This document is an asbestos abatement information attachment for Federal contract 6973GH-26-R-00081, HQB Mechanical and Electrical Upgrades. It contains four floor plans (basement, first floor, second floor, and third floor) of the Headquarters Building with designated asbestos-containing areas marked for removal prior to construction activities.
The document specifies that the FAA (Federal Aviation Administration), as the owner, is responsible for performing all asbestos abatement work. Abatement must be completed prior to the contractor beginning mechanical and electrical upgrade work. The floor plans use color-coded designations to indicate areas: red-hatched areas identify asbestos-containing floor tile locations to be abated by the FAA, blue-hatched areas on the second and third floors indicate asbestos-containing flooring material that will remain, and areas without hatching contain no asbestos floor tile. Specific attention is given to the second floor, which includes 12"x12" grey tile with black specks identified as asbestos-containing material. The third floor notes "No Access Assumed" in certain areas. The first floor notation indicates Foundation Expansion Joints assumed to contain asbestos. These plans serve as the technical reference for identifying the scope of FAA-required abatement activities before construction commencement.
View the file
Other files
Show all 34
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
001-HEADQUARTERS BUILDING BASEMENT – UPDATED ASBESTOS CONTAINING FLOOR TILE (UNDER CARPET) LOCATIONS - 08-01-2022
Notes:
1. Hatched areas are to remain.
2. Solid areas to be abated.
3. Areas without hatching do not contain asbestos floor tile.
General Notes:
A. Abatement will be performed by owner.
B. Abatement will be completed prior to contractor starting work.
6973GH-26-R-00081
HQB Mechanical and Electrical Upgrades
ASBESTOS ABATEMENT INFORMATION
Asbestos Containing areas Areas to be Abated by FAA prior to construction
SIR 6973GH-26-R-00082, Amendment 0003 Attachment 3
001-HEADQUARTERS BUILDING FIRST FLOOR – UPDATED ASBESTOS CONTAINING FLOOR TILE (UNDER CARPET) LOCATIONS
Foundation Expansion Joints (Assumed to contain asbestos)
Asbestos Containing areas Areas to be Abated by FAA prior to construction
6973GH-26-R-00081
HQB Mechanical and Electrical Upgrades
ASBESTOS ABATEMENT INFORMATION
001-HEADQUARTERS BUILDING SECOND FLOOR – UPDATED ASBESTOS CONTAINING FLOOR TILE (UNDER CARPET) LOCATIONS - 08-01-2022
12"x12" Grey w/ Black Speck
Asbestos Containing areas Areas to be Abated by FAA prior to construction
6973GH-26-R-00081
HQB Mechanical and Electrical Upgrades
ASBESTOS ABATEMENT INFORMATION
Asbestos Containing Flooring Material=
001-HEADQUARTERS BUILDING THIRD FLOOR – UPDATED ASBESTOS CONTAINING FLOOR TILE (UNDER CARPET) LOCATIONS - 08-01-2022
No Access Assumed
6973GH-26-R-00081
HQB Mechanical and Electrical Upgrades
ASBESTOS ABATEMENT INFORMATION
Asbestos Containing Flooring Material=
Asbestos Containing areas Areas to be Abated by FAA prior to construction