About this file

This document is a specification for the renovation of the Albion Armory, a state and local contract opportunity for the State of Michigan. The project involves repairing or replacing defective work in the armory, including the installation of new manufactured plastic-laminate-clad casework and countertops. The project requires the submission of product data, shop drawings, and samples, and the work must be performed by a qualified fabricator. The document outlines the requirements for delivery, storage, handling, and installation of the materials, as well as the environmental conditions and field measurements needed.

The specification also includes requirements for common work results for the plumbing systems, including piping, hangers and supports, identification, and insulation. This includes the installation of general-duty valves, plumbing piping and equipment, and insulation materials such as calcium silicate, glass fiber, and mineral fiber. The document provides details on the approved manufacturers, materials, and installation methods for these plumbing components.

View the file

Other files

File Type Posted
Addendum 2 270500 DATA COMMUNICATION SYSTEM 220428.docx DOCX document
Addendum 5 21187.pdf PDF
MtgAttend1 - 21187.pdf PDF
Advertisement 21187.pdf PDF
Addendum No.2 08122022 - 21187.pdf PDF
21-046 Albion Armory - A0.0 - Cover Sheet.pdf PDF
21-046 Albion Armory Civil Drawings.pdf PDF
MtgAttend1 - 21187_REVISED.pdf PDF
Addendum 3 06 Wood Plastics and Composites 21187.pdf PDF
Addendum No.6 08222022 - 21187.pdf PDF
Addendum 1 - 21187.pdf PDF
Albion Armory MEP Set.pdf PDF
Albion Armory Specification 14 of 15.pdf PDF
Albion Armory Specification 12 of 15.pdf PDF
Addendum 3 07 Thermal and Moisture Protection 21187.pdf PDF
Albion Armory Specification 3 of 15.pdf PDF
Addendum 2 M-303 - MECHANICAL CONTROLS DIAGRAMS.pdf PDF
Albion Armory Specification 1 of 15.pdf PDF
Albion Armory Specification 7 of 15.pdf PDF
Addendum 3 21187.pdf PDF
Addendum 3 05 Metals 21187.pdf PDF
Albion Armory Draft Logs 11-23-21.pdf PDF
Albion Armory Specification 8 of 15.pdf PDF
Addendum 2 M-301 - MECHANICAL SCHEDULES_ —
Albion Armory Specification 4 of 15.pdf PDF
Addendum 3 08 Openings 21187.pdf PDF
Albion Armory Specification 6 of 15.pdf PDF
Specifications 21187.pdf PDF
Addendum 4 21187.pdf PDF
21-046 Albion Armory Architectural A4-S1 Set.pdf PDF
Albion Armory Draft Map 11-23-21.pdf PDF
Albion Armory Specification 13 of 15.pdf PDF
Albion Armory Specification 9 of 15.pdf PDF
Albion Armory Specification 15 of 15.pdf PDF
Albion Armory Specification 10 of 15.pdf PDF
Albion Armory Specification 2 of 15.pdf PDF
Albion Armory Specification 5 of 15.pdf PDF
21-046 Albion Armory Architectural A0-A3 Set.pdf PDF
Addendum 2 E-301 - ELECTRICAL DATA.pdf PDF
Show all 39

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RENOVATE ARMORY - ALBION ARMORY

A. Repair or remove and replace defective work as directed on completion of installation.

B. Clean finished surfaces, touch up as required, and remove or refinish damaged or soiled areas to match original factory finish, as approved by Architect.

END OF SECTION 123216

MANUFACTURED PLASTIC-LAMINATE-CLAD

CASEWORK

123216 - 6

SECTION 123623.13 - PLASTIC-LAMINATE-CLAD COUNTERTOPS

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1.2 ACTION SUBMITTALS

A. Product Data: For each type of product.

B. Shop Drawings: For plastic-laminate-clad countertops.

1.Include plans, sections, details, and attachments to other work. Detail fabrication and installation, including field joints.

2.Show locations and sizes of cutouts and holes for items installed in plastic-laminate-clad countertops.

C. Samples: Plastic laminates in each type, color, pattern, and surface finish required in manufacturer's standard size.

D. Samples for Initial Selection: For plastic laminates.

1.3 QUALITY ASSURANCE

A. Fabricator Qualifications: Shop that employs skilled workers who custom fabricate products similar to those required for this Project and whose products have a record of successful in-service performance.

1.4 DELIVERY, STORAGE, AND HANDLING

A. Deliver countertops only after casework and supports on which they will be installed have been completed in installation areas.

B. Store countertops in areas where environmental conditions comply with requirements specified in "Field Conditions" Article.

C. Keep surfaces of countertops covered with protective covering during handling and installation.

1.5 FIELD CONDITIONS

A. Environmental Limitations without Humidity Control: Do not deliver or install countertops until building is enclosed, wet-work is complete, and HVAC system is operating and maintaining temperature and relative humidity at levels planned for building occupants during the remainder of the construction period.

B. Field Measurements: Where countertops are indicated to fit to other construction, verify dimensions of other construction by field measurements before fabrication and indicate measurements on Shop Drawings. Coordinate fabrication schedule with construction progress to avoid delaying the Work.

PART 2 - PRODUCTS

2.1 PLASTIC LAMINATE

PLASTIC-LAMINATE-CLAD COUNTERTOPS 123623.13 - 1

A.Manufacturer: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following:

1.Wilsonart

2. Nevamar

3. Formica

See Drawings finish schedule sheet A6.0 for selection color and style

2.2 WOOD MATERIALS

A. Wood Products: Provide materials that comply with requirements of referenced quality standard unless otherwise indicated.

1.Wood Moisture Content: 5 to 10 percent.

B. Composite Wood Products: Provide materials that comply with requirements of referenced quality standard for each type of countertop and quality grade specified unless otherwise indicated.

2.3 MISCELLANEOUS MATERIALS

A. Adhesives: Do not use adhesives that contain urea formaldehyde.

B. Adhesive for Bonding Plastic Laminate: Unpigmented contact cement.

1.Adhesive for Bonding Edges: Hot-melt adhesive.

C. Installation Adhesive:

1.Adhesives shall have a VOC content of 70 g/L or less.

2.4 FABRICATION

A. Sand fire-retardant-treated wood lightly to remove raised grain on exposed surfaces before fabrication.

B. Fabricate countertops to dimensions, profiles, and details indicated. Provide front and end overhang of 1 inch over base cabinets. Ease edges to radius indicated for the following:

1.Solid-Wood (Lumber) Members: 1/16 inch unless otherwise indicated.

C. Complete fabrication, including assembly, to maximum extent possible before shipment to Project site. Disassemble components only as necessary for shipment and installation. Where necessary for fitting at site, provide ample allowance for scribing, trimming, and fitting.

