Amendment 0003 Attachment 1 - QA Log.pdf
PDF 263 KB Posted
- Solicitation number
- 6973GH-26-R-00082
About this file
This is a Questions & Answers Log for federal contract 6973GH-26-R-00081, Amendment 0003, addressing inquiries from prospective offerors regarding HQ Mechanical and Electrical Upgrades at the Mike Monroney Aeronautical Center in Oklahoma City. The document contains 159 questions and government responses covering scope clarification, scheduling, hazardous materials, personnel requirements, and submission procedures.
Key scope elements include Division 27 communications work limited to infrastructure support; remediation of asbestos and lead paint by others prior to contractor mobilization (scheduled February 11–March 10, 2027); demolition of an existing generator requiring FAA coordination; and wet pipe sprinkler system modifications to accommodate floor plan changes per NFPA 13 (2025). The project involves mechanical and electrical upgrades including HVAC system modifications, fire alarm system replacement with voice/speaker capability, electrical panel and circuit breaker replacement, lighting and controls installation in select areas, and emergency response and recovery communications system (ERRCS) installation with fiber connectivity. Work shall be conducted between 6:00 a.m. and 6:00 p.m. on normal government workdays, with after-hours and weekend work permitted upon seven calendar days' advance notice and approval. The building will not be fully vacated; contractor must maintain continuous service to occupied spaces including the Cafe, Conference Area 148A/B, Stem Lab 102, telecommunications room BC04B, and rooms BS13, BS14, 117, 186, and 338 (a mission-critical SCIF requiring security escort). Utility outages require seven working days' notice. The FAA will compensate for utilities per Specification 015000. Crane operations require FAA Form 7460-1 submission with 45-day approval duration. The contract includes a base bid plus six optional items, all additive and awardable in any combination. Past performance evaluations require submissions from proposed mechanical and electrical subcontractors; teaming agreements are acceptable in lieu of fully executed subcontracts at proposal submission. Proposals must be submitted electronically in four separate volumes with pricing in both Attachment 1 (lump sum) and Attachment 14 (cost element breakdown). Bid bonds may be submitted electronically. The period of performance and final completion requirements are detailed in Addendum 01 and its attachments.
View the file
Other files
Show all 34
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions & Answers Log 6973GH-26-R-00081, Amendment 0003 - Attachment 1
HQ Mechanical and Electrical Upgrades
# Comment/Question Response 1 We need clarification on the scope of work for Div 27. Division 27 scope as part of our work; however, based on the contract documents, Division 27 on this project appears to be limited. The documents primarily indicate supporting infrastructure only, including:
Providing new raceways/conduit. Modifying or extending existing raceways. Coordinating with the user’s/owner’s contractor for telecommunications systems. There is no clearly defined scope for structured cabling or network equipment, will those elements are assumed to be by others?
Div 27 requirements and specifications apply as required for communications work identified on the drawings, fire alarm, and ERRCS.
2 Is this project Tax Exempt? If so, will a Tax Exempt Certificate be provided? No 3 Are there liquidated damages associated with this project? No 4 Please provide : Who are Authorities Having Jurisdiction (AHJs) on this project other than the Federal Aviation Administration (FAA)/Government), their contact information and in what areas they have jurisdictional authority.
The OKC Fire Department will be involved in the inspection and approval of the Fire Alarm and ERRCS. For all other items, FAA is the AHJ.
5 Please provide the most recent Hazardous Materials Report (Asbestos and Lead Paint).
The “Project Manual” (Specifications), indicates under Division 00 – Procurement and Contracting Requirements, Section 00 31 26 – Existing Hazardous Material Information, Part 1 – General, Paragraph 1.1.B, that “An existing asbestos floor plan dated August 1, 2022, is available for viewing as appended to this Document.” Please note that the document is NOT provided in the Specifications. Please provide.
Remediation of Aesbestos will be performed by others prior to the contractor performing work. Spaces will be made safe prior the the contractor performing construction activies in spaces where asbestos is present. Refer to attached document.
6 Will the abatement work include mold remediation as well as lead and asbestos materials if encountered?
Any remediaiton/abatement will be performed by others. If suspected hazardous materials are identified, notify AMP-400 project manager immediately.
What time frame does the government expect to take to do the abatement work prior to the contractor starting work?
Abatement is scheduled to begin 2/11/27 and be complete 3/10/27
8 Reference Sheet AD-104, Sheet Keynotes #4, the note states, “Demolish existing generator. Coordinate with AMP400 for removal – Please clarify if it is the Contractor who is responsible for demolition or if it is AMP400.
Demolition of the generator is the contractors responsibility, the coordination required includes maintaining power to the comm room in the basement.
9 If a crane is required to perform any scopes of work on this project, will a Crane Permit and Crane Lift Plan be required? If so, what is the process for obtaining a crane permit and the duration?
Yes, perform 1A survey, fill out form FAA-7460-1. Submit to OCAT, duration to obtain once submitted is 45 days. Refer to CFR-2016-Title 14, Volume 2 section 77.15 for where required.
10 Reference Drawings Sheet AD-104, Sheet Keynotes #6 (typical as it pertains to partitions;
Sheet Keynotes #s vary throughout the Architectural Sheets), what is the composition of the wall or Wall Type? What are the dimensions to be demoed?
Contract Documents indicate the approximate extent and composition of wall to be demoed. Contractor shall field verify existing wall construction, dimensions, and all associated conditions necessary to complete demolition and subsequent construction.
Demolition required to accommodate the Work shall be included as part of the Contract.
