Albion Armory Specification 10 of 15.pdf

PDF 3 MB Posted

Attached to
511/21187. CAK; Albion Armory - Renovate Armory
Solicitation number
RFQ - 171 - 220000000461
Issued by
Calhoun County, Alden CDP, Michigan

About this file

This document appears to be the specifications for a State of Michigan and Calhoun County contract opportunity to renovate the Albion Armory. The project includes work on interior painting, high-performance coatings, visual display units, room-identification signage, metal toilet compartments, operable partitions, toilet and bath accessories, fire protection cabinets, fire extinguishers, metal lockers, and plastic-laminate-clad casework. The contract will be awarded to a single contractor and no bid breakdown or set-aside requirements are specified. The document provides detailed technical specifications for each of the required products and installation services. No information is provided about the project timeline, bid due dates, or award dates.

The document does not mention any incumbent contractors, funding sources, or pricing terms. It appears to be strictly focused on outlining the technical requirements for the renovation work at the Albion Armory facility located in Alden, Michigan, which is within Calhoun County.

View the file

Other files

File Type Posted
Addendum 2 270500 DATA COMMUNICATION SYSTEM 220428.docx DOCX document
Addendum 5 21187.pdf PDF
MtgAttend1 - 21187.pdf PDF
Advertisement 21187.pdf PDF
Addendum No.2 08122022 - 21187.pdf PDF
21-046 Albion Armory - A0.0 - Cover Sheet.pdf PDF
21-046 Albion Armory Civil Drawings.pdf PDF
MtgAttend1 - 21187_REVISED.pdf PDF
Addendum 3 06 Wood Plastics and Composites 21187.pdf PDF
Addendum No.6 08222022 - 21187.pdf PDF
Addendum 1 - 21187.pdf PDF
Albion Armory MEP Set.pdf PDF
Albion Armory Specification 14 of 15.pdf PDF
Albion Armory Specification 12 of 15.pdf PDF
Addendum 3 07 Thermal and Moisture Protection 21187.pdf PDF
Albion Armory Specification 11 of 15.pdf PDF
Albion Armory Specification 3 of 15.pdf PDF
Addendum 2 M-303 - MECHANICAL CONTROLS DIAGRAMS.pdf PDF
Albion Armory Specification 1 of 15.pdf PDF
Albion Armory Specification 7 of 15.pdf PDF
Addendum 3 21187.pdf PDF
Addendum 3 05 Metals 21187.pdf PDF
Albion Armory Draft Logs 11-23-21.pdf PDF
Albion Armory Specification 8 of 15.pdf PDF
Addendum 2 M-301 - MECHANICAL SCHEDULES_ —
Albion Armory Specification 4 of 15.pdf PDF
Addendum 3 08 Openings 21187.pdf PDF
Albion Armory Specification 6 of 15.pdf PDF
Specifications 21187.pdf PDF
Addendum 4 21187.pdf PDF
21-046 Albion Armory Architectural A4-S1 Set.pdf PDF
Albion Armory Draft Map 11-23-21.pdf PDF
Albion Armory Specification 13 of 15.pdf PDF
Albion Armory Specification 9 of 15.pdf PDF
Albion Armory Specification 15 of 15.pdf PDF
Albion Armory Specification 2 of 15.pdf PDF
Albion Armory Specification 5 of 15.pdf PDF
21-046 Albion Armory Architectural A0-A3 Set.pdf PDF
Addendum 2 E-301 - ELECTRICAL DATA.pdf PDF
Show all 39

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RENOVATE ARMORY - ALBION ARMORY

B. Remove hardware, covers, plates, and similar items already in place that are removable and are not to be painted. If removal is impractical or impossible because of size or weight of item, provide surface-applied protection before surface preparation and painting.

1. After completing painting operations, use workers skilled in the trades involved to reinstall items that were removed. Remove surface-applied protection if any.

C. Clean substrates of substances that could impair bond of paints, including dust, dirt, oil, grease, and incompatible paints and encapsulants.

1. Remove incompatible primers and reprime substrate with compatible primers or apply tie coat as required to produce paint systems indicated.

D. Concrete Substrates: Remove release agents, curing compounds, efflorescence, and chalk. Do not paint surfaces if moisture content or alkalinity of surfaces to be painted exceeds that permitted in manufacturer's written instructions.

E. Masonry Substrates: Remove efflorescence and chalk. Do not paint surfaces if moisture content or alkalinity of surfaces or mortar joints exceeds that permitted in manufacturer's written instructions.

F. Steel Substrates: Remove rust, loose mill scale, and shop primer, if any. Clean using methods recommended in writing by paint manufacturer.

G. Shop-Primed Steel Substrates: Clean field welds, bolted connections, and areas where shop paint is abraded. Paint exposed areas with the same material as used for shop priming to comply with SSPC-PA 1 for touching up shop-primed surfaces.

H. Aluminum Substrates: Remove loose surface oxidation.

I. Wood Substrates:

1. Scrape and clean knots, and apply coat of knot sealer before applying primer.

2. Sand surfaces that will be exposed to view, and dust off.

3. Prime edges, ends, faces, undersides, and backsides of wood.

4. After priming, fill holes and imperfections in the finish surfaces with putty or plastic wood filler. Sand smooth when dried.

J. Cotton or Canvas Insulation Covering Substrates: Remove dust, dirt, and other foreign material that might impair bond of paints to substrates.

3.3 INSTALLATION

A. Apply paints according to manufacturer's written instructions and to recommendations in "MPI Manual."

1. Use applicators and techniques suited for paint and substrate indicated.

INTERIOR PAINTING (MPI STANDARDS) 099124 - 5

2. Paint surfaces behind movable equipment and furniture same as similar exposed surfaces.

Before final installation, paint surfaces behind permanently fixed equipment or furniture with prime coat only.

3. Paint front and backsides of access panels, removable or hinged covers, and similar hinged items to match exposed surfaces.

4. Do not paint over labels of independent testing agencies or equipment name, identification, performance rating, or nomenclature plates.

5. Primers specified in painting schedules may be omitted on items that are factory primed or factory finished if acceptable to topcoat manufacturers.

B. Tint each undercoat a lighter shade to facilitate identification of each coat if multiple coats of same material are to be applied. Tint undercoats to match color of topcoat, but provide sufficient difference in shade of undercoats to distinguish each separate coat.

C. If undercoats or other conditions show through topcoat, apply additional coats until cured film has a uniform paint finish, color, and appearance.

