Amendment 0008 Attachment 14 Major Cost Element Breakdown.xlsx
XLSX spreadsheet 31 KB Posted
- Solicitation number
- 6973GH-26-R-00082
About this file
This file is Amendment 0008 Attachment 14, a Major Cost Element Breakdown for solicitation 6973GH-26-R-00082, detailing the financial structure for mechanical and electrical upgrades at the Mike Monroney Aeronautical Center (MMAC) Headquarters Building in Oklahoma City, Oklahoma. The base proposal totals $22,118,289.00, comprised of $11,680,277.13 in estimated renovation construction costs (FAA F18 funding) and $10,438,011.87 in OCAT Sr. Lien funds. The base proposal includes general conditions, electrical closets, ceiling grids, emergency generator infrastructure, HVAC replacements and upgrades, electrical system upgrades, lighting controls, and related work distributed across multiple Contract Line Items (CLINs 0001-0007) on a Fixed Price (FFP) basis. Cost responsibilities are shared between FAA (52.81% of total responsibility) and OCAT (47.19%), with detailed breakdowns by discipline including general conditions ($1,905,878.00), architectural, mechanical, and electrical components.
Six optional items are priced separately: HVAC Ductwork replacement ($2,501,624.00), Lighting Controls upgrade ($2,028,724.00), In-Slab Raceway Conductors replacement ($350,063.00), Carpet/Wall Base/Paint ($1,559,789.00), Fire Alarm System upgrade ($1,744,208.00), and ERRCS System installation ($543,348.00), totaling $8,727,756.00. The attachment also includes relocation plans for 65 personnel and office assignments across basement, first, second, and third floors with identified points of contact, plus supplementary program costs estimated at $3,857,731.41 for A/E fees, asbestos abatement ($350,000.00), relocation to temporary facilities ($30,000.00), change orders ($2,211,828.90), and moving services ($180,000.00).
View the file
Other files
Show all 39
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| 6973GH-26-R-00082, AMENDMENT 0008 |
| ATTACHMENT 14, MAJOR COST ELEMENT BREAKDOWN |
| Priority | Item | Cost |
| BASE PROPOSAL | ||
| General Conditions | ||
| 1.1A - General Conditions (Field Personnel, Equipment, Safety, General Expenses, Close Out | ||
| 1.1B - General - Protect Existing Flooring & FF&E | ||
| Architectural | ||
| 1.2A -Build Out New Electrical Closets (all disciplines) | ||
| 1.2B - New Ceiling Grid in Areas of Base Proposal, Restroom Access Doors | ||
| 1.2D - Build Out New Screen Wall for Emergency Generator | ||
| Mechanical | ||
| 1.3A - Replace Basement AHU and Basment FCU's | ||
| 1.3B - Provide New Medium Pressure Gas Supply Feed and Associated Meter for Genset | ||
| 1.3C - Replace HVAC Terminal Units | ||
| 1.3D - Replace Existing Control Valves and Sensors | ||
| 1.3E - Add new isolation dampers to main duct branches at the shaft to each floor to be isolated | ||
| 1.3F - Install New Minisplits | ||
| 1.3G - Clean Existing Ductwork on Roof | ||
| Electrical | ||
| 1.4A - HVAC Upgrade Electrical Work | ||
| 1.4B - Upgrade Panels to Accommodate Future Growth | ||
| 1.4C - Replace all overcurrent protection devices with fused disconnects and antiquated breakers | ||
| 1.4D - Upgrade main service entrance surge protective device | ||
| 1.4E - Replace fuses in existing bus plugs. New fuses shall be utilized in SCCA and AFHA Studies | ||
| 1.4F Remedy existing electrical system code compliance issues | ||
| 1.4G - Replace building generator | ||
| 1.4H Replace generator automatic transfer switch | ||