11 What is AMP400? Please describe their role on the project. AMP-400 is the Architecture and Engineering division of Facilities Management at Mike Monroney Aeronautical Center. AMP-400 is managing this project.
12 Refer to Demolition Ceiling Notes (typical of Notes throughout). Where new gypsum wallboard ceilings are to be installed in restrooms or janitors’ closets, will access panels be required? If so, please provide quantity, type and size.
Per drawings new ceiling access panels to be installed in same location as existing. Size to match existing.
13 Will the FAA require a 3rd party locate service to perform utility locates at and around the area of the new generator?
Prior to excavation, contractor is required perform utility locate via the Oklahoma one-call (OKIE811) system.
14 What is the thickness of the existing concrete and/or asphalt at the area where the new generator is to be placed? See Detail AS102/2
Existing paving is concrete. For purposes of preparing a proposal, assume concrete thickness of 8 inches, or less.
15 What percentage of hours should be assumed for work that will need to be performed outside of normal business hours and/or on the weekends?
Refer to Addendum 01 and attachments. It is the Offeror's responsibility to determine the amount of after-hours work or weekend work required based on the Construction Documents.
16 Will this project be impacted by FAA Moratoriums where work is not allowed to be scheduled during high travel times (e.g. Thanksgiving, Christmas, New Year’s)?
This is not a requirement of this project.
17 For the purposes of scheduling, if the contractor chooses, will it be acceptable to work four, ten-hour work days (Monday – Thursday) or does the FAA prefer five, eight-hour work days?
Work shall be conducted between 6:00 a.m. and 6:00 p.m. on normal government workdays. Work may be conducted after-hours or on weekends and holidays with seven
(7) calendar days advance notice and submission/approval of an after-hours work request.
18 The drawings indicate in numerous areas under the section “General Phasing Notes,” that the “Contractor is responsible for securing Temporary Occupancy Permits.” From whom shall this be secured? Who is the Authority Having Jurisdiction (AHJ)?
Refer Addendum 01 & attachments, and response to Question 4.
19 Confirm full unoccupied status: the project manual repeatedly states the building will remain partially occupied. Please confirm the building will be fully unoccupied / vacant for the entire duration of construction.
a. If so, confirm:
b. no temporary dust proof partitions, egress protections, or occupant safety barriers required.
c. no temporary cooling/heating/ventilation is required for occupied spaces.
Refer Addendum 01 & attachments.
20 Assuming the building is unoccupied please confirm there are no restrictions on work hours, weekends, holidays.
See response to Question 17, above and refer to Addendum 01 & attachments.
Please confirm utility outages/shutdowns (MEP, Fire Alarm, etc) can occur any time without the 7-day notice or weekend only requirement.
Outage notices are required. Refer to Addendum 01 & attachments.
22 Please confirm GC has no responsibility for moving, protecting, or raising existing furniture/FF&E items (including option 4 finishes).
Contractor will be responsible for protection of existing furniture, fixtures, and equipment that are to remain. FAA will be responsible for relocation of furniture.
23 Please confirm the FAA moving services will relocate furniture/FF&E items out of the construction areas
Furniture will remain in spaces. FAA will relocate furnishings within rooms as needed for access.
24 Please confirm the usage of Johnson Controls is required. Existing Fire Alarm and HVAC controls are by Johnson Controls.
Modifications/replacement to these systems must be performed by Johnson Controls.
25 Bid Option Clarification: please confirm options 1-6 are additive only and may be awarded in any combination.
Bid options are additive and may be awarded in any order.
26 Is the prime contractor responsible for Test and Balance & Commissioning or is this agent Owner provided?
Prime contractor is responsible for Test & Balance. The commissioning agent is hired by the owner per specifications.
27 Please confirm the limits new 1 hour fire barrier and 2 hour fire barrier(s) are shown on drawing G-102 sealed on 2.20.2025
Seal and firestop all penentrations within the indicated spaces on sheet G-102 with an approved 2HR UL firestopping.
28 Please confirm the limits of sealing all new and existing penetrations with an approved 2 hour firestopping at mechanical rooms and shafts is limited to the red-dashed line shown on page G-102, sealed 2.20.25. Please confirm this work is intended to be coordinated with specification section 01 21 00 – Allowances Para 3.3.A
Refer Section 01 21 00 Allowance - this applies to existing openings or penetrations only.
29 Please confirm the areas shown via the red-dashed line on sheet G-102 are constructed with a 2 hour wall construction and extend to deck. Please confirm this work is intended to be coordinated with specification section 01 21 00 – Allowances Para 3.3.A
See response to Question 28.
30 Please confirm the limits of penetration and joint sealant is limited to the 1 hour and 2 hour fire barriers shown on sheet G-102.
a. Specifically:
i. 2 hour fire barrier in basement
ii. 1 hour fire barrier at electric closets on floors 1, 2, & 3
b. Please confirm this work is intended to be coordinated with specification section 01 21 00 – Allowances Para 3.3.A
See response to Question 28.
31 General Phasing Note B states that “all work that may create a nuisance shall be accomplished outside of normal working hours when occupied.” Please identify all work that shall be accomplished outside of normal working excluding standard outages.
Refer to Addendum 01 & attachments.
31A General Phasing Note E mentions temporary dust partitions. Please provide locations & details for temporary dust partitions required for the project.
Refer to Addendum 01 & attachments.
31B General Phasing Note J states “Contractor is responsible for covering and protecting the furniture during construction.” Please provide details on the level of covering and protection required for furniture scheduled to remain.
Cover and protect furniture from dust, debris, and construction damage.
32 Please provide a furniture plan showing any/all furniture/FF&E scheduled to remain.
Please provide photos so contractor can verify field conditions.