D. Apply paints to produce surface films without cloudiness, spotting, holidays, laps, brush marks, roller tracking, runs, sags, ropiness, or other surface imperfections. Cut in sharp lines and color breaks.

E. Painting Fire-Suppression, Plumbing, HVAC, Electrical, Communication, and Electronic Safety and Security Work:

1. Paint the following work where exposed in equipment rooms or occupied spaces:

a. Equipment, including panelboards.

b. Uninsulated metal piping.

c. Uninsulated plastic piping.

d. Pipe hangers and supports.

e. Metal conduit.

f. Plastic conduit.

g. Duct, equipment, and pipe insulation having cotton or canvas insulation covering or other paintable jacket material.

2. Paint portions of internal surfaces of metal ducts, without liner, behind air inlets and outlets that are visible from occupied spaces.

3.4 FIELD QUALITY CONTROL

A. Dry-Film Thickness Testing: Owner may engage the services of a qualified testing and inspecting agency to inspect and test paint for dry-film thickness.

1. Contractor shall touch up and restore painted surfaces damaged by testing.

2. If test results show that dry-film thickness of applied paint does not comply with paint manufacturer's written recommendations, Contractor shall pay for testing and apply

INTERIOR PAINTING (MPI STANDARDS) 099124 - 6

additional coats as needed to provide dry-film thickness that complies with paint manufacturer's written recommendations.

3.5 CLEANING AND PROTECTION

A. At end of each workday, remove rubbish, empty cans, rags, and other discarded materials from Project site.

B. After completing paint application, clean spattered surfaces. Remove spattered paints by washing, scraping, or other methods. Do not scratch or damage adjacent finished surfaces.

C. Protect work of other trades against damage from paint application. Correct damage to work of other trades by cleaning, repairing, replacing, and refinishing, as approved by Architect, and leave in an undamaged condition.

D. At completion of construction activities of other trades, touch up and restore damaged or defaced painted surfaces.

3.6 INTERIOR PAINTING SCHEDULE

A. Concrete Substrates, Nontraffic Surfaces:

1. Latex System, MPI INT 3.1A:

a. Prime Coat: Primer, alkali resistant, water based, MPI #3.

1) Sherwin Williams Conflex Block Filler

b. Intermediate Coat: Latex, interior, matching topcoat.

c. Topcoat: Latex, interior (MPI Gloss Level 3), MPI #52.

1) Sherwin Williams Pro Mar 400.

B. Concrete Substrates, Traffic Surfaces:

1. Water-Based Concrete Floor Sealer System.

a. First Coat: Sealer, water based, for concrete floors, matching topcoat.

1) Sherwin Williams Armorseal Water Based Epoxy Primer

b. Topcoat: Sealer, water based, for concrete floors

1) Sherwin Williams Pro Industrial Water Based Epoxy

INTERIOR PAINTING (MPI STANDARDS) 099124 - 7

C. CMU Substrates:

1. Latex System, MPI INT 4.2A:

a. Block Filler: Block filler, latex, interior/exterior, MPI #4.

1) Sherwin Williams Pro Industrial Block Filler.

b. Intermediate Coat: Latex, interior, matching topcoat.

c. Topcoat: Latex, interior (MPI Gloss Level 3), MPI #52.

1) Sherwin Williams Pro Mar 400.

2. Water-Based Light-Industrial Coating System:

D. Steel Substrates:

1. Alkyd System, MPI INT 5.1EE:

a. Prime Coat: Primer, alkyd, anticorrosive, for metal, MPI #79.

1) Sherwin Williams Kem Bond HS.

b. Intermediate Coat: Alkyd, interior, matching topcoat.

c. Topcoat: Alkyd, interior, semigloss (MPI Gloss Level 5), MPI #47.

1) Sherwin Williams Industrial Enamel.

E. Wood Substrates: Wood trim, Architectural woodwork, & Doors.

1. Latex over Alkyd Primer System:

a. Prime Coat: Primer sealer, alkyd, interior, MPI #45.

1) Sherwin Williams Easy Sand Primer.

b. Intermediate Coat: Latex, interior, matching topcoat.

c. Topcoat: Latex, interior (MPI Gloss Level 4), MPI #43.

1) Sherwin Williams Duration.

F. Gypsum Board and Plaster Substrates:

1. Latex over Latex Sealer System, MPI INT 9.2A:

a. Prime Coat: Primer sealer, latex, interior, MPI #50.

INTERIOR PAINTING (MPI STANDARDS) 099124 - 8

1) Sherwin Williams PVA Drywall Primer & Sealer

b. Intermediate Coat: Latex, interior, matching topcoat.

c. Topcoat: Latex, interior (MPI Gloss Level 3), MPI #52.

1) Sherwin Williams Pro Mar 400.

G. Cotton or Canvas and ASJ Insulation-Covering Substrates: Including pipe and duct coverings.

1. Latex System, MPI INT 10.1A:

a. Prime Coat: Primer sealer, latex, interior, MPI #50.

1) Sherwin Williams PVA Drywall Primer & Sealer

b. Intermediate Coat: Latex, interior, matching topcoat.

c. Topcoat: Latex, interior, flat (MPI Gloss Level 1), MPI #53.

1) Sherwin Williams Pro Mar 400.

END OF SECTION 099124

INTERIOR PAINTING (MPI STANDARDS) 099124 - 9

SECTION 099600 - HIGH-PERFORMANCE COATINGS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes surface preparation and the application of high-performance coating systems. on the following substrates:

1. Interior Substrates:

a. Concrete, horizontal surfaces.

b. Concrete masonry units (CMUs)

c. Gypsum board.

B. Related Requirements:

1. Section 099113 "Exterior Painting" for general field painting.

2. Section 099123 "Interior Painting" for general field painting.

1.3 DEFINITIONS

A. MPI Gloss Level 5: 35 to 70 units at 60 degrees, according to ASTM D523.

B. MPI Gloss Level 6: 70 to 85 units at 60 degrees, according to ASTM D523.

C. MPI Gloss Level 7: More than 85 units at 60 degrees, according to ASTM D523.

1.4 ACTION SUBMITTALS

A. Product Data: For each type of product. Include preparation requirements and application instructions.

1. Include printout of current "MPI Approved Products List" for each product category specified, with the proposed product highlighted.

2. Indicate VOC content.

B. Samples for Initial Selection: For each type of topcoat product indicated.

1. Submit Samples on rigid backing, 8 inches (200 mm) square.

HIGH-PERFORMANCE COATINGS 099600 - 1

2. Apply coats on Samples in steps to show each coat required for system.

3. Label each coat of each Sample.

4. Label each Sample for location and application area.

C. Product List: Cross-reference to coating system and locations of application areas. Use same designations indicated on Drawings and in schedules. Include color designations.