D. Shop cut openings to maximum extent possible to receive appliances, plumbing fixtures, electrical work, and similar items. Locate openings accurately, and use templates or roughing-in diagrams to produce accurately sized and

PLASTIC-LAMINATE-CLAD COUNTERTOPS 123623.13 - 2

shaped openings. Sand edges of cutouts to remove splinters and burrs.

1.Seal edges of cutouts by saturating with varnish.

PART 3 - EXECUTION

3.1 PREPARATION

A. Before installation, condition countertops to average prevailing humidity conditions in installation areas.

B. Before installing countertops, examine shop-fabricated work for completion and complete work as required, including removal of packing.

3.2 INSTALLATION

A. Grade: Install countertops to comply with same grade as item to be installed.

B. Assemble countertops and complete fabrication at Project site to the extent that it was not completed in the shop.

1.Provide cutouts for appliances, plumbing fixtures, electrical work, and similar items. Locate openings accurately, and use templates or roughing-in diagrams to produce accurately sized and shaped openings. Sand edges of cutouts to remove splinters and burrs.

2.Seal edges of cutouts by saturating with varnish.

C. Field Jointing: Where possible, make in the same manner as shop jointing, using dowels, splines, adhesives, and fasteners recommended by manufacturer. Prepare edges to be joined in shop so Project-site processing of top and edge surfaces is not required. Locate field joints where shown on Shop Drawings.

1.Secure field joints in countertops with concealed clamping devices located within 6 inches of front and back edges and at intervals not exceeding 24 inches. Tighten in accordance with manufacturer's written instructions to exert a constant, heavy-clamping pressure at joints.

D. Scribe and cut countertops to fit adjoining work, refinish cut surfaces, and repair damaged finish at cuts.

E. Countertop Installation: Anchor securely by screwing through corner blocks of base cabinets or other supports into underside of countertop.

1.Install countertops level and true in line. Use concealed shims as required to maintain not more than a 1/8-inch-in-96-inches variation from a straight, level plane.

PLASTIC-LAMINATE-CLAD COUNTERTOPS 123623.13 - 3

2.Secure backsplashes to tops with concealed metal brackets at 16 inches o.c. and to walls with adhesive.

3.Seal joints between countertop and backsplash, if any, and joints where countertop and backsplash abut walls with mildew-resistant silicone sealant or another permanently elastic sealing compound recommended by countertop material manufacturer.

3.3 ADJUSTING AND CLEANING

A. Repair damaged and defective countertops, where possible, to eliminate functional and visual defects. Where not possible to repair, replace countertops. Adjust joinery for uniform appearance.

B. Clean countertops on exposed and semiexposed surfaces.

C. Protection: Provide Kraft paper or other suitable covering over countertop surfaces, taped to underside of countertop at a minimum of 48 inches o.c. Remove protection at Substantial Completion.

END OF SECTION 123623.13

PLASTIC-LAMINATE-CLAD COUNTERTOPS 123623.13 - 4

RENOVATE ARMORY – ALBION ARMORY

COMMON WORK RESULTS FOR PLUMBING 22 0500 - 1

SECTION 22 0500 - COMMON WORK RESULTS FOR PLUMBING

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. This Section includes the following:

1. Piping materials and installation instructions common to most piping systems.

2. Transition fittings.

3. Dielectric fittings.

4. Mechanical sleeve seals.

5. Sleeves.

6. Escutcheons.

7. Grout.

8. Plumbing demolition.

9. Equipment installation requirements common to equipment sections.

10. Painting and finishing.

11. Concrete bases.

12. Supports and anchorages.

1.3 CODES, ORDINANCES, PERMITS, FEES OR ASSESSMENTS

A. All work and materials shall be installed in accordance with the standards as described by local and state codes or ordinances including the rules of the National Plumbing Code, National Board of Fire Underwriters, American Standards Association, and with the prevailing rules and regulations pertaining to adequate protection and guarding of any moving parts or otherwise hazardous locations.

B. Should the drawings or specifications call for sizes and grades different than required by the governing code, this Contractor shall furnish and install the larger size of the higher grade.

C. In addition, this Contractor shall give all notices, file all drawings, obtain all necessary approv-als, obtain all permits and pay for all fees, deposits and expenses required for installation of all work under this contract, as stated therein and in the General Requirements. In such instances where permits are not required, the contractor shall engage a third party, preferably the local official, to inspect the work.

D. In addition to all applicable federal, state and local codes, the standards and codes listed below shall apply to all mechanical work. Where standards or codes are mentioned in these specifica-tions, the latest edition or revision shall be followed; hence, the specified numbers may be su-perseded by new numbers.

1. American National Standard Institute (ANSI)

2. American Society for Testing Materials (ASTM)

3. American Society of Mechanical Engineers (ASME)

COMMON WORK RESULTS FOR PLUMBING 22 0500 - 2

4. American Water Works Association (AWWA)

5. Air Moving and Condition Association, Inc. (AMCA)

6. National Electrical Manufacturer's Association (NEMA)

7. ANSI Code of Pressure Piping and Unfired Pressure Vessels

8. Cast Iron Soil Pipe Institute

9. Occupational Safety and Health Acts (OSHA)

10. State of Michigan Plumbing Code

11. State of Michigan Building Code

12. ICC International Plumbing Code

13. All local codes.

1.4 DEFINITIONS

A. Finished Spaces: Spaces other than mechanical and electrical equipment rooms, furred spaces, pipe chases, unheated spaces immediately below roof, spaces above ceilings, unexcavated spaces, crawlspaces, and tunnels.

B. Exposed, Interior Installations: Exposed to view indoors. Examples include finished occupied spaces and mechanical equipment rooms.

C. Exposed, Exterior Installations: Exposed to view outdoors or subject to outdoor ambient temperatures and weather conditions. Examples include rooftop locations.

D. Concealed, Interior Installations: Concealed from view and protected from physical contact by building occupants. Examples include above ceilings and in chases.

E. Concealed, Exterior Installations: Concealed from view and protected from weather conditions and physical contact by building occupants but subject to outdoor ambient temperatures.

Examples include installations within unheated shelters.

F. The following are industry abbreviations for plastic materials:

1. CPVC: Chlorinated polyvinyl chloride plastic.

2. PE: Polyethylene plastic.

3. PVC: Polyvinyl chloride plastic.

G. The following are industry abbreviations for rubber materials:

1. EPDM: Ethylene-propylene-diene terpolymer rubber.

2. NBR: Acrylonitrile-butadiene rubber.

H. Product Data:

1. Description of function, normal operating characteristics and limitations, performance curves, engineering data and tests and complete nomenclature and commercial numbers of replacement parts.