Refer to attached document.
33 Please provide the August 1, 2022 asbestos floor plan per 00 31 26 para 1.1.B Refer to attached document.
33A Phase 2 Note 2 calls for “Install floor protection in areas where flooring is to remain.”
Please confirm the Contractor to install floor protection as per detail 4/AE600 Masonite Flooring Joint Detail.
a. Please confirm Masonite floor protection sheets shall be 1/8” thick
b. Please confirm Masonite floor protection joints shall be taped
Contractor to provide floor protection as necssary to protect existing flooring from damage by demolition and construction.
34 Please provide the permit application per 00 31 43 para 1.1.B Permitting is not required.
Please provide the balance of the permitting fees. If the fee is unknown, please provide an allowance amount to be carried by the Prime Contractor for bidding purposes with modification to the contract provided should the fee amount exceed the allowance amount.
Permitting is not required.
36 01 01 00 Para D.1 - Please confirm the Contractor is required to complete demolition work between the hours of 6:00PM – 6:00AM.
a. Specifically work pertaining to: removal of concrete slab, sub-soil removal below existing concrete slab, demolition and removal of interior GWB, Flooring, wall and ceiling finishes, HVAC equipment & ductwork, electrical demolition and removal, any and all other items related to demolition
Refer to Addendum 01 & attachments.
37 01 01 00 Para D.1 – Please confirm demolition of CMU partitions, windows, and plumbing/waste lines are intended for removal within this project.
Refer Contract Documents.
38 01 01 00 Para D.1 – Please confirm demolition of CMU partitions, windows, and plumbing/waste lines are intended for removal within this project.
Refer Contract Documents.
39 01 01 00 Para E – requires 7 working days prior notifications for utility outages and shutdowns. Please confirm 7 working days is required as opposed to the MMAC standard 72 hours prior notice.
The 7-day requirement is correct.
40 01 01 00 Para F – requires temporary heating, air conditioning, ventilation. Please provide the levels of temporary heating/cooling required for occupants.
Refer to Addendum 01 & attachments.
41 01 01 00 Para 1.6.B – requires Project Closeout to be valued at 5% to 10%. Please confirm 5% Project Close out is acceptable.
5% is acceptable
42 01 01 00 Para 1.6.C.2 – Mentions sub-soil removal and disposal. Please confirm contractor is to dispose of sub soils off the MMAC Facility.
It is possible that excavated soil under existing concrete has been impacted by industrial wastewater transport and storage operations. Contractor will dispose of any excess soil as Special Waste. Contractor will transport and legally dispose the unsuitable soil to a Non-Hazardous Industrial Wast Landfill located in Oklahoma County and Certified by the Oklahoma Dept of Environmental Quality. Each landfill has their own requirements for testing the soil before accepting it. Contractor is responsible for sampling and testing the soil. Soil analysis must be submitted to FAA prior to moving soil off site. FAA will profile and manifest the waste for transport to the landfill. Contractor will transport in a lined container.
43 01 01 00 Para 1.6.C.3 – Mentions removal and replacement of existing windows at the first floor base bid area. Please confirm this scope of work applies to this project.
Window removal is not part of the scope.
44 01 03 00 Para 1.2..C – Instructs the contractor to give a 7 day notice to AMP-400 project manager to coordinate with FAA Moving Services for furniture removal. Please confirm FAA Moving Services will remove/relocate furniture at the contractors convivence with a 7 day notice.
Provide per Contract Documents.
45 01 03 00 Para 1.8.A Bid Option 4 – states “in particular, new finishes are not included in main corridors, which were updated to FAA standards in a previous project.” However, the contract drawing conflict with this statement as per sheets AD150 – AE180. Please confirm the construction requirements within the building’s main corridors.
Refer to Drawing Sheets I-001 through IN108 for finishes required.
46 Please confirm specification sections apply to the project.
a. 32 17 16
b. 33 31 11
c. 33 41 00
These specifications do not apply to this project.
47 Please confirm Room 338 is a SCIF, sheet FA103B Sheet note 1. Note is correct. See response to Question 61.
48 Please confirm the extent of the specification section 21 13 13 as it pertains to the subject project.
The existing fire suppression system is to be modified to accomiate floor plan changes indicated on the contract documents.
49 Is the intent to provide delegated design and provide a new wet sprinkler system with Bid Option #5 when replacing the Fire Alarm System?
Bid Option #5 is for fire alarm system replacement.
50 01 03 00 Para 1.2.A - Is the intent to only provide delegated design and provide new fire protection (wet sprinkler systems) in newly construction electrical closets only?
The fire suppression system is to be modified to accomodate floor plan changes shown on the Contract Documents.
51 Please confirm delegated design is necessary for the wet sprinkler system additions to the new electric rooms?
See NFPA 13 (2025) 30.1.5 for existing system modification requirements.
52 Please provide any hydraulic calculations pertaining to the building. Hydraulic calculations on the existing system are not avaiable. Nature of work is modification of the existing system to accommodate floor plan changes. Fire suppression is a delegated design.
53 09 91 23 Para 3.1.E.1 Is the contractor required to paint existing or new fire quenching fluid uninsulated piping?
Referenced piping to be painted only if exposed in finished spaces/rooms or if exposed to weather.
54 09 91 23 Para 3.1.E 2-7. Are there any requirements for painting uninsulated piping for the subject project?
Referenced piping to be painted only if exposed in finished spaces/rooms or if exposed to weather.
55 Please provide geotechnical report or existing sub-soil data for the concrete demolition area.
Contractor shall assume that existing soil is suitable for use.