1.5 QUALITY ASSURANCE

A. Mockups: Apply mockups of each coating system indicated to verify preliminary selections made under Sample submittals and to demonstrate aesthetic effects and set quality standards for materials and execution.

1. Architect will select one surface to represent surfaces and conditions for application of each coating system.

a. Wall and Ceiling Surfaces: Provide samples of at least 100 sq. ft. (9 sq. m).

b. Other Items: Architect will designate items or areas required.

2. Final approval of color selections will be based on mockups.

a. If preliminary color selections are not approved, apply additional mockups of additional colors selected by Architect at no added cost to Owner.

3. Approval of mockups does not constitute approval of deviations from the Contract Documents contained in mockups unless Architect specifically approves such deviations in writing.

4. Subject to compliance with requirements, approved mockups may become part of the completed Work if undisturbed at time of Substantial Completion.

1.6 DELIVERY, STORAGE, AND HANDLING

A. Store materials not in use in tightly covered containers in well-ventilated areas with ambient temperatures continuously maintained at not less than 45 deg F (7 deg C).

1. Maintain containers in clean condition, free of foreign materials and residue.

2. Remove rags and waste from storage areas daily.

1.7 FIELD CONDITIONS

A. Apply coatings only when temperature of surfaces to be coated and ambient air temperatures are between 50 and 95 deg F (10 and 35 deg C).

B. Do not apply coatings when relative humidity exceeds 85 percent; at temperatures less than 5 deg F (3 deg C) above the dew point; or to damp or wet surfaces

HIGH-PERFORMANCE COATINGS 099600 - 2

PART 2 - PRODUCTS

2.1 MANUFACTURERS

A. Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following:

Sherwin Williams, PPG Paints, Dur-a-flex, and Benjamin Moore

B. Subject to compliance with requirements, available products that may be incorporated into the Work include, but are not limited to products listed in the Exterior High-Performance Coating Schedule or Interior High-Performance Coating Schedule for the coating category indicated.

2.2 HIGH-PERFORMANCE COATINGS, GENERAL

A. MPI Standards: Products shall comply with MPI standards indicated and shall be listed in its "MPI Approved Products Lists."

B. Material Compatibility:

1. Materials for use within each paint system shall be compatible with one another and substrates indicated, under conditions of service and application as demonstrated by manufacturer, based on testing and field experience.

2. For each coat in a paint system, products shall be recommended in writing by topcoat manufacturers for use in paint system and on substrate indicated.

3. Products shall be of same manufacturer for each coat in a coating system.

C. Colors: As selected by Architect from manufacturer's full range.

2.3 EXAMINATION

A. Examine substrates and conditions, with Applicator present, for compliance with requirements for maximum moisture content and other conditions affecting performance of the Work.

B. Maximum Moisture Content of Substrates: When measured with an electronic moisture meter as follows:

1. Concrete: 12 percent.

2. Masonry (Clay and CMUs): 12 percent.

3. Gypsum Board: 12 percent.

C. Gypsum Board Substrates: Verify that finishing compound is sanded smooth.

HIGH-PERFORMANCE COATINGS 099600 - 3

D. Verify suitability of substrates, including surface conditions and compatibility, with existing finishes and primers.

E. Proceed with coating application only after unsatisfactory conditions have been corrected.

1. Application of coating indicates acceptance of surfaces and conditions.

2.4 PREPARATION

A. Comply with manufacturer's written instructions and recommendations in "MPI Architectural Painting Specification Manual" applicable to substrates and coating systems indicated.

B. Remove hardware, covers, plates, and similar items already in place that are removable and are not to be painted. If removal is impractical or impossible because of size or weight of item, provide surface-applied protection before surface preparation and painting.

1. After completing painting operations, use workers skilled in the trades involved to reinstall items that were removed. Remove surface-applied protection if any.

C. Clean substrates of substances that could impair bond of coatings, including dust, dirt, oil, grease, and incompatible paints and encapsulants.

1. Remove incompatible primers and reprime substrate with compatible primers or apply tie coat as required to produce coating systems indicated.

D. Concrete Substrates: Remove release agents, curing compounds, efflorescence, and chalk. Do not coat surfaces if moisture content or alkalinity of surfaces to be coated exceeds that permitted in manufacturer's written instructions.

E. Masonry Substrates: Remove efflorescence and chalk. Do not coat surfaces if moisture content, alkalinity of surfaces, or alkalinity of mortar joints exceeds that permitted in manufacturer's written instructions.

2.5 APPLICATION

A. Apply high-performance coatings according to manufacturer's written instructions and recommendations in "MPI Architectural Painting Specification Manual."

1. Use applicators and techniques suited for coating and substrate indicated.

2. Coat surfaces behind movable equipment and furniture same as similar exposed surfaces.

Before final installation, coat surfaces behind permanently fixed equipment or furniture with prime coat only

3. Do not apply coatings over labels of independent testing agencies or equipment name, identification, performance rating, or nomenclature plates.

HIGH-PERFORMANCE COATINGS 099600 - 4

B. If undercoats or other conditions show through final coat, apply additional coats until cured film has a uniform coating finish, color, and appearance.

C. Apply coatings to produce surface films without cloudiness, spotting, holidays, laps, brush marks, runs, sags, ropiness, or other surface imperfections. Produce sharp glass lines and color breaks.

2.6 CLEANING AND PROTECTION

A. At end of each workday, remove rubbish, empty cans, rags, and other discarded materials from Project site.

B. After completing coating application, clean spattered surfaces. Remove spattered coatings by washing, scraping, or other methods. Do not scratch or damage adjacent finished surfaces.

C. Protect work of other trades against damage from coating operation. Correct damage to work of other trades by cleaning, repairing, replacing, and recoating, as approved by Architect, and leave in an undamaged condition.

D. At completion of construction activities of other trades, touch up and restore damaged or defaced coated surfaces.

2.7 INTERIOR HIGH-PERFORMANCE COATING SCHEDULE

A. Concrete Substrates, Vertical Surfaces:

1. Epoxy-Modified Latex System MPI INT 3.1G:

a. Prime Coat: Epoxy-modified latex, matching topcoat.

1) Sherwin Williams Armorseal Water Based Epoxy Primer

b. Topcoat: Epoxy-modified latex, semi-gloss (MPI Gloss Level 5), MPI #215.

1) Sherwin Williams Pro Industrial Water Based Epoxy.

