33-01710 Cleaning.pdf

PDF 116 KB Posted

Attached to
Route 54 Sanitary Sewer Extension Project
Solicitation number
Not on record
Issued by
Lycoming County, Pennsylvania

About this file

This is a Cleaning specification section for the Route 54 Sanitary Sewer Extension Project issued by the West Branch Regional Authority in Clinton Township, Lycoming County, Pennsylvania. The cleaning contract, designated as Contract No. WB-1, requires the contractor to maintain work sites, buildings, and storage facilities to specified cleanliness standards throughout the construction period and upon project completion. Progress cleaning obligations include daily site inspections and debris removal, with comprehensive removal of scrap and waste materials at least twice monthly. The contractor must maintain interior structures through weekly inspections and sweeping, prepare surfaces as required for subsequent material installations, and conduct daily cleaning of finish floor areas during active work. Final cleaning must be completed prior to project acceptance and includes removal of all tools, surplus materials, equipment, and debris from the site, with broom cleaning of all paved areas and restoration of seeded areas. Sealed bids for the overall project were due by 1:00 PM local time on Monday, February 16, 2026, submitted online through PennBid. The project encompasses approximately 1,520 linear feet of gravity sanitary sewer, 11 manholes, 13 lateral connections, one duplex sewage pumping station, 404 linear feet of force main, one stream crossing, and surface restoration work.

The contractor is responsible for providing all personnel, equipment, and cleaning materials compatible with surfaces being cleaned and approved by the Engineer, with no materials permitted that create health hazards or damage finishes. The contractor bears full responsibility for correction or replacement of any work damaged during progress or final cleaning at no additional cost to the Owner. All work is subject to Pennsylvania prevailing wage rates established by the Department of Labor and Industry and compliance with the Pennsylvania Steel Products Procurement Act of 1978. Bids must be accompanied by a certified check or bid bond equal to ten percent of the total bid amount as security for proper contract execution. Project information and bid documents are exclusively available through the PennBid website, with no responsibility assumed by the Owner or Engineer for documents obtained from other sources.

View the file

Other files

File Type Posted
63-REV 1.19.26 16000 Elect Gen Prov.pdf PDF
17-00700 Gen Cond.pdf PDF
31-01600 Mat and Equp.pdf PDF
4-00250 Experience Equipmt and Finan Stmt.pdf PDF
52-05900 Miscelanous Metals.pdf PDF
47-02820 Topsoil Seeding.pdf PDF
14-00660 Form Change Order No 1.pdf PDF
1-1 CD COVER.pdf PDF
36-02000 Site Wrk.pdf PDF
42-02310 Horizontal DD.pdf PDF
7-00630 Public Verification Form.pdf PDF
26-01340 Shop Draw.pdf PDF
70-REV 1.19.26 16402 Underground Construction.pdf PDF
27-01380 Construct Photos.pdf PDF
50-03200 Concrete Reinforcement.pdf PDF
11-00610 Release of Lien.pdf PDF
32-01700 Cont Close.pdf PDF
24-01090 Ref Stand.pdf PDF
8-00350 Non-Discrimination.pdf PDF
66-REV 1.19.26 16130 Boxes.pdf PDF
56-15015 NonPress PVC.pdf PDF
30-01570 Traffic Reg.pdf PDF
38-02110 Demolition.pdf PDF
69-REV 1.19.26 16161 Grounding.pdf PDF
60-15100 Basic Req Plumb Wrk.pdf PDF
10-00600 Bonding Forms.pdf PDF
34-01720 Proj Rec Doc.pdf PDF
67-REV 1.19.26 16140 Wiring Devices.pdf PDF
64-REV 1.19.26 16111 Conduit.pdf PDF
44-02600 Paving Surface.pdf PDF
53-09900 Painting.pdf PDF
48-02900 Landscaping.pdf PDF
46-02710 Chain Link Fence.pdf PDF
62-15136 Basic Pip Mat and Meth.pdf PDF
5-00300 Bid Form.pdf PDF
61-15115 Supp and Anchors.pdf PDF
35-01740 Warranty and Bonds.pdf PDF
3-00200 Instructions to Bidders.pdf PDF
51-03300 Cast in Place.pdf PDF
37-02102 Clear Grub.pdf PDF
58-2 TOC.pdf PDF
21-01000 Summ of Work.pdf PDF
18-00800 Supp Cond.pdf PDF
45-02607 Manholes.pdf PDF
55-11930 Pump Equp.pdf PDF
71-REV 1.19.26 16511 Led Exterior Lighting.pdf PDF
19-Wage Rates.pdf PDF
68-REV 1.19.26 16160 Panelboards.pdf PDF
41-02300 HDPE Pipe.pdf PDF
15-00670 Payment Application.pdf PDF
Show 40 more

Latest 50 of 75 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION 01710

CLEANING DIVISION 1

West Branch Regional Authority 01710-1 January 2026 Route 54 Sanitary Sewer Extension Project Cleaning Contract No. WB-1

PART 1 - GENERAL

1.01 SECTION INCLUDES

A. Throughout the construction period, maintain the work sites, buildings and storage facilities in a standard of cleanliness as described in this section.