56 Please confirm who bears cost/risk for unforeseen sub-soil conditions, contamination, or off-site disposal.
Once discovered, any unforeseen conditions shall be brought to the attention of the Contracting Officer and FAA project manager.
57 Please confirm all basement below-slab conduit and conductors must be relocated above-slab per electrical plans and specification section 01 03 00 1.4.N
Correct.
58 Please confirm BAA compliance requirements for the following: generator set (26 32 13.16), air handling units, panelboards, LED lighting, transfer switches, and any other major MEP Equipment.
BAA is required for all generator, air handling units, panelboards, LED lighting, transfer switches, and any other major MEP Equipment.
59 Confirm the in-slab walker raceway conductor replacement under bid option 3 is limited to the areas shown on the electrical power plans.
Bid Option 3 conductor replacement is limited to the outlined areas identified in the electrical power plans
60 Provide current as-built/record drawings, BAS Points Lists, duct condition reports, and MEP one-lines.
No additional information is available pre-proposal. Provide proposal based on the Contract Documents and addenda provided.
61 Please confirm room 338 (SCIF) has any special demolition, power, or security requirements.
Room 338 is mission critical and must remain in service. HVAC, Electrical, IT and security must be continuous. Security escort is required. No photos or communication d i ll d R f t Add d 01 & tt h t f dditi l i f ti62 Confirm the exact scope of the “remedy existing electrical system code compliance issues” per 01 30 00 Para 1.4.F Scope of 01 30 00 1.4.F includes remediation of all existing code compliance issues listed in the contract documents. If any additional issues found during demoltion and construction not previously identified due to observational constraints notify the 63 Confirm whether roof work associated with Bid Option 1 (duct replacement / cleaning) includes any structural modifications, curb work, or roofing penetrations.
Contractor is responsible for all associated work to provide complete system per bid option scope. Structural modifications are not anticipated at this time. Roof modifications shall be done in accordance with roofing system manufacturer's recommendations/requirements to maintain roof warranty. Existing roof system is Siplast and was installed by Alva Roofing.
64 Is the Contractor responsible for furnishing and installing all new roof curbs, supports, flashings, and patching required for the new rooftop units and ductwork?
Yes. See response to Question 63.
65 Must all roof penetrations and patching be coordinated with the existing roofing manufacturer to maintain current roof warranty
Yes. See response to Question 63.
66 Please provide the manufacturer and current roof warranty holder. See response to Question 63.
67 Will an allowance be provided for roof patching/coordination or is this fully included in the base bid / bid option ?
Work is to be included in the Base Bid & Bid Options. See responses above.
68 Confirm crane access, rigging, and hoisting requirements for new rooftop units and generator. Are there any FAA or MMAC restrictions on crane operations?
Yes, perform 1A survey, fill out form FAA-7460-1. Submit to OCAT, duration to obtain once submitted is 45 days. Refer to CFR-2016-Title 14, Volume 2 section 77.15 for where required.
69 Will contractor need to procure its own 1A survey? See response to Question 68.
70 Confirm when equipment/system warranties begin (substantial completion, final acceptance, or owner occupancy).
Final Acceptance
71 Confirm the contractor may rely on the pre-bid site visit and that no additional investigation time or compensation will be granted for concealed conditions.
Refer to Contract Documents, Addenda, and bid amendments for scope requirements.
72 Are there any existing as-built drawings that would indicate the magnitude of the existing below slab conduit and conductors to be replace with above slab overhead routing per note “26267” on sheet ED100A.
As-builts of underground routing are not available. Existing to remain basement devices and equipment are fed from under slab raceways
73 Base bid scope indicates to remedy the existing electrical system code compliances issues. Please clarify any known, and undefined NEC code violations above & beyond the ones to be remedied by providing new electrical closets that provide proper code required dedicated and working space requirements, as well as overcurrent protection to be provided on the secondary side of some transformers where missing.
No additional existing NEC code violations are documented at this time. Contractor is responsible for providing a code-compliant installation associated with their defined scope-of-work. Any existing code violations discovered that are outside the defined scope-of-work for the project shall be brought to the attention of the CO and PM for possible contract modification.
74 Can additional information be provide regarding the existing GE panelboards (pictures or model numbers) that indicate “Existing panelboard, preplace all existing circuits breakers in the panel with new”. Such as 1N4A, 1N4B, 1N4D, 2N2B, 2N2D, 2N2F, 2N2G, 2N2K, 2N2M, 2N2N, 2N4A, 2N4B, 2N4E, 3N2C, 3N4A, 3N4B, 3N4C, 3N4E, 3N4F.
1N4A - GE A Series 1N4B - GE A Series 1N4D - GE A Series 2N2B - GE A Series 2N2D - GE A Series 2N2F - GE A Series 2N2G - GE A Series 2N2K - GE A Series 2N2M - GE A Series 2N2N - GE A Series 2N4A - GE AE Series 2N4B - GE A Series 2N4E - GE A Series 3N2C - GE A Series 3N4A - GE A Series 3N4B - GE E Series 3N4C - GE AE Series 3N4E - GE A Series 3N4F - QMB Series
75 Will the elevators be able to be utilized during constructionto move materials and manpower between floors?
Elevators can be utilized, but contractor must protect cab finishes and door finishes.
Weight limits must be observed.
76 Will pre reads be required for AHU 1,2,3,4A,4B,5,6,7,8,9, and MUA-1. Yes, both a pre-work Test and Balance and a post-work Test and Balance are required to provide an end result similar to the current existing air and water flows
77 Duct cleaning is just to be performed on the exposed ductwork on the roof at AHU’s 2,3,4A,4B,5,6,7,8,9, and MAU 1 is this correct?