B. Concrete Substrates, Horizontal Surfaces:

1. Epoxy System MPI INT 3.2C:

a. Prime Coat: Epoxy, matching topcoat.

b. Intermediate Coat: Epoxy, matching topcoat.

c. Topcoat: Epoxy, gloss, MPI #77.

1) DUR-A-FLEX ‘DUR-A-GUARD’.

2. Clear (Two-Component) Polyurethane System MPI INT 3.2K:

HIGH-PERFORMANCE COATINGS 099600 - 5

a. Prime Coat: Two-component polyurethane matching topcoat.

b. Intermediate Coat: Two-component polyurethane, matching topcoat.

c. Topcoat: Varnish, aliphatic polyurethane, two component (MPI Gloss Level 6 or

MPI Gloss Level 7), MPI #78.

1) DUR-A-FLEX ‘HYBRI-FLEX EC’

C. CMU Substrates:

1. Epoxy- Modified Latex System MPI INT 4.2J:

a. Block Filler: Block filler, epoxy, MPI #116.

1) Sherwin Williams Armorseal Water Based Epoxy Primer.

b. Topcoat: Epoxy, gloss, MPI #77.

1) Sherwin Williams Pro Industrial Water Based Epoxy.

D. Gypsum Board Substrates:

1. Epoxy-Modified Latex System MPI INT 9.2F:

a. Prime Coat: Primer sealer, latex, interior, MPI #50.

1) Sherwin Williams Armorseal Water Based Epoxy Primer.

b. Topcoat: Epoxy, gloss, MPI #77.

1) Sherwin Williams Pro Industrial Water Based Epoxy.

END OF SECTION 099600

HIGH-PERFORMANCE COATINGS 099600 - 6

SECTION 101100 - VISUAL DISPLAY UNITS

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1.Visual display board assemblies.

2.Rail support systems for visual display board assemblies.

3.Modular support systems for visual display board assemblies.

1.2 ACTION SUBMITTALS

A. Product Data: For each type of product.

1.Include construction details, material descriptions, dimensions of individual components and profiles, finishes, and accessories for visual display units.

B. Samples for Initial Selection: For each type of visual display unit indicated, for units with factory-applied color finishes, and as follows:

1.Samples of facings for each visual display panel type, indicating color and texture.

2.Fabric swatches of fabric facings for tackboards.

3.Actual factory-finish color samples, applied to aluminum substrate.

C. Samples: For each type of visual display unit indicated.

1.Visual Display Panel: Not less than 8-1/2 by 11 inches, with facing, core, and backing indicated for final Work. Include one panel for each type, color, and texture required.

2.Trim: 6-inch- long sections of each trim profile.

3.Display Rail: 6-inch- long section of each type.

4.Rail Support System: 6-inch- long sections.

1.3 CLOSEOUT SUBMITTALS

A. Maintenance Data: For visual display units to include in maintenance manuals.

1.4 DELIVERY, STORAGE, AND HANDLING

A. Deliver factory-fabricated visual display units completely assembled in one piece. If dimensions exceed maximum manufactured unit size, or if unit size is impracticable to ship in one piece, provide two or more pieces with joints in locations indicated on approved Shop Drawings.

1.5 FIELD CONDITIONS

A. Environmental Limitations: Do not deliver or install visual display units until spaces are enclosed and weathertight, wet-work in spaces is complete and dry, work above ceilings is complete, and temporary HVAC system is operating and maintaining ambient temperature and

VISUAL DISPLAY UNITS 101100 - 1

humidity conditions at occupancy levels during the remainder of the construction period.

1.6 WARRANTY

A. Special Warranty for Porcelain-Enamel Face Sheets:

Manufacturer agrees to repair or replace porcelain-enamel face sheets that fail in materials or workmanship within specified warranty period.

1.Failures include, but are not limited to, the following:

a. Surfaces lose original writing and erasing qualities.

b. Surfaces exhibit crazing, cracking, or flaking.

2.Warranty Period:

a. 10 years from date of Substantial

Completion.

PART 2 - PRODUCTS

2.1 PERFORMANCE REQUIREMENTS

A. Surface-Burning Characteristics: Comply with ASTM E84;

testing by a qualified testing agency. Identify products with appropriate markings of applicable testing agency.

1.Flame-Spread Index: 25 or less.

2.Smoke-Developed Index: 450 or less.

2.2 MARKERBOARD PANELS

A. Porcelain-Enamel Markerboard Panels: Balanced, high-pressure, factory-laminated markerboard assembly of three-ply construction, consisting of moisture-barrier backing, core material, and porcelain-enamel face sheet with low-gloss finish. Laminate panels under heat and pressure with manufacturer's standard, flexible waterproof adhesive.

1.Face Sheet Thickness: 0.021 inch uncoated base metal thickness.

2.Manufacturer's Standard Core: Minimum 1/4 inch thick, with manufacturer's standard moisture-barrier backing.

3.Laminating Adhesive: Manufacturer's standard moisture-resistant thermoplastic type.

2.3 TACKBOARD PANELS

A. Tackboard Panels:

1.Facing:

a. natural cork [plastic-impregnated cork].

2.Core:

VISUAL DISPLAY UNITS 101100 - 2

a. Manufacturer's standard.

2.4 MATERIALS

A. Porcelain-Enamel Face Sheet: PEI-1002, with face sheet manufacturer's standard two- or three-coat process.

B. Natural-Cork Sheet: Seamless, single-layer, compressed fine-grain cork sheet; bulletin board quality; face sanded for natural finish.

C. Plastic-Impregnated-Cork Sheet: Seamless, homogeneous, self-sealing sheet consisting of granulated cork, linseed oil, resin binders, and dry pigments that are mixed and calendared onto fabric backing; with washable vinyl finish and integral color throughout.

D. Extruded Aluminum: ASTM B221, Alloy 6063.

E. Adhesives for Field Application: Mildew-resistant, nonstaining adhesive for use with specific type of panels, sheets, or assemblies; and for substrate application; as recommended in writing by visual display unit manufacturer.

1.Adhesives shall have a VOC content of 50 g/L or less.

2.5 GENERAL FINISH REQUIREMENTS

A. Comply with NAAMM/NOMMA 500 for recommendations for applying and designating finishes.

B. Protect mechanical finishes on exposed surfaces from damage by applying a strippable, temporary protective covering before shipping.

C. Appearance of Finished Work: Noticeable variations in same piece are unacceptable. Variations in appearance of adjoining components are acceptable if they are within the range of approved Samples and are assembled or installed to minimize contrast.