2. Manufacturer’s printed operating procedures to include start-up, break-in and routine and normal operating instructions; regulation, control, stopping, shutdown and emergency instructions; and summer and winter operating instructions.

3. Maintenance procedures for routine preventative maintenance and troubleshooting;

disassembly, repair and reassembly; aligning and adjusting instructions.

COMMON WORK RESULTS FOR PLUMBING 22 0500 - 3

4. Servicing instructions and lubrication charts and schedules.

1.5 SUBMITTALS

A. Product Data: For the following:

1. Transition fittings.

2. Dielectric fittings.

3. Mechanical sleeve seals.

4. Escutcheons.

5. Valves, strainers, backflow devices, etc..

6. Plumbing fixtures, supports and accessories.

B. Welding certificates.

1.6 RECORD DOCUMENTS

A. Prepare record documents in accordance with the requirements in Division 1 Section, Project Closeout. In addition to the requirements specified in Division 1, indicate the following in-stalled conditions:

1. Mains and branches of piping systems, with valves and control devices located and num-bered, concealed unions located, and with items requiring maintenance located (i.e., traps, strainers, expansion compensators, tanks, etc.). Valve location diagrams, complete with valve tag chart. Indicate actual inverts and horizontal locations of underground pip-ing.

2. Approved substitutions, Contract Modifications, and actual equipment and materials in-stalled.

3. Contract Modifications, actual equipment and materials installed.

1.7 MAINTENANCE MANUALS

A. Prepare maintenance manuals in accordance with Division 1 Section, Project Closeout. In ad-dition to the requirements specified in Division 1, include the following information for equip-ment items:

1. Description of function, normal operating characteristics and limitations, performance curves, engineering data and tests, and complete nomenclature and commercial numbers of replacement parts.

2. Manufacturer's printed operating procedures to include start-up, break-in, and routine and normal operating instructions; regulation, control, stopping, shutdown, and emergency instructions; and summer and winter operating instructions.

3. Maintenance procedures for routine preventative maintenance and troubleshooting; disas-sembly, repair, and reassembly; aligning and adjusting instructions.

4. Servicing instructions and lubrication charts and schedules.

1.8 SUBSTITUTIONS

A. This Contractor shall be considered liable for all added costs both to himself and others (includ-ing those costs as incurred by the Engineer, for redesigning or redrawing) resultant from the substitution of products not the basis of the design.

COMMON WORK RESULTS FOR PLUMBING 22 0500 - 4

B. This Contractor shall be responsible for the verification of adequate space (considering dimen-sions, required clearances, weights, and roughing-in requirements) for the installation of items or systems not the basis of the design. He shall be responsible for advising all other trades. He shall submit revised drawing layouts for the approval of the Engineer and shall not proceed without this approval.

1.9 QUALITY ASSURANCE

A. Steel Support Welding: Qualify processes and operators according to AWS D1.1, "Structural Welding Code--Steel."

B. Steel Pipe Welding: Qualify processes and operators according to ASME Boiler and Pressure Vessel Code: Section IX, "Welding and Brazing Qualifications."

1. Comply with provisions in ASME B31 Series, "Code for Pressure Piping."

2. Certify that each welder has passed AWS qualification tests for welding processes involved and that certification is current.

C. Electrical Characteristics for Plumbing Equipment: Equipment of higher electrical characteristics may be furnished provided such proposed equipment is approved in writing and connecting electrical services, circuit breakers, and conduit sizes are appropriately modified. If minimum energy ratings or efficiencies are specified, equipment shall comply with requirements.

1.10 DELIVERY, STORAGE, AND HANDLING

A. Deliver pipes and tubes with factory-applied end caps. Maintain end caps through shipping, storage, and handling to prevent pipe end damage and to prevent entrance of dirt, debris, and moisture.

B. Store plastic pipes protected from direct sunlight. Support to prevent sagging and bending.

1.11 COORDINATION

A. Coordinate with all other trades for pipe spaces, chases, slots, and openings in building structure during progress of construction, to allow for plumbing installations.

B. Coordinate installation of required supporting devices and set sleeves in poured-in-place concrete and other structural components as they are constructed.

C. Coordinate requirements for access panels and doors for fire-suppression items requiring access that are concealed behind finished surfaces. Access panels and doors to be equal to Milcor or Vent-Lock, 10” x 18” steel access, flush type for mounting in walls or ceilings with prime coating, ready for field painting.

Access panels shall be provided by Plumbing Contractor for installation by General Trades.

Locate so as to provide access for all required maintenance. Provide more than one where required. Provide UL labeled panels where installed in rated walls or ceilings, and shall match the rating of the structure.

COMMON WORK RESULTS FOR PLUMBING 22 0500 - 5

PART 2 - PRODUCTS

2.1 MANUFACTURERS

A. In other Part 2 articles where subparagraph titles below introduce lists, the following requirements apply for product selection:

1. Manufacturers: Subject to compliance with requirements, provide products by the manufacturers specified, and all others by voluntary alternate.

2.2 PIPE, TUBE, AND FITTINGS

A. Refer to individual Division 22 piping Sections for pipe, tube, and fitting materials and joining methods.

B. Pipe Threads: ASME B1.20.1 for factory-threaded pipe and pipe fittings.

2.3 JOINING MATERIALS

A. Refer to individual Division 22 piping Sections for special joining materials not listed below.

B. Pipe-Flange Gasket Materials: Suitable for chemical and thermal conditions of piping system contents.

1. ASME B16.21, nonmetallic, flat, asbestos-free, 1/8-inch maximum thickness unless thickness or specific material is indicated.

a) Full-Face Type: For flat-face, Class 125, cast-iron and cast-bronze flanges.

b) Narrow-Face Type: For raised-face, Class 250, cast-iron and steel flanges.

2. AWWA C110, rubber, flat face, 1/8 inch thick, unless otherwise indicated; and full-face or ring type, unless otherwise indicated.

C. Flange Bolts and Nuts: ASME B18.2.1, carbon steel, unless otherwise indicated.

D. Plastic, Pipe-Flange Gasket, Bolts, and Nuts: Type and material recommended by piping system manufacturer, unless otherwise indicated.

E. Solder Filler Metals: ASTM B 32, lead-free alloys. Include water-flushable flux according to

ASTM B 813.

F. Brazing Filler Metals: AWS A5.8, BCuP Series, copper-phosphorus alloys for general-duty brazing, unless otherwise indicated; and AWS A5.8, BAg1, silver alloy for refrigerant piping, unless otherwise indicated.

G. Welding Filler Metals: Comply with AWS D10.12 for welding materials appropriate for wall thickness and chemical analysis of steel pipe being welded.

