Addendum 003 - Valves - Corporation Stops R0.pdf

PDF 3 MB Posted

Attached to
Request for Proposal - Construction Services for Project L-897, Central Plateau Water Treatment Facility
Solicitation number
338214
Issued by

View the file

Other files

File Type Posted
Addendum 003 - O and M Manual - Prelim Oper and Maint Manual - Template R0.pdf PDF
Addendum 003 - Equipment - Automatic Strainers R0.pdf PDF
Addendum 003 - Valves - Other Check Valves R0.pdf PDF
Addendum 003 - Recommended Electrical Spare Parts List R0.pdf PDF
Addendum 003 - Equipment - Tab 3 - Anchor Bolt List R0.pdf PDF
Addendum 003 - Valves - Butterfly Valves R0.pdf PDF
Addendum 003 - Electrical Drawings - REMOTE IO 24VDC POWER PANEL.pdf PDF
Addendum 003 - Valves - Air Release Valves R0.pdf PDF
Addendum 003 - Analytical Instrumentation Valve List R0.pdf PDF
Addendum 003 - Valves - Auto Drain Valve R0.pdf PDF
Addendum 003 - Equipment - Commissioning Plan R0.pdf PDF
Addendum 003 - Valves - Diaphragm Valves R0.pdf PDF
Addendum 003 - VDL 006-006 RFP Const Bidder Pall Documents.xlsx XLSX spreadsheet
Addendum 003 - Valves - Other Solenoid Valves R0.pdf PDF
Addendum 003 - Electrical Drawings - FEED STRAINER PLC IO PANEL.pdf PDF
Addendum 003 - Valves - Other Air Pressure Valves R0.pdf PDF
Addendum 003 - Analytical Instrumentation - Flow Instrumentation R1.pdf PDF
Addendum 003 - Valves - Solenoid Valves R0.pdf PDF
Addendum 003 - Equipment - Actuator Torque Tables R1.pdf PDF
Addendum 003 - Equipment - Filter Elements R0.pdf PDF
Addendum 003 - Valves - Dual Disc Check Valves R0.pdf PDF
Addendum 003 - Equipment - FRP Tanks R0.pdf PDF
Addendum 003 - Equipment - Equipment List R0 - Pall Comments.pdf PDF
Addendum 003 - O and M Manual - System Functional Description (SFD) R0.pdf PDF
Addendum 003 - Electrical Drawings - MAIN CONTROL PANEL.pdf PDF
Addendum 003 - Electrical Drawings - MF VALVE RACK PANEL.pdf PDF
Addendum 003 - Electrical Drawings - Main CP 24VDC Power Panel.pdf PDF
Addendum 003 - Analytical Instrumentation - Level Instrumentation R1.pdf PDF
Addendum 003 - Valves - Air Pressure Control Valves R0.pdf PDF
Addendum 003 - Equipment - FRP Tanks attachment.pdf PDF
Addendum 003 - Contractual Electrical Spare Parts List R0.pdf PDF
Addendum 003 - Equipment - Air System R1.pdf PDF
Addendum 003 - Analytical Instrumentation - Temperature Instrumentation R1.pdf PDF
Addendum 003 - Valves - Ball Valves R0.pdf PDF
Addendum 003 - Valves - Chemical Pressure Control Valves R0.pdf PDF
Addendum 003 - Major Electrical Comp R0.pdf PDF
Addendum 003 - Electrical Drawings - CIP CAUSTIC ROOM PLC IO PANEL.pdf PDF
Addendum 003 - Exceptions and Clarifications - Specification Cross Reference Matrix R0.pdf PDF
Addendum 003 - Equipment - Calibration Columns R0.pdf PDF
Addendum 003 - Equipment - Centrifugal Pumps R0.pdf PDF
Addendum 003 - Equipment - Indeeco Heater General Infor R0.pdf PDF
Addendum 003 - Mechanical Drawings - Membrane Train Assy Dwg R3.pdf PDF
Addendum 003.pdf PDF
Addendum 003 - Equipment - Wilden Pump General Information R0.pdf PDF
Addendum 003 - Equipment - Water Softener R0.pdf PDF
Addendum 003 - Electrical Drawings - Interconnect Diagram Pall Comments.pdf PDF
Addendum 003 - Analytical Instrumentation - Pressure Instrumentation R1.pdf PDF
Addendum 003 - Mechanical Drawings - P and ID R4 Pall Submittal Return Comments.pdf PDF
Addendum 003 - Valves - Water Pressure Control Valves R0.pdf PDF
Addendum 003 - Equipment - Other Strainers R0.pdf PDF
Show 40 more