2.6 ALUMINUM FINISHES

A. Clear Anodic Finish: AAMA 611, AA-M12C22A31, Class II, 0.010 mm or thicker.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine substrates and conditions, with Installer present, for compliance with requirements for installation tolerances, surface conditions of wall, and other conditions affecting performance of the Work.

B. Examine walls and partitions for proper preparation and backing for visual display units.

VISUAL DISPLAY UNITS 101100 - 3

C. Examine walls and partitions for suitable framing depth where sliding visual display units will be installed.

D. Proceed with installation only after unsatisfactory conditions have been corrected.

3.2 PREPARATION

A. Comply with manufacturer's written instructions for surface preparation.

B. Clean substrates of substances, such as dirt, mold, and mildew, that could impair the performance of and affect the smooth, finished surfaces of visual display boards.

C. Prepare surfaces to achieve a smooth, dry, clean surface free of flaking, unsound coatings, cracks, defects, projections, depressions, and substances that will impair bond between visual display units and wall surfaces.

3.3 INSTALLATION

A. General: Install visual display surfaces in locations and at mounting heights indicated on Drawings, or if not indicated, at heights indicated below. Keep perimeter lines straight, level, and plumb. Provide grounds, clips, backing materials, adhesives, brackets, anchors, trim, and accessories necessary for complete installation.

B. Field-Assembled Visual Display Board Assemblies:

Coordinate field-assembled units with grounds, trim, and accessories indicated. Join parts with a neat, precision fit.

1.Make joints only where total length exceeds maximum manufactured length. Fabricate with minimum number of joints, balanced around center of board, as acceptable to Architect.

C. Factory-Fabricated Visual Display Board Assemblies:

1.Attach concealed clips, hangers, and grounds to wall surfaces and to visual display board assemblies with fasteners at not more than 16 inches o.c.

Secure tops and bottoms of boards to walls.

D. Visual Display Board Assembly Mounting Heights: Install visual display units at mounting heights indicated on Drawings, or if not indicated, at heights indicated below.

1.Mounting Height 36 inches above finished flooR.

E. Rail Support System: Install horizontal support rail at mounting heights indicated on Drawings, or if not indicated, at height indicated below. Attach to wall with fasteners at 12 inches o.c.

1.Mounting Height: 72 inches above finished floor to top of rail.

VISUAL DISPLAY UNITS 101100 - 4

2.Hang visual display units on rail support system.

F. Sliding Visual Display Units: Install units at mounting heights indicated. Attach to wall framing with fasteners at not more than 16 inches o.c.

1.Adjust panels to operate smoothly without warp or bind. Lubricate operating hardware as recommended by manufacturer.

3.4 CLEANING AND PROTECTION

A. Clean visual display units in accordance with manufacturer's written instructions. Attach one removable cleaning instructions label to visual display unit in each room.

B. Touch up factory-applied finishes to restore damaged or soiled areas.

C. Cover and protect visual display units after installation and cleaning.

END OF SECTION 101100

VISUAL DISPLAY UNITS 101100 - 5

SECTION 101423 - ROOM-IDENTIFICATION SIGNAGE

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes room-identification signs that are directly attached to the building.

1.2 DEFINITIONS

A. Accessible: In accordance with the accessibility standard.

1.3 ACTION SUBMITTALS

A. Product Data: For each type of product.

B. Shop Drawings: For room-identification signs.

1.Include fabrication and installation details and attachments to other work.

2.Show sign mounting heights, locations of supplementary supports to be provided by other installers, and accessories.

3.Show message list, typestyles, graphic elements, and layout for each sign.

4.Include representative Samples of available typestyles and graphic symbols.

C. Samples for Verification: For each type of sign assembly showing all components and with the required finish(es), in manufacturer's standard size unless otherwise indicated and as follows:

1.Room-Identification Signs: Full-size Sample.

2.Variable Component Materials: Full-size Sample of each base material, character (letter, number, and graphic element) in each exposed color and finish not included in Samples above.

D. Product Schedule: For room-identification signs. Use same designations indicated on Drawings or specified.

1.4 CLOSEOUT SUBMITTALS

A. Maintenance Data: For signs to include in maintenance manuals.

1.5 WARRANTY

A. Special Warranty: Manufacturer agrees to repair or replace components of signs that fail in materials or workmanship within specified warranty period.

1.Failures include, but are not limited to, the following:

a. Deterioration of finishes beyond normal weathering.

b. Deterioration of embedded graphic image.

c. Separation or delamination of sheet materials and components.

ROOM-IDENTIFICATION PANEL SIGNAGE 101423.16 - 1

2.Warranty Period: 10 years from date of Substantial Completion.

PART 2 - PRODUCTS

2.1 MANUFACTURES

A. Room Name and number, universal toilet room ADA signage as manufactured by The Supersine Company,Mid MIchigan Stamp and Sign, Claridge Products and Equipment Inc. Signs to match existing, letters cut into plastic backboard. Provide room sign for ea room shown on room finish schedule, and ADA Toilet room signage

2.2 PERFORMANCE REQUIREMENTS

A. Accessibility Standard: Comply with applicable provisions in the USDOJ's "2010 ADA Standards for Accessible Design" and ICC A117.1.

2.3 SIGN MATERIALS

A. Aluminum Sheet and Plate: ASTM B209, alloy and temper recommended by aluminum producer and finisher for type of use and finish indicated.

B. Aluminum Extrusions: ASTM B221, alloy and temper recommended by aluminum producer and finisher for type of use and finish indicated.

C. Acrylic Sheet: ASTM D4802, category as standard with manufacturer for each sign, Type UVF (UV filtering).

2.4 ACCESSORIES

A. Fasteners and Anchors: Manufacturer's standard as required for secure anchorage of signs, noncorrosive and compatible with each material joined, and complying with the following:

1.Use concealed fasteners and anchors unless indicated to be exposed.

2.Exposed Metal-Fastener Components, General:

a. Fabricated from same basic metal and finish of fastened sign unless otherwise indicated.

b. Fastener Heads: Use flathead screws and bolts with tamper-resistant Allen-head slots unless otherwise indicated.

3.Sign Mounting Fasteners:

a. Concealed Studs: Concealed (blind), threaded studs welded or brazed to back of sign material or screwed into back of sign assembly unless otherwise indicated.

b. Through Fasteners: Exposed metal fasteners matching sign finish, with type of head indicated, and installed in predrilled holes.

B. Adhesive: As recommended by sign manufacturer.

1.Adhesives shall have a VOC content of 70 g/L or less.