| 1.4I - Separate the generator power system with life saftey and stand-by distribution systems | ||
| 1.4J - Connect existing stairwell lighting to inverter | ||
| 1.4J1 - Lighting controls for new electrical rooms | ||
| 1.4K - Provide new lighting inverters on each floor in new electrical closets | ||
| 1.4L - HVAC Power, Inverter Power, Recepticles and Lighting in new electrical closets | ||
| 1.4M - Overcurrent Protection and Arcflash Study | ||
| 1.4N - Identify/Replace basement conductor routing | ||
| BASE PROPOSAL Total | ||
| OPTIONAL ITEM 1 - Replace HVAC Ductwork | ||
| OPTIONAL ITEM 2 - Upgrade all lighting controls not in base proposal | ||
| OPTIONAL ITEM 3 - Replace Existing In-Slab Raceway Conductors | ||
| OPTIONAL ITEM 4 - Replace Carpet, Wall Base and Paint Walls | ||
| OPTIONAL ITEM 5 - Upgrade Fire Alarm System | ||
| OPTIONAL ITEM 6 - Install New ERRCS System |
| Total Cost Base + Optional Items |
| OCAT Maintenance/Defect Security Bond as required in Clause H.8 |
ATTACHMENT 14
MAJOR COST ELEMENT BREAKDOWN
Sheet 2
| Estimated Renovation Construction Cost | ||
| F18 | $11,680,277.13 | |
| OCAT Sr. Lien Funds | $10,438,011.87 | |
| Total Construction Cost | $22,118,289.00 | |
| Other Program Costs | ||
| (Not Included in this Acquisition) | ||
| A/E Fees Type A | Obligated | $104,727.00 |
| A/E Fees Type B | Obligated | $981,175.51 |
| Relocation to CAMI Modulars | Estimated | $30,000.00 |
| Asbestos Abatement | Estimated | $350,000.00 |
| Change Orders | Estimated | $2,211,828.90 |
| Moving Services | Estimated | $180,000.00 |
| Total Other Program Costs | $3,857,731.41 |
Sheet 4
| CLIN | CLIN | TYPE FUNDING |
| 0001 Base Proposal | FFP | F&E / OCAT Sr. Lien |
| 0002 Optional Item 1 - HVAC Ductwork | FFP | F&E |
| 0003 Optional Item 2 - Lighting Controls | FFP | F&E |
| 0004 Optional Item 3 - In-Slab Conductors | FFP | OCAT Sr. Lien |
| 0005 Optional Item 4 - Carpet, Wall Base, Paint | FFP | F&E |
| 0006 Optional Item 5 - Fire Alarm | FFP | F&E |
| 0007 Optional Item 6 - ERRCS | FFP | F&E |
Sheet4
| Base Proposal | |||||||
| Item | Responsibility | Share % | Cost | ||||
| Summary Base Proposal ( VAV's, Generator, | FAA | 20.10% | $2,308,213.00 | 0.11 | 217647.097798531 | ||
| Summary Base Bid | OCAT | 79.90% | $9,176,441.00 | 0.45 | 865269.258846323 | ||
| Summary Base Bid Total | $11,484,654.00 | 0.57 | 1082916.35664485 | ||||
| Optional Items | |||||||
| Item | Responsibility | Share % | Cost | ||||
| Optional Item 1 - Replace HVAC Ductwork | FAA | 100% | $2,501,624.00 | 0.12 | 235884.29810557 | $20,212,410.00 | 1905878 |
| Optional Item 2 - Upgrade Lighting Controls | FAA | 100% | $2,028,724.00 | 0.10 | 191293.390529482 | ||
| Optional Item 3 - Replace Inslab Raceway Conductors | OCAT | 100% | $350,063.00 | 0.02 | 33008.3038249274 | ||
| Optional Item 4 - Replace Carpet, Wall Base, Paint Walls | FAA | 100% | $1,559,789.00 | 0.08 | 147076.352584477 | ||
| Optional Item 5 - Upgrade Fire Alarm System | FAA | 100% | $1,744,208.00 | 0.09 | 164465.675029549 | ||
| Optional Item 6 - Install New ERRCS System | FAA | 100% | $543,348.00 | 0.03 | 51233.6232811426 | ||
| Optional Items Total | FAA | 95.99% | $8,377,693.00 | 0.41 | 789953.339530219 | ||
| Optional Items Total | OCAT | 4.01% | $350,063.00 | 0.02 | 33008.3038249274 | ||
| Optional Items Total | $8,727,756.00 | ||||||
| General Conditions / Overhead / Profit | |||||||
| Item | Responsibility | Share % | Cost | ||||
| General Conditions / Overhead / Profit | FAA | 52.17% | $994,371.13 | ||||