B. At the completion of the work, clean all buildings and property of the Owner.

1.02 RELATED SECTIONS

A. Standard General Conditions of the Construction Contract and Supplementary Conditions.

B. Section 01000: Summary of Work and Special Requirements.

C. In addition to standards described in this section, comply with all requirements for cleaning as described in various other sections of these specifications.

1.03 STANDARDS

A. Inspection: Conduct daily inspection and more often if necessary, to verify that requirements of cleanliness are being met.

B. Codes and Standards: In addition to the standards described in this section, comply with all pertinent requirements of governmental agencies having jurisdiction, including off-site disposal of all materials.

PART 2 - PRODUCTS

2.01 CLEANING MATERIALS AND EQUIPMENT

A. Provide all required personnel, equipment and materials needed to maintain the specified standard of cleanliness.

2.02 COMPATIBILITY

A. Use only the cleaning materials and equipment which are compatible with the surface being cleaned as recommended by the manufacturer of the material or equal, as approved by the Engineer.

B. Do not use materials which will create hazards to health or property, and which will damage finishes and surfaces.

PART 3 - EXECUTION

3.01 PROGRESS CLEANING

West Branch Regional Authority 01710-2 January 2026

A. Progress cleaning shall be the responsibility of Contractor unless otherwise specified.

B. General:

1. Retain all stored items in an orderly arrangement allowing maximum access not impeding drainage or traffic and providing the required protection of materials.

2. Do not allow the accumulation of scrap, debris, waste material and other items not required for construction of this work.

3. At least twice each month, and more often if necessary, completely remove all scrap, debris and waste from the job site.

4. Provide adequate storage for all items awaiting removal from the job site, observing all requirements for fire protection and protection of the ecology.

C. Site:

1. Daily, and more often if necessary, inspect the site and pick up all scrap, debris and waste material. Remove all such items to the place designated for their storage.

2. Weekly, and more often if necessary, inspect all arrangements of materials stored on the site. Restack, tidy or otherwise service all arrangements to meet the preceding requirements.

3. Maintain the site in a neat and orderly condition at all times.

D. Structures:

1. Weekly and more often if necessary, inspect the structures and pick up all scrap, debris and waste material; remove all such items to the place designated for their storage.

2. Weekly and more often if necessary, sweep all interior spaces clean, “clean”, for the purpose of this subparagraph, shall be interpreted as meaning free from dust and other material capable of being removed by use of reasonable effort and handheld broom.

3. As required preparatory to installation of succeeding materials, clean the structures or pertinent portions thereof to the degree of cleanliness recommended by the manufacturer of the succeeding material, using all equipment and materials required to achieve the required cleanliness.

4. Following the installation of finish floor materials, clean the finish floor daily (and more often if necessary) at all times while work is being performed in the space in which finish materials have been installed; “clean”, for the purpose of this

West Branch Regional Authority 01710-3 January 2026 subparagraph, shall be interpreted as meaning free from all foreign material which, in the opinion of the Owner/Engineer, may be injurious to the finish floor material.

E. The Contractor shall be responsible for correction or replacement of work, which has been damaged during progress cleaning, at no additional expense to the Owner.

3.02 FINAL CLEANING

A. Prior to completion of the work, the Contractor shall remove from the job site all tools, surplus materials, equipment, scrap, debris and waste and conduct final progress cleaning as described under Subsection 3.01.

B. Final cleaning shall be provided by Contractor.

C. Definition: Except as otherwise specifically provided, “clean” (for the purpose of this

Subsection 3.02) shall be interpreted as meaning the level of cleanliness generally provided by skilled cleaners using commercial quality building maintenance equipment and materials.

D. Site:

1. Unless otherwise specifically directed by the Owner/Engineer, make clean seeded areas, broom clean all paved areas on the site and all public paved areas directly adjacent to the site; completely remove all resultant debris.

2. Remove waste, foreign matter and debris from areaways and drainage systems.

E. Timing: Schedule final cleaning as approved by the Engineer to enable the Owner to accept a completely clean Project.

F. The Contractor shall be responsible for correction or replacement of work, which has been damaged during final cleaning, at no additional expense to the Owner.