This document is Addendum No. 2 dated August 12, 2022 for the "Renovate Armory - Albion Armory" project located at the National Guard Armory Battery Albion Armory in Albion, Michigan. The addendum includes clarifications and changes to the original contract documents, such as updates to the civil, architectural, mechanical, and electrical requirements. Key changes include requiring painted metal rather than aluminum railing, allowing substitutions for specified door hardware, bathroom partitions, lockers, and flooring, and revising the data cabling and fire alarm system details.
The related state and local contract opportunity is project 511/21187, which is located in Calhoun County, Michigan and the Alden CDP jurisdiction. No additional pricing, set aside, incumbent, funding, or other salient information is provided in the given materials.
View the file
Other files
Show all 39
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
August 12, 2022
Renovate Armory – Albion Armory
Addendum Number 02
Project Location National Guard Armory Battery Albion Armory 1023 N Clark Street Albion, Michigan 49224
Notice to Proposers
Receipt of this Addendum shall be acknowledged on the Proposal Form.
This Addendum forms part of the Contract documents for the above reference project and shall be incorporated integrally therewith.
Each proposer shall make necessary adjustments and submit their proposal with full knowledge of all modification, clarifications and supplemental data included therein. Where provisions of the following supplemental data differ from those of the original Contract Document, this Addendum shall govern.
Civil Items
1. All exterior ramp pipe railing shall be painted metal, not aluminum. Exterior stair pipe railing shall be aluminum.
Architectural Items
1. All exterior ramp pipe railing shall be painted metal, not aluminum. Exterior stair pipe railing shall be aluminum.
2. Finish metal panel ceiling at entry and new hallway shall be equal to ‘Centria’ IW-10A flush panel 24 GA 12” x 1½” G-90 galvanized steel color white with smooth finish.
3. Dormakaba Door Hardware (formerly BEST) is an acceptable substitution for door specified hardware.
4. The Mail Room blast door shall have standard PSF rating for blast doors.
5. Scranton Products Manufacturer is an acceptable substitution for the bathroom toilet partitions.
6. Scranton Products Manufacturer is an acceptable substations for the specified locker manufacturer.
7. Curries Hollow Metal Doors and Frames is an acceptable substation for a door and frame manufacturer.
8. All EPDM roofing specifications is found in Section 07 of the specifications.
9. Sika flooring manufacturer is an acceptable substitution for Dur-a-flex flooring.
Mechanical Items
1. Sheet M-1, please refer to Sheet M-301: Adjusted airflow of BCU01 & RTU-2.
2. Sheet M-2, please refer to Sheet M-303: Added sheet, controls diagrams, sequence of operation & DDC Equipment Schedule
Electrical Items
1. Sheet E-1, please provide six (6) yellow CAT 6 cables from new IT Room 134 to existing locations in Adjust Fire Sim Room 010.
2. Sheet E-2, all new data cabling shall be blue with exception of six (6) new yellow cables between the new IT Room and the existing IT Room.
3. Sheet E-3, please refer to reissued Sheet E-301 for revised data rack detail and new faceplate.
Items of Clarification
There is not an existing fire alarm system in the building. A new fire alarm system is being added to the complete building per the electrical drawings and specs
It is the Electrical Contractors responsibility to furnish and install the tele/data wiring and devices.
End of Addendum Number 02