H. Solvent Cements for Joining Plastic Piping:

1. CPVC Piping: ASTM F 493.

2. PVC Piping: ASTM D 2564. Include primer according to ASTM F 656.

COMMON WORK RESULTS FOR PLUMBING 22 0500 - 6

2.4 TRANSITION FITTINGS

A. AWWA Transition Couplings: Same size as, and with pressure rating at least equal to and with ends compatible with, piping to be joined.

1. Manufacturers:

a) Cascade Waterworks Mfg. Co.

b) Dresser Industries, Inc.; DMD Div.

c) Ford Meter Box Company, Incorporated (The); Pipe Products Div.

d) JCM Industries.

e) Smith-Blair, Inc.

f) Viking Johnson.

2. Underground Piping NPS 1-1/2 and Smaller: Manufactured fitting or coupling.

3. Underground Piping NPS 2 and Larger: AWWA C219, metal sleeve-type coupling.

4. Aboveground Pressure Piping: Pipe fitting.

B. Plastic-to-Metal Transition Fittings and Adaptors: CPVC and PVC one-piece fitting with manufacturer's Schedule 80 equivalent dimensions; one end with threaded brass insert, and one solvent-cement-joint end.

1. Manufacturers:

a) Eslon Thermoplastics.

b) Sioux Chief

c) Other manufacturers by voluntary alternate.

C. Flexible Transition Couplings for Underground Nonpressure Drainage Piping: ASTM C 1173 with elastomeric sleeve, ends same size as piping to be joined, and corrosion-resistant metal band on each end.

1. Manufacturers:

a) Cascade Waterworks Mfg. Co.

b) Fernco, Inc.

c) Mission Rubber Company.

d) Plastic Oddities, Inc.

e) Other manufacturers by voluntary alternate.

2.5 DIELECTRIC FITTINGS

A. Description: Combination fitting of copper alloy and ferrous materials with threaded, solder-joint, plain, or weld-neck end connections that match piping system materials.

B. Insulating Material: Suitable for system fluid, pressure, and temperature.

C. Dielectric Unions, Flanges and Couplings: Factory-fabricated, union assembly, for 250-psig minimum working pressure at 180 deg F.

1. Manufacturers:

COMMON WORK RESULTS FOR PLUMBING 22 0500 - 7

a) Watts Industries, Inc.; Water Products Div.

b) Zurn Industries, Inc.; Wilkins Div.

c) Other manufacturers by voluntary alternate.

2.6 SLEEVE SEALS

A. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

1. Advance Products & Systems, Inc.

2. Metraflex, Inc.

3. Pipeline Seal and Insulator, Inc.

4. Others by voluntary alternate.

B. Description: Modular sealing element unit, designed for field assembly, used to fill annular space between pipe and sleeve.

1. Sealing Elements: EPDM-rubber or NBR interlocking links shaped to fit surface of pipe.

Include type and number required for pipe material and size of pipe.

2. Pressure Plates: Carbon steel or stainless steel.

3. Connecting Bolts and Nuts: Carbon steel, with corrosion-resistant coating, or stainless steel of length required to secure pressure plates to sealing elements.

2.7 SLEEVES

A. Galvanized-Steel Sheet: 0.0239-inch minimum thickness; round tube closed with welded longitudinal joint.

B. Steel Pipe: ASTM A 53, Type E, Grade B, Schedule 40, galvanized, plain ends.

C. Cast Iron: Cast or fabricated "wall pipe" equivalent to ductile-iron pressure pipe, with plain ends and integral waterstop, unless otherwise indicated.

D. Stack Sleeve Fittings: Manufactured, cast-iron sleeve with integral clamping flange. Include clamping ring and bolts and nuts for membrane flashing.

1. Underdeck Clamp: Clamping ring with set screws.

E. Molded PVC: Permanent, with nailing flange for attaching to wooden forms.

F. PVC Pipe: ASTM D 1785, Schedule 40.

2.8 ESCUTCHEONS

A. Description: Manufactured wall and ceiling escutcheons and floor plates, with an ID to closely fit around pipe, tube, and insulation of insulated piping and an OD that completely covers opening.

B. One-Piece, Deep-Pattern Type: Deep-drawn, box-shaped brass with polished chrome-plated finish.

COMMON WORK RESULTS FOR PLUMBING 22 0500 - 8

C. One-Piece, Cast-Brass Type: With set screw.

1. Finish: Polished chrome-plated.

D. Split-Casting, Cast-Brass Type: With concealed hinge and set screw.

1. Finish: Polished chrome-plated.

E. One-Piece, Stamped-Steel Type: With set screw or spring clips and chrome-plated finish.

F. Split-Plate, Stamped-Steel Type: With concealed hinge, set screw or spring clips, and chrome-plated finish.

G. One-Piece, Floor-Plate Type: Cast-iron floor plate.

H. Split-Casting, Floor-Plate Type: Cast brass with concealed hinge and set screw.

2.9 GROUT

A. Description: ASTM C 1107, Grade B, nonshrink and nonmetallic, dry hydraulic-cement grout.

1. Characteristics: Post-hardening, volume-adjusting, nonstaining, noncorrosive, nongaseous, and recommended for interior and exterior applications.

2. Design Mix: 5000-psi, 28-day compressive strength.

3. Packaging: Premixed and factory packaged.

PART 3 - EXECUTION

3.1 PIPING SYSTEMS - COMMON REQUIREMENTS

A. Install piping according to the following requirements and Division 22 Sections specifying piping systems.

B. Drawing plans, schematics, and diagrams indicate general location and arrangement of piping systems. Indicated locations and arrangements were used to size pipe and calculate friction loss, expansion, pump sizing, and other design considerations.

Install piping as indicated unless deviations to layout are required due to field conditions.

Coordinate with all other trades prior to installation or fabrication.

C. Install piping in concealed locations, unless otherwise indicated and except in equipment rooms and service areas.

D. Install piping indicated to be exposed and piping in equipment rooms and service areas at right angles or parallel to building walls. Diagonal runs are prohibited unless specifically indicated otherwise.