Latest 50 of 88 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

COVER PAGE OF SELLER’S SUBMITTAL

City Name: Hanford, WA - MSA

Pall Project No.: 01.000287

Job Number: Project L-897, Subcontract 70816

Task Register 6 (Task 1 – VI Submittal Package)

To: (Contractor)

Mission Support Alliance, LLC (MSA)

PO Box 650

Richland, WA 99352

From: (Subcontractor)

Pall Water

A Division of Pall Corporation

839 State Route 13

Cortland, NY 13045

Patty Willis

Phone: 607-758-1699

Name of Project: Hanford, WA, Central Plateau WTF

Pall Document Number: NYCS000015357 Rev: 00

Description of Item: Corporation Stops, 01.287

Specification Section: 43 21 00

Deviations: See document NYCS000015386

INDEX:

Page 1: Cover Page Information

Page 2: Revision History and Approvals

Page 3: Tab 1 - NYCS000015414,CSS,Corporation Stops,01.287

Pages 4-5: Tab 2 - NYCS000015360,Corporation Stop,0.5in,PVC,WH172230

Date: 12/19/2019

PALL ADVANCED SEPARATIONS SYSTEMS

DIVISION OF PALL CORPORATION, CORTLAND, NY

Rev Name Date Created By

Approved By

Created By

Approved By

Created By

Approved By

Created By

Approved By

Revision Description

Title

Document # Revision griffinju Text Box These commodities, technology, or software may only be exported from the United States in accordance with the Export Administration Regulations. Diversion contrary to U.S. law is prohibited.

Doc Number: NYCS000015414R00 Doc Title: NYCS000015414,CSS,Corporation Stops,01.287.docx

Components Specification Sections

The following specification sections are relevant to the approval of submittal NYCS000015357, Corporation Stops,01.287:

L‐897,Attachment No. 2 ‐ HNF‐SPEC‐63538, Section 43 21 00, Pumping Equipment – Basic Requirement.

Any exceptions and clarifications to the specification section above can be found in submittal:

NYCS000015386, Es and Cs, Section 43 21 00,01.287.

Pall has not taken any exceptions or clarifications relevant to the corporation stop proposed.

The corporation stop is considered as equivalent to a quill.

Application The use of a corporation stop is required when the process water pipe cannot be drained at the diffuser to allow for maintenance. With a corporation stop, the diffuser can be removed while the process water pipe remains full and pressurized.

Corporation Stops 1⁄2", 3⁄4", 1", 11⁄4", 11⁄2", and 2" sizes

Water Pipe

Corporation Stop

FIGURE 1

SOLUTION TUBE

PENETRATION

LENGTH

L

D

L = D

Sizes and Material Options Sizes Ball Valve Solution Tube Assembly

1⁄2" PVC, CPVC PVC, CPVC

3⁄4" Brass, PVC, CPVC PVC, CPVC

1" Brass, PVC, CPVC PVC, CPVC, PVDF, PTFE, Stainless Steel

11⁄4" PVC, CPVC PVC, CPVC

11⁄2" Brass, PVC, CPVC PVC, CPVC, Stainless Steel

2" Brass PVC, CPVC

Hydro Instruments utilizes no-lead brass corporation stop valves certified to the requirements of NSF/ANSI 61 Annex F and G, and NSF/ANSI 372. All other wetter materials in the corporation stop assembly are plastic.