| General Conditions / Overhead / Profit | OCAT | 47.83% | $911,506.87 | ||||
| General Conditions / Overhead / Profit | $1,905,878.00 | ||||||
| Total Cost | |||||||
| Item | Responsibility | Share % | Cost | ||||
| Total Responsibility | FAA | 52.81% | $11,680,278.13 | ||||
| Total Responsibility | OCAT | 47.19% | $10,438,010.87 | ||||
| Total Responsibility | $22,118,289.00 |
Sheet5
| Basement | ||||||||
| Division | POC | Telework | Relocate | |||||
| AHF-S200 | Kinsley Kerlick | X | ||||||
| AJV-A | Jill Witter | X | ||||||
| AMC | Eddie Drake | X | ||||||
| Union Rep | Brenda Hooper | X | Will work in own cubicles, need conference rooom | |||||
| 1st Floor | ||||||||
| Division | POC | Telework | Relocate | |||||
| ACR-001 | Paul Philips | X | ||||||
| AHF | Kinsley Kerlick | X | ||||||
| AJW | Regina Hahn | X | ||||||
| AMC | Eddie Drake | X | ||||||
| 2nd Floor | ||||||||
| Division | POC | Telework | Relocate | |||||
| AAP-700 | David Byrd | X | ||||||
| AGC-001 | Cammie Sneed | X | Corey Staplefoote | Vincent DeRight | Include in correspondance | |||
| AGC-500 | Cammie Sneed | X | Corey Staplefoote | Vincent DeRight | Include in correspondance | |||
| AHF | Kinsley Kerlick | X | ||||||
| AJW-L | Andrea Clark | X | Tammy Loberg | Include in correspondance | ||||
| 3rd Floor | ||||||||
| Division | POC | Telework | Relocate | |||||
| ABP | Sarah Menz | X | ||||||
| AGC | Cammie Sneed | X | X | Corey Staplefoote | Vincent DeRight | Include in correspondance | 7 Offices | 1 Conference Room |
| AMK | Elizabeth Probst | X | 65 | Personnell (ESC) to relocate | ||||
| APM | X | |||||||
| ASP | Lisa Craig | X | X | 3 | Managers with Offices | |||
| AXE | Jennifer Waltrip | X | ||||||
| AXF | Jennifer Waltrip | X | ||||||
| AXH | Jennifer Waltrip | X | ||||||
| AXI | Jennifer Waltrip | X |
Funding
| Base Proposal | |||||||
| Item | Responsibility | Share % | Cost | ||||
| Summary Base Proposal (Electrical Closets, Ceilings, Generator) | FAA | 20.10% | $2,525,860.10 | $ 2,308,213.00 | 0.11 | $ 217,647.10 | |
| Summary Base Proposal (VAV's, AHU, FCU's, Electrical Distribution) | OCAT | 79.90% | $10,041,710.26 | $ 9,176,441.00 | 0.45 | $ 865,269.26 | |
| Summary Base Proposal Total | $12,567,570.36 | $ - 0 | |||||
| Optional Items | $ - 0 | ||||||
| Item | Responsibility | Share % | Cost | $ - 0 | |||
| Optional Item 1 - Replace HVAC Ductwork | FAA | 100% | $2,737,509.30 | $ 2,501,624.00 | 0.12 | $ 235,884.30 | |
| Optional Item 2 - Upgrade Lighting Controls | FAA | 100% | $2,220,017.39 | $ 2,028,724.00 | 0.10 | $ 191,293.39 | |
| Optional Item 3 - Replace Inslab Raceway Conductors | OCAT | 100% | $383,071.30 | $ 350,063.00 | 0.02 | $ 33,008.30 | |
| Optional Item 4 - Replace Carpet, Wall Base, Paint Walls | FAA | 100% | $1,706,865.35 | $ 1,559,789.00 | 0.08 | $ 147,076.35 | |
| Optional Item 5 - Upgrade Fire Alarm System | FAA | 100% | $1,908,673.68 | $ 1,744,208.00 | 0.09 | $ 164,465.68 | |
| Optional Item 6 - Install New ERRCS System | FAA | 100% | $594,581.62 | $ 543,348.00 | 0.03 | $ 51,233.62 | |
| Optional Items Total | FAA | 95.99% | $9,167,647.34 | $ 20,212,410.00 | 1.00 | $ 1,905,878.00 | |
| Optional Items Total | OCAT | 4.01% | $383,071.30 | ||||
| Optional Items Total | $9,550,718.64 | ||||||
| Total Cost | |||||||
| Item | Responsibility | Share % | Cost | ||||
| Total Responsibility | FAA | 52.81% | $11,680,278.13 | ||||
| Total Responsibility | OCAT | 47.19% | $10,438,010.87 | ||||
| Total Responsibility | $22,118,289.00 | $ 1,905,878.00 | $ 20,212,410.00 |