E. Install piping above accessible ceilings to allow sufficient space for ceiling panel removal.

F. Install piping to permit valve servicing.

G. Install piping at indicated slopes and as required by code.

COMMON WORK RESULTS FOR PLUMBING 22 0500 - 9

H. Install piping free of sags and bends.

I. Install fittings for changes in direction and branch connections.

J. Install piping to allow application of insulation.

K. Select system components with pressure rating equal to or greater than system operating pressure.

L. Install escutcheons for penetrations of walls, ceilings, and floors according to the following:

1. New Piping:

a) Piping with Fitting or Sleeve Protruding from Wall: One-piece, deep-pattern type.

b) Chrome-Plated Piping: One-piece, cast-brass type with polished chrome-plated finish.

c) Insulated Piping: One-piece, stamped-steel type with spring clips.

d) Bare Piping at Wall and Floor Penetrations in Finished Spaces: One-piece, stamped-steel type.

e) Bare Piping at Ceiling Penetrations in Finished Spaces: One-piece, stamped-steel type or split-plate, stamped-steel type with concealed hinge and set screw.

f) Bare Piping in Unfinished Service Spaces: One-piece, stamped-steel type with concealed or exposed-rivet hinge and set screw or spring clips.

g) Bare Piping in Equipment Rooms: One-piece, stamped-steel type with set screw or spring clips.

h) Bare Piping at Floor Penetrations in Equipment Rooms: One-piece, floor-plate type.

M. Sleeves are not required for core-drilled holes.

N. Permanent sleeves are not required for holes formed by removable PE sleeves.

O. Install sleeves for pipes passing through concrete and masonry walls, gypsum-board partitions, and concrete floor and roof slabs.

1. Cut sleeves to length for mounting flush with both surfaces.

a) Exception: Extend sleeves installed in floors of mechanical equipment areas or other wet areas 2 inches above finished floor level. Extend cast-iron sleeve fittings below floor slab as required to secure clamping ring if ring is specified.

2. Install sleeves in new walls and slabs as new walls and slabs are constructed.

3. Install sleeves that are large enough to provide 1/4-inch annular clear space between sleeve and pipe or pipe insulation. Use the following sleeve materials:

a) PVC or Steel Pipe Sleeves: For pipes smaller than NPS 6.

b) Steel Sheet Sleeves: For pipes NPS 6 and larger, penetrating gypsum-board partitions.

c) Stack Sleeve Fittings: For pipes penetrating floors with membrane waterproofing.

Secure flashing between clamping flanges.

COMMON WORK RESULTS FOR PLUMBING 22 0500 - 10

Install section of cast-iron soil pipe to extend sleeve to 2 inches above finished floor level. Refer to Division 07 Section "Sheet Metal Flashing and Trim" for flashing.

1) Seal space outside of sleeve fittings with grout.

4. Except for underground wall penetrations, seal annular space between sleeve and pipe or pipe insulation, using joint sealants appropriate for size, depth, and location of joint.

Refer to Division 07 Section "Joint Sealants" for materials and installation.

P. Aboveground, Exterior-Wall Pipe Penetrations: Seal penetrations using sleeves and mechanical sleeve seals. Select sleeve size to allow for 1-inch annular clear space between pipe and sleeve for installing mechanical sleeve seals.

1. Install steel pipe for sleeves smaller than 6 inches in diameter.

2. Install cast-iron "wall pipes" for sleeves 6 inches and larger in diameter.

3. Mechanical Sleeve Seal Installation: Select type and number of sealing elements required for pipe material and size. Position pipe in center of sleeve. Assemble mechanical sleeve seals and install in annular space between pipe and sleeve. Tighten bolts against pressure plates that cause sealing elements to expand and make watertight seal.

Q. Underground, Exterior-Wall Pipe Penetrations: Install cast-iron "wall pipes" for sleeves. Seal pipe penetrations using mechanical sleeve seals. Select sleeve size to allow for 1-inch annular clear space between pipe and sleeve for installing mechanical sleeve seals.

1. Mechanical Sleeve Seal Installation: Select type and number of sealing elements required for pipe material and size. Position pipe in center of sleeve. Assemble mechanical sleeve seals and install in annular space between pipe and sleeve. Tighten bolts against pressure plates that cause sealing elements to expand and make watertight seal.

R. Fire-Barrier Penetrations: Maintain indicated fire rating of walls, partitions, ceilings, and floors at pipe penetrations. Seal pipe penetrations with firestop materials. Refer to Division 07 Section "Penetration Firestopping" for materials.

S. Verify final equipment locations for roughing-in.

T. Refer to equipment specifications in other Sections of these Specifications for roughing-in requirements.

3.2 PIPING JOINT CONSTRUCTION

A. Join pipe and fittings according to the following requirements and Division 22 Sections specifying piping systems.

B. Ream ends of pipes and tubes and remove burrs. Bevel plain ends of steel pipe.

C. Remove scale, slag, dirt, and debris from inside and outside of pipe and fittings before assembly.

COMMON WORK RESULTS FOR PLUMBING 22 0500 - 11

D. Soldered Joints: Apply ASTM B 813, water-flushable flux, unless otherwise indicated, to tube end. Construct joints according to ASTM B 828 or CDA's "Copper Tube Handbook," using lead-free solder alloy complying with ASTM B 32.

E. Brazed Joints: Construct joints according to AWS's "Brazing Handbook," "Pipe and Tube" Chapter, using copper-phosphorus brazing filler metal complying with AWS A5.8.

F. Threaded Joints: Thread pipe with tapered pipe threads according to ASME B1.20.1. Cut threads full and clean using sharp dies. Ream threaded pipe ends to remove burrs and restore full ID. Join pipe fittings and valves as follows:

1. Apply appropriate tape or thread compound to external pipe threads unless dry seal threading is specified.

2. Damaged Threads: Do not use pipe or pipe fittings with threads that are corroded or damaged. Do not use pipe sections that have cracked or open welds.

G. Welded Joints: Construct joints according to AWS D10.12, using qualified processes and welding operators according to Part 1 "Quality Assurance" Article.

H. Flanged Joints: Select appropriate gasket material, size, type, and thickness for service application. Install gasket concentrically positioned. Use suitable lubricants on bolt threads.

I. Plastic Piping Solvent-Cement Joints: Clean and dry joining surfaces. Join pipe and fittings according to the following:

1. Comply with ASTM F 402 for safe-handling practice of cleaners, primers, and solvent cements.

2. CPVC Piping: Join according to ASTM D 2846/D 2846M Appendix.

3. PVC Pressure Piping: Join schedule number ASTM D 1785, PVC pipe and PVC socket fittings according to ASTM D 2672. Join other-than-schedule-number PVC pipe and socket fittings according to ASTM D 2855.

4. PVC Nonpressure Piping: Join according to ASTM D 2855.

J. Plastic Pressure Piping Gasketed Joints: Join according to ASTM D 3139.

K. Plastic Nonpressure Piping Gasketed Joints: Join according to ASTM D 3212.

3.3 PIPING CONNECTIONS

A. Make connections according to the following, unless otherwise indicated:

1. Install unions, in piping NPS 2 and smaller, adjacent to each valve and at final connection to each piece of equipment.

2. Install flanges, in piping NPS 2-1/2 and larger, adjacent to flanged valves and at final connection to each piece of equipment.

