About this file
This is Amendment 0008 to Solicitation 6973GH-26-R-00082, issued by AAQ-730 Facilities & Aviation Safety Acquisition on April 14, 2026, with an effective date of April 14, 2026. The amendment revises proposal submission requirements and extends the response deadline for updated proposals.
The amendment makes four substantive changes to the original solicitation. First, it revises Provision L.3 (Instructions for Preparation and Submission of Proposals), paragraph f(1), to refocus the technical proposal evaluation from demonstrating understanding of construction requirements and technical problems to specifically evaluating whether proposed key personnel meet the requirements. Second, it deletes the original Provision L.4 entirely and replaces it with new Provision L.12 (Technical Acceptable/Unacceptable Evaluation of Key Personnel, Revised November 24, 2026), requiring offerors to submit new Volume II Technical Proposals addressing key personnel qualifications by 5:00 p.m. Central Time on Friday, December 4, 2026. Third, offerors are given the opportunity to revise their Volume IV Cost/Price proposals and must complete the attached Amendment 0008 SIR Attachment 1 Section B (Supplies and Services) and Amendment 0008 SIR Attachment 14 (Major Cost Element Breakdown) regardless of whether costs change, with a submission deadline of 5:00 p.m. Central Time on Friday, December 18, 2026. All submissions are subject to AMS Clause 3.2.2.3-14 regarding late submissions, modifications, and withdrawals. Offerors must acknowledge receipt of this amendment prior to the specified deadline using one of the prescribed methods to avoid rejection.
View the file
Other files
Show all 39
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or telegram which includes a reference to the solicitation and amendment number. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: is not is required copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ.NO. 5. PROJECT NO. (If applicable)
7. ADMINISTERED BY (If other than Item 6)CODE
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NO.
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required.)
copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
(x) A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. CONTRACT AUTHORITY
(Signature of Contracting Officer)
PAGESOF
Contractor
The hour and date specified for receipt of Offers to sign this document and return
Cynthia L. Cooper
See continuation page
AAQ-730 FAC. & AVIATION SAFETY ACQ
PO BOX 25082
BLDG 014-AHQ, ROOM 233A
OKLAHOMA CITY OK 73125
AAQ730-AFN
6973GH-26-R-00082
04/14/2026
04/14/2026
1 3
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
ITEM NO.
(A)
QUANTITY
(C)
6973GH-26-R-00082/0008
The purpose of this amendment is to revise
Provision L.3 INSTRUCTIONS FOR PREPARATION AND
SUBMISSION OF PROPOSALS, add new Provision L.12
TECHNICAL ACCEPTABLE/UNACCEPTABLE EVALUATION OF
KEY PERSONNEL and request updated proposals.
FIRST: Provision L.3 INSTRUCTIONS FOR
PREPARATION AND SUBMISSION OF PROPOSALS,
paragraph f(1) is hereby revised as follows:
From:
The technical proposal must be sufficiently detailed to enable technically oriented personnel to make a thorough evaluation and to arrive at a sound determination as to whether the proposed construction effort meets the requirements of the Government and that the offered approach is valid and practical. The technical proposal must be specific, detailed and complete to clearly and fully demonstrate that the offeror has a thorough understanding of the requirements for, and the technical problems inherent in, providing construction services outlined in the Specifications and
Drawings included in this SIR. Clear evidence of construction effort previously demonstrated and currently in place relating to the factors and subfactors should be included in each evaluation area.
To:
The technical proposal must be sufficiently detailed to enable technically oriented personnel to make a thorough evaluation and to arrive at a sound determination as to whether the proposed key personnel meet the requirements.
SECOND: The original Provision L.4, included in the SIR, as amended, is hereby deleted in its entirety and replaced with the Provision
L.12 TECHNICAL ACCEPTABLE/UNACCEPTABLE
EVALUATION OF KEY PERSONNEL (REVISED NOV 24,
2026).
THIRD: New Volume II Technical Proposals prepared in accordance with Provision L.12
TECHNICAL ACCEPTABLE/UNACCEPTABLE EVALUATION OF
Continued...
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
ITEM NO.
(A)
QUANTITY
(C)
6973GH-26-R-00082/0008
KEY PERSONNEL (REVISED NOV 24, 2026) are due by
5:00 pm, Central Time on Friday, December 4, 2026. AMS Clause 3.2.2.3-14, Late Submissions, Modifications and Withdrawals of Submittals
(Apr 2018) applies to Offerors response to this request.
FOURTH: Offerors are hereby given an opportunity to revise their Volume IV, Cost/Price proposal. All Offerors are required to complete the attached Amendment 0008, SIR
Attachment 1, Section B - Supplies and Services as well as Amendment 0008, SIR Attachment 14, Major Cost Element Breakdown even in the event that the Offeror's Cost/Price proposal does not change from the original SIR response. The due date for submission of Volume IV Cost/Price proposals is 5:00 pm Central Time on Friday, December 18, 2026. AMS Clause 3.2.2.3-14, Late
Submissions, Modifications and Withdrawals of
Submittals (Apr 2018) applies to Offerors response to this request. Offerors that do elect to revise their Cost/Price proposal shall complete a new SIR Attachment
| Amendment of solicitation/modification of contract |
| Contract ID code |
| Amendment/modification number |
| Effective date |
| Requisition/purchase requisition number |
| Project number |
| Issued by |
| Code |
| Administered by |
| Code |
| Name and address of contractor |
| Code |
| Facility code |
| Amendment of solicitation number |
| Dated |
| Modification of contract/order number |
| Dated |
| This item only applies to amendments of solicitations |
| Accounting and appropriation data |
| This item applies only to modifications of contracts/orders. |
| This change order is issued pursuant to: |
| The above numbered contract/order is modified to reflect the administrative changes |
| This supplemental agreement is entered into pursuant to authority of: |
| Other |
| Important: |
| Description of amendment/modification |
| Name and title of signer |
| Contractor/offeror |
| Date signed |
| Name and title of contracting officer |
| Signature of Contracting Officer |
| Date signed |
| Continuation sheet |
| Reference Number |
| Name of Offeror or Contractor |
File details come from the government source that posted it. Updated .