ROOM-IDENTIFICATION PANEL SIGNAGE 101423.16 - 2

2.5 FABRICATION

A. General: Provide manufacturer's standard sign assemblies according to requirements indicated.

1.Preassemble signs and assemblies in the shop to greatest extent possible. Disassemble signs and assemblies only as necessary for shipping and handling limitations. Clearly mark units for reassembly and installation; apply markings in locations concealed from view after final assembly.

2.Mill joints to a tight, hairline fit. Form assemblies and joints exposed to weather to resist water penetration and retention.

3.Conceal connections if possible; otherwise, locate connections where they are inconspicuous.

4.Provide rabbets, lugs, and tabs necessary to assemble components and to attach to existing work. Drill and tap for required fasteners. Use concealed fasteners where possible; use exposed fasteners that match sign finish.

2.6 GENERAL FINISH REQUIREMENTS

A. Protect mechanical finishes on exposed surfaces from damage by applying a strippable, temporary protective covering before shipping.

B. Appearance of Finished Work: Noticeable variations in same piece are not acceptable. Variations in appearance of adjoining components are acceptable if they are within the range of approved Samples and are assembled or installed to minimize contrast.

2.7 ALUMINUM FINISHES

A. Clear Anodic Finish: AAMA 611, Class I, 0.018 mm or thicker.

PART 3 - EXECUTION

3.1 INSTALLATION

A. General: Install signs using mounting methods indicated and according to manufacturer's written instructions.

1.Install signs level, plumb, true to line, and at locations and heights indicated, with sign surfaces free of distortion and other defects in appearance.

2.Install signs so they do not protrude or obstruct according to the accessibility standard.

3.Before installation, verify that sign surfaces are clean and free of materials or debris that would impair installation.

ROOM-IDENTIFICATION PANEL SIGNAGE 101423.16 - 3

B. Accessibility: Install signs in locations on walls as indicated on Drawings and according to the accessibility standard.

C. Mounting Methods:

1.Concealed Studs: Using a template, drill holes in substrate aligning with studs on back of sign.

Remove loose debris from hole and substrate surface.

a. Masonry Substrates: Fill holes with adhesive. Leave recess space in hole for displaced adhesive. Place sign in position and push until flush to surface, embedding studs in holes. Temporarily support sign in position until adhesive fully sets.

b. Thin or Hollow Surfaces: Place sign in position and flush to surface, install washers and nuts on studs projecting through opposite side of surface, and tighten.

2.Through Fasteners: Drill holes in substrate using predrilled holes in sign as template. Countersink holes in sign if required. Place sign in position and flush to surface. Install through fasteners and tighten.

3.Adhesive: Clean bond-breaking materials from substrate surface and remove loose debris. Apply linear beads or spots of adhesive symmetrically to back of sign and of suitable quantity to support weight of sign after cure without slippage. Keep adhesive away from edges to prevent adhesive extrusion as sign is applied and to prevent visibility of cured adhesive at sign edges. Place sign in position, and push to engage adhesive. Temporarily support sign in position until adhesive fully sets.

3.2 ADJUSTING AND CLEANING

A. Remove and replace damaged or deformed signs and signs that do not comply with specified requirements. Replace signs with damaged or deteriorated finishes or components that cannot be successfully repaired by finish touchup or similar minor repair procedures.

B. Remove temporary protective coverings and strippable films as signs are installed.

C. On completion of installation, clean exposed surfaces of signs according to manufacturer's written instructions, and touch up minor nicks and abrasions in finish. Maintain

ROOM-IDENTIFICATION PANEL SIGNAGE 101423.16 - 4

signs in a clean condition during construction and protect from damage until acceptance by Owner.

END OF SECTION 101423.16

ROOM-IDENTIFICATION PANEL SIGNAGE 101423.16 - 5

SECTION 102113.13 - METAL TOILET COMPARTMENTS

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1.Metal toilet compartments.

1.2 COORDINATION

A. Coordinate requirements for blocking, reinforcing, and other supports concealed within wall to ensure that toilet compartments can be supported and installed as indicated.

1.3 ACTION SUBMITTALS

A. Product Data:

1.Metal toilet compartments.

a. Include construction details, material descriptions, dimensions of individual components and profiles, and finishes for toilet compartments.

B. Shop Drawings:

1.Include plans, elevations, sections, and attachment details.

2.Show locations of reinforcements for compartment-mounted grab bars and locations of blocking for surface-mounted toilet accessories.

3.Show locations of centerlines of toilet fixtures.

4.Show locations of floor drains.

5.Show overhead support or bracing locations.

C. Samples for Initial Selection: Manufacturer's standard color sheets, showing full range of available colors for each type of toilet compartment.

1.Include Samples of hardware and accessories involving material and color selection.

1.4 CLOSEOUT SUBMITTALS

A. Operation and Maintenance Data: For toilet compartments.

1.5 FIELD CONDITIONS

A. Field Measurements: Verify actual locations of toilet fixtures, walls, columns, ceilings, and other construction contiguous with toilet compartments by field measurements, and coordinate before fabrication.

PART 2 - PRODUCTS

2.1 SOURCE LIMITATIONS

A. Obtain metal toilet compartments from single source from single manufacturer.

2.2 PERFORMANCE REQUIREMENTS

A. Surface-Burning Characteristics: Comply with ASTM E84;

testing by a qualified testing agency. Identify products with appropriate markings of applicable testing agency.

METAL TOILET COMPARTMENTS 102113.13 - 1

1.Flame-Spread Index: 25 or less.

2.Smoke-Developed Index: 450 or less.

B. Regulatory Requirements: Comply with applicable provisions in the USDOJ's "2010 ADA Standards for Accessible Design" and ICC A117.1 for toilet compartments designated as accessible.

2.3 METAL TOILET COMPARTMENTS

A. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following:

1.Metpar ‘Dur-A-Tex’ 2.Republic Storage Products 3.Penco Products

B. Toilet-Enclosure Style: Overhead braced.

C. Urinal-Screen Style: Wall hung, flat panel.

D. Door, Panel, and Pilaster Construction: Seamless, metal facing sheets pressure laminated to core material; with continuous, interlocking molding strip or lapped-and-formed edge closures; corners secured by welding or clips and exposed welds ground smooth.

Exposed surfaces shall be free of pitting, seam marks, roller marks, stains, discolorations, telegraphing of core material, or other imperfections.

1.Core Material: Manufacturer's standard sound-deadening honeycomb of resin-impregnated kraft paper in thickness required to provide finished thickness of 1 inch for doors and panels and 1-1/4 inches for pilasters.