3. Dry Piping Systems: Install dielectric unions and flanges to connect piping materials of dissimilar metals.

4. Wet Piping Systems: Install dielectric coupling and nipple fittings to connect piping materials of dissimilar metals.

COMMON WORK RESULTS FOR PLUMBING 22 0500 - 12

3.4 EQUIPMENT INSTALLATION - COMMON REQUIREMENTS

A. Install equipment to allow maximum possible headroom unless specific mounting heights are not indicated.

B. Install equipment level and plumb, parallel and perpendicular to other building systems and components in exposed interior spaces, unless otherwise indicated.

C. Install plumbing equipment to facilitate service, maintenance, and repair or replacement of components. Connect equipment for ease of disconnecting, with minimum interference to other installations. Extend grease fittings to accessible locations.

D. Install equipment to allow right of way for piping installed at required slope.

3.5 PAINTING

A. Painting of plumbing systems, equipment, and components is specified in Division 09 Sections "Interior Painting" and "Exterior Painting."

B. Damage and Touchup: Repair marred and damaged factory-painted finishes with materials and procedures to match original factory finish.

3.6 CONCRETE BASES

A. Concrete Bases: Anchor equipment to concrete base according to equipment manufacturer's written instructions and according to seismic codes at Project.

1. Construct concrete bases of dimensions indicated, but not less than 4 inches larger in both directions than supported unit.

2. Install dowel rods to connect concrete base to concrete floor. Unless otherwise indicated, install dowel rods on 18-inch centers around the full perimeter of the base.

3. Install epoxy-coated anchor bolts for supported equipment that extend through concrete base, and anchor into structural concrete floor.

4. Place and secure anchorage devices. Use supported equipment manufacturer's setting drawings, templates, diagrams, instructions, and directions furnished with items to be embedded.

5. Install anchor bolts to elevations required for proper attachment to supported equipment.

6. Install anchor bolts according to anchor-bolt manufacturer's written instructions.

7. Use 3000-psi, 28-day compressive-strength concrete and reinforcement as specified in

Division 03 Section "Cast-in-Place Concrete."

3.7 ERECTION OF METAL SUPPORTS AND ANCHORAGES

A. Refer to Division 05 Section "Metal Fabrications" for structural steel.

B. Cut, fit, and place miscellaneous metal supports accurately in location, alignment, and elevation to support and anchor plumbing materials and equipment.

C. Field Welding: Comply with AWS D1.1.

COMMON WORK RESULTS FOR PLUMBING 22 0500 - 13

3.8 ERECTION OF WOOD SUPPORTS AND ANCHORAGES

A. Cut, fit, and place wood grounds, nailers, blocking, and anchorages to support, and anchor plumbing materials and equipment.

B. Select fastener sizes that will not penetrate members if opposite side will be exposed to view or will receive finish materials. Tighten connections between members. Install fasteners without splitting wood members.

C. Attach to substrates as required to support applied loads.

3.9 GROUTING

A. Mix and install grout for plumbing equipment base bearing surfaces, pump and other equipment base plates, and anchors.

B. Clean surfaces that will come into contact with grout.

C. Provide forms as required for placement of grout.

D. Avoid air entrapment during placement of grout.

E. Place grout, completely filling equipment bases.

F. Place grout on concrete bases and provide smooth bearing surface for equipment.

G. Place grout around anchors.

H. Cure placed grout.

END OF SECTION 22 0500

PLUMBING DEMOLITION FOR REMODELING 22 0501 - 1

SECTION 22 0501 – PLUMBING DEMOLITION FOR REMODELING

PART 1 - GENERAL

1.1 SECTION INCLUDES

A. Interior demolition, removal and abandonment of interior plumbing systems, including sanitary sewer/vent systems, storm systems, domestic hot and cold water systems, water heaters, plumbing fixtures, equipment, etc.

PART 2 - PRODUCTS

2.1 MATERIALS AND EQUIPMENT

A. Materials and equipment for patching work: As specified individual sections.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Verify that piping systems and equipment serve only areas scheduled for demolition.

B. Demolition shall be based on a field observation and existing record drawings if available.

Contractor to field verify exact conditions that exist.

C. Beginning of demolition means the contractor accepts the existing conditions.

3.2 PREPARATION

A. Disconnect piping systems in walls, floors and ceilings scheduled for removal.

B. Provide temporary connections to maintain existing systems in service during construction as directed in field.

3.3 DEMOLITION EXISTING PLUMBING WORK

A. Remove existing installations to accommodate requirements for new construction.

B. Remove abandoned piping and equipment.

END OF SECTION 22 0501

GENERAL-DUTY VALVES FOR PLUMBING PIPING 22 0523 - 1

SECTION 22 0523 - GENERAL-DUTY VALVES FOR PLUMBING PIPING

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Bronze angle valves.

2. Brass ball valves.

3. Bronze ball valves.

4. Iron, single-flange butterfly valves.

5. Bronze ball cone check valves.

6. Bronze gate valves.

7. Iron gate valves.

8. Bronze globe valves.

9. Iron globe valves.

B. Related Sections:

1. Division 22 plumbing piping Sections for specialty valves applicable to those Sections only.

1.3 DEFINITIONS

A. CWP: Cold working pressure.

B. EPDM: Ethylene propylene copolymer rubber.

C. NBR: Acrylonitrile-butadiene, Buna-N, or nitrile rubber.

D. NRS: Nonrising stem.

E. OS&Y: Outside screw and yoke.

F. RS: Rising stem.

1.4 SUBMITTALS

A. Product Data: For each type of valve indicated.

1.5 QUALITY ASSURANCE

A. Source Limitations for Valves: Obtain each type of valve from single source from single manufacturer.

GENERAL-DUTY VALVES FOR PLUMBING PIPING 22 0523 - 2

B. ASME Compliance:

1. ASME B16.10 and ASME B16.34 for ferrous valve dimensions and design criteria.

2. ASME B31.1 for power piping valves.

3. ASME B31.9 for building services piping valves.

C. NSF Compliance: NSF 61 for valve materials for potable-water service.

1.6 DELIVERY, STORAGE, AND HANDLING

A. Use the following precautions during storage:

1. Maintain valve end protection.

2. Store valves indoors and maintain at higher than ambient dew point temperature. If outdoor storage is necessary, store valves off the ground in watertight enclosures.

B. Use sling to handle large valves; rig sling to avoid damage to exposed parts. Do not use handwheels or stems as lifting or rigging points.

PART 2 - PRODUCTS

2.1 GENERAL REQUIREMENTS FOR VALVES

A. Refer to valve schedule articles for applications of valves.

B. Valve Pressure and Temperature Ratings: Not less than indicated and as required for system pressures and temperatures.