Clean ductwork on roof per construction documents.
78 Bid Option 1 note #3 and note #4 state Remove and Replace Supply/Return Air Ductwork inside the building. This would include the Vertical Chase Ductwork and any Horizontal Ductwork associated with AHU-4 and AHU-8. Is this correct?
Correct. Replace ductwork as directed per construction documents and remount appurtenances.
79 Bid Option 1 note #7 states Replace Shaft Ductwork. Does this pertain to AHU-4 and AHU- 8, or is this All-Shaft Ductwork?
Replace all ductwork as directed per construction documents and remount appurtenances. More than AHU-4 and install more ducts.
80 Will AHU #1 require all new valve packages (shutoff valve, strainer, gauges, petes plugs, etc. (each coil))? It somewhat says to replace shutoff valve, but I don’t see it being very clear on what is required.
Replace valves and appurtenances per plans for all AHU-1 coils.
81 “Fire alarm notes reference providing speakers for voice intelligibility, but the fire protection legend and FA riser identifies horns. Is a voice, speaker system the intent or a horn system the intent?
The fire alarm system is requried to be a voice system with speakers not horns.
83 Reference: Sheet F-001, General Note J and Specification Section 211313 – Wet Pipe Sprinkler Systems. The contract documents indicate that the existing wet pipe sprinkler system shall be modified to meet NFPA 13 and applicable codes. However, no specific areas of modification or sprinkler layouts are identified on the drawings. Please clarify if the Contractor is only responsible for modifying the sprinkler system in areas directly impacted by the work (e.g., new ceilings, walls, and MEP modifications), or if a full evaluation and upgrade of the existing building-wide sprinkler system to current code is required. If modifying is required, please provide locations of expected impact. If building-wide compliance is required, please provide design criteria, limits of work, and drawings defining the extent of modifications.
The existing fire suppression system is to be modified to accommodate the floor plan changes in the Contract Documents. Protect existing fire suppression system during construction.
84 Would the FAA take into consideration lowering the past performance requirement to 1 above 10 mil and other 3 being lower for the General Contractor.
These thresholds were revised in SIR Amendment 0002
85 Can you please provide overall photos of the project since none were allowed at the prebid. Please indicate on plan where photos were taken (perspective) 1.Hallway overall longitudinal 1st floor
2. Hallway overall longitudinal 2st floor
3. Hallway overall longitudinal 3st floor
4. Typical office space to be remodeled showing floor, walls and ceilings.
5. Typical restroom space to be remodeled showing floor, walls and ceilings
6. Overview photo of the café
7. Overview photo of the café back of house (kitchen area)
Refer to attached document.
Is the FAA willing to reduce the overall cost of project for both the mechanical and electrical subcontractors on this project. Those are shown in M.3 the relevant experience.
This information was revised in SIR Amendment 0002 posted to SAM.gov on May 15, 2026.
87 Can you please provide photos of the existing millwork. Can you please provide photos and perhaps dimensions of the built in millwork that we have to work over.
Refer to attached document.
88 Would the FAA be willing to receive the major cost element breakdown (attachment 14) with in 48 hours AFTER the bids are due. This is a lot of detail to breakdown, and it may prove difficult to accurately report this when the bids are due, specifically thinking receiving this info from multiple sub vendors (or not) and compiling that info on bid day. We are specifically mentioning the breakdown of the base proposal. In reality, the proposal could be evaluated on the base bid and Optional items, and THEN a breakdown could be submitted by the low selected contractor.
This is acceptable
In SIR Provision L.3 INSTRUCTIONS FOR PREPARATION AND SUBMISSION OF PROPOSALS, Paragraph e, Volume I - Contract Documentation, the sub-paragraph numbering shows (1), (2), (3), (4), (6) and (7). Was sub-paragraph (5) intentionally left out?
This issue was an inadvertent error. There is no sub-paragraph (5).
90 Clause 3.6.1.7, NORTH AMERICAN INDUSTRY CLASSIFICATION SYSTEM (NAICS) CODE does not contain the number of employees/the average number of employees over the last 24-month period. Please provide this information.
Some NAICS codes have size standards based upon dollar amounts and some NAICS codes have size standards based upon number of employees. The NAICS code utilized for this acquisition is 236220 and the associated size standard is based upon dollars.
More information about NAICS code size standards can be found at https://www.naics.com/wp-content/uploads/2017/10/SBA_Size_Standards_Table.pdf
Reference L.2, Mandatory Site Visit (Construction): Provision Does the mandatory site visit attendance requirement apply exclusively to the prime contractor (offeror), or are proposed subcontractors also required to attend the site visit for the proposal to be eligible for award?
Provision L.2 Mandatory Site Visit (Construction) states that "Prospective offerors are required to attend . . . " While is is certainly preferred that prospective subcontractors attend the Site Visit, Provision L.2 does not specifically state that attendance is mandatory for subcontractors is required.
92 Reference L.3(e), Instructions for Preparation and Submission of Proposals: Does the Government strictly require an original, physically signed hard copy of the bid bond to be mailed and received at the specified Oklahoma City address by the proposal due date, or is the electronic copy submitted via email with Volume I sufficient to satisfy the Proposal Guarantee requirement?
Since proposals are to be submitted electronically, the Government will accept an electronic copy of the required Bid Bond.
Reference Specification 010100-3 1.7 A (Addendum 01) and Specification 010100-2 1.4 D.1.: Does the emptying of the building negate the requirement to perform all demolition work described in specification 010100-2 1.4 D.1 at night or on approved weekends?
