Addendum 5 21187.pdf
PDF 459 KB Posted
- Attached to
- 511/21187. CAK; Albion Armory - Renovate Armory
- Solicitation number
- RFQ - 171 - 220000000461
- Issued by
- Calhoun County, Alden CDP, Michigan
About this file
This document is an Addendum to the solicitation for the Renovate Armory - Albion Armory project in Albion, Michigan. The project is located at the National Guard Armory Battery Albion Armory at 1023 N Clark Street, Albion, Michigan 49224. The addendum provides several clarifications and modifications to the original contract documents, including the omission of masonry block foam insulation, the use of solid surface material for the countertop and microwave shelf in the Break Room 145, the use of standard galvanized horizontal wire masonry block reinforcing, the change in masonry block wall thickness for the Women and Men's showers, and the specification of lacquered wood bench tops with prefinished metal stanchions for the wood finish metal supported benches in the Women and Men's locker room.
The contract opportunity is being solicited by the State of Michigan and involves the jurisdictions of Calhoun County and Alden CDP. No additional details are provided regarding pricing terms, set asides, incumbents, funding requirements and sources, or other salient information.
View the file
Other files
Show all 39
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
August 18, 2022
Renovate Armory – Albion Armory
Addendum Number 05
Project Location National Guard Armory Battery Albion Armory 1023 N Clark Street Albion, Michigan 49224
Notice to Proposers
Receipt of this Addendum shall be acknowledged on the Proposal Form.
This Addendum forms part of the Contract documents for the above reference project and shall be incorporated integrally therewith.
Each proposer shall make necessary adjustments and submit their proposal with full knowledge of all modification, clarifications and supplemental data included therein. Where provisions of the following supplemental data differ from those of the original Contract Document, this Addendum shall govern.
Architectural Items
1. Please omit masonry block foam insulation, Green Seal 183, from the project, we will not be insulating the new 8” perimeter block cavities.
2. The countertop and microwave shelf in the Break Room 145 will be solid surface not plastic laminate, this includes the 4” back splash.
3. The horizontal wire masonry block reinforcing shall be standard galvanized and not epoxy coat, typical at all locations.
4. Please note that all 4” masonry block walls at the Women and Men’s showers will be changed to 6” masonry block walls to accommodate for the shower valves. All adjustments to the floor plan will be done post bid.
5. All Four (4) wood finish metal supported benches in the Women and Men’s locker room shall be lacquered wood bench tops with prefinished metal stanchions with base plates bolted to the concrete floor slab. Prefabricated benches are acceptable, verify size with architect.
End of Addendum Number 05