C. Valve Sizes: Same as upstream piping unless otherwise indicated.

D. Valve Actuator Types:

1. Gear Actuator: For quarter-turn valves NPS 8 and larger.

2. Handwheel: For valves other than quarter-turn types.

3. Handlever: For quarter-turn valves NPS 6 and smaller.

E. Valves in Insulated Piping: With 2-inch stem extensions and the following features:

1. Gate Valves: With rising stem.

2. Ball Valves: With extended operating handle of non-thermal-conductive material, and protective sleeve that allows operation of valve without breaking the vapor seal or disturbing insulation.

3. Butterfly Valves: With extended neck.

F. Valve-End Connections:

1. Flanged: With flanges according to ASME B16.1 for iron valves.

2. Grooved: With grooves according to AWWA C606.

3. Solder Joint: With sockets according to ASME B16.18.

4. Threaded: With threads according to ASME B1.20.1.

G. Valve Bypass and Drain Connections: MSS SP-45.

GENERAL-DUTY VALVES FOR PLUMBING PIPING 22 0523 - 3

2.2 BRONZE ANGLE VALVES

A. Class 125, Bronze Angle Valves with Bronze or nonmetallic Disc:

1. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

a. Nibco, Inc.

b. Milwaukee Valve Company.

c. Other manufacturers by voluntary alternates.

2. Description:

a. Standard: MSS SP-80, Type 1.

b. CWP Rating: 200 psig.

c. Body Material: ASTM B 62, bronze with integral seat and screw-in bonnet.

d. Ends: Threaded.

e. Stem and Disc: Bronze.

f. Packing: Asbestos free.

g. Handwheel: Malleable iron, bronze, or aluminum.

2.3 BALL VALVES

A. Two-Piece, Full-Port, Bronze Body ASTM B584 Ball Valves with Brass or Stainless Steel Trim:

1. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

a. Apollo Valves 77C-LF or 77 CLF-11 (with Thermal Seal Stem Extension for Insulated Lines)

b. Milwaukee Valve Company.

c. NIBCO INC.

d. Others

2. Description:

a. Standard: MSS SP-110.

b. SWP Rating: 150 psig.

c. CWP Rating: 600 psig.

d. Body Design: Two piece.

e. Body Material: ASTM B584 Bronze Body.

f. Ends: Threaded.

g. Seats: PTFE or TFE.

h. Stem: Brass or Stainless Steel.

i. Ball: Chrome-plated brass or Stainless Steel.

j. Port: Full.

2.4 IRON, SINGLE-FLANGE BUTTERFLY VALVES

A. 200 CWP, Iron, Single-Flange Butterfly Valves.

GENERAL-DUTY VALVES FOR PLUMBING PIPING 22 0523 - 4

1. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

a. Apollo Valves Series 143

b. ABZ Valves Series 397

c. Milwaukee Valve Company.

d. NIBCO INC.

e. Others by voluntary alternate.

2. Description:

a. Standard: MSS SP-67, Type I.

b. CWP Rating: 200 psig.

c. Body Design: Lug type; suitable for bidirectional dead-end service at rated pressure without use of downstream flange.

d. Body Material: ASTM A 126, cast iron or ASTM A 536, ductile iron.

e. Seat: EPDM.

f. Stem: One- or two-piece stainless steel.

g. Disc: Aluminum bronze.

2.5 CHECK VALVES

A. Class 125, Ball Cone Check Valves.

1. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

a. Apollo Valves 61-500-LF.

b. Crane Co.; Crane Valve Group; Crane Valves.

c. Milwaukee Valve Company.

d. NIBCO INC.

e. Other manufacturers by voluntary alternates.

2. Description:

a. CWP Rating: 200 psig.

b. Body Design: Inline 2-piece.

c. Body Material: ASTM B584 Bronze.

d. Ends: Threaded.

e. Disc: EPDM Check Disc.

f. Soft seated.

2.6 GATE VALVES

A. Class 125, Gate Valves:

1. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

a. Apollo Valves 101T/101S-LF (Rising Stem), 102T/102S (Non-Rising Stem)

b. Crane Co.; Crane Valve Group; Crane Valves.

GENERAL-DUTY VALVES FOR PLUMBING PIPING 22 0523 - 5

c. Milwaukee Valve Company.

d. NIBCO INC.

e. Others by voluntary alternate.

2. Description:

a. Standard: MSS SP-80, Type 1.

b. CWP Rating: 200 psig.

c. Body Material: ASTM B 62, bronze or ASTM A126 (gray iron).

d. Ends: Threaded or solder joint.

e. Stem: Bronze.

f. Disc: Solid wedge.

g. Packing: Asbestos free.

h. Handwheel: Malleable iron, bronze, or aluminum.

2.7 GLOBE VALVES

A. Class 125, Globe Valves.

1. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

a. Apollo Valves 102T-LF/120S-LF

b. Crane Co.; Crane Valve Group; Crane Valves.

c. Milwaukee Valve Company.

d. NIBCO INC.

e. Others by voluntary alternate.

2. Description:

a. Standard: MSS SP-80 (bronze), MSS SP-85 (iron) Type 1.

b. CWP Rating: 200 psig.

c. Body Material: ASTM B 62, (bronze), ASTM A126 (gray iron).

d. Ends: Threaded or solder joint.

e. Packing: Asbestos free.

f. Handwheel: Malleable iron, bronze, or aluminum.

g. Disc: PTFE

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine valve interior for cleanliness, freedom from foreign matter, and corrosion. Remove special packing materials, such as blocks, used to prevent disc movement during shipping and handling.

B. Operate valves in positions from fully open to fully closed. Examine guides and seats made accessible by such operations.

C. Examine threads on valve and mating pipe for form and cleanliness.

GENERAL-DUTY VALVES FOR PLUMBING PIPING 22 0523 - 6

D. Examine mating flange faces for conditions that might cause leakage. Check bolting for proper size, length, and material. Verify that gasket is of proper size, that its material composition is suitable for service, and that it is free from defects and damage.

E. Do not attempt to repair defective valves; replace with new valves.

3.2 VALVE INSTALLATION

A. Install valves with unions or flanges at each piece of equipment arranged to allow service, maintenance, and equipment removal without system shutdown.

B. Locate valves for easy access and provide separate support where necessary.

C. Install valves in horizontal piping with stem at or above center of pipe.

D. Install valves in position to allow full stem movement.

E. Install check valves for proper direction of flow and as follows:

1. Swing Check Valves: In horizontal position with hinge pin level.

2. Center-Guided and Plate-Type Check Valves: In horizontal or vertical position, between flanges.

3. Lift Check Valves: With stem upright and plumb.

3.3 ADJUSTING

A. Adjust or replace valve packing after piping systems have been tested and put into service but before final adjusting and balancing. Replace valves if persistent leaking occurs.