Since the building will be unoccuped, demolition can occur at any time. However, demolition and noise in areas adjacent to areas that are in operation may need to perform work after-hours.
94 Reference Solicitation Section I – Contract Clause 3.2.2.3-55 vs. Specification 015000-1: :
Will the FAA pay for these utilities consumed during the construction of the project?
Specification 015000 is the requirement for this project.
95 Reference Specification 003126 1.1.B.: Can the Government please provide this asbestos floor plan?
Refer to attached document.
Reference Drawing Sheet F-001 General Note J: What part, or parts, of the existing wet pipe sprinkler system are currently not compliant with NFPA 13 and/or the Codes adopted by the City of Oklahoma City? Does this note only apply to the addition of the new electrical rooms, or are there other system-wide deficiencies that need to be corrected to make the building compliant? If there are other system-wide deficiencies, can these areas be identified as there is no way we can ascertain this information from the documents?
See response to Question 48
97 Please provide available photographs, furniture standards, or representative information identifying furniture, modular systems, and owner equipment anticipated to remain in place and require protection during construction.
Refer to attached document.
98 Please provide available furniture layout drawings or identify whether existing furniture plans/models are available for contractor coordination and protection planning.
Refer to attached document.
99 Please identify any known restricted access areas, badging requirements, escort requirements, or operational/security-sensitive spaces within HQB-001 that may affect construction access, work hours, manpower planning, or sequencing.
Rooms BS14, 117, 186, and 338 will require escort from security. See response to Question 61.
100 Please identify any maximum allowable HVAC outage durations, environmental control requirements, or operational constraints applicable to occupied or mission-critical areas during construction.
Refer to Addendum 01 & attachments.
101 Please confirm whether temporary construction filters, replacement filters, or final filters for existing and new HVAC equipment will be Government-furnished or contractor-furnished. If contractor-furnished, please provide available filter requirements, sizes, MERV ratings, and anticipated quantities.
Refer to Addendum 01 & attachments. Contractor to furnish MERV 8 filters.
102 Please identify any required temporary maintenance, monitoring, testing, balancing, shutdown coordination, or interim operational support requirements associated with existing MEP systems during construction.
Refer to Addendum 01 & attachments for areas to remain in operation. FAA maintenance on existing equipment will continue.
Are any Temporary HVAC required to be provided to occupied offices if HVAC is off?
Please confirm whether temporary HVAC systems will be required to maintain occupied, operational, IT, communications, or mission-critical spaces during planned HVAC outages.
Refer to Addenda and Contract Documents.
104 Is temporary power required to occupied offices if power is off? Please confirm whether temporary power will be required to support occupied, operational, IT, communications, or mission-critical spaces during planned electrical outages.
Refer to Addenda and Contract Documents.
105 Addendum 01 states that “all references to project phasing indicated in the construction document drawings and specifications are hereby voided and shall not apply” and that the work will be performed under a single construction contract. However, revised Specification Section 010100 still states that “the work shall be phased to accommodate continued operations within the facility.” Please clarify the intended project execution requirements and confirm whether the Headquarters Building will be fully vacated during construction or whether any occupied/operational areas must remain functional during performance.
Building will not be fully vacated. Addendum 01 and its attachments detail the rooms/spaces that will be occupied during construction and that require building infrastructure (i.e. access/egress, power, lighting, conditioning, data, alarm, security) to maintain FAA operations. Contractor is responsible for sequencing and scheduling the work to maintain these occupied spaces.
106 During the site visit, the Government indicated additional revisions to building occupancy and sequencing/phasing requirements may be forthcoming due to changes in planned occupancy status of the facility. Please advise when the Government anticipates issuing final revised phasing/occupancy requirements and whether additional drawing or specification revisions will be issued by amendment.
Refer to Addendum 01 & attachments
107 Please confirm whether copies of applicable Oklahoma state contractor licenses, including required electrical and mechanical trade licenses, are required to be submitted with the proposal for the prime contractor and/or proposed subcontractors. If required, please identify the applicable submission location and timing requirements.
This information is required to be submitted by the successful offerors after contract award.
108 Please clarify whether the revised non-phased approach permits concurrent work activities across multiple floors, sectors, and disciplines throughout the building, including simultaneous demolition, mechanical, electrical, fire alarm, and finish restoration activities, subject to standard safety and coordination requirements.
Concurrent work activies are permitted while maintaining requirements.
109 Section L.3(e)(6) requires an executed copy of any Teaming Agreement, Joint Venture Agreement, or Major Subcontract in Volume I for mechanical, electrical, and any other subcontractor performing work in excess of $750,000. Please confirm whether a fully executed subcontract is required at proposal submission, or whether an executed teaming agreement / letter of commitment is acceptable for proposed major subcontractors prior to award.
The Government can definitely understand that having a fully executed subcontract agreement for all major subcontracts could definitely be an issue because at that point in time, the successful general contractor has not been determined. The Government will accept signed and executed teaming agreements for proposed major subcontractors to be included in the general contractors proposal.
110 Section L.3(e)(6) requires rationale for subcontracting, how the specific subcontractor was determined, and the percentage of work to be performed by each mechanical, electrical, or other subcontractor over $750,000. Please confirm whether this information should be included only in Volume I, or also cross-referenced in Volume II where relevant to the technical approach.
The Technical Evaluation associated with this SIR addresses the evaluation of key personnel to include the Construction Project Manager and the Construction Superintendent. As you are aware, the Government does not have privity of contract with a subcontractor; therefore, the key personnel must be associated with the prime (general) contractor. Given this requirement, it may not make a lot of sense for the prime (general) contractor to cross-reference subcontractor information in the technical proposal.