Corporation stops are available with a variety of threaded and hose inlet connections. See Figures 2, 3, 4, and 5 for recommended installation configurations.

Solution Tube Penetration Length A corporation stop allows the injected chemical to enter the process water line away from the edge of the pipe. This facilitates more rapid and complete mixing of the injected chemical solution.

See Figure 1. It is recommended that the solution tube does not penetrate further than 1⁄3 of the process water line diameter. Please specify solution tube penetration length when ordering.

INSTRUMENTS

600 Emlen Way, Telford, PA 18969 • Telephone: (215) 799-0980 • Fax: (215) 799-0984 BULLETIN CS Rev. 12/13 Toll Free in the U.S.: 1 (888) 38-HYDRO • www.hydroinstruments.com • sales@hydroinstruments.com

PROUDLY

MADE IN USA

LarkinD Highlight

LarkinD Highlight

LarkinD Highlight

LarkinD Text Box comes with L = 6 inches, trim at installation

LarkinD Text Box

NYCS000015360R00

LarkinD Text Box

WH172330

Part #: CSP-050-PVC

Ejector Union

Ball Valve

FIGURE 2

EJECTOR CLOSE COUPLED PIPE INSTALLATION

Elbow

Water Pipe

Corporation Stop

Ejector

FIGURE 5

REMOTE HOSE CONNECTION

Hose

Water Pipe

Corporation Stop

Union

Ball Valve

FIGURE 4

REMOTE THREADED CONNECTION

Elbow

Water Pipe

Corporation Stop

Hose

Ejector

Water Pipe

Corporation Stop

FIGURE 3

EJECTOR CLOSE COUPLED HOSE INSTALLATION

Installations Any installation of a corporation stop must allow for sufficient clearance to remove the diffuser by pulling it toward the ejector after the nut has been loosened.

Rigid Pipe: See Figures 2 and 4. When using rigid pipe a shutoff valve and an elbow must be installed with a union after the turn. The shutoff valve will allow isolation of the section of pipe during removal. The union will allow withdrawal of the diffuser.

Hose: See Figures 3 and 5. Sufficient clearance must be available to remove the diffuser by pulling it toward the ejector after the nut has been loosened.

Safety Chain: The purpose of the safety chain is to prevent the solution diffuser from blowing out due to high pressure in the process water line after the nut has been loosened on the corporation stop. Take care when loosening the nut as the solution diffuser may be forced outward at high velocity. However, the safety chain will prevent the solution diffuser from coming completely out of the corporation stop. When the safety chain is taut, the corporation stop valve is to be closed. After this valve has been closed, the chain should be detached to allow removal of the solution diffuser assembly.

INSTRUMENTS

600 Emlen Way, Telford, PA 18969 • Telephone: (215) 799-0980 • Fax: (215) 799-0984 BULLETIN CS Rev. 12/13 Toll Free in the U.S.: 1 (888) 38-HYDRO • www.hydroinstruments.com • sales@hydroinstruments.com

PROUDLY

MADE IN USA

Cover Page Information
Revision History and Approvals
Tab 1 - NYCS000015414,CSS,Corporation Stops
Tab 2 - NYCS000015360,Corporation Stops,0.5in,PVC
Title: Corporation Stops, 01.287
Document: NYCS000015357
Revision: 00
RevRow1: 0
NameCreated By: DMLarkin
DateCreated By: 11-DEC-2019
NameApproved By: JHoskins
DateApproved By: 11-DEC-2019
Revision DescriptionRow1: Initial Issue
RevRow2:
NameCreated By_2:
DateCreated By_2:
NameApproved By_2:
DateApproved By_2:
Revision DescriptionRow2:
RevRow3:
NameCreated By_3:
DateCreated By_3:
NameApproved By_3:
DateApproved By_3:
Revision DescriptionRow3:
RevRow4:
NameCreated By_4:
DateCreated By_4:
NameApproved By_4:
DateApproved By_4:
Revision DescriptionRow4:

File details come from the government source that posted it. Updated .