2.Tapping Reinforcement: Provide concealed reinforcement for tapping (threading) at locations where machine screws are used for attaching items to units.

E. Urinal-Screen Construction:

1.Flat-Panel Urinal Screen: Matching panel construction.

F. Facing Sheets and Closures: Electrolytically coated steel or hot-dip galvanized-steel sheet with nominal base-metal (uncoated) thicknesses as follows:

1.Pilasters, Braced at Both Ends: Manufacturer's standard thickness, but not less than 0.036 inch.

2.Pilasters, Unbraced at One End: Manufacturer's standard thickness, but not less than 0.048 inch.

3.Panels: Manufacturer's standard thickness, but not less than 0.030 inch.

METAL TOILET COMPARTMENTS 102113.13 - 2

4.Doors: Manufacturer's standard thickness, but not less than 0.030 inch.

5.Flat-Panel Urinal Screens: Thickness matching panels.

G. Pilaster Shoes: Formed from stainless steel sheet, not less than 0.031-inch nominal thickness and 3 inches high, finished to match hardware.

H. Pilaster Sleeves (Caps): Formed from stainless steel sheet, not less than 0.031-inch nominal thickness and 3 inches high, finished to match hardware.

I. Brackets (Fittings):

1.Stirrup Type: Ear or U-brackets; chrome-plated zamac J. Steel Sheet Finish: Immediately after cleaning and pretreating, apply manufacturer's standard baked-on finish, including thermosetting, electrostatically applied, and powder coatings.

1.Color: As selected by Architect from manufacturer's full range.

2.4 HARDWARE AND ACCESSORIES

A. Door Hardware and Accessories: Manufacturer's operating hardware and accessories.

1.Hinges:

a. Manufacturer's gravity-actuated, cam-action, self-closing type that can be adjusted to hold doors open at any angle up to 90 degrees, allowing emergency access by lifting door.

1) Material, Gravity-Type Hinge:

Chrome-plated zamac.

2.Latch and Keeper: Manufacturer's recessed, with occupancy indicator latch unit designed for emergency access and with combination rubber-faced door strike and keeper. Provide units that comply with regulatory requirements for accessibility at toilet enclosures designated as accessible.

a. Material: Chrome-plated zamac.

3.Coat Hook: Manufacturer's combination hook and rubber-tipped bumper, sized to prevent inswinging door from hitting compartment-mounted accessories.

a. Material: Chrome-plated zamac.

4.Door Bumper: Manufacturer's rubber-tipped bumper at outswinging doors.

a. Material: Manufacturer's standard.

METAL TOILET COMPARTMENTS 102113.13 - 3

5.Door Pull: Manufacturer's unit at outswinging doors that complies with regulatory requirements for accessibility. Provide units on both sides of doors at toilet enclosures designated as accessible.

a. Material: Chrome-plated zamac.

B. Overhead Bracing: Manufacturer's standard continuous, extruded-aluminum head rail with antigrip profile and in manufacturer's standard finish.

C. Anchorages and Fasteners: Manufacturer's standard exposed fasteners of stainless steel, finished to match items they are securing, with theft-resistant-type heads. Provide sex-type bolts for through-bolt applications. For concealed anchors, use stainless steel, hot-dip galvanized steel, or other rust-resistant, protective-coated steel compatible with related materials.

2.5 MATERIALS

A. Aluminum Castings: ASTM B26/B26M.

B. Aluminum Extrusions: ASTM B221.

C. Steel Sheet: Commercial steel sheet for exposed applications; mill phosphatized and selected for smoothness.

1.Electrolytically Zinc Coated: ASTM A879/A879M, 01Z.

2.Hot-Dip Galvanized: ASTM A653/A653M, either hot-dip galvanized or galvannealed.

D. Zamac: ASTM B86, commercial zinc-alloy die castings, chrome plated.

2.6 FABRICATION

A. Fabricate toilet compartment components to sizes indicated. Coordinate requirements and provide cutouts for through-partition toilet accessories, and solid blocking within panel where required for attachment of toilet accessories.

B. Overhead-Braced Units: Manufacturer's standard corrosion-resistant supports, leveling mechanism, and anchors at pilasters and walls to suit floor and wall conditions. Provide shoes at pilasters to conceal supports and leveling mechanism.

C. Door Size and Swings: Unless otherwise indicated, provide 24-inch- wide, inswinging doors for standard toilet enclosures and 36-inch- wide, outswinging doors with a minimum 32-inch- wide, clear opening for toilet enclosures designated as accessible.

PART 3 - EXECUTION

3.1 EXAMINATION

METAL TOILET COMPARTMENTS 102113.13 - 4

A. Examine substrates, areas and conditions, with Installer present, for compliance with requirements for fastening, support, alignment, operating clearances, and other conditions affecting performance of the Work.

1.Confirm location and adequacy of blocking and supports required for installation.

B. Proceed with installation only after unsatisfactory conditions have been corrected.

3.2 INSTALLATION

A. General: Comply with manufacturer's written installation instructions. Install units rigid, straight, level, and plumb.

Secure units in position indicated with manufacturer's recommended anchoring devices.

1.Maximum Clearances:

a. Pilasters and Panels or Screens: 1/2 inch.

b. Panels or Screens and Walls: 1 inch.

2.Stirrup Brackets: Secure panels or screens to walls and to pilasters with no fewer than three brackets attached at midpoint and near top and bottom of panel.

a. Locate wall brackets so holes for wall anchors occur in masonry or tile joints.

b. Align brackets at pilasters with brackets at walls.

B. Overhead-Braced Units: Secure pilasters to floor and level, plumb, and tighten. Set pilasters with anchors penetrating not less than 1-3/4 inches into structural floor unless otherwise indicated in manufacturer's written instructions.

Secure continuous head rail to each pilaster with no fewer than two fasteners. Hang doors to align tops of doors with tops of panels, and adjust so tops of doors are parallel with overhead brace when doors are in closed position.

C. Urinal Screens: Attach with anchoring devices to suit supporting structure. Set units level and plumb, rigid, and secured to resist lateral impact.

3.3 ADJUSTING

A. Hardware Adjustment: Adjust and lubricate hardware in accordance with hardware manufacturer's written instructions for proper operation. Set hinges on inswinging doors to hold doors open approximately 30 degrees from closed position when unlatched. Set hinges on outswinging doors to return doors to fully closed position.