111 Volume III requires past performance submissions for the proposed Mechanical and Electrical subcontractors. Please confirm that subcontractors may be proposed as part of multiple offeror teams for this procurement unless subject to a separate exclusive agreement between private parties, and that subcontractor past performance submissions will be evaluated in the context of each individual offeror’s proposed team.
For past acquisitions that included similar past performance evaluation requirements to the current acquisition, the Government has received proposals where the same subcontractor was proposed by multiple prospective general contractors. This is completely allowable.
112 Attachment 11, Past Performance Survey, appears to reference “HQB Building Lobby Remodel” and includes “Pool Subcontractor” as a contractor role option, which do not appear specific to this HQ Mechanical and Electrical Upgrades project. Please confirm whether offerors should use Attachment 11 as issued without modification, or whether the Government will provide a corrected project-specific Past Performance Survey form.
Unfortunately, Attachment 11, Past Performance Survey did include a reference to "HQB Building Lobby Remodel" instead of utilizing the words "HQ Building Mechanical and Electrical Upgrades" and also made reference to "Pool Subcontractor". Since many completed PPS documents have already been submitted to the contracting office, it does not make sense to revise Attachment 11 at this point. Potential offerors are requested to utilize the words "HQ Building Mechanical and Electrical Upgrades" and disregard the words "Pool Subcontractor" in reference to Attachment 11, Past Performance Survey.
113 Section L.3 requires Volumes I, II, III, and IV to be submitted as separate documents.
Please confirm whether Attachment 14, Major Cost Element Breakdown, should be submitted in Volume IV only and excluded from Volume II and Volume III.
The Government confirms that Attachment 14, Major Cost Element Breakdown should only be included in Volume IV of an offerors proposal.
114 Please confirm whether the Contractor should disregard all temporary partitioning, swing space sequencing, phased turnover requirements, temporary occupancy controls, and phased life-safety restrictions shown in the original phasing sheets unless specifically identified elsewhere by amendment.
Refer to Addendum 01 & attachments.
115 Please provide a definitive list of all spaces, systems, telecommunications rooms, conference facilities, food service areas, IT areas, and occupied/operational functions required to remain active, accessible, or protected during construction under the revised non-phased project approach.
Refer to Addendum 01 & attachments and Contract Documents.
116 Addendum 01 states that Johnson Controls will be working concurrently with the Contractor on installation of the new controls system. Please clarify the division of responsibility between the Contractor and Johnson Controls for controls coordination, system integration, shutdown scheduling, startup, commissioning support, testing, and associated access requirements.
JCI may be performing work inside HQB that is outside of scope of this project. However JCI is required for new controls that are to be provided as a part of this project.
117 Please clarify required Government notification and approval durations for planned HVAC, electrical, fire alarm, communications, and utility outages not specifically identified elsewhere in the contract documents.
Refer to Addendum 01 & attachments. Approval/rejection time will vary based on complexity of request, but two days is typical.
118 Section L requires evidence that Past Performance Surveys (PPS) and Client Authorization Letters were transmitted no later than ten (10) days prior to the proposal due date. Given that pending Q&A responses may impact subcontractor selection, team composition, scope interpretation, and relevant project selection, will the Government consider extending the PPS transmission deadline or allowing updated/replacement PPS submissions where changes are necessitated by Government-issued Q&A responses, amendments, or clarifications?
The Government's understanding is that information that would impact the Past Performance Survey (PPS) of an offeror's proposed mechanical and electrical subcontractor was resolved with the issuance of SIR Amendment 0002, which was posted to SAM.gov on May 15, 2026. Completed PPS documents are due by May 28, 2026; therefore, the Government does not believe it is necessary to extend the due date for PPS submissions. In the event that the proposal due date is extended, the due date for PPS documents will also be extended.
119 Will the Government provide the inlet size of each fan powered box? Refer to Addendum #2 Mechanical Drawings dated 5-21-26.
120 After abatement of ACM flooring is completed by the owner, will the owner test the abated substrate to ensure no remaining chemical based mastic removal product No, the FAA will not be testing the abated substrate. The abatement contractor uses a detergent to clean the floor after abatement, but no warranty for chemical residue will be provided. Contractor shall provide necessary subfloor preparation as requried for proper floor adhesion. See response to Question 122.
121 Please provide owner ACM report in Spec Section 003126 Refer to attached document.
122 Will a VOC chemical-based product be used to remove mastic during abatement of floor tile?
Product to be used is Mast Away, MA-22 No Odor Mastic Remover manufacturered by Express Chem LLC of St. Louis, MO.
123 Is contractor required to protect furniture being handled by FAA moving services. Contractor will be responsible for protection of existing furniture and FF&E items.
Moving services will be responsible for relocation of furniture. PM will contact moving services to move furniture for access.
124 What is the estimated quantity of existing penetrations that require firestopping? Refer to Specification Section 012100.
125 Please confirm whether multiple floors/sectors may be worked concurrently under the revised non-phased approach, and whether any limits exist on the quantity of simultaneously impacted occupied areas, shutdown zones, or demolition areas.
Floors can be worked on concurrently so long as space required to remain in service is maintained.
126 Please confirm whether any spaces within HQB-001 are classified as mission critical, continuously occupied, secure, or environmentally sensitive spaces requiring enhanced shutdown coordination, escorting, noise limitations, vibration restrictions, or continuous HVAC/power service.
Refer to Addendum 01 & attachments, and response to Question 61.