3.4 GENERAL REQUIREMENTS FOR VALVE APPLICATIONS

A. If valve applications are not indicated, use the following:

1. Shutoff Service: Ball, butterfly, or gate valves.

2. Butterfly Valve Dead-End Service: Single-flange (lug) type.

3. Throttling Service: Ball, or butterfly valves.

4. Pump-Discharge Check Valves:

a. NPS 2 and Smaller: Bronze swing check valves with bronze disc.

b. NPS 2-1/2 and Larger for Domestic Water: Iron swing check valves with lever and weight or with spring or iron, center-guided, metal-seat check valves.

c. NPS 2-1/2 and Larger for Sanitary Waste and Storm Drainage: Iron swing check valves with lever and weight or spring.

B. If valves with specified SWP classes or CWP ratings are not available, the same types of valves with higher SWP classes or CWP ratings may be substituted.

C. Select valves, except wafer types, with the following end connections:

1. For Copper Tubing, NPS 2 and Smaller: Threaded ends except where solder-joint valve-end option is indicated in valve schedules below.

GENERAL-DUTY VALVES FOR PLUMBING PIPING 22 0523 - 7

2. For Copper Tubing, NPS 2-1/2 to NPS 4: Flanged ends except where threaded valve-end option is indicated in valve schedules below.

3. For Steel Piping, NPS 2 and Smaller: Threaded ends.

4. For Steel Piping, NPS 2-1/2 to NPS 4: Flanged ends except where threaded valve-end option is indicated in valve schedules below.

3.5 DOMESTIC, HOT- AND COLD-WATER VALVE SCHEDULE

A. Pipe NPS 2 and Smaller:

1. Bronze and Brass Valves: May be provided with solder-joint ends instead of threaded ends.

2. Bronze Angle Valves: Class 125 bronze disc.

3. Ball Valves: One or Two pieces, full port, brass or bronze with brass, bronze, or stainless-steel trim.

4. Bronze Swing Check Valves: Class 125 bronze disc.

B. Pipe NPS 2-1/2 and Larger:

1. Iron Valves, NPS 2-1/2 to NPS 4: May be provided with threaded ends instead of flanged ends.

2. Iron Ball Valves: Class 125.

3. Iron, Single-Flange Butterfly Valves: 200 CWP, EPDM or NBR seat, aluminum-bronze, ductile-iron or stainless-steel disc.

4. Iron Gate Valves: Class 125, NRS or OS&Y.

5. Iron Globe Valves: Class 125.

END OF SECTION 22 0523

HANGERS AND SUPPORTS FOR PLUMBING PIPING AND EQUIPMENT 22 0529 - 1

SECTION 22 0529 - HANGERS & SUPPORTS FOR PLUMBING PIPING AND EQUIPMENT

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes hangers and supports for mechanical systems piping and equipment.

1.2 DEFINITIONS

A. Terminology used in this section is defined in MSS SP-90.

1.3 SUBMITTALS

A. Product Data: For each type of manufactured hanger indicated.

1.4 QUALITY ASSURANCE

A. Qualify welding processes and welding operators according to AWS D1.1, Structural Welding

Code-Steel.

1. Certify that each welder has satisfactorily passed AWS qualification tests for welding processes involved and, if pertinent, has undergone recertification.

B. NFPA Compliance: Comply with NFPA 13 for hangers and supports used as components of fire protection systems.

C. Plumbing and Mechanical Codes Compliance: Comply with Michigan Plumbing Codes and

International Plumbing and Electrical Codes for hanger spacing.

PART 2 - PRODUCTS

2.1 MANUFACTURED PRODUCTS

A. Hangers, Supports and Components: Factory-fabricated according to MSS SP-58.

1. Components include galvanized coatings where installed for piping and equipment that will not have a field-applied finish.

2. Pipe attachments include nonmetallic coating for electro-lytic protection where attachments are in direct contact with copper tubing.

B. Thermal-Hanger Shield Inserts: 100-psi average compressive strength, waterproofed calcium silicate, encased with sheet metal shield. Insert and shield cover entire circumference of pipe and are of length indicated by manufacturer for pipe size and thickness of insulation.

2.2 MISCELLANEOUS MATERIALS

A. Structural Steel: ASTM A 36/A 36M, steel plates, shapes and bars, black and galvanized.

B. Bolts and Nuts: ASME B18.10 or ASTM A 183, steel, hex-head, track bolts and nuts.

HANGERS AND SUPPORTS FOR PLUMBING PIPING AND EQUIPMENT 22 0529 - 2

C. Washers: ASTM F 844, steel, plain, flat washers.

D. Grout: ASTM C 1107, Grade B, non-shrink, nonmetallic.

1. Characteristics include post-hardening, volume-adjusting, dry, hydraulic-cement-type grout that is non-staining, non-corrosive, non-gaseous and is recommended for interior and exterior applications.

2. Design Mix: 5000-psi, 28-day compressive strength.

3. Water: Potable.

4. Packaging: Premixed and factory-packaged.

PART 3 - EXECUTION

3.1 HANGER AND SUPPORT APPLICATIONS

A. Comply with MSS SP-69 for pipe hanger selections and applications that are not specified in piping specification sections.

3.2 HANGER AND SUPPORT INSTALLATION

A. General: Comply with MSS SP-69 and SP-89. Install hangers, supports, clamps and attachments as required to properly support piping for building structure.

B. Arrange for grouping of parallel runs of horizontal piping supported together on field-fabricated, heavy-duty trapeze hangers where possible.

C. Install supports with maximum spacing's complying with local plumbing codes and MSS SP-69 and table below. Refer to plumbing code for spacing requirements for suspended PVC piping systems, see also according to MSS SP-69 and specifications 22-1316.

1.

Nominal Pipe Or

Tube Size

STD WT STEEL PIPE COPPER TUBE

WATER

SERVICE

VAPOR

SERVICE

WATER

SERVICE

VAPOR

SERVICE

Ft M Ft M Ft M Ft m ¼ 7 2.1 8 2.4 5 1.5 5 1.5 3/8 7 2.1 8 2.4 5 1.5 6 1.8 ½ 7 2.1 8 2.4 5 1.5 6 1.8 ¾ 7 2.1 9 2.7 5 1.5 7 2.1 1 7 2.1 9 2.7 6 1.8 8 2.4

1 ¼ 7 2.1 9 2.7 6 2.1 9 2.7 1 ½ 9 2.7 12 3.7 8 2.4 10 3.0 2 10 3.0 13 4.0 8 2.4 11 3.4

2 ½ 11 3.4 14 4.3 9 2.7 13 4.0…