PDF
W56HZV21R0185-0005.pdf PDF
W56HZV21R0185_Conformed Copy 26 MAY 2022.pdf PDF
W56HZV21R0185-0003.pdf PDF
W56HZV21R0185 Conformed 24 FEB 22.pdf PDF
W56HZV21R0185 Conformed 17 FEB 22.pdf PDF
W56HZV21R0185-0002.pdf PDF
Attachment 0034 - Assertions.xlsx XLSX spreadsheet
W56HZV21R0185 Conformed 4FEB2022.pdf PDF
W56HZV21R0185-0001 4 FEB 2022 Signed.pdf PDF
Attachment 0001 - CATV Performance Specification 1FEB2021.pdf PDF
Attachment 0030 - End Item-Specific Special Tool Kit Component List.xlsx XLSX spreadsheet
Attachment 0007 - PDR Checklist 17DEC2021.pdf PDF
Attachment 0001 - CATV Perfromance Specification 6JAN2022.pdf PDF
Attachment 0026 - Government Furnished Property (GFP).pdf PDF
Attachment 0008 - FDR Checklist 17DEC2021.pdf PDF
Attachment 0024 - Advanced Manufacturing Candidate List.xlsx XLSX spreadsheet
Attachment 0019 - Provisioning Requirements Statement.pdf PDF
Attachment 0014 - TIR and FACAR Report Data.pdf PDF
Attachment 0012 - CATV Systems Specification Sheet.xlsx XLSX spreadsheet
W56HZV21R0185 CATV RFP Final Signed 14 JAN 2022.pdf PDF
Attachment 0009 - Pre-TRR Checklist.pdf PDF
Attachment 0022 - SESAME Guide.pdf PDF
Attachment 0015 - WindChill ECP Process.pdf PDF
Attachment 0028 - ARMY CDRL Module OEM Contractor Training FEB 2019.pdf PDF
Attachment 0032 - CATV Performance Specification Report.xlsx XLSX spreadsheet
Attachment 0005 - PEO CSCSS Armoring Systems SCG_2017.pdf PDF
Attachment 0020 - Data Reqmts Form for Acq Requirement Package (ARP).pdf PDF
Attachment 0029 - MPVS CDRL Module and ACE Submissions.pdf PDF
Attachment 0021 - CATV User Evaluation Plan and Soldier Survey.pdf PDF
Attachment 0027 - Welding Standards.pdf PDF
Attachment 0031 Pricing Workbook Final.xlsx XLSX spreadsheet
Attachment 0006 - PEO CSCSS OPSEC Program Oct 2016 SIGNED.pdf PDF
Attachment 0017 - HMMR Template.xlsx XLSX spreadsheet
Attachment 0010 - TRR Checklist.pdf PDF
Attachment 0013 - Risk Mgt Scoring Criteria and Report Template.xlsx XLSX spreadsheet
Attachment 0003 - Applicable Documents 10 DEC 21.pdf PDF
Attachment 0016 - Request for Use of Prohibited Material.docx DOCX document
Attachment 0023 - Army Advanced Methods_Materials_and_Equipment.pdf PDF
Attachment 0011 - Transportability Data Sheet.xlsx XLSX spreadsheet
Attachment 0025 Specifically Negotiated License Agreement for Advanced Manufacturing (SNL-AM).pdf PDF
Attachment 0018 - FMECA Requirements.pdf PDF
Show all 43

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

UNCLASSIFIED

Attachment 0002

Integrated Master Schedule in.pdf Format 11 May 2021

Distribution Statement A – Approved for Public Release; distribution unlimited

Attachment 0002

IMS .pdf Format Requirements:

PDF export shall be submitted as a 13 column table in 11X 17 landscape orientation. The following columns shall be depicted in the table in this order:

Column 1: Line item (I.D) Column 2: Task name Column 3: Duration Column 4: Start Column 5: Finish Column 6: Actual Start Column 7: Actual Finish Column 8: Baseline Start* Column 9: Baseline Finish* Column 10: Predecessors Column 11: Successors Column 13: Total Slack

Header shall identify the CDRL and the Data Date of the IMS at the time of the status update

Figure 1

*Baseline shall be the most recent Government approved baseline.

File details come from the government source that posted it. Updated .