127 Reference: L.3 – e. Volume I - Contract Documentation, (6) Any Teaming Agreement… Q:
Will the Government accept a letter of commitment in lieu of a teaming agreement or major subcontract?
Due to an unfortunate past experience, the Government requires a signed and executed Teaming Agreement.
128 Reference: L.3 – g. Volume III: Relevant Experience and Past Performance. If we (offeror) intend to self-perform either of the mechanical scopes or the electrical scopes, are we required to submit additional projects under sub-factor 1b or sub-factor 1c? or will the projects submitted under sub-factor 1a suffice?
Yes
129 Reference: L.3 – f. Volume II. Can the Government please clarify the requirements of Volume II? Is the Government only looking for resumes for the Project Manager and Superintendent? The evaluation factors in Sections L and M are indicated as such, but we wanted to confirm.
Potential offerors are required to fully demonstrate that their proposed key personnel meet all of the requirements included in the SIR. There are times when a resume will fully capture the required information but then there are also times when a resume may not clearly capture the required information. If a potential offeror believes that additional documentation is required to demonstrate that the potential offeror meets the technical requirements of the SIR, then this information should be provided in the technical proposal.
130 Reference: L.3 – g. Volume III & Can the Government confirm that we do not need to send out Client Authorization letters and request the completion of a PPS for projects that have a
CPAR?
Correct, Client Authorization letters are only required when utilizing a PPS. The Government does ask that if an offeror intends to use a CPAR evaluation for a given past performance reference, please include this information in your Volume III, Relevant Experience and Past Performance submission.
131 Factor 1 asks offerors to utilize Attachment 10 to provide information for each relevant experience project. However, page 83 outlines a list of information required for each project. Some of the requirements are the same as those on Attachment 10, but many are different. Does the government want offerors to use Attachment 10 for relevant experience or the list on page 83?
Yes, there is a significant list of items contained on Page 83 of the SIR that are to be provided to demonstrate relevant experience. The Government's intent was to request that the submissions contain all of this information and anticipate that potential offerors provide this information in the Project Description portion of Attachment 10. The Government is not stipulating the specific format for providing the required information - it is up to each potential offeror on how to format their response to fully address all required information.
132 Page 80 says the following about Volume 2: “The technical proposal must be specific, detailed and complete to clearly and fully demonstrate that the offeror has a thorough understanding of the requirements for, and the technical problems inherent in, providing construction services outlined in the Specifications and Drawings included in this SIR.
Clear evidence of construction effort previously demonstrated and currently in place relating to the factors and subfactors should be included in each evaluation area.” That makes it sound like we need to submit a work plan. However, L.4 on page 82 and M.2 on page 88 only address the requirements for the key personnel and resumes. Please confirm we only need to submit the resumes for the key personnel in volume 2.
Potential offerors are required to fully demonstrate that their proposed key personnel meet all of the requirements included in the SIR. There are times when a resume will fully capture the required information but then there are also times when a resume may not clearly capture the required information. If a potential offeror believes that additional documentation is required to demonstrate that the potential offeror meets the technical requirements of the SIR, then this information should be provided in the technical proposal.
133 Page 80 says that we are to submit Section B with Volume 1, Contract Documentation.
However, Section B contains pricing. Should Section B still be submitted with Volume 1?
Or should it go with Volume 4?
It is acceptable, but not mandatory, to include a copy os Section B in Volume IV of a potential offerors proposal.
134 Section H.6 on page 17 states, “The Government may exercise none, some or all Option items at the prices established in Section B, CLINs 0002-0005. Exercise of the option CLINs must be made in writing by the Contracting Officer within 30 days of contract award.”
However, Section B and Attachment 14 both have CLINS 0001-0006, not 0002-0005. Can you clarify this?
An upcoming SIR Amendment will correct the wording of Provision H.6 to read as follows: "The Government may exercise none, some or all Optional items at the prices established in Section B, Optional Items 1 through 6. Exercise of the Optional Items must be made in writing by the Contracting Officer within 30 days of contract award."
135 Do we need to submit Attachments and 16 with our proposal? The attachments state, “BIDDER MUST ELECTRONICALLY COMPLETE AND SIGN DOCUMENT PRIOR TO
SUBMITTING IN THE ELECTRONIC BID SYSTEM.” What electronic bidding system are the attachments referring to?
Yes, Attachments 15 and 16 are to be submitted as part of a potential offerors proposal.
The requirement is for potential offerors to electronically complete, sign and have the documents notorized and included in Volume I of their proposal. There is not a requirement for potential offerors to submit these document into an Electronic Bid System.
136 What is Attachment 13 referring to? Does this need to be submitted with our proposal? We do not understand the purpose of this form or to what it is referring. Please provide additional details.
Attachment 13, Contractor Release is a normal form utilized by the FAA. This form will be used by the successful offeror when they submit their final invoice for payment at the completion of work under the contract.
137 Please clarify what needs to be turned in for pricing. Attachment 1 has lump sum pricing for base bid through option 6. In attachment 14 (Major Cost Element Breakdown), there is a more detailed breakdown with following sheet that look like its an FAA budgeting worksheet. Do we just fill out Sheet1? Do we need both attachment 1 and 14?
Potential offerors are required to complete and submit both Attachment 1, Section B and Attachment 14, Major Cost Element Breakdown. Attachment 1, Section B will be incorporated into the successful offerors contract. Attachment 14, Major Cost Element Breakdown, is for the Government to review in order to understand what cost elements and values are included in each offerors proposal and ensure that the offeror understands the full requirements of this…
This is the start of the file's text. The full file is on GovTribe.