END OF SECTION 102113.13

METAL TOILET COMPARTMENTS 102113.13 - 5

SPECIFICATIONS - SECTION 10 22 26 OPERABLE PARTITIONS

Part 1 – General

1.1 Description

A. General:

1. Furnish and install operable partitions and suspension system. Provide all labor, materials, tools, equipment, and services for operable walls in accordance with provisions of contract documents.

1.2 Related work by others

A. Preparation of opening will be by General Contractor. Any deviation of site conditions contrary to approved shop drawings must be called to the attention of the architect.

B. All header, blocking, support structures, jambs, track enclosures, surrounding insulation, and sound baffles as required in 1.4 Quality Assurance.

C. Pre-punching of support structure in accordance with approved shop drawings.

D. Paint or otherwise finishing all trim and other materials adjoining head and jamb of operable partitions.

1.3 Submittals

A. Complete shop drawings are to be provided prior to fabrication indicating construction and installation details. Shop drawings must be submitted within 60 days after receipt of signed contract.

1.4 Quality Insurance

A. Installation shall be performed by an installer certified by the manufacturer.

B. Preparation of the opening shall conform to the criteria set forth by ASTM E557 Standard Practice for Architectural Application and Installation of Operable Partitions.

C. The partition STC (Sound Transmission Classification) shall be achieved per the standard test method ASTM E90-99 and E413-87. Test run under ASTM procedures prior to E90-99 shall not be permitted. All tests must be from an independent, currently operating, NIST-accredited laboratory available to verify results.

1.5 Product delivery, storage, and handling

A. Proper storage of partitions before installation, and continued protection during and after installation will be the responsibility of the General Contractor.

1.6 Warranty

A. Partition panels shall be guaranteed for a period of two years with all mechanical parts including track and carriers guaranteed for a period of five years. This guarantee is against defects in material or workmanship of manufacturer’s product, excluding abuse.

OPERABLE PARTITIONS 102226 - 1

Part 2 – Products

2.1 Manufacturers

A. Manufacturers: Subject to compliance with requirements, provide products by the following:

1. Moderco Inc.

2. Modern fold

3. approved equal

2.2 Operation

A. Signature 842 manually operated, top supported paired panels.

B. Initial seal:

2. Fixed wall jamb.

C. Final closure (select one):

1. Telescopic closure panel equipped with a telescopic jamb mounted to a rack and pinion mechanism and extended with a lever handle.

2. Hinged closure panel (up to 12'-0" [3658mm] height).

a. Same construction and face finish as partition panels.

b. Standard hardware:

(i). Flush pulls and roller latch.

c. Optional hardware:

(iii). Deadbolt lock.

2.2 Panel construction

A. Nominal 4" [102mm] thick panels, up to 48 1/2" [1230mm] width. Framing members to be steel-braced mechanically fastened 6065-T5 aluminum alloy extrusions. Thinnest extrusion section to be no less than 3/32" [2.5mm]. Trolley pipes welded to 1 1/2" X 1 1/2" X 3/32" [38mm X 38mm X 2.5mm] steel tube mechanically fastened to top frame extrusion. Panel cavity to be filled with acoustical insulation. Panel faces to be removable and replaceable on site to accommodate changes in room function, interior finishes, etc.

B. Acoustical rating:

1. 55 STC.

C. Panel face construction:

1. STC 47, 49, 52, 53, 55 with optional plastic laminate or wood veneer finish: 1/2" [13mm] Particle board with galvannealed steel liner. Steel thickness based on STC rating.

ULEF/NAUF Particle board. (Optional)

D. Hinges:

1. Discreet steel hinges to project no more than 1/4" [6mm] from the panel face.

E. Vertical trims :

1. Trimless vertical edges.

F. Panel weight:

1. Between 6 to 10.5 lbs/sq.ft (based on STC rating).

2.4 Panel finishes

OPERABLE PARTITIONS 102226 - 2

A. Face finish shall be (select as required):

1. Factory applied Class A reinforced vinyl wallcovering with woven backing, weighing 21 oz/lin.yard [545 g/lin.m]. Color selected from manufacturer’s standard color selector.

2. Wilsonart high pressure laminate (38 and 60 suffixes).

B. Panel frame finish shall be:

1. Clear satin anodized.

2.5 Sound seals

A. Vertical seals:

1. Dual aluminum and pvc tongue and groove interlocking seals in each panel edge.

B. Horizontal seals (select one):

1. Type MM: Manually operated top and bottom seals. Top and bottom seals extend and retract simultaneously with half a turn of a removable lever handle. (Optional)

(Select one)

a. MM-1 *: 1" [25mm] track clearance. 1" [25mm] floor clearance with 5/8"

[16mm] operating range.

* Type MM-1 horizontal seals are standard for STC 55 panels with the addition of fixed top sweeps.

2.6 Suspension system

A. Track and trolleys (select one):

1. #72 steel track: 11 ga. roll-formed steel with integral soffit trim supported by pairs of 3/8" [10mm] dia. threaded rods connected to structural support with hanger brackets.

(Optional)

a. #72 trolley: Each trolley shall have four precision ground ball bearing wheels with steel tires.

b. Usage: For panels up to 15'-3" [4648mm] height.

c. Each panel to be supported by one trolley.

B. Track finish (select applicable):

1. Steel track finish shall be :

a. White powder coating.

2.7 Optional features

A. ADA-compliant single pass through door:

1. Same construction and face finish as partition panels.

2. Standard hardware:

a. Flush pull on each side.

b. Roller latch.

3. Optional hardware:

a. Concealed automatic closer.

Part 3 – Execution

3.1 Installation

OPERABLE PARTITIONS 102226 - 3

A. The complete installation of the operable wall system shall be by an authorized factory-trained installer and be in strict accordance with the approved shop drawings and manufacturer’s installation instructions.

3.2 Cleaning

A. All track and panel surfaces shall be wiped clean and free of handprints, grease, and soil.

B. Packing and other installation debris shall be removed from the job site.

3.3 Training

A. Installer shall demonstrate proper operation and maintenance procedures to owner’s representative.

B. Operating handle and owner’s manuals shall be provided to owner’s representative.

OPERABLE PARTITIONS 102226 - 4

SECTION 102800 - TOILET, BATH, AND LAUNDRY ACCESSORIES

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1.Toilet-compartment occupancy-indicator systems.

1.2 COORDINATION

A. Coordinate accessory locations with other work to prevent interference with clearances required for access by people with disabilities, and for proper installation, adjustment, operation, cleaning, and servicing of accessories.

B. Deliver inserts and anchoring devices set into concrete or masonry as required to prevent delaying the…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .